sunguide sm software development project status meeting november 9, 2004

57
SunGuide SunGuide SM SM Software Development Project Software Development Project Status Meeting Status Meeting November 9, 2004 November 9, 2004

Upload: mary-phelps

Post on 05-Jan-2016

221 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: SunGuide SM Software Development Project Status Meeting November 9, 2004

SunGuideSunGuideSMSM Software Development Project Software Development Project

Status Meeting Status Meeting November 9, 2004November 9, 2004

Page 2: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 2

AgendaAgenda

Time Item Lead

10:00 – 10:05 Introductions Liang Hsia

10:05 – 10:10 License Updates:

- TxDOT and FDOT - MDX JPA

- TransGuide - GDT

- WSDOT TOU - SwRI/FDOT Modification

Liang Hsia

10:10 – 10:20 TMC and Software Deployment Schedule Updates D1 D2 D3 D4 D5 D6 D7 MDXTurnpike Enterprise

10:20 – 10:50 Project Status Report Steve Dellenback

10:50 – 11:00 SunGuideSM and TIM Coordination Meeting Briefing Liang Hsia

11:00 – 11:10 SunGuideSM Training Steve Dellenback

11:10 – 11:20 Canoga Micro Loops Steve Dellenback

11:20 – 11:35 SunGuideSM Demonstration and/or Screen Review Robert Heller

11:35– 11:40 Open Discussion / Action Item Summary All

Page 3: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 3

Introductions

Page 4: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 4

AgendaAgenda

Time Item Lead

10:00 – 10:05 Introductions Liang Hsia

10:05 – 10:10 License Updates:

- TxDOT and FDOT - MDX JPA

- TransGuide - GDT

- WSDOT TOU - SwRI/FDOT Modification

Liang Hsia

10:10 – 10:20 TMC and Software Deployment Schedule Updates D1 D2 D3 D4 D5 D6 D7 MDXTurnpike Enterprise

10:20 – 10:50 Project Status Report Steve Dellenback

10:50 – 11:00 SunGuideSM and TIM Coordination Meeting Briefing Liang Hsia

11:00 – 11:10 SunGuideSM Training Steve Dellenback

11:10 – 11:20 Canoga Micro Loops Steve Dellenback

11:20 – 11:35 SunGuideSM Demonstration and/or Screen Review Robert Heller

11:35– 11:40 Open Discussion / Action Item Summary All

Page 5: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 5

License UpdatesLicense Updates

SwRI / FDOT Sublicense– License executed on August 29, 2003 before the contract started.– License updated on September 5, 2003 covering distribution

source code to other Florida governmental entities.– TxDOT informed SwRI on January 22, 2004 that TransGuide

software was on “hold”.– License amended on April 12, 2004 (to support District 2 and

name change)

Page 6: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 6

License UpdatesLicense Updates

For a FDOT / TxDOT partnership to occur two things are needed:

– MOU and License:• FDOT provided TxDOT with comments and legal opinion on

March 2, 2004• TxDOT provided FDOT with draft MOU and License on March

16, 2004 • FDOT forwarded draft MOU & License to TxDOT on October

18, 2004– TxDOT Software License (solves TransGuide license issue)

• TxDOT provided FDOT with a license on June 30, 2004 (included previous FDOT requests for content).

• FDOT signed license on August 10, 2004.• TxDOT acknowledged the receiving of the FDOT signed

license on August 23, 2004.• TxDOT signed license on August 30, 2004 and sent to FDOT

on September 20, 2003.• FDOT Requested TransGuide software on October 4, 2004.• FDOT Received TransGuide software on October 19, 2004.

Page 7: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 7

License Updates - continuedLicense Updates - continued

FDOT / WSDOT Term of Use (TOU):

– WSDOT provided FDOT with standard TOU on February 11, 2004.

– FDOT provided recommendation on to WSDOT on March 13, 2004.

– FDOT provided comments to the WSDOT’s Office of General Counsel’s August 21, 2004.

– WSDOT began working on FDOT’s comments on August 26, 2004.

– FDOT requested status on September 14, 2004, October 7, 2004 and November 5, 2004.

Page 8: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 8

License Updates - continuedLicense Updates - continued

FDOT / MDX Joint Program Agreement (JPA)

– FDOT provided MDX with preliminary JPA on December 3, 2003.

– MDX provided FDOT with draft final JPA on June 23, 2004.

