Project Rehabilitation Report of KRS Dam
i | P a g e
Project Rehabilitation Report of
Krishnarajasagara (KRS) Dam,
Karnataka Water Resources Department
Doc. No.: CDSO_DSR_PRR_ KA06HH0020_KaWRD_v1.0
July, 2020
Central Water Commission
Ministry of Jal Shakti
Department of Water Resources,
River Development & Ganga Rejuvenation
Government of India
Project Rehabilitation Report of KRS Dam
ii | P a g e
Quality Control:
Version Date Writers/Contributors Checked by
1 31/07/2020 Dr. Hadush S Hagos (HSH) Hemant Joshi (HJ)
Rajiv Kumar Sawarn
Issued/Copied to:
I/C Date Name Organization
Issued 31/07/2020 Shri. Pramod Narayan Central Water Commission
Project Rehabilitation Report of KRS Dam
iii | P a g e
Abbreviations
DRIP Dam Rehabilitation & Improvement Project
CWC Central Water Commission
CPMU Central Project Management Unit
CSV Construction Site Visit
SPMU State Project Management Unit
IA Implementation Agency
PIC Project Identification Code
DSRP Dam Safety Review Panel
PST Project Screening Template
DFR Design Flood Review
MSL Mean Sea Level
FRL Full Reservoir Level
MWL Maximum Water Level
TBL Top Bund Level (Top Level of Dam)
MDDL Maximum Draw Down Level
LSL Lowest Sill Level
DSL Dead Storage Level
U/S Upstream
D/S Downstream
El. Elevation
L/B Left Bank
R/B Right Bank
PMF Probable Maximum Flood
SPF Standard Project Flood
CD Works Cross Drainage Works
VRB Village Road Bridge
WBM Water Bound Macadam
NDT Non Destructive Testing
DHARMA Dam Health And Rehabilitation Monitoring Application
O & M Operation and Maintenance
EAP Emergency Action Plan
Project Rehabilitation Report of KRS Dam
iv | P a g e
ESMF Environmental and Social Management Framework
E & S specialists Environmental and Social Specialists
HM Works Hydro-Mechanical Works
EM Works Electro-Mechanical Works
SCADA Supervisory Control and Data Acquisition System
DG Set Diesel Generator Set
MW Mega Watt
MU Million units
Ha Hectare
MCM Million Cubic Metre
Deg. Degree
Min. Minute
Sec. Second
CM Construction management
QC Quality control
m meter
m3 Cubic meter
m3/sec Cubic meter per second
Km2 Square kilometre
MCM Million cubic meter
TNWRD Tamil Nadu Water Resource Department
TANGEDCO Tamil Nadu Generation and Distribution Corporation
KWRD Kerala Water Resource Department
KSEB Kerala State Electricity Board
MPWRD Madhya Pradesh Water Resource Department
UJVNL Uttarakhand Jal Vidyut Nigam Limited
DVC Damodar Valley Corporation
Project Rehabilitation Report of KRS Dam
v | P a g e
DRIP Component Wise Project Cost
KaWRD Initial/Revised Projects & Cost
BACKGROUND
In April 2012, the Central Water Commission
(CWC) with assistance from the World Bank,
embarked upon a six year Dam
Rehabilitation and Improvement Project
(DRIP) at a preliminarily estimated initial cost
of Rs.2100 Crore targeting rehabilitation and
improvement of about 250 dams initially of
six, later of nine implementing agencies -
namely: MPWRD, OWRD, TNWRD,
TANGEDCO, KWRD, KSEB, KaWRD,
UJVNL and DVC.
In June 2018, the project was extended by
two years, until June 2020. The current
revised cost for DRIP is Rs.3466 Crore out of which Rs. 2920.5 Crore is allocated for
Component 1 (Rehabilitation and Improvement of Dams and Associated Appurtenances),
Rs.232.5 Crore for Component 2 (Dam Safety Institutional Strengthening), and Rs.313 Crore
for Component 3 (Project Management). Appropriate assistance is also provided under
DRIP to develop O & M Manuals and Emergency Action Plans (EAP) for these dams. The
project also promotes new technologies and improves institutional capacities for dam safety
evaluation and implementation at the Central and State levels as well as in some identified
premier academic and research institutes in the country. The actual total number of dams
under DRIP stands at 223.
The Implementing Agencies for DRIP are the Water Resources Departments and State
Electricity Boards in the participating States and Damodar Valley Corporation (DVC) with
Central Water Commission at Central Level. State Implementing Agencies are responsible
for implementation of works of dams under their charge. Co-ordination and management of
such works within a State rests with the
concerned State Project Management
Unit (SPMU). Overall project oversight
and coordination is carried out by Central
Project Management Unit (CPMU) headed
by the Project Director with assistance of
an Engineering and Management
Consultant.
Karnataka Water Resource Department
(KaWRD) joined DRIP in August 2014
with initial number of dams totalling 31.
Later, KaWRD dropped 9 dams and
continuing in DRIP with 22 dams.
