project rehabilitation report of amarja dam,
TRANSCRIPT
Project Rehabilitation Report of Amarja Dam
Project Rehabilitation Report
of Amarja Dam, Karnataka Water Resources Department
Doc. No.: CDSO_DSR_PRR_ KA06HH0199_KaWRD_v1.0
July 2019
Central Water Commission
Ministry of Water Resources,
River Development & Ganga Rejuvenation
Government of India
Project Rehabilitation Report of Amarja Dam
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Amarja Dam
Quality Control:
Version Date Writers/Contributors Checked by
1 31/06/2019 Dr. Hadush S Hagos (HSH) Pankaj Kumar Awasthi (PKA Anil Kumar Verma (AKV)
Rajiv Kumar Sawarn
Issued/Copied to:
I/C Date Name Organisation
Issued 08/07/2019 Shri. Pramod Narayan Central Water Commission
Project Rehabilitation Report of Amarja Dam
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Amarja Dam
Abbreviations
DRIP Dam Rehabilitation & Improvement Project
CWC Central Water Commission
CPMU Central Project Management Unit
CSV Construction Site Visit
SPMU State Project Management Unit
IA Implementation Agency
PIC Project Identification Code
DSRP Dam Safety Review Panel
PST Project Screening Template
DFR Design Flood Review
MSL Mean Sea Level
FRL Full Reservoir Level
MWL Maximum Water Level
TBL Top Bund Level (Top Level of Dam)
MDDL Maximum Draw Down Level
LSL Lowest Sill Level
DSL Dead Storage Level
U/S Upstream
D/S Downstream
El. Elevation
L/B Left Bank
R/B Right Bank
PMF Probable Maximum Flood
SPF Standard Project Flood
CD Works Cross Drainage Works
VRB Village Road Bridge
WBM Water Bound Macadam
NDT Non Destructive Testing
DHARMA Dam Health And Rehabilitation Monitoring Application
O & M Operation and Maintenance
EAP Emergency Action Plan
Project Rehabilitation Report of Amarja Dam
ESMF Environmental and Social Management Framework
E & S specialists Environmental and Social Specialists
HM Works Hydro-Mechanical Works
EM Works Electro-Mechanical Works
SCADA Supervisory Control and Data Acquisition System
DG Set Diesel Generator Set
MW Mega Watt
MU Million units
Ha Hectare
MCM Million Cubic Metre
Deg. Degree
Min. Minute
Sec. Second
CM Construction management
QC Quality control
m meter
m3 Cubic meter
m3/sec Cubic meter per second
Km2 Square kilometre
Mcm Million cubic meter
TNWRD Tamil Nadu Water Resource Department
TANGEDCO Tamil Nadu Generation and Distribution Corporation
KWRD Kerala Water Resource Department
KSEB Kerala State Electricity Board
MPWRD Madhya Pradesh Water Resource Department
UJVNL Uttarakhand Jal Vidyut Nigam Limited
DVC Damodar Valley Corporation
Project Rehabilitation Report of Amarja Dam
DRIP Component Wise Project Cost
KaWRD Initial/Revised Projects & Cost
BACKGROUND
In April 2012, the Central Water Commission
(CWC) with assistance from the World Bank,
embarked upon a six year Dam
Rehabilitation and Improvement Project
(DRIP) at a preliminarily estimated initial cost
of Rs.2100 Crore targeting rehabilitation and
improvement of about 250 dams initially of
six, later of nine implementing agencies -
namely: MPWRD, OWRD, TNWRD,
TANGEDCO, KWRD, KSEB, KaWRD,
UJVNL and DVC.
In June 2018, the project was extended by
two years, until June 2020. The current
revised cost for DRIP is Rs.3466 Crore out of which Rs. 2920.5 Crore is allocated for
Component 1 (Rehabilitation and Improvement of Dams and Associated Appurtenances),
Rs.232.5 Crore for Component 2 (Dam Safety Institutional Strengthening), and Rs.313 Crore
for Component 3 (Project Management). Appropriate assistance is also provided under
DRIP to develop O & M Manuals and Emergency Action Plans (EAP) for these dams. The
project also promotes new technologies and improves institutional capacities for dam safety
evaluation and implementation at the Central and State levels as well as in some identified
premier academic and research institutes in the country. The actual total number of dams
under DRIP stands at 223.
The Implementing Agencies for DRIP are the Water Resources Departments and State
Electricity Boards in the participating States and Damodar Valley Corporation (DVC) with
Central Water Commission at Central Level. State Implementing Agencies are responsible
for implementation of works of dams under their charge. Co-ordination and management of
such works within a State rests with the
concerned State Project Management
Unit (SPMU). Overall project oversight
and coordination is carried out by Central
Project Management Unit (CPMU) headed
by the Project Director with assistance of
an Engineering and Management
Consultant.
Karnataka Water Resource Department
(KaWRD) joined DRIP in August 2014
with initial number of dams totalling 31.
Later, KaWRD dropped 9 dams and
continuing in DRIP with 22 dams.
Preliminarily estimated initial DRIP project
cost for KaWRD was Rs.276.1 Crore and
the revised actual current project cost is
Rs.581.2 Crore.
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Amarja Dam
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Amarja Dam
Table of Contents
Abbreviations ........................................................................................................... 5
1. EXECUTIVE SUMMARY .................................................................................. 1
2. PROJECT DETAILS ......................................................................................... 2
2.1 Project Description .......................................................................................................... 2
2.2 Project Location ............................................................................................................... 2
2.3 Project Benefits ................................................................................................................ 3
2.4 Dam and Reservoir Features (Before rehabilitation under DRIP) ............................... 3
2.5 Any Emergency Spillway, Fuse Plug etc. ...................................................................... 4
2.6 Details of previous dam incidents, if any ...................................................................... 4
2.7 PST Details ....................................................................................................................... 5
2.8 DSRP, CPMU and World Bank Recommendations and Compliance ......................... 5
2.9 Scope of Rehabilitation Works as per PST ................................................................... 5
2.10 Drawings ......................................................................................................................... 14
3. DAM VISITS (PST STAGE) ............................................................................ 21
3.1 Dam Inspections ............................................................................................................ 21
3.2 Summary of observations made by CPMU ................................................................. 21
4. DESIGN FLOOD REVIEW (DFR) ................................................................... 21
4.1 DFR Outcome ................................................................................................................. 21
4.2 Brief Summary of Review.............................................................................................. 21
4.3 Recommendations ......................................................................................................... 22
5. REHABILITATION WORKS CARRIED OUT ................................................. 22
5.1 Summary of Investigations ........................................................................................... 22
5.2 Main Dam Works ............................................................................................................ 22
5.3 Basic facilities ................................................................................................................ 23
6. INSTRUMENTATION ..................................................................................... 23
6.1 List of existing instruments installed in dam and their condition ............................ 23
6.2 Details of new instruments installed ........................................................................... 23
6.3 CPMU Recommendations ............................................................................................. 23
7. PROCUREMENT OF WORKS ....................................................................... 24
7.1 Package wise details ..................................................................................................... 24
7.2 Details of Bidding Process ........................................................................................... 25
7.3 Reason for Variation, if any .......................................................................................... 25
7.4 Litigation / Arbitration, If Any ....................................................................................... 25
8. THIRD PARTY CONSTRUCTION SUPERVISION VISITS BY CPMU ........... 25
Project Rehabilitation Report of Amarja Dam
8.1. Summary of Visits undertaken .................................................................... 25
8.2. Summary of Third Party Material Testing ................................................... 25
8.3. Summary of Major Recommendations ........................................................ 25
8.4. Summary of Compliance by SPMU ............................................................. 29
8.5. Special Visits made by CWC/World Bank/Expert Committee ................... 29
8.6. Summary of Technical Assistance provided by CPMU ............................. 29
9. ENVIRONMENTAL AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) 29
9.1 Basic Details ................................................................................................................... 29
9.2 Summary of Observations ............................................................................................ 30
9.3 Details of ESMF/EIA study (if any) ............................................................................... 30
10. OTHER NON-STRUCTURAL INTERVENTIONS ........................................... 30
10.1 Basic Details ................................................................................................................... 30
10.2 Summary of Observations ............................................................................................ 30
11. PENDING REHABILITATION WORKS .......................................................... 30
11.1 Details of pending works .............................................................................................. 30
11.2 Further course of action................................................................................................ 30
12. REFERENCES ............................................................................................... 31
Annex A: PST Approval Letter .............................................................................. 33
Annex B: Drawings issued for Rehabilitation measures .................................... 39
Annex C: Completion Certificate .......................................................................... 45
Annex D: Third Party QC Tests ............................................................................. 53
Annex E: ESMF OK Card ....................................................................................... 61
Annex F: Photographs Before and After Rehabilitation Works ......................... 65
Annex G: DBA and Inundation Maps .................................................................... 77
LIST OF FIGURES
Figure 2-1: Index Map of Amarja Dam. ............................................................................... 14
Figure 2-2: Google Map of Amarja Dam. ............................................................................. 15
Figure 2-3: Water Catchment Map of Amarja Dam. ............................................................. 16
Figure 2-4: Layout Map of Amarja Dam............................................................................... 17
Figure 2-5: Longitudinal Section of Amarja Dam. ................................................................ 18
Figure 2-6: Typical Cross Section of Amarja Earth Dam. .................................................... 19
Figure 2-7: Spillway Cross-section of Amarja Dam. ............................................................ 20
Project Rehabilitation Report of Amarja Dam
1 | P a g e
1. EXECUTIVE SUMMARY
This Project Rehabilitation Report (PRR) is for Amaraja Dam, which is one of the 22
dams under DRIP in Karnataka. The Dam Safety Review Panel (DSRP) inspected
the dam on 7th April 2015 and recommended both structural & non-structural
measures to be taken up by the dam authorities.
DSRP main recommendations included reaming of porous and foundation drains
inside the gallery; concrete dam body grouting; concrete dam foundation curtain
grouting; provision of horizontal collector drain on dam crest and chute drains on dam
d/s slope; repair of disturbed riprap in selected sections; installation of V-notch weir;
renovation of spillway and sluice gates and hoisting mechanism including painting,
oiling, greasing and replacement of rubber seals. Non-structural measures included
review of design flood, dam stability analysis, preparation of EAP and O&M manual.
The original design flood was 2,832 cumec and the revised design flood (PMF) under
DRIP worked out to be 3,704 cumec. The MWL for the original design flood was at
EL 461.5 m. Flood routing study carried out by CPMU indicates that the MWL for the
revised design flood is at 461.52 m, which is only 0.02 m above the original MWL.
The TBL is at 464.5 m. The freeboard above the revised MWL is 2.98 m and fulfils
the minimum recommended 1.50 m for embankment dams as per IS 10635.
Following DSRP recommendations, rehabilitation works carried out under DRIP
included:
Improvements to Earthen Dam and Rough Stone Revetment
Construction of MSS Road on Top of Dam Bund
Construction of Surface Drains on Earthen Bund of D/s slope
Reaming of Porous and Drainage Holes
Grouting Treatment to Spillway of U/s and D/s, Stilling Basin
Providing Painting to Radial Crest Gates, Stop Log Gates and Overhauling
and Maintenance of Radial Crest Gates, Stop Log Gates and Gantry crane
Restoration of RBC Sluice Gate
Providing and Fixing Ladder to Crest Gates on D/s Side including Hand
Railing and to Catwalk, Drain Holes, Platform, Trash Rack for Sluices, and
Gauge Board Writing.
