sunguide sm software development project status meeting december 7, 2004
TRANSCRIPT
SunGuideSunGuideSMSM Software Development Project Software Development Project
Status Meeting Status Meeting December 7, 2004December 7, 2004
December 7, 2004SunGuide Status Meeting 2
AgendaAgenda
Time Item Lead
1:00 – 1:05 Introductions Liang Hsia
1:05 – 1:15 License Updates:
- TxDOT and FDOT - Lee County
- TransGuide - SwRI/FDOT Modification
- WSDOT TOU - GDT
- MDX JPA - Oracle
Liang Hsia
1:15 – 1:25 TMC and Software Deployment Schedule Updates D1 D2 D3 D4 D5 D6 D7 MDXTurnpike EnterpriseLee County
1:25 – 1:45 Project Status Report Steve Dellenback
1:45 – 1:50 Canoga Device Driver Update Steve Dellenback
1:50 – 2:00 Software Deployment Process Steve Dellenback
2:00 – 2:05 Web Server Prototype Screens Steve Dellenback / Robert Heller
2:05 – 2:10 Emergency Evacuation Prototype Screens Steve Dellenback / Robert Heller
2:10– 2:15 Open Discussion / Action Item Summary All
December 7, 2004SunGuide Status Meeting 3
Introductions
December 7, 2004SunGuide Status Meeting 4
AgendaAgenda
Time Item Lead
1:00 – 1:05 Introductions Liang Hsia
1:05 – 1:15 License Updates:
- TxDOT and FDOT - Lee County
- TransGuide - SwRI/FDOT Modification
- WSDOT TOU - GDT
- MDX JPA - Oracle
Liang Hsia
1:15 – 1:25 TMC and Software Deployment Schedule Updates D1 D2 D3 D4 D5 D6 D7 MDXTurnpike EnterpriseLee County
1:25 – 1:45 Project Status Report Steve Dellenback
1:45 – 1:50 Canoga Device Driver Update Steve Dellenback
1:50 – 2:00 Software Deployment Process Steve Dellenback
2:00 – 2:05 Web Server Prototype Screens Steve Dellenback / Robert Heller
2:05 – 2:10 Emergency Evacuation Prototype Screens Steve Dellenback / Robert Heller
2:10– 2:15 Open Discussion / Action Item Summary All
December 7, 2004SunGuide Status Meeting 5
License UpdatesLicense Updates
SwRI / FDOT Sublicense– License executed on August 29, 2003 before the contract started.– License updated on September 5, 2003 covering distribution
source code to other Florida governmental entities.– TxDOT informed SwRI on January 22, 2004 that TransGuide
software was on “hold”.– License amended on April 12, 2004 (to support District 2 and
name change)– SwRI provided FDOT with draft language on September 10, 2004 to include other Florida government entities
December 7, 2004SunGuide Status Meeting 6
License UpdatesLicense Updates
For a FDOT / TxDOT partnership to occur two things are needed:
– MOU and License:• FDOT provided TxDOT with comments and legal opinion on
March 2, 2004• TxDOT provided FDOT with draft MOU and License on March
16, 2004 • FDOT forwarded draft MOU & License to TxDOT on October
18, 2004– TxDOT Software License (solves TransGuide license issue)
• TxDOT provided FDOT with a license on June 30, 2004 (included previous FDOT requests for content).
• FDOT signed license on August 10, 2004.• TxDOT acknowledged the receiving of the FDOT signed
license on August 23, 2004.• TxDOT signed license on August 30, 2004 and sent to FDOT
on September 20, 2003.• FDOT Requested TransGuide software on October 4, 2004.• FDOT Received TransGuide software on October 19, 2004.
December 7, 2004SunGuide Status Meeting 7
License Updates - continuedLicense Updates - continued
FDOT / WsDOT Term of Use (TOU):
– WsDOT provided FDOT with standard TOU on February 11, 2004.
– FDOT provided recommendation on to WsDOT on March 13, 2004.