– FDOT worked on Locally Funded Agreement and MDX JPA.

– FDOT forwarded updated JPA and sublicense to MDX on October 26, 2004

Page 9: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 9

License Updates - continuedLicense Updates - continued

SwRI / FDOT / Lee County Sublicense

– Lee County provided FDOT with official letter for participation on July 27, 2004

– FDOT and SwRI started documentation preparation on July 30, 2004

– SwRI provided FDOT with draft language on September 10, 2004

– FDOT forwarded sublicense to Lee County on October 26, 2004

FDOT issued iFlorida Data Collection Process (DCP) notice to proceed on September 8, 2004.

GDT License:

– System Planning Office and Office of Information Systems are finalizing the license agreement on September 14, 2004.

– Kevin Thibault approved the $130,000 GDT Procurement on October 19, 2004

Page 10: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 10

AgendaAgenda

Time Item Lead

10:00 – 10:05 Introductions Liang Hsia

10:05 – 10:10 License Updates:

- TxDOT and FDOT - MDX JPA

- TransGuide - GDT

- WSDOT TOU - SwRI/FDOT Modification

Liang Hsia

10:10 – 10:20 TMC and Software Deployment Schedule Updates D1 D2 D3 D4 D5 D6 D7 MDXTurnpike Enterprise

10:20 – 10:50 Project Status Report Steve Dellenback

10:50 – 11:00 SunGuideSM and TIM Coordination Meeting Briefing Liang Hsia

11:00 – 11:10 SunGuideSM Training Steve Dellenback

11:10 – 11:20 Canoga Micro Loops Steve Dellenback

11:20 – 11:35 SunGuideSM Demonstration and/or Screen Review Robert Heller

11:35– 11:40 Open Discussion / Action Item Summary All

Page 11: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 11

Reports by Deployment and Reports by Deployment and Possible Integration SchedulePossible Integration Schedule

District 4

District 6

MDX

District 7

District 1

District 2

District 5

District 3

Turnpike Enterprise

Page 12: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 12

District 4 ScheduleDistrict 4 Schedule

September 2004 District 4 moves equipment to new TMC

October 12, 2004 SunGuideSM Software Team performs Milestone Demonstration

December 2004 SunGuideSM Software Team provides TMC operators with software training

January 2005 SunGuideSM Software Team sets upthe District 4 software

Page 13: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 13

District 4 Milestone DemonstrationDistrict 4 Milestone Demonstration

Page 14: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 14

District 4 ScheduleDistrict 4 Schedule

December 2004 I95/I595 Video Monitoring Project Starts.

January 2005 District 4 TMC Grand Opening.

January 2005 Complete I 95/I 595 Video Monitoring andDetector System

Page 15: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 15

District 6 RTMCDistrict 6 RTMC

Page 16: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 16

District 6 ScheduleDistrict 6 Schedule

June 25, 2004 New TMC Grand Opening

April 2005 Ramp metering subsystem to be installed and tested

June 2005 SunGuideSM Software Release 2deployment includes Ramp metering system

July 2005 I-95 Package B project completion

Page 17: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 17

MDX ScheduleMDX Schedule

April 7, 2003 MDX sent letter to ITS Office aboutparticipating in SunGuideSM Project

April 25, 2003 FDOT Responded, Welcoming MDX’s

participation

December 3, 2003 FDOT provided MDX with a draft Joint Program Agreement

June 2005 SunGuideSM Software Release 2 deployment at MDX

October 2005 MDX TMC Operational

Page 18: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 18

District 7 RTMCDistrict 7 RTMC

November 2005 Building Construction FinishApril 2006 SunGuideSunGuideSM Software Deployment

Page 19: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 19

District 2 RTMCDistrict 2 RTMC

FY 2004FY 2004 I-95 N ITS ImprovementI-95 N ITS ImprovementFY 2006FY 2006 SunGuideSunGuideSM Deployment (Tentative)Deployment (Tentative)

Page 20: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 20

District 5 RTMCDistrict 5 RTMCFY 2004FY 2004 Orlando RTMC retrofit and upgrade Orlando RTMC retrofit and upgradeSeptember 8, 2004 -September 8, 2004 - iFlorida Data Collection Process iFlorida Data Collection ProcessDecember 2005 December 2005 FY 2004-2005FY 2004-2005 iFlorida C2C between Districts 2 and 5 iFlorida C2C between Districts 2 and 5