The rehabilitation works were executed under 1 contract at a total completion cost of
Rs. 254.37 Lakhs. SPMU reported Rs. 70.19 Lakhs savings due to change in scope
of work during construction.
Following DSRP recommendations, dam body grouting was carried out on non-
overflow section of the concrete dam. However, no grouting was carried out in the
overflow section and heavy leakage still continues inside the gallery (see section 8.3
for details).
The SPMU carried out dam break analysis and prepared inundation maps, which
were reviewed by CPMU. Draft O&M manual prepared by SPMU as per guideline
published by CWC under DRIP has also been reviewed by CPMU. EAP is currently
under preparation by the SPMU.
Project Rehabilitation Report of Amarja Dam
2 | P a g e
2. PROJECT DETAILS
The Amarja dam is located across Amarja River in Gulbarga district, Karnataka state
at Latitude of 17º29’6.74” N and Longitude of 76º33’7.55” E. It was completed in the
year 1999.
The project consists of an earthen dam 827 m long and 5.0 m dam crest width. It has
77 m long spillway with 5 nos. radial gates having discharge capacity of 2,832
cumec.
The TBL, FRL, original MWL and Spillway Crest level are at EL 464.5 m, 461.5 m,
461.5 m and 452.5 m, respectively. The gross storage at FRL is 44.01 MCM (or 1.55
TMC).
2.1 Project Description
Sl. No.
Item Details
a. Project Identification Code (PIC) KA06HH0199
b. Project Name Amarja Dam
c. River Basin Krishina
d. Sub River Basin Manjra
e. River/Stream Bhima
f. Catchment area (km2) 530.85
g. Year of commencement of project 1973
h. Year of completion of project 1999
2.2 Project Location
Sl. No.
Item Details
a. State Karnataka
b. District Gulbarga
c. Earthquake Zone II
d. Survey of India Map Ref No’s 56C/11 & 56C/10
e. Nearest City Gulbarga
f. Nearest Airport Hyderabad
g. Nearest Railhead Ghanagapur
h. Name of Immediate U/S Project Nil
i. Name of Immediate D/S Project Nil
j. Latitude in Deg., Min, Sec. (North) 17º29’6.74”
k. Longitude in Deg., Min, Sec. (East) 76º33’7.55”
Project Rehabilitation Report of Amarja Dam
3 | P a g e
2.3 Project Benefits
Sl. No. Item Details
a. Type of Project Irrigation
b. Gross Command Area (Ha) 14959
c. Culturable Command Area (Ha) 8903
d. Annual Irrigation Potential (Ha) 8903
e. Hydropower –
Installed Capacity (MW) Nil
f. Hydropower –
Firm Power (MW) Nil
g. Hydropower –
Average Annual Generation (MU) Nil
h. Domestic/Municipal/Industrial Water –
Annual Quantum (MCM) 3.51
i. Domestic/Municipal/Industrial Water –
Area and Population Benefitted 10.5 KM² and 422,366
j. Flood Protection –
Flood Protected Area (Ha) Nil
k. Flood Protection –
Details of Area Benefitted Nil
l. Details of Tourism/Recreational Facilities Nil
2.4 Dam and Reservoir Features (Before rehabilitation under DRIP)
Sl. No.
Item Details
a. Full Reservoir Level (m) 461.5
b. Original Maximum Water Level (m) 461.5
c. Gross Reservoir Storage Capacity at FRL (Mm
3 )
44.01
d. Live Storage Capacity (Mm3 ) 40.07
e. Revised Live Storage Capacity, if any
(Mm3 )
-
f. Date of bathymetric survey, if any -
g. Dam Type Earthen embankment
h.
Length of Dam at Top (m)
i) Total length of the main dam
ii) Length of embankment dam
iii) Length of masonry/concrete dam
960
827
133 (central masonry dam/spillway)
i. Number and length of dykes (No. & m) Nil
j. Top of dam (El. in m.) 464.5
k. Top Level of Upstream Parapet Wall of -
Project Rehabilitation Report of Amarja Dam
4 | P a g e
Sl. No.
Item Details
main dam (El. in m.)
l.
Height of Dam (m)
i) Embankment dam – above river bed level (up to dam top without camber)
ii) Concrete/Masonry dam – above deepest foundation level (up to dam top)
24
18.5
m Top width of main dam (m) 5.0
n. Spillway details
i) Location Middle (CH 842 m to 919 m)
ii) Type of spillway Ogee
iii) Length of spillway (m) 77
iv) Spillway crest level (m) 452.5
v) Type of Gate Radial
vi) Number and size of gates (no. and
m. x m.) 5, 13 x 9
vii) Number and thickness of piers (no.
and m. x m.) 4
o.
Outlet/Sluice details
i) In Embankment dam
Number
Size (Width (m). x Height (m).)
Location
Invert level El. (m)
Discharging capacity (m3/s)
ii) In Concrete/Masonry dam
Number
Size (m. x m.)
Location
Invert level El. (m)
Discharging capacity (m3/s)
2 (LBC, RBC)
0.8 m x 2.2 m
CH 435 m, CH 975 m
449 m
2.27, 1.82
Nil
Note: All elevations are above MSL
2.5 Any Emergency Spillway, Fuse Plug etc.
Nil
2.6 Details of previous dam incidents, if any
Nil
Project Rehabilitation Report of Amarja Dam
5 | P a g e
2.7 PST Details
Sl.
No. Item Date/Cost Remarks
a. PST first received from SPMU 14/05/15
b. Proposed PST Cost (INR in Lakhs) 400
c. First review by CPMU 17/06/15
d. Final review by CPMU 02/09/15
e. World Bank Approval 23/09/15 E- mail dated 23/09/2015
f. Approved PST Cost (INR in Lakhs) 330
2.8 DSRP, CPMU and World Bank Recommendations and Compliance
2.8.1 DSRP Recommendations and Compliance
Compliance to DSRP recommendations as submitted by SPMU/dam authorities is
shown on pages 15 to 22 below.
2.8.2 CPMU/World Bank Recommendations and Compliance
WB Comments are in line with DSRP comments specially related to dam stability
analysis, foundation curtain grouting, and provision of sufficient pumps inside gallery.
The SPMU compliance to this comment is as given in item 2.9.1 of the compliance to
DSRP comments (see pages 17, 20 and 21).
2.9 Scope of Rehabilitation Works as per PST
(a) Remedial Measures (Structural)
i. Improvement to Earthen dam
ii. Construction of toe drain with chambers
iii. Construction of surface drain on D/s
iv. Repairs & Grouting of drainage gallery
v. Grouting treatment to observed seepage in the spillway
vi. Drilling of weep holes at right and left side training wall
vii. Restoration of RBC sluice gate
viii. Providing and fixing ladder to crest gates on d/s side including hand railing and to catwalk, drain holes, platform, gauge board writing.
(b) Non-structural
i. Removal of obstruction at stilling basin and river training works
ii. Providing painting to radial crest gates & allied works
iii. Providing instrumentation system
(c) Basic Facilities
i. Construction of CC Road on Dam bund
ii. Providing & installing of CCTV camera.
iii. Providing and supplying vehicle - Bolero Jeep.
Project Rehabilitation Report of Amarja Dam
6 | P a g e
Project Rehabilitation Report of Amarja Dam
7 | P a g e
Project Rehabilitation Report of Amarja Dam
8 | P a g e
Project Rehabilitation Report of Amarja Dam
9 | P a g e
Project Rehabilitation Report of Amarja Dam
10 | P a g e
Project Rehabilitation Report of Amarja Dam
11 | P a g e
Project Rehabilitation Report of Amarja Dam
12 | P a g e
Project Rehabilitation Report of Amarja Dam
13 | P a g e
Project Rehabilitation Report of Amarja Dam
14 | P a g e
2.10 Drawings
Figure 2-1: Index Map of Amarja Dam.
Project Rehabilitation Report of Amarja Dam
15 | P a g e
Figure 2-2: Google Map of Amarja Dam.
Project Rehabilitation Report of Amarja Dam
16 | P a g e
Figure 2-3: Water Catchment Map of Amarja Dam.
Project Rehabilitation Report of Amarja Dam
17 | P a g e
Figure 2-4: Layout Map of Amarja Dam.
Project Rehabilitation Report of Amarja Dam
18 | P a g e
Figure 2-5: Longitudinal Section of Amarja Dam.
Project Rehabilitation Report of Amarja Dam
19 | P a g e
Figure 2-6: Typical Cross Section of Amarja Earth Dam.
Project Rehabilitation Report of Amarja Dam
20 | P a g e
Figure 2-7: Spillway Cross-section of Amarja Dam.
Project Rehabilitation Report of Amarja Dam
21 | P a g e
3. DAM VISITS (PST STAGE)
3.1 Dam Inspections
Sl. No.
Item Date of visit Remarks
a. Dam Safety Review Panel (DSRP) April 2015
b. Site Visit made by CPMU experts 9 Oct 2015
3.2 Summary of observations made by CPMU
The following points were recommended for immediate consideration for
development of a final design and preparation of all tender documents:
Since the revised design flood magnitude (3704 m³/s) has increased by about
30% from its original magnitude (2832 m³/s), flood routing studies are
recommended to be carried out and the adequacy of the freeboard checked
as per IS 10635 for the revised design flood.
In the DSRP report, the drainage gallery in the concrete dam/spillway could
not be inspected due to standing water. During this site visit, the same
condition was experienced. Scheduled arrangements for automatic pumping
of seepage water collected in sump well needs to be attended to with
additional or standby automated pumps sited in a sump well that would be
located near the gallery entrance. Frequent, and regular, monitoring of
seepage is recommended to be carried out, all the choked drainage holes in
the dam body and foundations reamed/re-drilled to make them functional and
the gallery maintained in a dry condition. Provisions for these works are
recommended to be made in the estimate.
4. DESIGN FLOOD REVIEW (DFR)
4.1 DFR Outcome
Sl. No.
Item Original
Value
Revised
Value Remarks
a. Inflow Design Flood (m3/s) 2,832 3,704 PMF
b. Spillway Capacity / Routed Outflow (m
3/s)
- 3,612.80 Flood routing
study by CPMU
c. Maximum Water Level (m) 461.5 461.52 TBL = 464.5
4.2 Brief Summary of Review
The original design flood was 2,832 cumec and the revised design flood (PMF) under DRIP worked out to be 3,704 cumec. The MWL for the original design flood was at EL 461.5 m. Flood routing study carried out by CPMU indicates that the MWL for the revised design flood is at 461.52 m, which is only 0.02 m above the original MWL. The TBL is at 464.5 m. The freeboard above the revised MWL is 2.98 m and fulfils the minimum recommended 1.50 m for embankment dams as per IS 10635.
Project Rehabilitation Report of Amarja Dam
22 | P a g e
4.3 Recommendations
Structural measures - Nil.
Non-structural measures - EAP.
5. REHABILITATION WORKS CARRIED OUT
5.1 Summary of Investigations
Sl. No.
Item Details Remarks
a. Geo-Physical Investigations Not carried out
b. Geo-Technical Investigations Done
c. Hydraulic Model Studies NA
d. Under-Water Scanning NA
5.2 Main Dam Works
Sl. No.
