SunGuideSunGuideTMTM Software Development Project Software Development Project
Release 3.1: I-95 Express Lanes Release 3.1: I-95 Express Lanes Design Review Follow-upDesign Review Follow-up
January 29, 2008January 29, 2008
![Page 2: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/2.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 2
AgendaAgenda
Time Item Lead
8:30 – 8:45 Introductions and Opening Remarks Tillander
8:45 – 9:00 ConOps and Requirements Status Santana
9:00 – 9:15 High Level Overview – meeting objectives Heller
9:15 – 9:30 Admin Editor Updates Misra
9:30 – 10:15 Operator Map Option #2 Revision Misra
10:15 – 10:30 Break
10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra
11:30 – 12:45 Lunch
12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra
1:00 – 1:30 Schedule Review Heller
1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra
3:00 – 3:30 Open Discussion All
FDOT PM Meeting
3:30 – 4:00 Testing
4:00 – 4:30 Support
![Page 3: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/3.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 3
Introductions
![Page 4: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/4.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 4
AgendaAgenda
Time Item Lead
8:30 – 8:45 Introductions and Opening Remarks Tillander
8:45 – 9:00 ConOps and Requirements Status Santana
9:00 – 9:15 High Level Overview – meeting objectives Heller
9:15 – 9:30 Admin Editor Updates Misra
9:30 – 10:15 Operator Map Option #2 Revision Misra
10:15 – 10:30 Break
10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra
11:30 – 12:45 Lunch
12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra
1:00 – 1:30 Schedule Review Heller
1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra
3:00 – 3:30 Open Discussion All
FDOT PM Meeting
3:30 – 4:00 Testing
4:00 – 4:30 Support
![Page 5: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/5.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 5
ConOps and Requirements Status
![Page 6: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/6.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 6
AgendaAgenda
Time Item Lead
8:30 – 8:45 Introductions and Opening Remarks Tillander
8:45 – 9:00 ConOps and Requirements Status Santana
9:00 – 9:15 High Level Overview – meeting objectives Heller
9:15 – 9:30 Admin Editor Updates Misra
9:30 – 10:15 Operator Map Option #2 Revision Misra
10:15 – 10:30 Break
10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra
11:30 – 12:45 Lunch
12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra
1:00 – 1:30 Schedule Review Heller
1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra
3:00 – 3:30 Open Discussion All
FDOT PM Meeting
3:30 – 4:00 Testing
4:00 – 4:30 Support
![Page 7: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/7.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 7
High Level Overview – Meeting High Level Overview – Meeting ObjectivesObjectives
Requirements and Design:
– Review high level design
– Provide clarification to SwRI’s initial design interpretation
– Present revised prototype screens
Not an objective:
– Revise requirements
![Page 8: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/8.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 8
AgendaAgenda
Time Item Lead
8:30 – 8:45 Introductions and Opening Remarks Tillander
8:45 – 9:00 ConOps and Requirements Status Santana
9:00 – 9:15 High Level Overview – meeting objectives Heller
9:15 – 9:30 Admin Editor Updates Misra
9:30 – 10:15 Operator Map Option #2 Revision Misra
10:15 – 10:30 Break
10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra
11:30 – 12:45 Lunch
12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra
1:00 – 1:30 Schedule Review Heller
1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra
3:00 – 3:30 Open Discussion All
FDOT PM Meeting
3:30 – 4:00 Testing
4:00 – 4:30 Support
![Page 9: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/9.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 99
Admin Editor: System Admin Editor: System ConfigurationConfiguration
![Page 10: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/10.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 1010
Admin Editor: Defining Holidays/SpecialAdmin Editor: Defining Holidays/Special
![Page 11: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/11.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 1111
Admin Editor: SegmentsAdmin Editor: Segments
![Page 12: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/12.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 1212
Admin Editor: Daily Rate SchedulesAdmin Editor: Daily Rate Schedules
![Page 13: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/13.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 1313
Admin Editor: Import Rate ScheduleAdmin Editor: Import Rate Schedule
![Page 14: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/14.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 1414
Admin Editor: Configure Rate ScheduleAdmin Editor: Configure Rate Schedule
![Page 15: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/15.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 1515
Admin Editor: Segment/Rate Schedule Admin Editor: Segment/Rate Schedule AssociationAssociation
![Page 16: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/16.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 1616
Admin Editor: Segment/Rate Schedule Admin Editor: Segment/Rate Schedule AssociationAssociation