Preliminarily estimated initial DRIP project
cost for KaWRD was Rs.276.1 Crore and
the revised actual current project cost is
Rs.581.2 Crore.
Project Rehabilitation Report of KRS Dam
vi | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of KRS Dam
vii | P a g e
Table of Contents
1. EXECUTIVE SUMMARY .................................................................................. 1
2. PROJECT DETAILS ......................................................................................... 2
2.1 Project Description .......................................................................................................... 2
2.2 Project Location ............................................................................................................... 2
2.3 Project Benefits ................................................................................................................ 2
2.4 Dam and Reservoir Features (Before rehabilitation under DRIP) ............................... 3
2.5 Any Emergency Spillway, Fuse Plug etc. ...................................................................... 4
2.6 Details of previous dam incidents, if any ...................................................................... 4
2.7 PST Details ....................................................................................................................... 4
2.8 DSRP, CPMU and World Bank Recommendations and Compliance ......................... 5
2.9 Scope of Rehabilitation Works as per PST ................................................................... 5
2.10 Drawings ......................................................................................................................... 19
3. DAM VISITS (PST STAGE) ............................................................................ 26
3.1 Dam Inspections ............................................................................................................ 26
3.2 Summary of observations made by CPMU ................................................................. 26
4. DESIGN FLOOD REVIEW (DFR) ................................................................... 26
4.1 DFR Outcome ................................................................................................................. 26
4.2 Brief Summary of Review.............................................................................................. 26
4.3 Recommendations ......................................................................................................... 26
5. REHABILITATION WORKS CARRIED OUT ................................................. 26
5.1 Summary of Investigations ........................................................................................... 26
5.2 Main Dam Works ............................................................................................................ 27
5.3 Basic facilities ................................................................................................................ 27
6. INSTRUMENTATION ..................................................................................... 27
6.1 List of existing instruments installed in dam and their condition ............................ 27
6.2 Details of new instruments installed ........................................................................... 28
6.3 CPMU Recommendations ............................................................................................. 28
7. PROCUREMENT OF WORKS ....................................................................... 29
7.1 Package wise details ..................................................................................................... 29
7.2 Details of bidding process ............................................................................................ 31
7.3 Reason for Variation, if any .......................................................................................... 31
7.4 Litigation / Arbitration, If Any ....................................................................................... 31
8. THIRD PARTY CONSTRUCTION SUPERVISION VISITS BY CPMU ........... 31
8.1 Summary of Visits undertaken ..................................................................................... 31
8.2 Summary of Third Party Material Testing .................................................................... 31
8.3 Summary of Major Recommendations ........................................................................ 31
Project Rehabilitation Report of KRS Dam
viii | P a g e
8.4 Summary of Compliance by SPMU .............................................................................. 37
8.5 Summary of any Special Visits made by CWC/World Bank/Expert Committee ...... 37
8.6 Summary of Technical Assistance provided by CPMU ............................................. 37
9. ENVIRONMENTAL AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) 37
9.1 Basic Details ................................................................................................................... 37
9.2 Summary of Observations ............................................................................................ 37
9.3 Details of ESMF/EIA study (if any) ............................................................................... 37
10. OTHER NON-STRUCTURAL INTERVENTIONS ........................................... 37
10.1 Basic Details ................................................................................................................... 37
10.2 Summary of Observations ............................................................................................ 38
11. PENDING REHABILITATION WORKS .......................................................... 38
11.1 Details of pending works .............................................................................................. 38
11.2 Further course of action................................................................................................ 38
12. REFERENCES ............................................................................................... 38
LIST OF FIGURES
Figure 2-1: Bird’s eye View of KRS Dam ......................................................................... 19 Figure 2-2: Google Map of KRS Dam ............................................................................... 20 Figure 2-3: Water Catchment Map of KRS Dam .............................................................. 21 Figure 2-4: Index Map KRS Dam ...................................................................................... 22 Figure 2-5: Plan of KRS Dam and Brindavan Ganden .................................................... 23 Figure 2-6: Site Plan and Longitudinal Section of KRS Dam ......................................... 24 Figure 2-7: Cross-section of non-overflow section ........................................................ 25
Annex A: PST Approval Letter .............................................................................. 39
Annex B: Drawings issued for Rehabilitation measures .................................... 43
Annex C: Completion Certificate .......................................................................... 51
Annex D: Photographs Before and After Rehabilitation Works ......................... 57
Annex E: Compliance as Received from Project Authorities ............................. 69
Annex F: DBA and Inundation Maps .................................................................... 93
Project Rehabilitation Report of KRS Dam
1 | P a g e
1. EXECUTIVE SUMMARY
This Project Rehabilitation Report (PRR) is for KRS Dam, which is one of the 22
dams under DRIP in Karnataka. The Dam Safety Review Panel (DSRP) inspected
the dam in May 2014 and recommended both structural & non-structural measures to
be taken up by the dam authorities.