Item Details Remarks
a. Works from hydrological angle Design flood review Design flood Completed.
b. Resetting of disturbed upstream pitching (rip-rap)
Improvements to Earthen Dam and Rough Stone
Revetment Completed
c. Repairs to d/s toe drains, provision of V-Notches for seepage measurements
Construction of Surface Drains on Earthen Bund of
D/s slope Completed
d. Repairs / provision of d/s rock toe
e. Provision for d/s turfing
f. Re-drilling / Reaming of drainage holes in the dam body and in the foundations
Reaming of porous and
foundation drains inside
gallery
Partially Done (not
completed due to heavy leakage in
drain holes)
g. Works because of Seepage / leakage issues
Grouting Treatment to
Concrete dam
Completed (in non-flow section only)
h. Hydro-mechanical works
i. Main spillway gates & hoists
Providing Painting to Radial
Crest Gates, Stop Log Gates
and Overhauling and
Maintenance of Radial Crest
Gates, Stop Log
Gates and Gantry crane
Completed
ii. Outlet gates & hoists Restoration of RBC Sluice
Gate Completed
i. Other miscellaneous works d/s of embankment dam
Providing and Fixing Ladder to Crest Gates on Dis Side
including Hand Railing and to Catwalk, Drain Holes,
Platform, Trash Rack for
Completed
Project Rehabilitation Report of Amarja Dam
23 | P a g e
Sl. No.
Item Details Remarks
Sluices, Gauge Board Writing
5.3 Basic facilities
S/N Item Details Status
a. b. Roads
Construction of MSS Road on Dam Bund Top
Completed
6. INSTRUMENTATION
6.1 List of existing instruments installed in dam and their condition
Automatic water level recorder (gauge reading instrument) is fixed near RBC Sluice Gate. Other instruments such as piezometers, v-notch weir, etc., are yet to be installed.
6.2 Details of new instruments installed
Nil.
6.3 CPMU Recommendations
Nil.
Project Rehabilitation Report of Amarja Dam
24 | P a g e
7. PROCUREMENT OF WORKS
7.1 Package wise details
Work Package No.
Name of Works
Estimated
Cost
(INR in Lakhs)
Procurement
Method
Invitation for bids / NIT Issue
date
Pre-Bid Meeting
date
Bid Opening
date
Contract Agreement
No.
Contract Agreement
date
Contractor’s Name &
Address
Scheduled
Duration (Months)
Scheduled Completio
n date
Contract /
Award Value
(INR in Lakhs)
Completion Cost (INR in Lakhs)
Actual Date of
Completion
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
1
Rehabilitation and Improvement
works to Amarja Dam under World Bank Aided DRIP
Programme
330.00 NCB 17/10/19 27/10/16 19/01/17 99/ 2016-17 20/03/17
Sri B.S.Loni, Class-I
Contractor, Basava Nagar, Gokak
12 19/03/18 262.77 254.37 31/07/18
*SPMU reported there was a saving of 70.2 Lakh from the original Contract Amount.
Project Rehabilitation Report of Amarja Dam
25 | P a g e
7.2 Details of Bidding Process
As per details in the above table.
7.3 Reason for Variation, if any
SPMU reported Rs. 70.19 Lakhs savings due to change in scope of work during
construction.
7.4 Litigation / Arbitration, If Any
No litigation.
8. THIRD PARTY CONSTRUCTION SUPERVISION VISITS BY
CPMU
8.1. Summary of Visits undertaken
Sl. No. Date of visit Transmittal details of CSV Report
a. 13-07-2017 4805 / 24-07-2017
b. 28-09-2017 5402/01-01-2018
c. 12-10-2017
d. 23-03-19 5781 / 13-04-2018
e. 26-07-19 6489 / 25.10.2018
8.2. Summary of Third Party Material Testing
Third party quality control tests were performed on M15 concrete for dam d/s slope
chute drains, as well as on M10 concrete for dam top drain and upstream riprap
templates using non-destructive Schmidt hammer test (NDT). For chute drains, the
tests gave unsatisfactory results and were recommended for rectification by CPMU.
For dam top drain and riprap templates, the tests gave satisfactory results. Detailed
test report is attached as Annexure D.
8.3. Summary of Major Recommendations
1st Construction Site Visit Report
Dam Safety: The DSRP in their comprehensive review of the health of the dam and
their recommendations that followed, include multiple pre-construction details to
ensure successful implementation of the approved rehabilitation measures. Many of
these recommendations have not been incorporated into the work plan. CPMU
recommends that the SPMU ensure all rehabilitation measures in the contract are
carefully followed and documented for the record.
Major Observations:
• Drilling and grouting of the NOF portion of the dam is in progress and the field data indicates that the pre-grout permeability is greater than (>) 150 Lugeon.
• The DSRP in their report and with concurrence from CPMU recommended a geophysical scan be conducted to determine the points of inflows and that the
Project Rehabilitation Report of Amarja Dam
26 | P a g e
grouting scheme be based on directional grouting instead of blanket or “blind” grouting.
• A full galley inspection was not possible due to 1-meter-deep flooding at the starting point of the overflow section. CPMU recommends larger pumps are employed to maintain a dry gallery to enable a thorough inspection.
• CPMU observed that the porous drains are packed from the bottom by using wooden pegs and bags. As per the advice of SPMU consultants 3 to 4 porous drain holes are cleared of the blockage insertions made at the bottom. Heavy seepage is observed in one porous hole of NOF portion and one porous hole of Overflow portion. The seepage in one NOF porous drain was observed by CPMU at over 30-litres-minute but another porous drain in the overflow section could not be approached due to depth of flooding. (Fig-8)
• Other package items are in various stages of completion and the WBM has been satisfactory completed.
Project Management: Implementing this project will require strong oversight by the
EIC to ensure all works are qualitatively carried out. This includes ensuring all
methodologies and material detail are fully documented. A detailed OK card system
for all major works is recommended to be incorporated to help in this effort. The
quality of the works is dependent on these procedures, measure and pay purposes,
and award of a work completion certificate.
2nd and 3rd Construction Site Visit Report
Major Observation on 28.09.2017:
Water loss test results after tertiary grouting of NOF section on the right bank exceeds minimum requirements of < 5 Lu.
Honeycombing on all lift joints along OF and NOF sections, piers, gallery walls. Uplift pressure from foundation drains exceeds 3kg/cm2. Discovery of limestone in the near-surface of the foundation materials Grout overflow in gallery gutter that needs to be cleaned by Contractor
Major Observations on 12.10.2017:
Drilling and grouting of first row holes located at 2.00 m d/s of the u/s dam face in the NOF section are completed. Drilling and grouting of second row holes located at 1.50 m d/s of the first row is in progress. 3 Nos of primary holes are drilled and grouted as on 12.10.17.
Drain works at the d/s slope of earthen dam are completed. It is observed that the some of the porous drains appear to be plugged with
concrete and some with wooden pegs and bags. Underwater videography depicts significant honeycombs & cavities on the u/s
face of the dam. These honeycombs and cavities most likely causing heavy seepage in the opened porous drains, in spillway piers & d/s face of the dam. There is no provision for taking up under water treatment in the present contract.
No Observation / Deficiency
Status Remarks
Observation during visit on 13.7.17
1
Out of cleared 3 to 4 porous drain holes, heavy seepage is coming in two. Because of this, water is heading up in the drainage gallery. Dewatering is being carried out using 7.50 HP pump, which is
Open
The seepage in one porous drain is 30 litres per minute. The seepage in another porous drain measured during visit on12.10.17 is about 80 litres per minute. The cause for the heavy seepage may be due to existence of some suction points at u/s face of the dam. Blind grouting of the dam body and inside the gallery may not control the seepage of this magnitude. The leakage points are to be
Project Rehabilitation Report of Amarja Dam
27 | P a g e
No Observation / Deficiency
Status Remarks
not sufficient. If the blockages in all the porous blocks are removed it is not known what may be the amount of seepage.
identified by deploying divers and they should be plugged first before taking up the grouting.
2
The pre-grout water loss of >150 Lu observed seems to be very high. Maybe because of testing is being conducted without saturation of holes.
Closed Following the proper procedure to conduct the water loss test. However, Lugeon values must be reduced to less than or equal to 5.
3 Grouting is stopped at thick mix
Open
It is conveyed that they are stopping the grout at thin mix now. But not recorded in the register. It is advised to record the same in the register.
4 Vigilant observation is required during grouting
Open
As there is heavy seepage in the gallery vigilant observation is required during grouting, as there are chances of leakage of grout from the porous hoes and from the u/s face of the dam.
Observation during this visit on 12.10.17
5
Some of the porous drains appeared to be plugged with concrete and some with wooden pegs and plastic bags.
Open
Reaming of porous drains to be done after taking up the treatment to u/s face to plug the water ingress points and treating the honeycomb formations.
6
Even after completion of drilling & grouting of 1st row of holes at NOF portion of the dam, seepage is observed at the d/s face of the dam.
Open
Observation is to be made after completion of drilling & grouting of 2nd row of holes. If seepage persists even after completion of grouting of 2nd row of grout holes, alternative remedial measures like treatment to u/s face of dam has to be thought of.
7 Seepage is observed at left & right abutment piers.
Open
Grouting to the piers or treatment to the u/s face of piers and its adjacent areas may have to be taken up to stop the seepage. But there is no provision in the contract to take up this work
4th Construction Site Visit Report Observations:
Key observations and recommendations:
Amarja gravity dam section is highly permeable and leakage is observed in several sections. After grouting of the NOF section, Lugeon values have reduced but remain high (40 to 127 Lugeon) exceeding allowable limits. No grouting has been carried out in the OF section to date. Previously recommended foundation curtain grouting to minimize uplift pressure is also yet to be taken up.
Very heavy leakage is observed in two porous holes inside the gallery under the OF section. Heavy leakage is also observed in the foundation drains (see photos below).
A few trial holes (0.75 m deep) were recently drilled for radial grouting from the gallery (see photo 10). The Contractor will mobilize another longer drill bit capable of drilling at least 1.5 m deep.
Project Rehabilitation Report of Amarja Dam
28 | P a g e
Heavy Leakage in Porous and Foundation Drains inside Gallery
Considering the heavy leakage observed in several sections of the highly pervious concrete dam, and the challenge of dam body grouting in the OF section u/s of the gallery, SPMU is recommended to consider u/s face treatment as budget and schedule allow but only after a successful bathymetric study in the reservoir. Possible options include geomembrane, cementitious material, block joint hydrophilic, and nipple grouting treatments.
During the site inspection, the LBC service gate was inoperative and lowering the stop log gate was not possible due to high reservoir water level. This has resulted in uncontrolled flow in the LBC, which is undesirable in terms of downstream flooding and dam safety risk due to possible erosion at the toe of the embankment dam. The attempt made to stop the flow by dumping debris into the gate grooves is unacceptable. SPMU is recommended to quickly remove the debris and put the gate back in order.
Embankment dam d/s slope cross drains are completed. However, 3rd party NDT test results on M15 concrete indicate unsatisfactory quality and needs to be rectified. Rock toe protection is required at the d/s end of the cross drains. No longitudinal drains are provided at the berm.
Noted construction deficiencies and dam safety observations:
No. Deficiency / Observation Status Remarks
1.
Very heavy leakage from porous and drain holes inside the gallery under the OF section
Open As budget and time allow, SPMU to consider bathymetric survey and underwater u/s face treatment.
