nur aqila e’zzany binti kamarulzamandocshare01.docshare.tips/files/23710/237106501.pdf · - ramp...
TRANSCRIPT
NUR AQILA E’ZZANY BINTI KAMARULZAMAN
NUR AZIMAH ADILA BINTI MOHD SHUKRI
SAKINAH KHALIDAH BINTI KAHARUDDIN
SITI NADIRAH BINTI JAMIL
INTRODUCTION Definition Basement:
• A basement excavation is a construction dig.
• There are several common method of excavation, in order to build basement.
• Essential that the excavation is adequately supported, and the groundwater properly controlled.
SELECTION OF EXCAVATION FOR BASEMENT CONSTRUCTION
Subsoil conditions and ground water
level
Working space requirements and site
constraints
Maintenance of the wall and support
system in permanent condition
Cost and times of construction
Local experience and available
construction plant
TYPES OF EXCAVATION
FOR BASEMENT
CONSTRUCTION
DIAPHRAGM WALL
SHEET PILE
WALL
CONTIGUOUS BORED PILES
WALL
SECANT PILES
a form of driven piling using thin interlocking
sheets of steel.
Used vibrating hammer, t-crane and crawler
drilling to establish it
suitable for sites where the space around the
excavation is insufficient for sloping back the
sides
SHEET PILE WALL
SHEET PILE WALL It consist of rolled steel sections with interlocking
edge joints
The interlocking edges allow each sheet pile to
slide into the next with relative ease.
ADVANTAGES DISADVANTAGES
Rapid installation Direct driving effect on the subsoil
Steel can be either permanent or recovered
Noisy
very economical compare with the alternative of a diaphragm wall
High capital investment if re-usage is restricted
Seal may not be perfect
Constructed by excavation in a trench which
temporarily supported by bentonite slurry.
Suitable for :
• sites where obstructions in the ground prevent sheet
piles from being driven where the occurrence of
groundwater is unfavorable for other methods of
support.
• Also suitable for sites where considerations of noise
and vibration
On reaching founding level steel reinforcement is
lowered into the trench, followed by concrete to
displace the bentonite
DIAPHRAGM WALL
ADVANTAGES DISADVANTAGES
Permanent basement wall A lot of labour is needed
Scan be designed to form part of a permanent foundation
Long period of construction
Minimum vibration and noise
High cost
Can be used in restricted space
CONTIGUOUS PILE WALL
• line of bored pile installed close together or touching.
• Smaller diameter micro-pile may be installed in between each adjacent pile.
• Gaps between the micro-pile
and main piles are grouted.
Advantages
Disadvantages
Built-up areas where noise and vibration should be
limited
Concrete in shaft susceptible to squeezing or
necking in soft soil where conventional types are
used
In industrial complexes where access, headroom
and/or restriction on vibration may make other
methods such as steel sheet piling or diaphragm
walling less suitable
Special techniques needed for concreting in water
bearing soils
Lower cost
Concrete can be readily inspected after installation
Speed in construction for temporary and
permanent wall where drilling conditions are
conducive
Drilling a number of pile in group may cause loss of
ground and settlement of adjacent structures
Higher capacity to overcome obstruction like rock
compare to other system
Additional work are needed to form an acceptable
surface to the wall
Drilling tools can be break up boulders or other
obstructions
Lack of water tightness
Secant pile • similar to contiguous bored piles except that
they are constructed in:
- male
- female
• interlock each other.
• male piles are reinforced while the female piles are not.
• In cases where lateral pressure from the soil is excessively high, male-male secant piles may be used.