DSRP main recommendations included arresting leakage/seepage through the dam
body by deep racking of the joints and filling with epoxy mortar, as well as covering
the treated portion of the dam with shortcreting (8 to 10 cm thick) over steel mesh
which should be fixed to the upstream face; rectification of damaged sections of the
right side guide wall of scouring sluice at +50 levels; repair/covering all prominent
scour depression noticed in the chute spillway channel at 34.30 m and 81.30 m
downstream of the dam axis with apron concrete on the top surface; replacement of
all broken and cracked gates by new gates having indigenous Teflon cladded seals.
Non-structural measures included checking profile of the dam for full uplift conditions
as well as seismic conditions of loading as stipulated in relevant IS code; assessing
Probable Maximum Flood (PMF) discharge at the dam after obtaining updated Hydro
meteorological data from IMD; preparation of Emergency Action Plan including
suitable communication system of flood forewarning as well as continuation of
bathymetric survey being carried out by KERS at ever 5 to 10 years interval.
The existing surplus flood release sluices were designed for a flood release capacity
of 9911 cumec. The revised design flood (PMF) under DRIP worked out to be 17010
cumec. Flood routing study carried by the SPMU as part of the Dam Breach Analysis
(DBA) indicates that the revised MWL is at EL 754.88 m. The Top level of dam (TBL)
is at EL 754.08 m. Hence the available freeboard is not sufficient for the revised
design flood as per IS 6512. Therefore, structural and non-structural measures are
needed to accommodate the revised design flood for dam safety.
Following DSRP recommendations, rehabilitation works carried out under DRIP
included:
i) Racking and pointing of upstream face with UV resistant, high strength, non-
shrink Poly Ironite Ceramic Cementitious (PICC) mortar.
ii) Drilling and grouting of dam body.
iii) Steel Fibre Reinforcement Shotcrete (SFRS) treatment to U/S above FRL in
view of severe wave splashing impact.
iv) Conducting videography in drilled 150 mm diameter core holes.
v) Carryout the water percolation/permeability test in investigation hole and test
holes.
The rehabilitation works were executed under 1 package at a total completion cost of
Rs. 6661 Lakhs including a variation of Rs. 2999 Lakhs. The other package of
replacement of 136 gates at a Contract Amount of 58.46 Crore is currently under
progress. Hence, this PRR needs to be updated in the future after the 136 gates
replacement work is completed.
SPMU carried out dam break analysis and prepared inundation maps, which were
reviewed and approved by CPMU. Based on this, the SPMU prepared Emergency
Action Plan (EAP), which was reviewed by CPMU and being finalized by SPMU. The
SPMU also prepared Operation and Maintenance (O&M) manual as per CWC/DRIP
guidelines, which was reviewed by CPMU and published.
Project Rehabilitation Report of KRS Dam
2 | P a g e
2. PROJECT DETAILS
The Krishnarajasagara Dam is located across Cauvery River near Krishnarajasagara village, Sriranagapatna taluk and Mandya district of Karnataka state, at Latitude of 12º 25’00” N and Longitude of 76º 33’ 30” E. It was completed in the year 1932 and the project consists of a masonry gravity dam constructed of surki mortar of 2621 m long, maximum height of 44.66 m and 4.12 m dam crest width. It has a total of 152 surplus sluices at different elevations (excluding 8 sluices at lowest level permanently plugged) with a design flood discharge capacity of 9911 cumec.
The TBL, FRL, and original MWL are at EL 754.32 m, 752.489 m, and 752.489 m, respectively. The surplus flood sluices are at RL +12 FT (8 Nos. all plugged), RL +80 FT (16 Nos.), RL +103 FT (48 Nos.), RL +106 FT (40 Nos.), and RL +114 FT (48 Nos.). The gross storage at FRL is 1400.32 MCM (or 49.452 TMC).
2.1 Project Description
Sl. No.
Item Details
a. Project Identification Code (PIC) KA06HH0020
b. Project Name Krishnarajasagara Dam
c. River Basin Cauvery
d. Sub River Basin Cauvery
e. River/Stream Cauvery
f. Catchment area (km2) 10619
g. Year of commencement of project 1911
h. Year of completion of project 1932
2.2 Project Location
Sl. No.
Item Details
a. State Karnataka
b. District Mandya
c. Earthquake Zone II
d. Survey of India Map Ref No’s 57D/11
e. Nearest City Mysore
f. Nearest Airport Mysore
g. Nearest Railhead KRS Railway Station
h. Name of Immediate U/S Project Hemavathy and Harangi
i. Name of Immediate D/S Project Mettur
j. Latitude in Deg., Min, Sec. (North) 12º 25’00”
k. Longitude in Deg., Min, Sec. (East) 76º 33’ 30”
2.3 Project Benefits
Sl. No. Item Details
Project Rehabilitation Report of KRS Dam
3 | P a g e
Sl. No. Item Details
a. Type of Project Multipurpose
b. Irrigation –
Gross Command Area (Ha.) 111681
c. Irrigation –
Colourable Command Area (Ha.) 111681
d. Irrigation –
Annual Irrigation Potential in (Ha). 111681
e. Hydropower –
Installed Capacity (MW) 16
f. Hydropower –
Firm Power (MW) 12+4
g. Hydropower –
Average Annual Generation (MU) 72
h. Domestic/Municipal/Industrial Water –
Annual Quantum (MCM) Nil
i. Domestic/Municipal/Industrial Water –
Area and Population Benefitted Nil
j. Flood Protection –
Flood Protected Area (Ha) Nil
k. Flood Protection –
Details of Area Benefitted Nil
l. Details of Tourism/Recreational Facilities Nil
2.4 Dam and Reservoir Features (Before rehabilitation under DRIP)
Sl. No.