2. Lugeon values still high after grouting of NOF section
Open
3. LBC gate not operational and water flowing uncontrolled
Open Remove debris inside gate groove and repair gate as quickly as possible.
4.
Unsatisfactory results in some sections from 3rd party NDT test on M15 concrete cross drain on embankment d/s slope
Open To be rectified.
5. Rock toe protection is required at the d/s end of the cross drains
Open To be rectified. No provision in Contract.
6. No longitudinal drains provided at d/s slope berm of embankment dam.
Open No provision in contract. To be considered as budget and schedule allow.
7. No provision for renovation and painting spillway stop logs.
Open No provision in contract. To be considered as budget and schedule allow.
Project Rehabilitation Report of Amarja Dam
29 | P a g e
4th Construction Site Visit Report Observations:
Key observations and recommendations:
There was not much progress in this site since last visit. The only activity on-going during this inspection was construction of dam top longitudinal drain using M10 concrete. 3rd party NDT test carried out following this inspection on part of the completed drain gave satisfactory results based on IS 13311 (part 2): 1992, clause 8.1 of ± 25% accuracy.
As previously reported, after grouting of the NOF section, Lugeon values significantly reduced but remain high (40 to 127 Lugeon) exceeding allowable limits. No grouting has been carried out in the OF section to date. Previously recommended radial grouting from gallery and foundation curtain grouting to minimize uplift pressure is also yet to be taken up.
Very heavy leakage was observed in two porous holes inside the gallery under the OF section. Heavy leakage was also observed in the foundation drains.
Considering the heavy leakage observed in several sections of the highly pervious concrete dam, and the challenge of dam body grouting in the OF section u/s of the gallery, SPMU is recommended to consider u/s face treatment as budget and schedule allow but only after a successful bathymetric study in the reservoir. Possible options include geomembrane, cementitious material, block joint hydrophilic, and nipple grouting treatments.
During the previous inspection, the LBC service gate was inoperative. The same has been repaired and is now functional.
8.4. Summary of Compliance by SPMU
Compliance letter received from SPMU against the CPMU experts’ comments during
construction site visits is attached in Appendix E.
8.5. Special Visits made by CWC/World Bank/Expert Committee
Nil
8.6. Summary of Technical Assistance provided by CPMU
Review of PST. Review of design flood and flood routing.
Provided technical guidance on maintaining quality of works as per design, contract agreement technical specification and best engineering practices.
Third party quality control tests.
Review of dam break analysis and inundation maps.
Review of O&M manual.
9. ENVIRONMENTAL AND SOCIAL MANAGEMENT
FRAMEWORK (ESMF)
9.1 Basic Details
Sl. No.
Item Yes / No Remarks
a. ESMF Issue Identified in PST Yes
Project Rehabilitation Report of Amarja Dam
30 | P a g e
b. Mitigation Measures Proposed Yes
c. Any Rehabilitation and Resettlement involved No
d. Site Visit Date of CPMU E&S Specialists -
e. Site Visit Report of CPMU E&S Specialists -
9.2 Summary of Observations
ESMF management during implementation was generally satisfactory but PPE was
hardly used during construction. ESMF OK Card is attached in Annexure F.
9.3 Details of ESMF/EIA study (if any)
Nil.
10. OTHER NON-STRUCTURAL INTERVENTIONS
10.1 Basic Details
Sl. No.
Item Yes / No Remarks
a
Emergency Action Plan (EAP)
(i) EAP Available at Site
(ii) EAP Prepared under DRIP
(iii) EAP Published
(iv) Stake holder consultations
No
Yes
No
No
Draft Inundation maps reviewed by CPMU on 11/10/2018, revised version received from SPMU on 22/05/2019 is under review by CPMU.
b. O&M Manual availability Yes
Draft O&M manual revised from SPMU on 14/05/19 as per guidelines issued by Central Water Commission (CWC) was reviewed by CPMU and comments sent to CPMU on 17/06/2019.
c. Inflow Forecasting No
d. DHARMA Implementation Yes In progress. So far 91% data uploaded.
e. Siren No Needs to be installed
10.2 Summary of Observations
Nil
11. PENDING REHABILITATION WORKS
11.1 Details of pending works
i. Finalization of O&M manual.
ii. Finalization of DBA and Preparation of EAP.
iii. Completion of data entry in DHARMA.
iv. Taking action on compliance issues to DSRP recommendations.
11.2 Further course of action
All pending actions stated above should be completed before December 2019.
Project Rehabilitation Report of Amarja Dam
31 | P a g e
12. REFERENCES
i. PST
ii. DSRP report
iii. Construction site visit report.
iv. Information received from SPMU from time to time
v. Completion Certificate.
vi. World Bank approval
vii. Third party testing.
viii. Compliance letters from SPMU.
ix. ESMF OK Card
x. DBA and Inundation Maps
Project Rehabilitation Report of Amarja Dam
32 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Amarja Dam
33 | P a g e
Annex A: PST Approval Letter
Project Rehabilitation Report of Amarja Dam
34 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Amarja Dam
35 | P a g e
Project Rehabilitation Report of Amarja Dam
36 | P a g e
Project Rehabilitation Report of Amarja Dam
37 | P a g e
Project Rehabilitation Report of Amarja Dam
38 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Amarja Dam
39 | P a g e
Annex B: Drawings issued for
Rehabilitation measures
Project Rehabilitation Report of Amarja Dam
40 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Amarja Dam
41 | P a g e
Project Rehabilitation Report of Amarja Dam
42 | P a g e
Project Rehabilitation Report of Amarja Dam
43 | P a g e
Project Rehabilitation Report of Amarja Dam
44 | P a g e
Project Rehabilitation Report of Amarja Dam
45 | P a g e
Annex C: Completion Certificate
Project Rehabilitation Report of Amarja Dam
46 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Amarja Dam
47 | P a g e
Project Rehabilitation Report of Amarja Dam
48 | P a g e
Project Rehabilitation Report of Amarja Dam
49 | P a g e
Project Rehabilitation Report of Amarja Dam
50 | P a g e
Project Rehabilitation Report of Amarja Dam
51 | P a g e
Project Rehabilitation Report of Amarja Dam
52 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Amarja Dam
53 | P a g e
Annex D: Third Party QC Tests
Project Rehabilitation Report of Amarja Dam
54 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Amarja Dam
55 | P a g e
Project Rehabilitation Report of Amarja Dam
56 | P a g e
Project Rehabilitation Report of Amarja Dam
57 | P a g e
Project Rehabilitation Report of Amarja Dam
58 | P a g e
Project Rehabilitation Report of Amarja Dam
59 | P a g e
Project Rehabilitation Report of Amarja Dam
60 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Amarja Dam
61 | P a g e
Annex E: ESMF OK Card
Project Rehabilitation Report of Amarja Dam
62 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Amarja Dam
63 | P a g e
Project Rehabilitation Report of Amarja Dam
64 | P a g e
Project Rehabilitation Report of Amarja Dam
65 | P a g e
Annex F: Photographs Before and
After Rehabilitation Works
Project Rehabilitation Report of Amarja Dam
66 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Amarja Dam
67 | P a g e
Project Rehabilitation Report of Amarja Dam
68 | P a g e
Project Rehabilitation Report of Amarja Dam
69 | P a g e
Project Rehabilitation Report of Amarja Dam
70 | P a g e
Project Rehabilitation Report of Amarja Dam
71 | P a g e
Project Rehabilitation Report of Amarja Dam
72 | P a g e
Project Rehabilitation Report of Amarja Dam
73 | P a g e
Project Rehabilitation Report of Amarja Dam
74 | P a g e
Project Rehabilitation Report of Amarja Dam
75 | P a g e
Project Rehabilitation Report of Amarja Dam
76 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Amarja Dam
77 | P a g e
Annex G: DBA and Inundation Maps
Project Rehabilitation Report of Amarja Dam
78 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Dam Break Analysis and
Inundation Maps for
Amarja Dam
KA06HH0199
Water Resources Department
State of Karnataka.
Advanced Centre for Integrated Water Resources Management
Water Resources Department, Govt. of Karnataka
No. 1/1, 1st Floor, K.S.F.C Bhawan, Thimmaiah Road Bengaluru – 560052
Phone No: 080-22262042/43/44 Fax No: 080-22262045
Dam Break Analysis Report &
Maps for Amarja Dam,
Karnataka
Project ID Code: KA06HH0199
Doc. No: KaWRD_MAP_AMARJA_01
Advanced Centre for Integrated Water Resources Management
Water Resources Department, Govt. of Karnataka
No. 1/1, 1st Floor, K.S.F.C Bhawan, Thimmaiah Road Bengaluru – 560052
Phone No: 080-22262042/43/44 Fax No: 080-22262045
Dam Break Analysis Report & Maps for Amarja
Dam, Karnataka
Project ID Code: KA06HH0199
Prepared By:
Siddaraj H P
Assistant Engineer
Advanced Centre for Integrated Water Resources Management
Water Resources Department,
Government of Karnataka
GIS Support By:
Asra Kubra Khan
GIS Specialist, ACIWRM
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK i
ABSTRACT
Amarja dam (Project id KA06HH0199) s classified as intermediate dam as per IS 11223-1985, the
potential risk factor in case of dam breach is also higher. The Dam Break Analysis for Amarja
Dam is carried out using HEC-RAS 5.0.3. The ALOS Global Digital Surface Model (DSM)
“ALOS World 3D-30m” (AW3D30) DSM is used for the terrain. The embankment portion of the
composite dam was breached for assessment of flood inundation downstream of the dam. The dam
failure was assessed for the scenarios such as overtopping failure and non-flood failure (piping
failure). Inundation due to large controlled releases from the dam was also considered in the study.
The inundation maps for the critical parameters such as water surface elevation, depth of water,
velocity of flow and flood wave arrival time are prepared for all the three flood scenarios. The
villages which are likely to be inundated in case of Amarja dam breach were identified using
Google map. The population affected due to inundation was obtained from the 2011 census data
hosted on data.gov.in website. Open source road and rail layers were also used in the map
preparation.
The peak discharge obtained for overtopping failure and non-flood failure (piping) are 10,546.36
m3/s and 8248.88 m3/s respectively. However, for large controlled releases, the peak flood is the
design discharge capacity of the spillways. The reasonableness of the peak discharge was
ascertained by evaluating the velocity through the breach which has to be less than 3m/s for breach
in embankment portion. The discharge at the end of the downstream boundary is 1600.68 m3/s
and 799.34 m3/s for overtopping failure and non-flood failure respectively.
Around 32 villages will be affected due to the dam break flood especially in case of overtopping
failure. The villages which are very close to the dam are the most vulnerable as the flood wave
arrival time is less than 12 minutes in case of overtopping failure and sufficient time for evacuation
may not be available. As such the villages which are located within 1 km downstream from the
dam needs quick response from the disaster management team in case of Amarja dam breach.
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK ii
TABLE OF CONTENTS
Contents Page No.