Page 21: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 21

Turnpike RTMCTurnpike RTMC

Page 22: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 22

Turnpike ScheduleTurnpike Schedule

March 2004 SunNav 1.1 Test

April 2004 SunNav 1.2 Development

June 2005 Observe D 4, D 6, & MDX C2C Deployment

Page 23: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 23

District 1District 1

May 2005 May 2005 I-75 Safety Barrier System upgrade I-75 Safety Barrier System upgrade December 2006 December 2006 SunGuideSunGuideSM Deployment at Ft. Myers RTMC Deployment at Ft. Myers RTMC FY 2011 (2005) FY 2011 (2005) Sarasota RTMCSarasota RTMC

Page 24: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 24

District 3District 3

FY 2007 Pensacola RTMC FY 2007 Pensacola RTMC FY 2008 Tallahassee RTMCFY 2008 Tallahassee RTMC

Page 25: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 25

Lee County Bridge Incident Lee County Bridge Incident ManagementManagement

July 27, 2004 Lee County Public Works will participate in SunGuide Software

Page 26: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 26

C2C ScheduleC2C Schedule

February 16, 2004 SunGuideSM and C2C Project Team completed Interface Control Document (ICD)

February 20, 2004 SunGuideSM and C2C Project Coordination Teleconference

March 9, 2004 SunGuideSM & C2C Project Coordination Meeting

June, 2005 C2C deployment among Districts 4, 6, and MDX

Page 27: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 27

AgendaAgenda

Time Item Lead

10:00 – 10:05 Introductions Liang Hsia

10:05 – 10:10 License Updates:

- TxDOT and FDOT - MDX JPA

- TransGuide - GDT

- WSDOT TOU - SwRI/FDOT Modification

Liang Hsia

10:10 – 10:20 TMC and Software Deployment Schedule Updates D1 D2 D3 D4 D5 D6 D7 MDXTurnpike Enterprise

10:20 – 10:50 Project Status Report Steve Dellenback

10:50 – 11:00 SunGuideSM and TIM Coordination Meeting Briefing Liang Hsia

11:00 – 11:10 SunGuideSM Training Steve Dellenback

11:10 – 11:20 Canoga Micro Loops Steve Dellenback

11:20 – 11:35 SunGuideSM Demonstration and/or Screen Review Robert Heller

11:35– 11:40 Open Discussion / Action Item Summary All

Page 28: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 28

Project Web SiteProject Web Site

http://sunguide.datasys.swri.edu

Page 29: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 29

Release-Oriented Release-Oriented Development ApproachDevelopment Approach

Page 30: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 30

Status of Release 1 ActivitiesStatus of Release 1 Activities

Project Management:– PM / Meetings / Reviews– Process documents– Interface Control Documents

(ICDs)

Core software framework:– Database– User administration– Executive handler– Status logger– User interface– Map– Data Bus

DMS:– General Subsystem– NTCIP Florida MIB driver– Mark IV version 2.5 driver

Page 31: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 31

Status of Release 1 Activities - Status of Release 1 Activities - continuedcontinued

CCTV Control:

– General Subsystem

– NTCIP 1205 driver

Video Switching

– General Subsystem

– IP Video switching driver

Video Wall

– General Subsystem

– Barco/Argus video wall driver

Traffic Detection, driver for:

– General Subsystem

– Bitrans B238-I4 driver

– RTMS (EIS and Wavetronix) driver

Page 32: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 32

Status of Release 1 Activities - Status of Release 1 Activities - continuedcontinued

Incident Management:– GUI– Subsystem– TIM coordination

Training:– Training Plan– Classes being adjusted– Material being developed

Testing– Integration testing – Document development

Documents:– Software User’s Manual (SUM– Version Description Document (VDD)– Software Design Document (SDD)

Page 33: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 33

Status of Release 2 ActivitiesStatus of Release 2 Activities

Ramp Metering:– Design activities initiated– Initial GUI design completed– High level design completed

Emergency Evacuation:– Requirements refined and

provided to FDOT– Design initiated

Data Archive– Requirements refined– Design initiated

Web Server– Requirements refined– Design initiated

HAR– Requirements refined– Design initiated

Center-to-Center– Requirements refined– Design initiated

RWIS– Requirements refined– Design initiated

Inventory and Maintenance– Requirements to be refined

Optional Service:– iFlorida Data Collection

Process (DCP)