Item Details
a. Full Reservoir Level (m) 752.489
b. Original Maximum Water Level (m) 752.489
c. Gross Reservoir Storage Capacity at FRL (Mm3 )
1400.32
d. Live Storage Capacity (Mm3 ) 1275.38
e. Revised Live Storage Capacity, if any
(Mm3 )
NA
f. Date of bathymetric survey, if any NA
g. Dam Type
h.
Length of Dam at Top (m)
i) Total length of the main dam
ii) Length of embankment dam
iii) Length of masonry/concrete dam
2621
NA
2621
i. Number and length of dykes (No. & m)
Project Rehabilitation Report of KRS Dam
4 | P a g e
Sl. No.
Item Details
j. Top of dam (El. in m.) 754.32
k. Top Level of Upstream Parapet Wall of main dam (El. in m.)
l.
Height of Dam (m)
i) Embankment dam – above river bed level (up to dam top without camber)
ii) Concrete/Masonry dam – above deepest foundation level (up to dam top)
NA
44.66
m Top width of main dam (m) 4.12
n.
Details of Surplus Release Sluice Gates
Sluice Level Height
(m) Width (m) Nos. REMARKS
+12 FT -- -- 08 Permanently plugged since May 2007
+80 FT 3.00 6.00 16 All gates are replaced recently under state grants.
+103 FT 2.44 3.00 48 Proposed to replace under DRIP (Work in Progress)
+106 FT 3.66 2.66 40 Proposed to replace under DRIP (Work in Progress)
+114 FT 3.00 3.00 48 Proposed to replace under DRIP (Work in Progress)
o.
Outlet/Sluice details
i) Turbine Sluices +53’ – 4 Gates (Since inception it is not Operated)
ii) Irrigation Sluices +60’ – 6 Gates
Note: All elevations are above MSL
2.5 Any Emergency Spillway, Fuse Plug etc.
Nil
2.6 Details of previous dam incidents, if any
Nil
2.7 PST Details
Sl.
No. Item Date/Cost Remarks
a. PST first received from SPMU May 2015
b. Proposed PST Cost (INR in Lakhs) 5958
c. First review by CPMU 28.08.2015
d. Second Version of PST January 2016
e. Proposed PST Cost (INR in Lakhs) 6781
g. Second review by CPMU 22.04.2016
Project Rehabilitation Report of KRS Dam
5 | P a g e
h. Final Version of PST May 2016
i. Proposed PST Cost (INR in Lakhs) 6633.00
j. Final review by CPMU 21.06.2016
n. World Bank Approval 16.08.2015 Via e-mail
o.. Approved PST Cost (INR in Lakhs) 5958.00
2.8 DSRP, CPMU and World Bank Recommendations and Compliance
2.8.1 DSRP Recommendations and Compliance
Compliance to DSRP recommendations as obtained from dam authorities as part of
SPMU draft PRR is shown on pages 7 to 17 below.
2.8.2 CPMU/World Bank Recommendations and Compliance
Compliance to World Bank observations during PST review stage is attached in
Annexure E.
2.9 Scope of Rehabilitation Works as per PST
(a) Remedial measures
Rehabilitation & improvements to 100 years old Krishna Raja Sagara dam
under DRIP by conducting detailed investigations, carrying out treatment to
upstream face by pointing with UV resistant and anti-shrink materials like
cements using crystalline technology(CT) or Poly Ironite Ceramic
Cementitious(PICC) or equivalent materials (where required) conforming to
BIS/EN-1504-3, ClassR4(2014) standard, steel fibre reinforced shotcrete
above FRL in view of severe splashing /impact of water, extraction of cores,
videography of boreholes and water loss testing as directed, dam body
grouting(where required) to arrest the seepage & to improve the structural
strength of the dam. (Package-I)”
Providing and supplying 2 Nos. Scorpio vehicles to K.R.S. Dam.
Replacing flood Gates of +103 feet Sluice Gates covering +114 & +103 vents
and Replacement of +106 Ft Sluice gates at KRS Dam.
Consultancy services for CWPRS, Pune or any reputed institution for
construction and control supervision of the works relating to the treatment of
the upstream face of masonry dam.
Consultancy services for, engaging a grouting specialist / reputed agency well
versed in drilling & grouting to supervise grouting operations on a continuing
basis.