– FDOT provided comments to the WsDOT’s Office of General Counsel’s August 21, 2004.
– WsDOT began working on FDOT’s comments on August 26, 2004.
– FDOT requested status on September 14, 2004, October 7, 2004 and November 5, 2004.
– FDOT & WsDOT attorneys and project managers had teleconference on November 30, 2004.
December 7, 2004SunGuide Status Meeting 8
License Updates - continuedLicense Updates - continued
FDOT / MDX Joint Program Agreement (JPA)
– FDOT provided MDX with preliminary JPA on December 3, 2003.
– MDX provided FDOT with draft final JPA on June 23, 2004.
– FDOT worked on Locally Funded Agreement and MDX JPA.
– FDOT forwarded updated JPA and sublicense to MDX on October 26, 2004
– MDX concerned about software support, FDOT developed a draft software support requirements.
December 7, 2004SunGuide Status Meeting 9
License Updates - continuedLicense Updates - continued
SwRI / FDOT / Lee County Sublicense
– Lee County provided FDOT with official letter for participation on July 27, 2004
– FDOT and SwRI started documentation preparation on July 30, 2004
– SwRI provided FDOT with draft language on September 10, 2004
– FDOT forwarded sublicense to Lee County on October 26, 2004
FDOT issued iFlorida Data Collection Process (DCP) notice to proceed on September 8, 2004.
GDT License:
– System Planning Office and Office of Information Systems are finalizing the license agreement on September 14, 2004.
– Kevin Thibault approved the $130,000 GDT Procurement on October 19, 2004
December 7, 2004SunGuide Status Meeting 10
License Updates - License Updates - Oracle Oracle continuedcontinued
Transportation Management Center Date Required OIS Licensed Processor Current License Duration
District 1 Ft. Myers RTMC Sun 12/31/06
District 1 Sarasota RTMC Sat 12/31/11
District 2 Jacksonville RTMC Sun 12/31/06 2 10/3/03 to 10/3/08
District 3 Pensacola RTMC Mon 12/31/07
District 3 Tallahassee RTMC Wed 12/31/08
District 4 Ft. Lauderdale RTMC Mon 1/31/05 2 10/3/03 to 10/3/08
District 4 West Palm RTMC Mon 12/31/12
District 5 Orlando RTMC Mon 12/31/07 4 Required with RAC in December 2004 for iFlorida
District 6 Miami RTMC Thu 6/30/05 2 10/3/03 to 10/3/08
District 7 Tampa RTMC Sun 4/30/06 2 10/3/03 to 10/3/08
Lee County RTMC Sat 12/31/05
Miami-Dade Expressway RTMC Thu 6/30/05
Statewide TMC & Testing Lab Tue 5/31/05 2 10/3/03 to 10/3/08
Turnpike Pompano RTMC Mon 12/31/12
Turnpike Turkey Lake RTMC Mon 12/31/12
December 7, 2004SunGuide Status Meeting 11
AgendaAgenda
Time Item Lead
1:00 – 1:05 Introductions Liang Hsia
1:05 – 1:15 License Updates:
- TxDOT and FDOT - Lee County
- TransGuide - SwRI/FDOT Modification
- WSDOT TOU - GDT
- MDX JPA - Oracle
Liang Hsia
1:15 – 1:25 TMC and Software Deployment Schedule Updates D1 D2 D3 D4 D5 D6 D7 MDXTurnpike EnterpriseLee County
1:25 – 1:45 Project Status Report Steve Dellenback
1:45 – 1:50 Canoga Device Driver Update Steve Dellenback
1:50 – 2:00 Software Deployment Process Steve Dellenback
2:00 – 2:05 Web Server Prototype Screens Steve Dellenback / Robert Heller
2:05 – 2:10 Emergency Evacuation Prototype Screens Steve Dellenback / Robert Heller
2:10– 2:15 Open Discussion / Action Item Summary All
December 7, 2004SunGuide Status Meeting 12
Reports by Deployment and Reports by Deployment and Possible Integration SchedulePossible Integration Schedule
District 4
District 6
MDX
District 7
District 1
Lee County
District 2
District 5
District 3
Turnpike Enterprise
December 7, 2004SunGuide Status Meeting 13
District 4 Milestone DemonstrationDistrict 4 Milestone Demonstration
December 7, 2004SunGuide Status Meeting 14
District 4 ScheduleDistrict 4 Schedule
September 2004 District 4 moves equipment to new TMC
October 12, 2004 SunGuideSM Software Team performs Milestone Demonstration
December 2004 I95/I595 Video Monitoring Project Starts.