![Page 17: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/17.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 17
Admin Editor: Toll Rate DMSAdmin Editor: Toll Rate DMS
![Page 18: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/18.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 1818
Admin Editor: Toll Rate SignsAdmin Editor: Toll Rate Signs
![Page 19: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/19.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 19
AgendaAgenda
Time Item Lead
8:30 – 8:45 Introductions and Opening Remarks Tillander
8:45 – 9:00 ConOps and Requirements Status Santana
9:00 – 9:15 High Level Overview – meeting objectives Heller
9:15 – 9:30 Admin Editor Updates Misra
9:30 – 10:15 Operator Map Option #2 Revision Misra
10:15 – 10:30 Break
10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra
11:30 – 12:45 Lunch
12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra
1:00 – 1:30 Schedule Review Heller
1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra
3:00 – 3:30 Open Discussion All
FDOT PM Meeting
3:30 – 4:00 Testing
4:00 – 4:30 Support
![Page 20: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/20.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 20
Operator Map Option #2 RevisionOperator Map Option #2 Revision
![Page 21: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/21.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 21
AgendaAgenda
Time Item Lead
8:30 – 8:45 Introductions and Opening Remarks Tillander
8:45 – 9:00 ConOps and Requirements Status Santana
9:00 – 9:15 High Level Overview – meeting objectives Heller
9:15 – 9:30 Admin Editor Updates Misra
9:30 – 10:15 Operator Map Option #2 Revision Misra
10:15 – 10:30 Break
10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra
11:30 – 12:45 Lunch
12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra
1:00 – 1:30 Schedule Review Heller
1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra
3:00 – 3:30 Open Discussion All
FDOT PM Meeting
3:30 – 4:00 Testing
4:00 – 4:30 Support
![Page 22: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/22.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 22
AgendaAgenda
Time Item Lead
8:30 – 8:45 Introductions and Opening Remarks Tillander
8:45 – 9:00 ConOps and Requirements Status Santana
9:00 – 9:15 High Level Overview – meeting objectives Heller
9:15 – 9:30 Admin Editor Updates Misra
9:30 – 10:15 Operator Map Option #2 Revision Misra
10:15 – 10:30 Break
10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra
11:30 – 12:45 Lunch
12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra
1:00 – 1:30 Schedule Review Heller
1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra
3:00 – 3:30 Open Discussion All
FDOT PM Meeting
3:30 – 4:00 Testing
4:00 – 4:30 Support
![Page 23: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/23.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 23
Toll Viewer: Search ScreenToll Viewer: Search Screen
![Page 24: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/24.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 24
Toll Viewer: General View ScreenToll Viewer: General View Screen
![Page 25: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/25.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 25
Toll Viewer: Advanced User Toll Viewer: Advanced User ScreenScreen
![Page 26: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/26.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 26
AgendaAgenda
Time Item Lead
8:30 – 8:45 Introductions and Opening Remarks Tillander
8:45 – 9:00 ConOps and Requirements Status Santana
9:00 – 9:15 High Level Overview – meeting objectives Heller
9:15 – 9:30 Admin Editor Updates Misra
9:30 – 10:15 Operator Map Option #2 Revision Misra
10:15 – 10:30 Break
10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra
11:30 – 12:45 Lunch
12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra
1:00 – 1:30 Schedule Review Heller
1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra
3:00 – 3:30 Open Discussion All
FDOT PM Meeting
3:30 – 4:00 Testing
4:00 – 4:30 Support
![Page 27: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/27.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 27
AgendaAgenda
Time Item Lead
8:30 – 8:45 Introductions and Opening Remarks Tillander
8:45 – 9:00 ConOps and Requirements Status Santana
9:00 – 9:15 High Level Overview – meeting objectives Heller
9:15 – 9:30 Admin Editor Updates Misra
9:30 – 10:15 Operator Map Option #2 Revision Misra
10:15 – 10:30 Break
10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra
11:30 – 12:45 Lunch
12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra
1:00 – 1:30 Schedule Review Heller
1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra
3:00 – 3:30 Open Discussion All
FDOT PM Meeting
3:30 – 4:00 Testing
4:00 – 4:30 Support
![Page 28: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/28.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 28
Toll Viewer DMZ Requirements Toll Viewer DMZ Requirements
7: A web based browser application shall be available for authorized users to view data related to the Express Lanes.
– SwRI recommends striking the word “authorized.” If not, then will need to define what is meant by “authorized” user.
7.2: Users shall be assigned permissions to use the Toll Viewer and the Detail Level that they will use.
– Strike this entire requirement assuming “authorized” is removed.