Conducting Test Pre and Post Grouting Non-Destructive Surface Geophysical
Investigations using Electrical Resistivity Imaging, Seismic Refraction and
Refraction Micro-Tremor (ReMi) for a section length of 750m at dam crest to
determine electrical resistivity distribution, P wave velocities and S wave
velocities”
Consultancy services including inspection & supervision of each and every
activity covering quality assurance plan, procurement of materials, fabrication,
erection, testing and commissioning of gates for Replacing flood Gates of
+114, +103 & +106 feet Sluice Gates at KRS Dam.
Project Rehabilitation Report of KRS Dam
6 | P a g e
Consultancy services for Review of Operation and maintenance manual of
gates, Stability analysis of KRS Dam, Preparation of inundation maps, Setting
up of warning system, Flood routing study, Preparation of PSTs.,
Providing and fixing of Echo Sounder-Model: Bathy 500 dual frequency,
DGBS Beacon-cum-heading receiver-Model SPS 461, Single Beam Software
for Data logging and processing-Model NAVISUITE, Panasonic/equivalent
tough book,
Supplying and installing wire piezo meter / pore pressure meter, wire uplift
pressure system unit, Surface settlement units, automatic non-contact Radar
based water level monitoring system, Mechanical Type Crack Meter,
Automatic Weather Station, Wind speed and Direction, Tipping Bucket Rain
gauge, Relative humidity, Solar panel, with Telemetry & Sonic Tomography
Video Ray/equivalent ROV including voyager submersible, control box,
Turbidity sensor system and real time video enhancement for the ROV
system.
Project Rehabilitation Report of KRS Dam
7 | P a g e
Project Rehabilitation Report of KRS Dam
8 | P a g e
Project Rehabilitation Report of KRS Dam
9 | P a g e
Project Rehabilitation Report of KRS Dam
10 | P a g e
Project Rehabilitation Report of KRS Dam
11 | P a g e
Project Rehabilitation Report of KRS Dam
12 | P a g e
Project Rehabilitation Report of KRS Dam
13 | P a g e
Project Rehabilitation Report of KRS Dam
14 | P a g e
Project Rehabilitation Report of KRS Dam
15 | P a g e
Project Rehabilitation Report of KRS Dam
16 | P a g e
Project Rehabilitation Report of KRS Dam
17 | P a g e
Project Rehabilitation Report of KRS Dam
18 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of KRS Dam
19 | P a g e
2.10 Drawings
Figure 2-1: Bird’s eye View of KRS Dam
Project Rehabilitation Report of KRS Dam
20 | P a g e
Figure 2-2: Google Map of KRS Dam
Project Rehabilitation Report of KRS Dam
21 | P a g e
Figure 2-3: Water Catchment Map of KRS Dam
Project Rehabilitation Report of KRS Dam
22 | P a g e
Figure 2-4: Index Map KRS Dam
Project Rehabilitation Report of KRS Dam
23 | P a g e
Figure 2-5: Plan of KRS Dam and Brindavan Ganden
Project Rehabilitation Report of KRS Dam
24 | P a g e
Figure 2-6: Site Plan and Longitudinal Section of KRS Dam
Project Rehabilitation Report of KRS Dam
25 | P a g e
Figure 2-7: Cross-section of non-overflow section
Project Rehabilitation Report of KRS Dam
26 | P a g e
3. DAM VISITS (PST STAGE)
3.1 Dam Inspections
Sl. No.
Item Date of visit Remarks
a. Dam Safety Review Panel (DSRP) May 2014
b. Site Visit made by CPMU experts August 2015
3.2 Summary of observations made by CPMU
All the observation along with compliance is attached as Annex. - E.
4. DESIGN FLOOD REVIEW (DFR)
4.1 DFR Outcome
Sl. No. Item Original
Value
Revised
Value Remarks
a. Inflow Design Flood (m3/s) 9911 17010
b. Spillway Capacity / Routed Outflow (m3/s) 9911 --
c. Maximum Water Level (m) 754.32 754.88* TBL-754.08 m
*Based on results of flood routing carried out as part of DBA study.
4.2 Brief Summary of Review
The existing surplus flood release sluices were designed for a flood release capacity of 9911 cumec. The revised design flood (PMF) under DRIP worked out to be 17010 cumec. Flood routing study carried by the SPMU as part of the Dam Breach Analysis (DBA) indicates that the revised MWL is at EL 754.88 m. The Top level of dam (TBL) is at EL 754.08 m. Hence the available freeboard is not sufficient for the revised design flood as per IS 6512. Therefore, structural and non-structural measures are needed to accommodate the revised design flood for dam safety.
4.3 Recommendations
Structural measures – detailed flood routing study to be carried out and come up
with structural measure to accommodate the revised design flood.
Non-structural measures – modifying rule curve, EAP.
5. REHABILITATION WORKS CARRIED OUT
5.1 Summary of Investigations
Sl. No.
Item Details Remarks
a. Geo-Physical Investigations Borehole videography of
150 mm dia. Holes predrilled up to 40 m depth
b. Geo-Technical Investigations Nil
c. Hydraulic Model Studies Nil
Project Rehabilitation Report of KRS Dam
27 | P a g e
5.2 Main Dam Works
Sl. No.