December 2004 SunGuideSM Software Team provides TMC operators with software training
December 7, 2004SunGuide Status Meeting 15
District 4 ScheduleDistrict 4 Schedule
January 2005 SunGuideSM Software Team sets upthe District 4 software
January 2005 District 4 TMC Grand Opening
January 2005 Complete I 95/I 595 Video Monitoring and
Detector System
December 7, 2004SunGuide Status Meeting 16
District 6 RTMCDistrict 6 RTMC
December 7, 2004SunGuide Status Meeting 17
District 6 ScheduleDistrict 6 Schedule
June 25, 2004 New TMC Grand Opening
April 2005 Ramp metering subsystem to be installed and tested
June 2005 SunGuideSM Software Release 2deployment includes Ramp metering system
July 2005 I-95 Package B project completion
December 7, 2004SunGuide Status Meeting 18
MDX ScheduleMDX Schedule
April 7, 2003 MDX sent letter to ITS Office aboutparticipating in SunGuideSM Project
April 25, 2003 FDOT Responded, Welcoming MDX’s
participation
December 3, 2003 FDOT provided MDX with a draft Joint Program Agreement
June 2005 SunGuideSM Software Release 2 deployment at MDX
October 2005 MDX TMC Operational
December 7, 2004SunGuide Status Meeting 19
District 7 RTMCDistrict 7 RTMC
November 2005 Building Construction FinishApril 2006 SunGuideSunGuideSM Software Deployment
December 7, 2004SunGuide Status Meeting 20
District 2 RTMCDistrict 2 RTMC
FY 2004FY 2004 I-95 N ITS ImprovementI-95 N ITS ImprovementFY 2006FY 2006 SunGuideSunGuideSM Deployment (Tentative)Deployment (Tentative)
December 7, 2004SunGuide Status Meeting 21
District 5 RTMCDistrict 5 RTMCFY 2004FY 2004 Orlando RTMC retrofit and upgrade Orlando RTMC retrofit and upgradeSeptember 8, 2004 -September 8, 2004 - iFlorida Data Collection Process iFlorida Data Collection ProcessDecember 2005 December 2005 FY 2004-2005FY 2004-2005 iFlorida C2C between Districts 2 and 5 iFlorida C2C between Districts 2 and 5
December 7, 2004SunGuide Status Meeting 22
Turnpike RTMCTurnpike RTMC
December 7, 2004SunGuide Status Meeting 23
Turnpike ScheduleTurnpike Schedule
March 2004 SunNav 1.1 Test
April 2004 SunNav 1.2 Development
June 2005 Observe D 4, D 6, & MDX C2C Deployment
December 7, 2004SunGuide Status Meeting 24
District 1District 1
May 2005 May 2005 I-75 Safety Barrier System upgrade I-75 Safety Barrier System upgrade December 2006 December 2006 SunGuideSunGuideSM Deployment at Ft. Myers RTMC Deployment at Ft. Myers RTMC FY 2011 (2005) FY 2011 (2005) Sarasota RTMCSarasota RTMC
December 7, 2004SunGuide Status Meeting 25
District 3District 3
FY 2007 Pensacola RTMC FY 2007 Pensacola RTMC FY 2008 Tallahassee RTMCFY 2008 Tallahassee RTMC
December 7, 2004SunGuide Status Meeting 26
Lee County Bridge Incident Lee County Bridge Incident ManagementManagement
July 27, 2004 Lee County Public Works sent letter to FDOT
indicating Lee County’s participation in
SunGuide Software Project
December 7, 2004SunGuide Status Meeting 27
C2C ScheduleC2C Schedule
February 16, 2004 SunGuideSM and C2C Project Team completed Interface Control Document (ICD)
February 20, 2004 SunGuideSM and C2C Project Coordination Teleconference