Advantages
Disadvantages
- Provide higher degree of water
tightness
- High cost for installation
- Stronger resistance to lateral
pressure
- Ensuring complete contact of all
piles over their full length
- Can be used on small and
confined sites
- May be difficult in practice
- Suitable to built near building,
roads and other sensitive
structures
- Minimum noise and vibration
CONTRACT TITTLE Purpose to build 33 storey office tower developed by KL Sentral & MRCB for Lembaga Tabung Haji SCOPE OF WORKS 1 BLOCK OFFICE WHICH CONSISTS OF : - 3 levels of basement parking - 2 levels of Main lobbies - 5 levels of elevated car parks - 1 level of M&E Floor - 20 levels of Offices - 2 levels of Penthouse
PROJECT BRIEFING
- Location of site : KL Sentral - Located at congested area ( Putra,KTM,Erl station,shop lots building, private parking area,hotel, office building, etc ) - The land is existed flat - According to soil engineer, type of soil consist : sandy clay, silty clay, silty sand, shale and shale rock. - It was busy area – within working hours
NATURE OF SITE
METHOD STATEMENT OF
BASEMENT WORKS SURVEY STAGE - Land surveyor play their role the original ground level and set out control point SITE CLEARING - demolition of existing building – small shop building - grubbing out bushes, trees and removal soil to reduce level - After site clear - hoarding, wash trough, storage and temporary site office
CONSTRUCTION OF DIAPHRAGM WALL AND CONTIGUOUS BORED PILE - two type of retaining wall has decided by engineer – diaphragm wall and contiguous bored pile. - use existing diaphragm wall – save cost and limited space ( refer layout plan) - reason : if build new diaphragm wall, ground anchor fixed to diaphragm wall will disturbed the foundation of existing building - use contiguous bored piled - For perimeter area – did not have existing building - Bored piled : - total used : 260 nos - size : 750 mm - depth : 16 m - gap : 75 mm - use helical reinforcement - I machine can build only 2 bored pile in one day – have 4 machine at site - after completion, use concrete 200 mm thk – as skin wall + waterproofing - advantages using contig.bored pile : It is free standing – didn’t use anchor
EXCAVATION - after completion of diaphragm wall and contiguous bored pile, excavate basement. - excavate 10.00 m depth - use 1m3 bucket excavator. - ramp system – purpose of transportation – loading and unloading construction material.( refer figure 5.19 ) - the ramp will remove after excavation process. - temporary opening – entering excavation area ( refer figure 5.20 )
CONSTRUCTION TECHNOLOGY IV - BASEMENT
CONSTRUCTION BASEMENT FOUNDATION - use raft foundation as a foundation - depth : 2.75 m - size of reinforcement : 25 mm , 32 mm - concreting process – concrete + ice cube – low the temperature - reason use raft foundation : - carry a great load - soil hard material at site
View 1 raft foundation construction
CONSTRUCTIONN OF BASEMENT FRAME AND STRUCTURE
- method of construction : bottom up method ( refer figure below ) - starting by construction of basement column - start from B1 - B2 – B3 - construction including concrete, formwork , reinforcement
Construction of Basement Frame
BACKFILLING - after completion of basement frame – backfilling process - backfilling process – by stage - after completion of B3, contractor constructing B2 level – backfilling process proceed at level B3 - repeat backfilling sequence – until upper level
Backfilling the remaining excavated area
COMPLETE BASEMENT - after backfilling process –structural work for basement completely finished - proceed upper level construction – floor , wall, etc.
Complete Basement
This property is a detached Victorian house in Hampstead, which had no existing cellar, a
timber suspended floor and an existing partial lower ground floor. London Basement were
asked to carry out the construction of a basement below the house and rear and side patio’s,
creating an area of 196M² (2109 sq.ft.), with a head height of 3M below the house and 2.9M
below the patio’s.
As you will see from the artist’s rendition, the majority of the basement space was to be used
as an Art Gallery.
The property had a part timber suspended, part solid floor and our clients lived in the
property throughout the works, which took approx. 30 weeks.
Two conveyors belts were installed from the areas of excavation into the skip situated on the
road.
Initially we carried out the design and installation of the temporary works required to support
the existing building structure. This involved the installation of a series of cantilever needle
beams passing through the external walls, at critical load points, supported on temporary
compression piles placed adjacent to the external walls. This enabled us to be able to break
out the existing foundations and replace them with the new designed steel support system.
conclusion Whichever method supporting basement chosen
and any consideration will have to be given to additional measures to achieve good performance corresponding to modern consumer expectations.