Item Details Remarks
a.
Works because of Seepage / leakage issues in Gravity dams / spillways (u/s face treatment, grouting of dam body etc.)
Providing and applying PICC pointing and grouting to the body of dam
Drilling and grouting of dam body as well as nipple grouting of leaked areas
Completed
b. Any other works
Steel Fibre Reinforcement Shotcrete (SFRS) treatment to U/S face above FRL in view of severe wave splashing impact.
Drilling 150 mm diameter core hole fore bore hole videography.
Conducting Bore hole videography in drilled 150 mm diameter core hole.
Drilling of 76 mm diameter hole for investigation.
Carryout water percolation/permeability test in investigation holes.
Drilling 51-57 diameter core holes and re-drilling 51-57 mm diameter core holes.
Providing upheaval gauge in dam body.
Completed
c. Hydro-mechanical works
i. Main spillway gates & hoists Replacement of 136 gates for surplus flood release Work in
Progress
To be incorporated in
to this PRR after completion
ii. Outlet gates & hoists
5.3 Basic facilities
S/N Item Details Status
a. Lighting Nil
b. Roads Nil
c. Security Nil
6. INSTRUMENTATION
6.1 List of existing instruments installed in dam and their condition
Digital Water Level Recorder Automatic Water Level Recorder Radar River Gauging System
All of the above instruments are not in working condition.
Project Rehabilitation Report of KRS Dam
28 | P a g e
6.2 Details of new instruments installed
Nil
6.3 CPMU Recommendations
The following instruments have been recommended under DRIP and are currently in the process of
procurement
No. INSTRUMENTS
1 Automatic Water Level Recorder
2 AUTOMATIC WEATHER STATION
3 Automatic pendulum
4 Normal Plumb line device
5 Resistance type Temperature sensor
6 vibrating wire/ MEMS biaxial type Tilt meter
7 vibrating wire type Joint meter / Crack meter
8 vibrating wire type Uplift pressure meter
9 V-Notch weir
10 Settlement Plate/ Survey markers.
11 Data Collection Unit and Transmission equipment
12 Piezometer
13 Electronic Total Station
Project Rehabilitation Report of KRS Dam
29 | P a g e
7. PROCUREMENT OF WORKS
7.1 Package wise details
Work Package No.
Name of Works
Estimated Cost
(INR in Lakhs)
Procurement
Method
Invitation for bids / NIT
Issue date
Pre-Bid Meeting date
Bid Opening date
Contract Agreement
No.
Contract Agreement date
Contractor’s Name &
Address
Scheduled
Duration (Months)
Scheduled
Completion date
Actual Date of
Completion
Contract / Award Value
(INR in Lakhs)
Completion Cost (INR in Lakhs)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
1
Rehabilitation and
improvements to 100 years
old KRS DAM under DRIP by
conducting detailed
investigations, carrying out treatment to
upstream face by pointing with
UV resistant and anti-shrink materials like
cements using crystalline
technology(CT) or poly ironite
ceramic cementitious
(PICC0 or eqivalent materials (where
reqired)conforming to BIS/ EN-1504-3,class
R4(2014)
3864.20
NCB 11.01.
16 10.12.
15 11.01.
16
Original Agreement
No. 127/2016-17 Dated
21.07.2016
Supplementary
Agreement No. No.
1/2018-19 Dated
27.12.2018
Supplementary
Agreement No. No.
2/2019-20 Dated
31.10.2019
21.07.16 (Original
)
M/s Ferro Concrete
(India) Private
Limited, #42 Bhagirath Pura Main
Road Rafeli, Bhagirathpura, Indore, Madhya Pradesh
24 20.07.18 26.06.19
Initial 3662
Amendment (2 no)
2999
6661
Project Rehabilitation Report of KRS Dam
30 | P a g e
Work Package No.
Name of Works
Estimated Cost
(INR in Lakhs)
Procurement
Method
Invitation for bids / NIT
Issue date
Pre-Bid Meeting date
Bid Opening date
Contract Agreement
No.
Contract Agreement date
Contractor’s Name &
Address
Scheduled
Duration (Months)
Scheduled
Completion date
Actual Date of
Completion
Contract / Award Value
(INR in Lakhs)
Completion Cost (INR in Lakhs)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
standard, steel fibre reinforced
shotcrete above FRL in
view of servere splashing/impa
ct of water, extraction of
cores, videography of boreholes and
water loss testing as
directed, dam body
grouting(where required) to arrest the
seepage & to improve the
structural strength of the
dam works
6661 6661
Project Rehabilitation Report of KRS Dam
31 | P a g e
7.2 Details of bidding process
As per details in the above table.
7.3 Reason for Variation, if any
Increase in actually required quantities more than in the BoQ quantities tendered
awarded initially.