Page 34: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 34

Development ActivityDevelopment Activity

Software development for Release 1 is complete Current Release 1 activities:

– Integration Testing

– System Testing

– Endurance Testing

– Documentation (ICDs and SDD)

Release 2 activities:

– Design

– Prototyping (preview in the December meeting)

– Coding to start soon

Page 35: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 35

Development ScheduleDevelopment Schedule

For the last 12 months:– Factory Acceptance Testing in San Antonio on November

17-19, 2004– Deployment in District 4 on December 2, 2004

Recent developments:– District 4 ready to deploy late January, early February 2005– Additional review time for testing documents– FDOT’s request to add District 4 DMS Message rules to the

Incident Management Subsystem PRIOR to Release 1 testing

New Schedule:– Factory Acceptance Testing in San Antonio on January 10-

12, 2005– Deployment in District 4 on January 24, 2004

Page 36: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 36

Deliverable StatusDeliverable Status

SwRI waiting for FDOT comments:– Concept of Operations– Version Description Document

Future documents to be provided by SwRI:– Software Integration Case Procedures (final version)– Software User’s Manual (draft and final version)– Software Design Document (final version)– District 4 Deployment Plan (draft and final version)

All documents delivered to FDOT

are available on the project web site.

http://SunGuide.datasys.swri.edu

Page 37: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 37

Cost StatusCost Status

Release 1:– Budget amount: $3,863,374– As of 9/24/04, ~$3,257,000 has been expended

Release 2:– Budget amount: $2,568,339– As of 9/24/04, ~$254,000 has been expended

Adjustments:– Reductions (funds back to FDOT):

• Eliminating DTS Efforts: $75,009.71• Combining 2a and 2b: $66,827.29 (this includes a “training

adjustment” to add classes) – Additions:

• iFlorida DCP Task: $64,531.00 • Distinct 4 Message Rules: $30,854.32

Page 38: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 38

Spending CurveSpending Curve

Page 39: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 39

Schedule StatusSchedule Status

Current areas of concern:– Documents:

• None

– Software:• None

Page 40: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 40

Schedule Status – continuedSchedule Status – continuedLast Reporting PeriodLast Reporting Period

Page 41: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 41

Schedule Status - continuedSchedule Status - continuedCurrent Reporting PeriodCurrent Reporting Period

Page 42: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 42

Functional ThreadsFunctional Threads

Page 43: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 43

Schedule Status - continuedSchedule Status - continued

Integration/Testing:– Proceeding well– Continuing long term “endurance” testing

“Factory” Acceptance Testing:– Tentatively January 10-12 in San Antonio

Future status meetings that need to be scheduled:– December 8, 2004 (“short” meeting in Jacksonville)

Future reviews that need to be scheduled:– Release 2 Software Design Review: sometime early

2005, will be held once other Release 1 and Release 2 enhancement requests are complete

Page 44: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 44

AgendaAgenda

Time Item Lead

10:00 – 10:05 Introductions Liang Hsia

10:05 – 10:10 License Updates:

- TxDOT and FDOT - MDX JPA

- TransGuide - GDT

- WSDOT TOU - SwRI/FDOT Modification

Liang Hsia

10:10 – 10:20 TMC and Software Deployment Schedule Updates D1 D2 D3 D4 D5 D6 D7 MDXTurnpike Enterprise

10:20 – 10:50 Project Status Report Steve Dellenback

10:50 – 11:00 SunGuideSM and TIM Coordination Meeting Briefing Liang Hsia

11:00 – 11:10 SunGuideSM Training Steve Dellenback

11:10 – 11:20 Canoga Micro Loops Steve Dellenback

11:20 – 11:35 SunGuideSM Demonstration and/or Screen Review Robert Heller

11:35– 11:40 Open Discussion / Action Item Summary All

Page 45: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 45

TIM Coordination MeetingTIM Coordination Meeting

Meeting:– Held: Thursday, October 22, 2004– Where: Orlando RTMC

Attendees:– Mike Akridge, FDOT– Elizabeth McCrary, FDOT– Liang Hsia, FDOT– Dong Chen, FDOT– Steve Corbin, FDOT– Denny Pedrick, FDOT– James Bitting, FDOT– Kendra Blackforce, TPK– Ranzy Whiticker, TPK– Mike Meincke, TPK– Mike Washburn, TPK