Abstract i
Table of Contents ii
List of Tables iv
List of Figures v
1.0 Introduction
1.1 Preface 1
1.2 General 1
1.2.1 Overtopping Failure 1 & 2
1.2.2 Piping Failure 2
1.2.3 Large controlled Release 2 & 3
1.3 Objectives 3
1.4 Scope 3
2.0 Description of Amarja Dam 4 - 9
3.0 Dam Breach Analysis
3.1 Model Selection 10
3.2 Dam Breach and Flood Inundation Scenarios 10 – 11
3.3 Study Area Boundaries 11
3.4 Data Inputs for Hydraulic Model 11
3.4.1 Elevation Data 11
3.4.2 Land Use Land Cover Data 12
3.4.3 Population Data 12
3.4.4 Hydraulic Data 13
3.4.5 Hydrologic Data 13
3.4.5.1 Inflow Design Flood 13 - 14
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK iii
4. Model Development
4.1 Grid/ Mesh Resolution 15
4.2 Roughness Co-efficient 15
4.3 Flow and Boundary Conditions 15-16
4.4 Dam Breach Parameters 16-22
4.5 Calibration and Sensitivity Analysis 22
4.5.1 Computational Aspects 22
4.6 Peak Discharge Reasonableness 27
4.7 Results 27
4.8 Output Hydrograph 28-32
4.9 Flood Vulnerability 32-33
4.10 Flood Hazard Reference Values/Population at Risk 33
5.0 Flood Inundation Mapping 37
6.0 Conclusion 38
References 39
Annexure-1 Inundation Maps (soft copy in DVD) vi
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK iv
LIST OF TABLES
Tables Page No.
2.1 Salient features of Amarja Reservoir Project
4 & 5
3.1 Existing dam classification for inflow design flood selection
13
4.1 The land use land cover downstream of Amarja dam and its Manning’s N
values
15
4.2 Dam breach parameters and expected peak outflow for Overtopping failure
20
4.3 Dam breach parameters and expected peak outflow for Non- Flood failure
(Piping)
21
4.4 Trapezoidal dam breach model parameters and obtained dam breach flood
peak discharges
22
4.5 Classification limits for vulnerability thresholds of combined hazard curves 33
4.6 Showing the Potential loss of Life based on percentage area of Inundation for
the Projected Population from 2012-2021
34
4.7 Flood hazard reference values
35-36
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK v
LIST OF FIGURES
Figures Page
No.
Fig 2.1 Plan of Amarja Dam 6
Fig 2.2 CS of spillway portion of Amarja Dam 7
Fig 2.3 Typical cross section of embankment and LS Amarja Dam 8-9
Fig 3.1 DEM of the study area 11
Fig 3.2 LULC map of study area 12
Fig 3.5: SPF @ Amarja Irrigation Project 22
Fig 4.1: Reservoir Routing showing Inflow and Outflow Discharge 16
Fig 4.2 Overtopping failure computation log file 23
Fig 4.3 Non-flood failure computation log file 24
Fig 4.4 Large controlled releases computation log file 25
Fig 4.5 Runtime message for overtopping failure 26
Fig 4.6 Runtime message for piping failure 26
Fig 4.7 Runtime message for large controlled releases 27
Fig 4.8 Overtopping failure dam breach flood hydrograph 28
Fig 4.9: Flood hydrograph at the boundary line (BC-1) for overtopping failure 28
Fig 4.10: Flood hydrograph at the boundary line (BC-2) for overtopping failure 29
Fig 4.11: Non-Flood Failure (Piping) dam breach flood hydrograph 29
Fig 4.12: Flood hydrograph at the boundary line (BC-1) for piping failure 30
Fig 4.13: Flood hydrograph at the boundary line (BC-2) for piping failure 30
Fig 4.14: Flood hydrograph for large controlled releases 31
Fig 4.15: Flood hydrograph at the boundary line (BC-1) for large controlled releases 31
Fig 4.16: Flood hydrograph at the boundary line (BC-2) for large controlled releases
32
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK vi
ANNEXURE-1 – FLOOD INUNDATION MAPS
The data used to carry out dam break studies of three scenarios using HECRAS software and the
maps are included in the DVD files and DVD is organized in folders as shown below:
➢ Dam Name – state
• Common data
• Model data
▪ Overtopping failure
▪ Piping Failure
▪ Large Controlled release
• Output maps
▪ Overtopping failure
▪ Piping Failure
▪ Large Controlled release
The common data folder contains information related to three flood simulations including digital terrain models and land use / land cover data and other data required to carry dam breach study. The inundation maps for the three failure scenarios (Overtopping, Piping, Large Control release) showing - Depth (max.) in m, Velocity (max) in m/s, Water surface elevation (max), flood arrival time in hrs. flood vulnerability maps are attached in this report as Annexure-1.
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 1
1. INTRODUCTION:
1.1 Preface:
Advanced Center for Integrated Water Resources management (ACIWRM) is a think tank to the
government’s Water resources Department (WRD). It engages in policy analysis, research,
planning, capacity building and develop the knowledge base to gear up the department up for its
future vision. ACIWRM was entrusted with the dam break analysis and preparation of inundation
maps for emergency action plan for Amarja Dam by Project Authorities.
The necessary training and inputs for dam break modelling have been provided by CWC under
DRIP. The required information and details of the Amarja dam have been provided by the project
Authorities.
1.2 General:
Based on the type of dam and conditions of the dam site, a dam may fail due to multiple causes.
The most common causes of dam failure are flood or dam overtopping. The next common cause
is piping or seepage. The structural failure occurs on influence of various factors and its third most
common category. Sometimes dam may even fail due to the failure of spillway gate, earthquake
or even poor design/construction. Depending on the nature / type of dam the failure of dam varies.
Concrete gravity dams may suffer a partial breach with failure of one or more monolith sections.
Concrete arch dams may fail suddenly and completely within a few minutes. Embankment dams
do not fail completely or suddenly as their concrete counterparts. Breaching action in an earthen
dam continues to the point where the reservoir is deleted completely or to the point where the
breached materials resist erosion.
1.2.1 Overtopping Failure:
Overtopping due to large inflow flood is the most common failure mode for embankment dams. It
occurs when the water surface elevation in the reservoir exceeds the height of the dam. The flow
of water over the crest of the dam, an abutment, or a low point in the reservoir rim follows as a
consequence. The foundation and abutments of a concrete dam may also be eroded due to
overtopping, leading to loss of support and failure due to sliding or overturning. For embankment
dams, the failure begins at a downstream location, with head cutting progressing upwards
gradually. As it reaches the dam top, the width of the dam crest is eroded fast, before the reduction
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 2
in height starts taking place. This proceeds at a fast rate and may include the phase of maximum
outflow for a reservoir with capacity small compared to its height. In this phase, the earthen dam
without a core behaves mostly like a sharp crested weir.
The opening created by erosion expands gradually, almost in the shape of a trapezoid. As the height
is reduced to the foundation level, outflow may continue for a long time if the reservoir is of
sufficiently large capacity. For such cases, the peak rate of outflow is also expected to occur during
this phase. The flow mostly resembles the overflow pattern observed over a broad crested weir
with long crest.
1.2.2 Piping Failure:
Piping occurs when concentrated seepage paths develop within an embankment dam. The seepage
slowly continues to erode the dam embankment or foundation, leaving behind large voids in the
soil. Piping begins near the downstream toe of the dam and works its way towards the reservoir
upstream. Erosion proceeds at a more rapid rate as the voids become larger and larger. As the
erosion reaches the reservoir upstream, it may enlarge and cause total failure of the dam. The
process of internal erosion and piping may be broken up into four phases: initiation of erosion,
continuation of erosion, progression to form a pipe and ultimately, the formation of a breach.
Piping failures occur in earthen dams only. Once such a pipe connection is formed, it is almost
impossible to save the dam from failure.
1.2.3 Large Controlled Releases:
Flood risks at locations downstream of the dam may also arise without any failure of the dam and
its components. After construction of a dam, the safe carrying capacity of the river channel
normally keeps on decreasing, due to the diversion of water as well as flood moderation by the
reservoir. Consequently, after many years of dam construction, the river channel downstream of a
dam loses its capacity to carry the peak flood magnitudes. So, extensive bank overflows become
associated with flood discharges. The situation gets further aggravated due to developmental
activities taking place in the floodplain because of reduced frequency of inundation.
In the event of a severe flood in the dam catchment having a magnitude of peak discharge near to
the design flood of the dam, the priority of dam operation will shift to saving the dam. Otherwise,
a dam breach may endanger the lives of many more persons residing in the downstream area. With
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 3
the passage of flood flows near to the spillway capacity, severe floods causing huge inundation
may occur. It may even lead to loss of lives which has to be minimized through implementation
of strict floodplain regulatory management plans and flood warning.
1.3 Objectives:
• The main purpose of the study is to find out the areas downstream of Amarja Dam which
will be inundated due dam breach scenarios such as overtopping and non-flood failure
(piping) and to find out the inundation scenario in case of large controlled release.
• To estimate the number of villages and people at risk due to dam failure and large
controlled release.
• To assess the submergence of infrastructure facilities such as roads and railways.
• To prepare the inundation maps for the breach scenarios such as overtopping and piping
and for controlled large release.
1.4 Scope:
• The scope of the study is restricted to failure of the dam due to overtopping and piping
only. However, inundation maps are prepared for both the cases of failure and for large
controlled releases. No other failure scenarios such as landslide, earthquake, malfunction
of gates and planned removal are considered in this study because the HEC-RAS software
cannot simulate these conditions.
• A tier-2 approach to dam breach and inundation mapping are followed which is an
intermediate level of analysis using medium resolution terrain data. A tier 3 approach to
dam breach analysis could be carried out using high resolution LIDAR data.
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 4
2. DESCRIPTION OF AMARJA DAM
The Amarja is a river flows in Kalaburagi District, Karnataka, India. Born at Koralli and flows up
to 50–60 kilometers and will merge into Bhima river at Sangam Kshetra Ganagapura village in
Kalaburagi District. The water of these rivers, especially at their confluence, called Sangam, are
considered extremely holy. There is a temple in Sangam in which Shree Narasimha Saraswathi
Swamy (The second incarnation of Lord Dattatreya)
Amarja Dam is located in Aland town near the city of Kalaburagi in the Kalaburagi district of
Karnataka. The Dam is built across the river Amarja that flows through the Krishna basin in the
Southern part of India. The dam was constructed in the year 1998, this is a multi-purpose dam.
The reservoir is used for irrigation of the surrounding areas, for providing water supply and for
solving the problem of drinking water in the area. The dam is 960-meter-long and 31.85-meter-
high from the foundation. It covers a catchment area of 53.095 Thousand ha. The design flood of
the dam is 2837 Cumecs. The dam has Ogee type of spillway and 5 spillway gates. The maximum
water level of the dam is 461.5 meters. The type of Dam is Earthen + Gravity and gross capacity
of the reservoir is 1.554 TMC.