7.4 Litigation / Arbitration, If Any
Nil
8. THIRD PARTY CONSTRUCTION SUPERVISION VISITS BY
CPMU
8.1 Summary of Visits undertaken
Sl. No. Date of visit Transmittal details of CSV
Report
a. 29.07.2016 3592/12.08.2016
b. 15.12.2016 4040/30.12.2016
c. 15.12.2016 & 02.02.2017 7672/06.06.2017
d. 07.06.2017 4728 /28.06.2017
e. 08.09.2017 5264/20.11.2017
8.2 Summary of Third Party Material Testing
Nil
8.3 Summary of Major Recommendations
1st Construction Site Visit Report
Observations & Recommendations:
Low quality of Safety Standards. Masonry wall treatment was performed using inadequate scaffold.
Insufficient length of the bracket: The platform could not reach properly the wall surface for the presence of a masonry wedge
The platform itself did not have adequate handrail. Adequate PPE were not distributed to the labors (Safety Shoes).
Recommendations
The Contractor is recommended to address aforementioned observations at the earliest.
Lab test needs to be set up.
2nd Construction Site Visit Report
Observations and Quality Control issues:
Site visit and discussions:
This was the first such visit to KRS dam, when there was no water in the u/s part of the dam and the embedded parts & u/s dam was fully accessible and could be closely seen. The majority of the cast iron tracks and side angles were
Project Rehabilitation Report of KRS Dam
32 | P a g e
found in very good condition. The grooves were found in very sound masonry not requiring any special treatment, if used as such.
On detailed inspection and site discussions, it transpired that it will be preferable not to disturb the existing masonry structure as well as the embedded parts which may endanger the structure itself which is approximately 80 years old. It was considered prudent to utilize these cast iron embedded parts by undertaking suitable modifications by use of special welding technology between cast iron and structural steel or corrosion resistant stainless steel materials for modifying the tracks and seal seats, guides etc. as per the requirements of the IS 4622, as similar modification earlier got carried by the Project on + 80’ gates were intimated to be serving well and were found satisfactory by the Project.
It was noticed that no steel liner exists at any location for these three gates, although the technical specifications had mentioned provision of steel liners.
It was also observed that all the piers are not alike & the project was advised for a detailed survey to provide the detailed dimensions of civil structure as well as the existing embedment, for all the three locations namely +103, + 106 and +114covering each of the 136 number individual spans of these gates with reference to the center line of each span. This shall cover the civil structure shapes, dimensions in elevations and plan views with requisite X-sections.
During the site visit it was jointly decided that the work is required to be accomplished with least disturbance to the masonry structure keeping in view safety aspect of structure, utilizing the existing embedment and anchors etc.
Project authority was advised to carry out the revision in PST and Bid documents, and in the specification drawings accordingly.
Project site data to be supplied:
Project authority was also advised to simultaneously submit the following basic site data after
thorough survey and site measurements of the existing arrangement to CPMU:
Exact details and dimensioning of the existing piers, gate grooves, existing embedded parts, from the center line of each bay to be marked on drawings for all gates.
As Flood Routing Study for standard conditions has been done by KRSE, Mysore, wherein there an increase of 0.83 m water level has been reported above MWL It is advised to submit this studies to CWC Officially and team of KRSE along with all relevant records, input data and reports may be deputed to CWC so that official discussion may be held and final MWL may be firmed up. The MWL to be estimated with all gates operative and with 10% of gates considered as inoperative. It is suggested that design of all new gates shall be done for this revised MWL so that safety of gates under critical hydraulic conditions may be ensured.
Hydraulic Model studies to be got conducted for sluices with gates at RL +103’, + 114’ and + 106’ gates in parallel. Discharging capacity at revised MWL to be checked. Need for aeration at the d/s to be looked in to in the sectional models. Pressures in the sluices to be measured. This work could be carried out as a parallel activity.
Detailed construction planning and schedule of completion to be made part of bid document.
Reservoir Operation/regulation frame work/ Rule curve, and revised rule curve may also be required to be generated for the revised MWL in case MWL is incrased beyond the present MWL in order to ensure structural safety.
Technical specifications and detailed technical specification drawings, scope and estimate for associated civil works.
Project Rehabilitation Report of KRS Dam
33 | P a g e
Detailed design of gates to be based on head up to FRL, and checking for MWL (with 10% gates inoperative) with 33% increased stresses.
At site the pier details, especially the face of pier was found to be at variance with details available with C.P.M.U. The pier details of all the gates namely +103, + 106 need to be provided as per actual measurements. Similarly the details of bell mouth curves at various levels in the civil structure need to be shown for guidance to the bidders.
A suitable condition needs to be made part of bid document for installation of get 2 gates of each type in beginning along with their dry testing prior to proceeding for installation of balance gates .
Other Observations:
To provide stainless steel side guide wheels in place of side guides to be designed for side thrust of 10% of the gate weight, especially in view of the historical side bumping experienced on gates under partial operation due to skew alignment between the two parts of the dam in this reach.
The groove liners earlier proposed in the technical specification drawings without stiffeners were not found desirable and Project authority was advised to utilize the existing track with provision of 30 cr13, stainless steel track plates of suitable size through welding after filling the cavity existing in the cast iron track through specialized welding technology (TIG welding) as used on + 80 gates. This process shall need to be elaborated in the technical specifications.