– Nelson Figueroa, FDOT– Larry Rivera, FDOT– Paul Dixon, FHP– Mark Roberts, FDOT– Brenda Young, FDOT– Jennifer Heller, FDOT– Robert Heller, SwRI– Bret Sadler, SwRI– Walt Townsend, ITS-Siemens– Charles Wallace, PBF

Page 46: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 46

TIM Coordination Meeting:TIM Coordination Meeting: Capability for ConsiderationCapability for Consideration

Link to Computer Aided Dispatch (CAD) system, which is a standard, statewide system. SunGuideSM has a C2C capability through which CAD data could be transmitted but logic would need to be added when received in SunGuideSM.

Some districts have adopted three levels of incidents based on both severity (length) of the incident and lane closures. This was not in the IM requirements per se (there are three “levels”: Minor, Moderate and Severe that are functions of user-defined percentages of lanes blocked). The new MUTCD uses three levels based on time (which are similar to Florida’s time-based criteria. The conclusion was that the definition of incident severity (and their labels) should be user configurable, and that the history of an incident’s evolution should be fully reproducible. (Note: there must be some commonalities in order to report and measure performance at a statewide level.)

District 4 has proposed a standard template for DMS messages that is being implemented in SunGuideSM.

Page 47: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 47

TIM Coordination Meeting:TIM Coordination Meeting:Capability for Consideration – con’tCapability for Consideration – con’t

The software should associate a lane configuration with each TSS link on the map. When the operator clicks on a link to create an incident, automatically pre-select the lane configuration associated with that link. (Currently, when an operator creates an incident, they must manually choose a lane configuration for the location associated with the incident.)

In the message sign control GUI, add a way to bring up a camera that can see the sign, in order to confirm message activation.

When logging incident data, include TSS data so that “end of congestion” time can be tracked as well as closure of incidents.

The TIM group suggested identifying incident data by region (rural and urban), route, number of accidents, time to clear and recover from incidents, vehicle types, and highest location of incidents. The TIM Group needs to refine these requirements, including explicit reporting requirements.

Page 48: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 48

TIM Coordination Meeting:TIM Coordination Meeting:Capability for Consideration – con’tCapability for Consideration – con’t

It was suggested that incidents should identify types of vehicles involved in the incident (CV/auto, auto/auto, CV/CV, multiple vehicles of all types, etc.).

SunGuideSM needs to include the statewide TIM performance measures currently being researched.

SunGuideSM ‘s geo-location system is based entirely on lat-long. It will be important to add mile marker locations, particularly in view of a possible deployment of location reference markers extensively throughout the state. This process needs to be automated. Also, freeway cross streets are common reference points, so a quicker way for operators to locate them is desirable. Similarly, it needs to be determined whether it is necessary to include the link-node system.

SunGuideSM has a flag to indicate that a hazardous material is involved in the incident, but the type of material is not captured. A set of HAZMAT categories at least, or actual chemicals at most, should be added.

Page 49: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 49

TIM Coordination Meeting:TIM Coordination Meeting:Capability for Consideration – con’tCapability for Consideration – con’t

It is further suggested that other data, such as ambient lighting, be added. The TIM Program will need to specify all such data that are not currently being captured.

The contacts list currently has to be created for each incident. The capability to have contact groups should be added, and incidents should be able to have pre-designated groups to notify, by severity level and perhaps even other criteria. (Note: these pre-designated groups would be a minimum given the incident.)

Dispatching of Road Rangers should be automated in the software.

The use of PDAs for Road Ranger logging needs to be recognized and the ability to upload these data be added.

Consider changing the DMS editor to allow selecting multiple signs to update with the same message, dragging one sign into another to copy text, etc. Also, when adding a sign to an incident response plan midstream, allow its proposed message to be populated automatically.

Add Incident Management reporting capabilities. Districts are to submit examples of their desired reports.