March 9, 2004 SunGuideSM & C2C Project Coordination Meeting
June, 2005 C2C deployment among Districts 4, 6, and MDX
December 7, 2004SunGuide Status Meeting 28
AgendaAgenda
Time Item Lead
1:00 – 1:05 Introductions Liang Hsia
1:05 – 1:15 License Updates:
- TxDOT and FDOT - Lee County
- TransGuide - SwRI/FDOT Modification
- WSDOT TOU - GDT
- MDX JPA - Oracle
Liang Hsia
1:15 – 1:25 TMC and Software Deployment Schedule Updates D1 D2 D3 D4 D5 D6 D7 MDXTurnpike EnterpriseLee County
1:25 – 1:45 Project Status Report Steve Dellenback
1:45 – 1:50 Canoga Device Driver Update Steve Dellenback
1:50 – 2:00 Software Deployment Process Steve Dellenback
2:00 – 2:05 Web Server Prototype Screens Steve Dellenback / Robert Heller
2:05 – 2:10 Emergency Evacuation Prototype Screens Steve Dellenback / Robert Heller
2:10– 2:15 Open Discussion / Action Item Summary All
December 7, 2004SunGuide Status Meeting 29
Project Web SiteProject Web Site
http://sunguide.datasys.swri.edu
December 7, 2004SunGuide Status Meeting 30
Release-Oriented Release-Oriented Development ApproachDevelopment Approach
December 7, 2004SunGuide Status Meeting 31
Status of Release 1 Development Status of Release 1 Development ActivitiesActivities
Efforts complete:– Core software framework:
• Database• User administration• Executive handler• Status logger• User interface• Map• Data Bus
– DMS:• General Subsystem• NTCIP Florida MIB driver• Mark IV version 2.5 driver
– CCTV Control:• General Subsystem• NTCIP 1205 driver
– Video Switching• General Subsystem• IP Video switching driver
Efforts complete (continued):– Video Wall
• General Subsystem• Barco/Argus video wall driver
Traffic Detection, driver for:• General Subsystem• Bitrans B238-I4 driver• RTMS (EIS and Wavetronix)
driver
Efforts still ongoing:– Incident Management:
• GUI• Subsystem
– Integration Testing– Documentation– Training Material
December 7, 2004SunGuide Status Meeting 32
Status of Release 2 ActivitiesStatus of Release 2 Activities
Ramp Metering:– Design completed– Initial GUI design completed– Coding in process
Emergency Evacuation:– Screen prototypes developed– Design initiated
Data Archive– Requirements refined– Design Completed– Development initiated
Web Server– Requirements refined– Design initiated
HAR– Requirements refined– Design initiated
Center-to-Center– Requirements refined– Design initiated
RWIS– Requirements refined– Design initiated
Inventory and Maintenance– Requirements to be refined
Optional Service:– iFlorida Data Collection
Process (DCP)
December 7, 2004SunGuide Status Meeting 33
Deliverable StatusDeliverable Status
SwRI waiting for FDOT comments:– Concept of Operations– Version Description Document– Software User’s Manual– Software Integration Case Procedures
Future documents to be provided by SwRI:– Software Integration Case Procedures (final version)– Software User’s Manual (final version)– Software Design Document (final version)– District 4 Deployment Plan (draft and final version)
All documents delivered to FDOTare available on the project web site.