Table:2.1 Salient features of the Amarja dam
Name of the Project Amarja Reservoir Project
Type of Project Multi-Purpose Project
Name of the Dam Amarja Dam
Location of Dam Across Amarja River about 1.5 km D/S of
Sangolgi Village Taluk. Aland District
Gulbarga
Name of the River Basin location Krishna Basin
River Tributary Amarja
Latitude 17° 92 '
Longitude 76° 33'
Catchment Area 530.95 Sq.kms
Gross Storage Capacity 1.554 TMC
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 5
Live Storage 1.415 TMC
Dead Storage 0.139 TMC
Lowest River Bed Level (m) RL 436.655
Crest Level (m) RL 452.5
Full Reservoir Level (m) RL 461.5
Maximum Water Level (m) RL 461.5
Top of the Dam RL 465
Maximum water spread area at FRL 640.20 ha
Type of Dam Earthen dam with zonal section with gated
ogee spillway at gorge
Length of the Dam (m) 960
Height of the dam above the Lowest River bed
level (m)
28.345
Top width of road way (m) 8.0
Designed flood intensity (Cumecs) 2837
Discharging length of spillway (m) 77
Spillway crest Ogee Section
Crest gates 5 nos. Radial gates of size 13 m x 9 m
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 6
FIGURE 2.1 PLAN OF AMARJA DAM
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 7
FIGURE 2.2 C/S OF SPILLWAY PORTION OF AMARJA DAM
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 8
FIGURE 2.3 TYPICAL CROSS SECTION OF EMBANKMENT OF AMARJA DAM
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 9
FIGURE 2.4 LONGITUDINAL SECTION OF AMARJA DAM
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 10
3. DAM BREACH ANALYSIS
3.1 Model Selection:
HEC-RAS software is used for the dam breach analysis of Amarja Dam. 2D modeling approach
was adopted because of its simplicity when compared to 1D modeling and the advantages of 2D
modeling with 1D modeling is enumerated below;
• 2D modeling can perform 1D, 2D and combined 1D and 2D modeling. In the present study
2D flow areas were created which were directly connected to 1D storage with a hydraulic
structure.
• There is also an option of choosing either Saint Venant or diffusion wave equations.
• The 2D flow area can start completely dry and handle sudden rush of water into the area.
• The algorithm can handle subcritical, supercritical and mixed flow regimes.
• The computational meshes can be both unstructured and structured.
• The detailed hydraulic table properties for 2D computational cells and cell faces are
computed.
• Detailed flood mapping and flood animations are obtained.
The limitations to the 2D modeling approach are less flexibility in adding internal hydraulic
structures; cannot perform sediment transport erosion/ deposition; cannot perform water quality
modeling and cannot connect pump stations to 2D flow area.
3.2 Dam Breach and Flood inundation Scenarios:
The following three dam breach scenarios are considered in the study;
1. A dam failure caused by overtopping from the inflow design flood leading to breaching
and uncontrolled flow of impounded water.
2. A dam failure caused by internal erosion (piping) with the reservoir at FRL leading to
breaching and uncontrolled flow of impounded water.
3. A large controlled-release flood with IDF and without dam failure.
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 11
The hazard potential will be at its maximum when there is a dam breach failure due to overtopping,
downstream hazards due to a dam failure because of piping or even passage of high discharge
(design spillway capacity) through the spillway gates may sometimes be hazardous. The sudden
release of water of even lesser magnitude from a dam without proper warning may also cause loss
of life and property.
3.3 Study Area Boundaries
The study area boundaries are limited to an extent of 53 km downstream of the Amarja dam where
in the flow gets restricted to the natural channel i.e., the total outflow in the downstream end of
the model is within the channel carrying capacity of the main stream.
3.4 Data Inputs for the Hydraulic Model
3.4.1 Elevation Data
“ALOS World 3D-30m” (AW3D30) dataset, the global digital surface model (DSM) dataset with
a horizontal resolution of approximately 30-meter mesh (1 arcsec. latitude and longitude)
generated from 5m resolution DSM and provides open distribution of this high-resolution global
data set through JAXA website. The elevation data is in Georeferenced Tagged Image File Format
(GeoTIFF) which is a TIFF file with embedded geographic information. This dataset is highly
expected to be used in scientific research and geospatial information application services.
Fig 3.1 DEM OF THE STUDY AREA
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 12
3.4.2 Land Use Land Cover Data
LISS 4 image extracted to a scale of 1:10000 and a spatial resolution 5.8 m is used as the input to land
cover data. The land cover map was provided by Karnataka State Remote Sensing Application Center
(KSRSAC).
Fig 3.2 LULC MAP OF STUDY AREA
3.4.3 Population Data
The estimated population for each settlement as per 2011 census was obtained from data.gov.in
portal. However, the present population in each of these settlements needs to be ascertained. The
village-wise population data hosted in the site is having all the demographic information as per the
2011 census
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 13
3.4.4 Hydraulic Data
The Amarja Dam has five radial gates of size 9m x 13 m with ogee spillway. The crest level of the
gate is 452.5 m. The weir width considered is 8.0 m with an elevation of 452.5 m. The length of
the weir 960 m. The discharge co-efficient for weir is taken as 1.44 considering it as broad crested
weir whereas for the ogee weir the weir co-efficient is taken as 2.2. The radial gate flow parameters
considered are radial discharge co-efficient as 0.6, trunnion exponent as 0, opening exponent as
1.0, head exponent as 0.5 and trunnion height as 0.0 m
3.4.5 Hydrologic Data
The dam classification system in India depends on the static head and gross storage capacity of the
reservoir. The Amarja dam is classified as Intermediate dam as per IS: 11223 (1985) “Guidelines
for Fixing Spillway Capacity”.
Table 3.1: Existing dam classification for inflow design flood selection (IS:11223 - 1985)
Class
Gross storage capacity
(Mm3)
Static head (m)
Inflow Design Flood
(IDF)
Small
0.5 to 10
7.5 to 12
100-year flood
Intermediate
10 to 60
12 to 30
Standard Project
Flood (SPF)
Large
> 60
> 30
Probable Maximum
Flood (PMF)
3.4.5.1 Inflow Design Flood
Inflow Design Flood was carried out by Hydrology Unit, WRDO. The spillway capacity is
originally designed for 2832 Cumecs (1,00,000 cusecs). The dam comes under the classification
of “Intermediate dams” as the gross storage and the height of earthen dam is 28.345m and 44.01
Mcum respectively.
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 14
In absence of closed interval gauge data for developing a unit hydrograph, recourse has been made
for computing the maximum design flood discharge from the Synthetic unit graph by making use
of the flood Estimation Report for Krishna & Pennar Basins (Sub Zone-3(h)” prepared and
published by Directorate of Hydrology (small catchments), Central Water Commission, New
Delhi, which involves a method based on Unit Hydrograph principle.
As the storage of the dam is more than 10 Mcum, and height of the dam is more than 12 m and
less than 30 m, dam has been classified as intermediate dam is hence SPS needs to be considered.
As per Generalized PMO ATLAS of CWC of Krishna Basin Prepared during the Feb-2007, The
1-day PMP value has been reduced to 1-day SPS value by dividing the 1-day PMP value with
Moisture maximum Factor (MMF) of 1.23, as per table 16, vide page no.105 of the said ATLAS.
Thus, the Design Flood has been calculated by adopting the SPS, which works out to 130811
cusecs say 1.31 lakh cusecs.
As per the above classification and based upon the study carried out by Hydrology Unit, WRDO
with KERS the dam was classified as Intermediate dam and probable maximum flood was
considered as 3704.16 m3/s for the present study.
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 15
4. MODEL DEVELOPMENT
4.1: Grid/Mesh Resolution:
The two-dimensional depth averaged model was used in the study. The grid resolution of
90mx90m was selected and the total cells were 30724. Break lines are not used in the model.
4.2: Roughness Co-efficient:
The roughness co-efficient was selected based on the land use land cover of the study area, which
was obtained from Karnataka State Remote Sensing Application Center (KSRSAC).
Table 4.1: Land use and Land Cover downstream of Amarja Dam and its Manning’s N Value
Sl.no. Land Use and Land Cover type Manning’s ‘N’ Value
1 Agriculture land 0.034
2 Water body 0.04
3 Waste land 0.035
4 Buildup 0.4
5 Forest 0.05
4.3: Flow and Boundary Conditions:
The initial condition assumed for overtopping failure is the top of embankment dam F.R.L level
461.50 m (critical depth for overtopping failure). For Overtopping failure F.R.L level is considered
as the critical depth because reservoir routing shows (Figure 4.1) the peak discharge 3704.16 m3/s
occurs at elevation 460.07 which is below the level of F.R.L for piping failure the storage elevation
at FRL i.e., 461.50 m of the reservoir and for large controlled release the crest level i.e.,652.50 m
of spillway is considered. The boundary conditions (BC-1 & BC-2 were considered on the
downstream as the flow joins the river Bhima @ downstream) for overtopping failure are lateral
inflow hydrograph for the reservoir, elevation-controlled gates (gates are fully opened) for the
storage area connection i.e., dam and normal depth of 0.001 is assumed for the 2D flow area.
However, for the piping failure, only normal depth and elevation-controlled gates (gates are fully
closed) are used as the boundary condition. For controlled large releases, IDF as lateral inflow,
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 16
gates opening at a rate of 0.1m/min and the normal depth of 0.001 is considered. The breach
progression is modeled as sine wave progression where, breach grows very slowly at the beginning
and end of development and rapidly in between.
Figure 4.1: Reservoir Routing showing Inflow and Outflow Discharge in Cumecs
4.4: Dam Breach Parameters:
The key parameters for arriving at a dam breach hydrograph are the breach parameters related to
the geometry and timing of the breach formation (e.g., width, depth, shape, and time of failure).
The selection of breach parameters for modelling dam breaches contain the greatest uncertainty of
all aspects of dam failure analysis and therefore a careful evaluation and understanding of the
associated breach parameters is necessary.
174.20 229.85
0.00
300.00
600.00
900.00
1200.00
1500.00
1800.00
2100.00
2400.00
2700.00
3000.00
3300.00
3600.00
3900.00
8.0 10.0 12.0 14.0 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0
INFL
OW
/OU
TFLO
W (
CU
MEC
)
TIME (HRS)
Inflow (Cumec) Outflow (Cumec)
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 17
Breaching begins when the reservoir water surface elevation reaches the failure elevation (above
the datum). The formulae for the embankment breach parameters are
𝐵𝑎𝑣𝑔 = 0.23 𝑋 𝑘𝑀 𝑋 𝑉𝑤
1
3
Where,
𝑘𝑀 = {1.5 𝑓𝑜𝑟 𝑂𝑣𝑒𝑟𝑡𝑜𝑝𝑝𝑖𝑛𝑔 𝑓𝑎𝑖𝑙𝑢𝑟𝑒𝑠1.0 𝑜𝑡ℎ𝑒𝑟 𝑓𝑎𝑖𝑙𝑢𝑟𝑒 𝑚𝑜𝑑𝑒𝑠
𝑚 = {1.0 𝑓𝑜𝑟 𝑂𝑣𝑒𝑟𝑡𝑜𝑝𝑝𝑖𝑛𝑔 𝑓𝑎𝑖𝑙𝑢𝑟𝑒𝑠0.7 𝑜𝑡ℎ𝑒𝑟 𝑓𝑎𝑖𝑙𝑢𝑟𝑒 𝑚𝑜𝑑𝑒𝑠
𝑡𝑓 = 60 𝑋 √𝑉𝑤
𝑔𝐻𝑏2
(Froehlich, 2017a)
The formulae for the masonry/ concrete breach parameters are
(Froehlich, 2017 b)
Two mathematical models are presented for predicting peak discharge from gradually breached
embankment dams. The first model is an empirical formula based on previously developed
statistical relations using measures of embankment and reservoir properties as predictors. The
second model is a semi theoretical which reduces the maximum possible discharge from an
instantaneous reservoir breach having prescribed dimensions.