![Page 29: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/29.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 29
Toll Viewer DMZ Server Setup Toll Viewer DMZ Server Setup
Toll Viewer Web
Application
DMS, Rate, & Event Archive
Tables
Toll Viewer Web Service
WorkstationIE 7
External Servers
SunGuide Servers
![Page 30: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/30.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 30
AgendaAgenda
Time Item Lead
8:30 – 8:45 Introductions and Opening Remarks Tillander
8:45 – 9:00 ConOps and Requirements Status Santana
9:00 – 9:15 High Level Overview – meeting objectives Heller
9:15 – 9:30 Admin Editor Updates Misra
9:30 – 10:15 Operator Map Option #2 Revision Misra
10:15 – 10:30 Break
10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra
11:30 – 12:45 Lunch
12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra
1:00 – 1:30 Schedule Review Heller
1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra
3:00 – 3:30 Open Discussion All
FDOT PM Meeting
3:30 – 4:00 Testing
4:00 – 4:30 Support
![Page 31: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/31.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 31
Schedule ReviewSchedule Review
SwRI reviewed the V4.0 Requirements and prioritized the requirements marked as “Phase 1”
– The requirements were grouped into functions Each function was stratified according to one of the
following:
• Complete by 4/30/08 – Assume FAT gets moved to 1st part of April and IV&V occurs after 4/30/08
• Complete by 5/15/08
• Complete by 5/3/08
![Page 32: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/32.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 32
Prioritization of Phase 1 of Prioritization of Phase 1 of Version 4.0 RequirementsVersion 4.0 Requirements
Can Complete by: 4/30/2008
Can Complete by: 5/15/2008
Can Complete by: 5/30/2008
![Page 33: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/33.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 33
Prioritization of Phase 1 of Prioritization of Phase 1 of Version 4.0 Requirements Cont’dVersion 4.0 Requirements Cont’d
Development Completed: 3/31/08
Development Completed: 4/14/2008
Development Completed: 4/30/2008
Can Complete by: 4/30/2008
Can Complete by: 5/15/2008
Can Complete by: 5/30/2008
![Page 34: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/34.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 34
Prioritization of Phase 1 of Prioritization of Phase 1 of Version 4.0 Requirements Cont’dVersion 4.0 Requirements Cont’d
Can Complete by: 4/30/2008
Can Complete by: 5/15/2008
Can Complete by: 5/30/2008
![Page 35: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/35.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 35
AgendaAgenda
Time Item Lead
8:30 – 8:45 Introductions and Opening Remarks Tillander
8:45 – 9:00 ConOps and Requirements Status Santana
9:00 – 9:15 High Level Overview – meeting objectives Heller
9:15 – 9:30 Admin Editor Updates Misra
9:30 – 10:15 Operator Map Option #2 Revision Misra
10:15 – 10:30 Break
10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra
11:30 – 12:45 Lunch
12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra
1:00 – 1:30 Schedule Review Heller
1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra
3:00 – 3:30 Open Discussion All
FDOT PM Meeting
3:30 – 4:00 Testing
4:00 – 4:30 Support
![Page 36: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/36.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 36
Action ItemsAction Items
![Page 37: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/37.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 37
Action Items - continuedAction Items - continued
![Page 38: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/38.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 38
Action Items - continuedAction Items - continued
![Page 39: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/39.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 39
Action Items - continuedAction Items - continued
![Page 40: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/40.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 40
Action Items - continuedAction Items - continued
![Page 41: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/41.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 41
Action Items - continuedAction Items - continued
![Page 42: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/42.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 42
Action Items - continuedAction Items - continued
![Page 43: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/43.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 43
Action Items - continuedAction Items - continued
![Page 44: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/44.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 44
AgendaAgenda
Time Item Lead
8:30 – 8:45 Introductions and Opening Remarks Tillander
8:45 – 9:00 ConOps and Requirements Status Santana
9:00 – 9:15 High Level Overview – meeting objectives Heller
9:15 – 9:30 Admin Editor Updates Misra
9:30 – 10:15 Operator Map Option #2 Revision Misra
10:15 – 10:30 Break
10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra
11:30 – 12:45 Lunch
12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra
1:00 – 1:30 Schedule Review Heller
1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra
3:00 – 3:30 Open Discussion All
FDOT PM Meeting
3:30 – 4:00 Testing
4:00 – 4:30 Support
![Page 45: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/45.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 45
Discussion ?
![Page 46: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008](https://reader035.vdocuments.site/reader035/viewer/2022062511/551415da550346dd488b52dc/html5/thumbnails/46.jpg)
Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 46
AgendaAgenda
Time Item Lead
8:30 – 8:45 Introductions and Opening Remarks Tillander
8:45 – 9:00 ConOps and Requirements Status Santana
9:00 – 9:15 High Level Overview – meeting objectives Heller
9:15 – 9:30 Admin Editor Updates Misra
9:30 – 10:15 Operator Map Option #2 Revision Misra
10:15 – 10:30 Break
10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra
11:30 – 12:45 Lunch
12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra
1:00 – 1:30 Schedule Review Heller
1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra
3:00 – 3:30 Open Discussion All
FDOT PM Meeting
3:30 – 4:00 Testing
4:00 – 4:30 Support