http://SunGuide.datasys.swri.edu
December 7, 2004SunGuide Status Meeting 34
Cost StatusCost Status
Release 1:– Budget amount: $3,925,789– As of 11/19/04, ~$3,496,000 has been expended
Release 2:– Budget amount: $2,601,310– As of 11/19/04, ~$342,000 has been expended
Adjustments:– Reductions (funds back to FDOT):
• Eliminating DTS Efforts: $75,009.71• Combining 2a and 2b: $66,827.29 (this includes a “training
adjustment” to add classes) – Additions:
• iFlorida DCP Task: $64,531.00 • Distinct 4 Message Rules: $30,854.32 • Safety Barrier Subsystem: $146,992.90 (not yet in development)
December 7, 2004SunGuide Status Meeting 35
Spending CurveSpending Curve
December 7, 2004SunGuide Status Meeting 36
Schedule StatusSchedule Status
Current areas of concern:– Documents:
• None
– Software:• None
Deployments:– District 4 tentatively scheduled for week of January
24, 2005 but this will likely be updated to meet District 4’s requirements
December 7, 2004SunGuide Status Meeting 37
Schedule Status – continuedSchedule Status – continuedLast Reporting PeriodLast Reporting Period
December 7, 2004SunGuide Status Meeting 38
Schedule Status - continuedSchedule Status - continuedCurrent Reporting PeriodCurrent Reporting Period
December 7, 2004SunGuide Status Meeting 39
Schedule Status - continuedSchedule Status - continued
Integration/Testing:– Proceeding well– Continuing long term “endurance” testing
“Factory” Acceptance Testing:– Week of January 10, 2005 in San Antonio
Future status meetings that need to be scheduled:– January– February– March
Future reviews that need to be scheduled:– Release 2 Software Design Review: sometime early 2005, will
be held once other Release 1 and Release 2 enhancement requests are complete
December 7, 2004SunGuide Status Meeting 40
AgendaAgenda
Time Item Lead
1:00 – 1:05 Introductions Liang Hsia
1:05 – 1:15 License Updates:
- TxDOT and FDOT - Lee County
- TransGuide - SwRI/FDOT Modification
- WSDOT TOU - GDT
- MDX JPA - Oracle
Liang Hsia
1:15 – 1:25 TMC and Software Deployment Schedule Updates D1 D2 D3 D4 D5 D6 D7 MDXTurnpike EnterpriseLee County
1:25 – 1:45 Project Status Report Steve Dellenback
1:45 – 1:50 Canoga Device Driver Update Steve Dellenback
1:50 – 2:00 Software Deployment Process Steve Dellenback
2:00 – 2:05 Web Server Prototype Screens Steve Dellenback / Robert Heller
2:05 – 2:10 Emergency Evacuation Prototype Screens Steve Dellenback / Robert Heller
2:10– 2:15 Open Discussion / Action Item Summary All
December 7, 2004SunGuide Status Meeting 41
Canoga Loop BackgroundCanoga Loop Background
Limitations of older 3M devices: must poll the device often (essentially every vehicle):– C822/C824– C922/C924 (new version of the above)
3M has a newer product:– "Traffic Monitoring Card (TMC)“ - numbered as 942/944– Provides the capability to establish a monitoring interval
in the range of 1 second to 15 minutes
3M sent email to FDOT on 11/10/2004 indicating that 3M would upgrade all of MDX’s units to the “TMC” configuration
SunGuideSM TSS driver will only support the TMC card
December 7, 2004SunGuide Status Meeting 42
AgendaAgenda
Time Item Lead
1:00 – 1:05 Introductions Liang Hsia
1:05 – 1:15 License Updates:
- TxDOT and FDOT - Lee County
- TransGuide - SwRI/FDOT Modification
- WSDOT TOU - GDT
- MDX JPA - Oracle
Liang Hsia
1:15 – 1:25 TMC and Software Deployment Schedule Updates D1 D2 D3 D4 D5 D6 D7 MDXTurnpike EnterpriseLee County
1:25 – 1:45 Project Status Report Steve Dellenback