Page 50: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 50

AgendaAgenda

Time Item Lead

10:00 – 10:05 Introductions Liang Hsia

10:05 – 10:10 License Updates:

- TxDOT and FDOT - MDX JPA

- TransGuide - GDT

- WSDOT TOU - SwRI/FDOT Modification

Liang Hsia

10:10 – 10:20 TMC and Software Deployment Schedule Updates D1 D2 D3 D4 D5 D6 D7 MDXTurnpike Enterprise

10:20 – 10:50 Project Status Report Steve Dellenback

10:50 – 11:00 SunGuideSM and TIM Coordination Meeting Briefing Liang Hsia

11:00 – 11:10 SunGuideSM Training Steve Dellenback

11:10 – 11:20 Canoga Micro Loops Steve Dellenback

11:20 – 11:35 SunGuideSM Demonstration and/or Screen Review Robert Heller

11:35– 11:40 Open Discussion / Action Item Summary All

Page 51: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 51

Hands-On TrainingHands-On Training

On November 5, 2004 SwRI received the following comment:– Section 2.1.9 – Page 6: It states that this is not a hands on

Training Course. This needs to be so the operators will get a feel and fully understand how to operate the system.

SwRI’s Position:– SwRI received request for hands-on training.– SwRI had planned on having a laptop version of the

software for the instructor to use.– Happy to alter the training for hands-on.– Problem is hardware. Will the Districts have a test

environment with field equipment to support training?

Discussion?

Page 52: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 52

AgendaAgenda

Time Item Lead

10:00 – 10:05 Introductions Liang Hsia

10:05 – 10:10 License Updates:

- TxDOT and FDOT - MDX JPA

- TransGuide - GDT

- WSDOT TOU - SwRI/FDOT Modification

Liang Hsia

10:10 – 10:20 TMC and Software Deployment Schedule Updates D1 D2 D3 D4 D5 D6 D7 MDXTurnpike Enterprise

10:20 – 10:50 Project Status Report Steve Dellenback

10:50 – 11:00 SunGuideSM and TIM Coordination Meeting Briefing Liang Hsia

11:00 – 11:10 SunGuideSM Training Steve Dellenback

11:10 – 11:20 Canoga Micro Loops Steve Dellenback

11:20 – 11:35 SunGuideSM Demonstration and/or Screen Review Robert Heller

11:35– 11:40 Open Discussion / Action Item Summary All

Page 53: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 53

Canoga Loop BackgroundCanoga Loop Background

Limitations of older 3M devices: must poll the device often (essentially every vehicle):– C822/C824– C922/C924 (new version of the above)

3M has a newer product:– "Traffic Monitoring Card" (numbered as 942/944)– Works in conjunction with the C922/C924– Provides the capability to establish a monitoring interval in the

range of 1 second to 15 minutes– Driver can then poll at this interval, the device will provide

average speed, occupancy, volume for the specified interval– The device can be polled for the last 300 intervals (i.e. it keeps

a history of 300 intervals) or you can request the data for the last 500 vehicles (i.e. it keeps a history of the last 500 vehicle reads)

Same protocol is used for all above devices (some additional messages to support the Traffic Management Card

Page 54: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 54

Canoga Loop Issues:Canoga Loop Issues:Discussion TopicsDiscussion Topics

Use of 170 controllers– SwRI would recommend using SunGuideSM application servers

rather than 170s if the communications infrastructure supports the protocol bandwidth

Price of Canoga units– How do they compare to RTMS or other devices?

Installation costs– How do they compare to other devices?

Does FDOT want a Canoga driver for SunGuideSM?

Page 55: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 55

AgendaAgenda

Time Item Lead

10:00 – 10:05 Introductions Liang Hsia

10:05 – 10:10 License Updates:

- TxDOT and FDOT - MDX JPA

- TransGuide - GDT

- WSDOT TOU - SwRI/FDOT Modification

Liang Hsia

10:10 – 10:20 TMC and Software Deployment Schedule Updates D1 D2 D3 D4 D5 D6 D7 MDXTurnpike Enterprise

10:20 – 10:50 Project Status Report Steve Dellenback

10:50 – 11:00 SunGuideSM and TIM Coordination Meeting Briefing Liang Hsia

11:00 – 11:10 SunGuideSM Training Steve Dellenback

11:10 – 11:20 Canoga Micro Loops Steve Dellenback

11:20 – 11:35 SunGuideSM Demonstration and/or Screen Review Robert Heller

11:35– 11:40 Open Discussion / Action Item Summary All

Page 56: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 56

See Other Presentation

Page 57: SunGuide SM Software Development Project Status Meeting November 9, 2004

November 9, 2004SunGuide Status Meeting 57

Action Item RecapAction Item Recap

Number Person Action

55

56

57

58

59

60

61