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 18
Expected outflow (empirical);
𝑄�̂� = 0.0175 𝑋 𝑘𝑀 𝑋 𝑘𝐻 𝑋 √ 𝑔𝑉𝑤 𝐻𝑤𝐻𝑏
2
𝑊𝑎𝑣𝑔
Where,
𝑘𝑀 = {1.0 𝑓𝑜𝑟 𝑛𝑜𝑛 − 𝑂𝑣𝑒𝑟𝑡𝑜𝑝𝑝𝑖𝑛𝑔 𝑓𝑎𝑖𝑙𝑢𝑟𝑒 𝑚𝑜𝑑𝑒𝑠1.85 𝑓𝑜𝑟 𝑜𝑣𝑒𝑟𝑡𝑜𝑝𝑝𝑖𝑛𝑔 𝑓𝑎𝑖𝑙𝑢𝑟𝑒 𝑚𝑜𝑑𝑒𝑠
𝑘𝑀 = {
1: 𝑓𝑜𝑟 𝐻𝑏 ≤ 𝐻𝑠
(𝐻𝑏
𝐻𝑠)
1
8∶ 𝑓𝑜𝑟 𝐻𝑏 > 𝐻𝑠
𝐻𝑠 = {6.1 𝑚 (𝑓𝑜𝑟 𝑆𝐼 𝑢𝑛𝑖𝑡𝑠)20 𝑓𝑡 (𝑓𝑜𝑟 𝑈. 𝑆. 𝑐𝑢𝑠𝑡𝑜𝑚𝑎𝑟𝑦 𝑢𝑛𝑖𝑡𝑠)
(Froehlich,2016)
Maximum outflow for instantaneous breach;
(Froehlich,2016)
Expected outflow (semi-theoretical)
(Froehlich,2016)
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 19
Where;
Bavg = expected value of average breach width in meters
Tf = breach formation time in seconds
Qp is the peak discharge in m3/s
KM is the factor that accounts for failure mode
KH is the factor that accounts for embankment height
g is acceleration due to gravity in m/s2
Vw is the volume of water above breach bottom in m3
Hw is the height of water above breach bottom in m
Hb is the height of breach in m
Hs is height of small embankment in m
Wavg is the average embankment width in m
m is the average side slope ratio (horizontal: vertical) of trapezoidal opening
The top level of the dam is taken as 461.50 m and the breach bottom level as the river bed level.
The reservoir volume for overtopping is considered to be 44.21 M Cum at 461.50 m (F.R.L level
of the dam) and for the piping the capacity at FRL is considered i.e., 44.21 Mcum. The center
station considered for the breach is 700 m from the chainage “0” measured from the left end of the
earthen dam. It is assumed that the left earthen embankment is more vulnerable for breach in the
study. The breach parameters and expected outflow as obtained from the above equations are given
below.
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 20
TABLE 4.2: THE DAM BREACH PARAMETERS AND EXPECTED PEAK OUTFLOW
FOR OVERTOPPING FAILURE
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 21
TABLE 4.3: DAM BREACH PARAMETERS AND EXPECTED PEAK OUTFLOW FOR
NON-FLOOD FAILURE (PIPING)
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 22
Table 4.4: Trapezoidal Dam Breach Model Parameters and obtained Dam Breach Flood
Peak Discharges
Breach Parameters Units Dam Failure Mode
Overtopping Piping
Height m 24 24
Bottom Width m 117 103
Average Side Slope (horz: vert) -- 1:1 0.7:1
Formation time hrs. 2.18 2.09
Obtained Peak Discharge m3/s 10546.36 8248.88
4.5: Calibration and Sensitivity Analysis:
Calibration and sensitivity analysis were not carried out. However, the breach parameters were
finalized by conducting trials and verifying the breach velocity for embankment breach to be less
than 3 m/s. The velocity threshold was monitored just after the breach formation time and was
established based on the construction material of the dam.
4.5.1: Computational Aspects:
Full momentum equation is used for the analysis and the computation interval or the time step
adopted is 1 sec, Hydrograph output interval 1 minute, mapping Output interval 5 min and detailed
output interval 5 min for Overtopping, Piping & large Control release simulation.
The percent volume accounting error for the storage and 2D flow area for overtopping failure
simulation and for non-flood failure simulation for embankment breach are 0.5822 & 0.08433 and
1.364 & 0.1683 respectively. There is no convergence error in both the simulations. In case of
large controlled releases, the percent volume accounting error for the storage and 2D flow area are
0.01999 and 0.02049 respectively. There was no runtime error.
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 23
Figure 4.2: Overtopping Failure Computation Log File
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 24
Figure 4.3: Piping Failure Computation Log File
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 25
Figure 4.4: Large Control Release Failure Computation Log File
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 26
Figure 4.5: Runtime Message for Overtopping Failure
Figure 4.6: Runtime Message for Piping Failure
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 27
Figure 4.7: Runtime Message for Large Controlled Releases
4.6: PEAK DISCHARGE REASONABLENESS:
The reasonableness of the peak discharge downstream of the dam breach is ascertained by expected
peak outflow (gradual breach- semi theoretical and empirical equations) as given by Froehlich,
2016.
4.7: RESULTS:
The simulation results show that for embankment breach, the breach velocity for overtopping
failure is 2.70 m/s whereas for piping failure it is 2.24 m/s at the time of breach. The peak discharge
obtained for overtopping failure is 10546.36 m3/s and for piping failure it is 8248.88 m3/s. The
discharge at the end of the downstream boundary is 1600.68 m3/s and 799.24 m3/s for overtopping
failure and non-flood failure respectively
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 28
4.8: OUTFLOW HYDROGRAPH:
The output hydrograph as obtained after simulation in HEC RAS for overtopping and non-flood failure
are given below;
Figure 4.8: Overtopping Failure Dam Breach Flood Hydrograph
Figure 4.9: Flood Hydrograph at the Boundary Line (BC Line-1) for Overtopping Failure
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 29
Figure 4.10: Flood Hydrograph at the Boundary Line (BC Line-2) for Overtopping Failure
Figure 4.11: Non-Flood Failure (Piping) Dam Breach Flood Hydrograph
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 30
Figure 4.12: Flood Hydrograph at the Boundary Line (BC Line-1) for Non-Flood (Piping) Failure
Figure 4.13: Flood Hydrograph at the Boundary Line (BC Line-2) for Non-Flood (Piping) Failure
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 31
Figure 4.14: Flood Hydrograph for Large Controlled Releases
Figure 4.15: Flood Hydrograph at the Boundary Line (BC Line-1) for Large Controlled Releases
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 32
Figure 4.16: Flood Hydrograph at the Boundary Line (BC Line-2) for Large Controlled Releases
4.9 Flood Vulnerability
The vulnerability by Smith et al. (2014), of the community and its assets can be described by using
thresholds related to the stability of people as they walk or drive through floodwaters, or take
shelter in a building during a flood. The vulnerability to hazard will also be influenced by whether
the primary consideration is strategic land use planning aimed at ensuring that the land use is
compatible with the flood risk or assessing development proposals or emergency management
planning aimed at addressing residual flood risks.
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 33
Table 4.5: Classification limits for vulnerability thresholds of combined hazard curves.
Hazard
Vulnerability
Classification
Description Classification
Limit (D and
V in
combination,
m2s-1
Limiting Still
Water Depth
(d, m)
Limiting
Velocity
(V, m s-1)
H1 Generally safe for vehicles, people and
buildings.
D x V ≤ 0.3 0.3 2.0
H2 Unsafe for small vehicles D x V ≤ 0.6 0.5 2.0
H3 Unsafe for vehicles, children and the elderly D x V ≤ 0.6 1.2 2.0
H4 Unsafe for vehicles and people D x V ≤ 1.0 2.0 2.0
H5 Unsafe for vehicles and people. All buildings
vulnerable to structural damage. Some less
robust building subject to failure.
D x V ≤ 4.0 4.0 4.0
H6 Unsafe for vehicles and people. All building
types considered vulnerable to failure.
D x V ≤ 4.0 - -
4.10 FLOOD HAZARD REFERENCE VALUES/ POPULATION AT RISK (PAR) /
POTENTIAL LOSS OF LIFE (PLL):
Flood hazard reference values consisting of maximum water depth, maximum depth-averaged
velocity, and flood wave arrival time at various locations downstream of Amarja Dam, Population
at risk as per the 2011 census data and potential loss of life are presented in Table 4.6. The potential
loss of life is approximately estimated based on the settled area inundated to the total settlement
area and then multiplied with the total population and actual population data provided by the
Amarja Dam Engineer. The Reference values were determined close to the identified positions
and represent the degree of danger that would be created by the flood. The settlements along the
downstream of the Amarja Dam were identified using Google earth.
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 34
Sl.no. Location Name Area in Sq.km
Area Intersected in
Sq.km
Percentage of
Intersection
Population as
per 2011
census
Projected Population at
17.13 % as per
Karnataka statics dept
report from 2012-2021. Potential Loss of
Life
1 Auradi 0.128 0.000 0.077 1102 1290.77 1.0
2 Badanhalli 0.062 0.003 4.229 461 539.97 22.8
3 Busnur 0.445 0.056 12.590 5190 6079.05 765.3
4 Chaudapur 0.433 0.021 4.924 4142 4851.52 238.9
5 Chaudapur Tanda 0.164 0.002 1.421 400 468.52 6.7
6 D.Ghangapur Sangama 0.038 0.006 17.113 3900 4568.07 781.7
7 D.Ghangapur Sangama 0.098 0.011 11.641 3960 4638.35 540.0
8 Dangapur 0.241 0.006 2.677 2340 2740.84 73.4
9 Dannur 0.027 0.014 50.956 500 585.65 298.4
10 Diksangi 0.042 0.011 25.394 1516 1775.69 450.9
11 Gangapur 0.804 0.002 0.270 1200 1405.56 3.8
12 Gaudgaon 0.101 0.002 1.721 1615 1891.65 32.6
13 Harnala 0.036 0.000 0.022 550 644.22 0.1
14 Hittal Sirur 0.297 0.016 5.248 3136 3673.20 192.8
15 Ingalgi 0.085 0.001 1.492 188 220.20 3.3
16 Itagi 0.232 0.000 0.015 1589 1861.20 0.3
17 Jawali 0.079 0.021 26.962 1673 1959.58 528.3
18 Karabosga 0.028 0.003 12.066 602 705.12 85.1
19 Karalli 0.065 0.021 33.006 2477 2901.31 957.6
20 Koganur 0.169 0.001 0.431 1350 1581.26 6.8
21 Koganur Cross 0.011 0.005 46.227 300 351.39 162.4
22 Koganur Cross Extn 0.034 0.001 4.378 100 117.13 5.1
23 Kudaki 0.058 0.001 1.475 1304 1527.38 22.5
24 Madra Buzurg 0.149 0.004 2.529 711 832.79 21.1
25 Madra Khurd 0.047 0.004 9.614 2076 2431.62 233.8
26 Place 2 near Korahalli 0.050 0.004 8.838 500 585.65 51.8
27 Tellur 0.158 0.000 0.148 2105 2465.59 3.6
Table 4.6: showing the Potential loss of Life based on percentage area of Inundation for the Projected Population from 2012-2021
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 35
TABLE 4.7: FLOOD HAZARD REFERENCE VALUES
Sl.
no
Location Name Dist_
km
Populati
on at
risk as
per
2011
census
Projecte
d
Populati
on at
17.13 %
as per
Karnata
ka
statics
dept
report
from
2012-
2021.