1:45 – 1:50 Canoga Device Driver Update Steve Dellenback
1:50 – 2:00 Software Deployment Process Steve Dellenback
2:00 – 2:05 Web Server Prototype Screens Steve Dellenback / Robert Heller
2:05 – 2:10 Emergency Evacuation Prototype Screens Steve Dellenback / Robert Heller
2:10– 2:15 Open Discussion / Action Item Summary All
December 7, 2004SunGuide Status Meeting 43
Deployment ActivitiesDeployment Activities
For each deployment, an “Implementation Plan” will be developed
Deployment will take a significant amount of effort from the District
During contract negotiations, FDOT greatly reduced installation costs to meet overall budget restrictions:
– As proposed by SwRI: $1,059,993
– As approved by FDOT: $397,292
December 7, 2004SunGuide Status Meeting 44
FDOT ResponsibilitiesFDOT Responsibilities
Review SunGuide documentation:– SRS– VDD– SUM– Implementation Plan– Test procedures
Computer/Network hardware:– Computer installation and setup, includes:
• Servers (Windows Server 2003, Service Releases, Oracle)• Workstations (Windows XP, Service Releases, Adobe SVG)
– Network installation and setup– Windows domain controller
Devices– Device installation and setup (verify with vendor master software)– TCP/IP access to all devices (except dialup DMS devices)– Collect device configuration information (see device data collection
slide) During installation (must be available throughout software installation – no
distractions or other obligations)– Lead system administrator– Lead operator
December 7, 2004SunGuide Status Meeting 45
SunGuideSunGuideSMSM Development Team Development Team ResponsibilitiesResponsibilities
Develop installation plan: Prior to software installation:
– Verify computer setup and connectivity– Verify device connectivity
Software installation– Install SunGuideSM software– Configure (this will require FDOT assistance):
• IIS (Web Server)• SunGuide general configuration• Device configuration (e.g. DMS, CCTV, Video Wall, IP-Video, TSS)• Links configuration• Lanes configuration• Roadways configuration• Cross Streets configuration• Alternate Routes configuration• Contacts configuration• Resources Configuration
– Test utilizing SunGuideSM testing documents Training
– Provide training classes (3 classed defined)– Provide on-site support immediately after install
December 7, 2004SunGuide Status Meeting 46
Sample Device Forms: DMSSample Device Forms: DMS
December 7, 2004SunGuide Status Meeting 47
SwRI Funded Deployment SwRI Funded Deployment Activities (per BAFO)Activities (per BAFO)
District 4 and District 6 installations:– Site survey– Develop implementation plan– One (1) week of installation on-site (2 staff)– One (1) week of acceptance testing on-site (2 staff)
Others installations:– Site survey– Develop implementation plan– 1 week of support on-site (1 staff)
General Support Task– A support task exists for each FY through 6/2012– Level of effort varies from 504 to 1,061 hours a FY
December 7, 2004SunGuide Status Meeting 48
AgendaAgenda
Time Item Lead
1:00 – 1:05 Introductions Liang Hsia
1:05 – 1:15 License Updates:
- TxDOT and FDOT - Lee County
- TransGuide - SwRI/FDOT Modification
- WSDOT TOU - GDT
- MDX JPA - Oracle
Liang Hsia
1:15 – 1:25 TMC and Software Deployment Schedule Updates D1 D2 D3 D4 D5 D6 D7 MDXTurnpike EnterpriseLee County
1:25 – 1:45 Project Status Report Steve Dellenback
1:45 – 1:50 Canoga Device Driver Update Steve Dellenback
1:50 – 2:00 Software Deployment Process Steve Dellenback
2:00 – 2:05 Web Server Prototype Screens Steve Dellenback / Robert Heller
2:05 – 2:10 Emergency Evacuation Prototype Screens Steve Dellenback / Robert Heller
2:10– 2:15 Open Discussion / Action Item Summary All
December 7, 2004SunGuide Status Meeting 49
Web ServerWeb Server
Developing prototype screens
– Using FDOT guidelines
– Significant limitations:
• 600 pixel wide displays
Reusing much of the SunGuideSM Operator map (SVG based map) on the web server
December 7, 2004SunGuide Status Meeting 50
Web Server: Initial OverviewWeb Server: Initial Overview
December 7, 2004SunGuide Status Meeting 51
Web Server: Selecting a RegionWeb Server: Selecting a Region
December 7, 2004SunGuide Status Meeting 52
Web Server: Map RepositioningWeb Server: Map Repositioning
December 7, 2004SunGuide Status Meeting 53
Web Server: Snapshots and DMSWeb Server: Snapshots and DMS
December 7, 2004SunGuide Status Meeting 54
Web Server: Incident and DMS Web Server: Incident and DMS DataData
December 7, 2004SunGuide Status Meeting 55
Web Server: Traffic Speed and Web Server: Traffic Speed and Weather DataWeather Data
December 7, 2004SunGuide Status Meeting 56
AgendaAgenda
Time Item Lead
1:00 – 1:05 Introductions Liang Hsia
1:05 – 1:15 License Updates:
- TxDOT and FDOT - Lee County
- TransGuide - SwRI/FDOT Modification
- WSDOT TOU - GDT
- MDX JPA - Oracle
Liang Hsia
1:15 – 1:25 TMC and Software Deployment Schedule Updates D1 D2 D3 D4 D5 D6 D7 MDXTurnpike EnterpriseLee County
1:25 – 1:45 Project Status Report Steve Dellenback
1:45 – 1:50 Canoga Device Driver Update Steve Dellenback
1:50 – 2:00 Software Deployment Process Steve Dellenback
2:00 – 2:05 Web Server Prototype Screens Steve Dellenback / Robert Heller
2:05 – 2:10 Emergency Evacuation Prototype Screens Steve Dellenback / Robert Heller
2:10– 2:15 Open Discussion / Action Item Summary All
December 7, 2004SunGuide Status Meeting 57
Emergency Evacuation: Emergency Evacuation: Web Site Design Concept OverviewWeb Site Design Concept Overview
The EE Web site is separate from SunGuide travel conditions Web site
The sites will have links to each other
Only the data presentation is shown and not the data entry interface
A separate administration interface will be part of the Web site
December 7, 2004SunGuide Status Meeting 58
Emergency Evacuation: Emergency Evacuation: Entry ScreensEntry Screens
December 7, 2004SunGuide Status Meeting 59
Emergency Evacuation: Emergency Evacuation: Evacuation ZonesEvacuation Zones
December 7, 2004SunGuide Status Meeting 60
Emergency Evacuation: Emergency Evacuation: Various InformationVarious Information
December 7, 2004SunGuide Status Meeting 61
AgendaAgenda
Time Item Lead
1:00 – 1:05 Introductions Liang Hsia
1:05 – 1:15 License Updates:
- TxDOT and FDOT - Lee County
- TransGuide - SwRI/FDOT Modification
- WSDOT TOU - GDT
- MDX JPA - Oracle
Liang Hsia
1:15 – 1:25 TMC and Software Deployment Schedule Updates D1 D2 D3 D4 D5 D6 D7 MDXTurnpike EnterpriseLee County
1:25 – 1:45 Project Status Report Steve Dellenback
1:45 – 1:50 Canoga Device Driver Update Steve Dellenback
1:50 – 2:00 Software Deployment Process Steve Dellenback
2:00 – 2:05 Web Server Prototype Screens Steve Dellenback / Robert Heller
2:05 – 2:10 Emergency Evacuation Prototype Screens Steve Dellenback / Robert Heller
2:10– 2:15 Open Discussion / Action Item Summary All
December 7, 2004SunGuide Status Meeting 62
Action Item RecapAction Item Recap
Number Person Action
56
57
58
59