Potential
Loss of
life
(considerin
g the area
of
inundation
%age)
Overtopping Failure Non-Flood Failure Large Control
Releases
Max
Depth
(m)
Max
Velocity
(m/s)
Flood
wave
arrival
time(hrs)
Max
Depth
(m)
Max
Velocity
(m/s)
Flood
wave
arrival
time(hrs)
Max
Depth
(m)
Max
Velocity
(m/s)
1 Badanhalli 26.80 461.00 539.97 23 5.65 1.41 4.30 4.21 1.24 5.03 4.66 1.15
2 Busnur 3.12 5190.00 6079.05 766 4.53 2.08 0.60 3.65 1.74 1.12 1.82 0.94
3 Chaudapur 28.06 4142.00 4851.52 239 2.89 0.39 4.75 1.43 0.33 5.63 1.93 0.24
4 Chaudapur Tanda 27.67 400.00 468.52 7 0.89 0.26 5.32 0.00 0.00 0.00 0.00 0.00
5 D.Ghangapur
Sangama 34.81 3900.00 4568.07 782 5.69 1.31 6.65 3.79 0.71 7.67 6.10 1.13
6 D.Ghangapur
Sangama 35.21 3960.00 4638.35 540 5.69 1.31 6.65 3.79 0.71 7.67 6.10 1.13
7 Dangapur 6.94 2340.00 2740.84 74 4.48 1.67 1.40 3.74 1.43 1.85 2.55 0.86
8 Dannur 25.03 500.00 585.65 299 5.63 3.05 3.90 4.36 2.37 4.58 4.60 2.30
9 Dannur 24.76 419.00 490.77 0.00 5.63 3.05 3.90 4.36 2.37 4.58 4.60 2.30
10 Diksangi 21.60 1516.00 1775.69 451 4.43 3.20 3.55 2.76 1.94 4.23 2.75 1.90
11 Gangapur 33.73 1200.00 1405.56 4 0.36 0.09 9.63 0.00 0.00 0.00 0.82 0.07
12 Gaudgaon 17.95 1615.00 1891.65 33 2.77 0.93 3.05 1.42 0.72 3.70 1.05 0.59
13 Harnala 37.05 550.00 644.22 1 0.59 0.08 8.82 0.00 0.00 0.00 0.95 0.08
14 Hittal Sirur 11.73 3136.00 3673.20 193 3.69 1.74 2.00 2.88 1.49 2.48 2.10 1.23
15 Ingalgi 29.15 188.00 220.20 4 1.02 0.31 5.97 0.00 0.00 0.00 0.31 0.03
16 Itagi 34.72 1589.00 1861.20 1 0.03 0.05 10.85 0.00 0.00 0.00 0.48 0.05
17 Jawali 7.04 1673.00 1959.58 529 2.85 1.67 1.27 2.20 1.58 1.72 1.31 0.99
18 Karabosga 19.96 602.00 705.12 86 3.43 1.46 3.42 1.85 1.16 4.10 1.82 1.05
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 36
19 Karalli 1.70 2477.00 2901.31 958 4.68 1.34 0.20 3.76 1.24 0.75 1.23 0.49
20 Karbhosga 20.31 600.00 702.78 0.00 2.00 0.06 3.80 0.38 0.02 4.78 0.37 0.01
21 Kerakanahalli 35.30 1162.00 1361.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
22 Koganur 16.64 1350.00 1581.26 7 0.40 0.18 3.47 0.00 0.00 0.00 0.00 0.00
23 Koganur Cross 17.40 300.00 351.39 163 2.17 1.27 3.03 0.83 1.00 3.75 0.46 0.80
24 Koganur Cross
Extn 17.71 100.00 117.13 6 1.56 0.89 3.18 0.31 0.29 4.03 0.00 0.00
25 Kudaki 15.39 1304.00 1527.38 23 1.13 0.64 2.83 0.12 0.66 3.62 0.00 0.00
26 Madra Buzurg 24.53 711.00 832.79 22 1.05 1.04 4.45 0.00 0.00 0.00 0.00 0.00
27 Madra Khurd 21.80 2076.00 2431.62 234 5.27 2.51 3.53 3.56 2.26 4.18 3.56 2.12
28 Place 2 near
Korahalli 1.76 500.00 585.65 52 1.62 0.95 0.75 0.69 0.70 1.20 0.00 0.00
29 Tellur 33.31 2105.00 2465.59 4 1.56 1.13 6.58 0.00 0.00 0.00 1.57 0.94
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 37
5. FLOOD INUNDATION MAPPING
An Emergency Action Plan (EAP) is a formal document that identifies potential emergency
conditions at a dam and specifies pre planned actions which are required to be followed for
minimizing damage to proper-ties and loss of life. The EAP specifies actions for the dam owner,
in coordination with emergency management authorities, to be taken while responding to incidents
or emergencies related to the dam. It presents procedures and information for assisting the dam
owner in issuing warnings and notification messages to responsible downstream emergency
management authorities. The EAP includes inundation maps for assisting the dam owner and
emergency management authorities in identifying critical infrastructure and sites with huge
population at risk, which may require protective measures and warning as well as evacuation
planning.
Inundation maps showing
1) Maximum water depth in m
2) Maximum water velocity in m/s
3) Maximum water-surface elevation in m-MSL and
4) Flood wave arrival time are prepared for each of the three flood scenarios considered.
Flood inundation maps for the parameters mentioned above were prepared using Arc GIS software.
The Scale of the map is 1:25,000. The total length of the inundation downstream of Amarja Dam
is about 53 km has 17 tiles per scenario. The projection type is WGS-84 UTM zone 43 N. The
settlement layer is obtained by distinguishing the settlement boundary from google earth.
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 38
6. CONCLUSIONS:
❖ The Amarja dam break analysis is carried out for tier 2 approach using medium resolution
terrain data.
❖ About 29 villages are found to be affected in case of Amarja dam breach.
❖ The people living in villages within 1 km downstream of Amarja dam are most vulnerable
as the flood wave arrival time is less.
❖ The peak breach flow obtained is 10,546.36 m3/s and 8248.88 m3/s for overtopping and
piping failure respectively.
❖ The breach velocity at the time of failure is 2.70 m/s and 2.24 m/s for overtopping failure
and piping failure respectively which are well within the recommended limits.
❖ It is observed that the inundation on both sides of the river is significant in case of flood
due to large controlled release.
❖ At a distance of approximately 53 km from the dam site, it is observed that the flood water
will be confined to the river course.
❖ Flood maximum depth, maximum velocity, Flood arrival time, Water surface elevation and
vulnerability maps are prepared at a scale of 1:25000.
❖ The developed inundation maps are useful for preparation of EAP (Emergency Action
Plan).
Amarja -Flood Inundation Maps, Karnataka
Advanced Center for Integrated Water Resources Management (ACIWRM), GoK 39
REFERENCES:
1. ALOS Global Digital Surface Model (DSM) “ALOS World 3D-30m” (AW3D30) Dataset,
Version 1 Earth Observation Research Center (EORC), Japan Aerospace Exploration
Agency (JAXA). March 2017.
2. Design Flood Studies report of Amarja Dam “Water Resources Development
Organization” May 2015.
3. KERS report on “Kabini Dam Break Studies” March 2018.
4. TD-39 Using HEC-RAS for Dam break studies, August 2014, US Army Corps of
Engineers, Hydrologic Engineering Center.
5. CPD-68A; HEC-RAS River Analysis System 2D Modeling User’s Manual, Version 5, Feb
2016.
6. Doc.No. CDSO-GUD-DS-05-VI.0 Guidelines for Mapping Flood Risks Associated with
Dams January 2018, CWC, MOWR, River Development and Ganga Rejuvenation, GOI.
7. An Empirical Model of Embankment Dam Breaching by David C Froehlich, third National
Dam Safety Conference 18-19 Feb 2017, Roorkee, India.
8. Embankment Dam Breach Parameters and their Uncertainties by David C Froehlich,
Journal of Hydraulic Engineering, Dec 2008.
9. Manual on Estimation of Design Flood by CWC, New Delhi Mar 2001.
10. Predicting Peak Discharge for gradually breached embankment dam, by David C
Froehlich, Journal of Hydrologic Engineering, July 2016.
11. IS 11223-1985 (RA-1995), Guidelines for fixing spillway capacity.
12. CPD-74A; Hydrologic Modeling System HEC-HMS, User’s Manual version 4.2, Aug
2016 by US Army Corps of Engineers, Hydrologic Engineering Center.
13. Projected Population of Karnataka 2012 – 2021 issued by Directorate of Economics and
Statistics, Bangalore – 2013.
14. Population 2011 census data, GoI, data.gov.in
Advanced Centre for Integrated Water Resources Management
Water Resources Department, Govt. of Karnataka
No. 1/1, 1st Floor, K.S.F.C Bhawan, Thimmaiah Road Bengaluru – 560052
Phone No: 080-22262042/43/44 Fax No: 080-22262045
ACIWRM
The Advanced Centre for Integrated Water Resources Management (ACIWRM) was
established to become a Global Centre of Excellence by Government of Karnataka in
February 2012. ACIWRM acts as a think tank to the government’s Water Resources
Department (WRD). It is engaged in policy analysis, research, planning, capacity building
and developing the knowledge base for gearing up the department up to its future vision
2030. The ACIWRM works with the various departments, civil society, the private sector,
farmers and water user associations and other organizations to produce integrated advice to
the WRD for managing the State’s water resources.
KEY AREAS ❖ Karnataka Water Resources Information System (K-WRIS)
❖ IWRM Training and Capacity Building
❖ River Basin Planning & Management
❖ River Basin Modelling
❖ Communication, Awareness Raising and Participation
❖ Water Use Efficiency, Water Accounting and Water Productivity
❖ State IWRM Policy and Strategy
❖ Sustainable Groundwater Management
❖ Participative Land and Water Management Plans (LWMP)
❖ Climate Change / Variability / Adaptability for Water Sector
SUGAR FACTORY
KARALLI
PLACE 2 NEAR KORAHALLI
AMARJA DAM
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, andthe GIS User Community
76°34'0"E
76°34'0"E
76°35'0"E
76°35'0"E
76°33'0"E
76°33'0"E17
°29'0"
N17
°28'0"
N
9
8
5
76
32
4
111512 13 16
17
1014
Source: Esri, DigitalGlobe, GeoEye,Earthstar Geographics, CNES/AirbusDS, USDA, USGS, AeroGRID, IGN,and the GIS User Community
Depth (m)0 - 0.30.30 - 0.600.60 - 1.201.20 - 2.002.00 - 3.003.00 - 5.005.00 - 10.00> 10.00
ROADSRAILWAYSSETTLEMENT
Locator Map
AMARJA DAM, KARNATAKAOVERTOPPING FAILURE
MAXIMUM DEPTH ¯
0 0.4 0.8 1.2 1.60.2Km
WATER RESOURCES DEPARTMENTGOVT. OF KARNATAKADAM REHABILITATION AND IMPROVEMENT PROJECTADVANCED CENTRE FOR INTEGRATED WATER RESOURCES MANAGEMENT (ACIWRM)
Name of Dam : AMARJA DAM, KARNATAKAState : KARNATAKA
Doc No :MAP No: MARCH, 2019
Title : OVERTOPPING FAILUREMAXIMUM DEPTHKaWRD_MAP_AMARJA_01
1 / 17 May 2019