The existing track in respect of gates at RL +103’ & + 106’ gates was found very near to the edge of the masonry structure but had endured the stresses without causing any shear, it was advised to provide eight number stainless steel wheels, four in each of the two units of each gate to be spliced together with fit bolts, the wheels with a provision of crown was felt more appropriate to provide contact stresses at the center of existing track to keep the loading pattern on masonry to be in line with the earlier loading pattern.
There were no embedded parts in the deeper face of the block outs for provision of embedded guides. This may require a modified approach to utilize existing anchors available in the groove area to provide an alternative guiding arrangement. (To be supported on available anchor provisions in the groove area). It was further decided to use the through bolts for fixing of first stage plates for guides / any other component as required.
Sill beam for + 103’ and + 106 gates shall be of Minimum ISMB 250 with provision of S.S. seal seat welded at top and to be flush with surrounding concrete.
For + 114’ gates, the earlier proposed arrangement vide transmittal 3970 dated 08.12.2016 requires to be modified as per the revised sketch attached to meet the actual site conditions. The sill beams proposed for these gates is also shown in the revised sketch (attached).
Bid documents need complete review based on the past observations already transmitted as well as the updating based on the recent site visit and discussions held at site on 15th December 2016. The irrelevant parts like provision of single gate for +103’ & + 114’ gates need to be removed. The PST may be updated accordingly based on firmed up drawings and other details.
KRS project expert committee in its meeting dated 06.05.2016 had cleared the provision of independent hoists on trestles, based on CPMU recommendations for provision of skid mounted compact wire hoists conforming to IS 3938. The specification drawings submitted are not in line with it and are showing common hoists with clutch arrangement which already stand again discussed and not accepted during this visit. It was agreed to revise the documents and drawings accordingly as it even contravenes the requirement of remote control system.
Project Rehabilitation Report of KRS Dam
34 | P a g e
The sample GTS made available to SPMU be reviewed to incorporate the relevant aspects as per the now agreed provisions.
Provision of AMC for a period of 5 years for Remote control system, compact hoists, and electrical control and measuring system needs to be included in the scope of work.
Provision of steel liners introduced in the specifications needs to be deleted as it was not existing as noted during the recent site visit.
The weights of gates, capacities of compact hoists need not be mentioned as done in recent revision of bid & PST documents. May like to provide that “the hoist capacity shall not be less than -----T capacity”
The PST does not include the works to be identified for + 50’ & + 60’ gates etc. as per the site visit report as per transmittal 3593 dated 16.08.2016.
Provision of “ monorails” in place of compact hoists is still being mentioned at few locations in PST & Bid Document, needs to be deleted.
Observations already sent vide M.O.M 3671 dated 06.09.2016 and 3970 dated 08th December, 2016, need to be taken care of.
Elevations for FRL, MWL, and MDDL etc. need to be mentioned in documents and drawings.
The masonry grooves face if required shall be deepened and extended or levelled by grinding. The chipping etc. needs to be avoided.
Miscellaneous provisions, like water repellent paintings of all existing cast iron gate grooves along with its fitting, RCC provision for floor d/s of sill beam etc. may also be made part of work
The cost estimate needs to be reviewed to make it realistic covering all proposed and agreed changes as per past and recent review meeting at site on 15.12.2016.
The Concluding Remarks By Director, DRIP:
The Director DRIP mentioned that the submission of revised Bid document had already
been delayed and that the World Bank in the last 16th TC . meeting held in December
2016 has given a clear cut deadline of February 2017 for the award of this work, failing
which the Project is not likely to be considered under DRIP. He advised that the Project/
SPMU need to modify the documents in accordance with the decisions taken on these
works in the past with modifications to the extent agreed during this visit and meeting at
KRS to meet the deadline set by the World Bank.
SPMU, site Engineers and the Project consultants who attended this meeting were
fully apprised on the basic important agreed aspects requiring proper incorporation in
the Revised PST and Bid documents in detail.
Important Past Observations:
The Edge distance of track needs to be checked for shear strength of masonry as per
IS 1905 (1987) especially for 103’ & 106’gates.
Technical specifications for + 103 and + 114’ gates need to be made separately instead
of common one.
Connected Civil works are required to be fully included both in in BOQ.
Use of independent compact hoists as per IS3938 were agreed for all the three type of
gates. Drawings details need to be made as per the agreement.
The project expert committee in its meeting dated 06.05.2016 had cleared the provision
of independent hoists on trestles for all 136 gates including replacement of existing
embedded parts by stainless steel embedded parts. Provision in documents needs to
be made accordingly.
The cost estimate is varying at different locations in PST as Rs 24.5 Cr, Rs 26.63
crores. This needs to be revised considering all civil works to be included.
Project Rehabilitation Report of KRS Dam
35 | P a g e
The sample General Technical Specifications (GTS) provided by CPMU were to be
reviewed to exclude all non-applicable aspects before appending into the document.
Item 13 on page 252 envisages steel liners. There were no liners seen during site visit.
This needs to be reviewed.
All the gates need to be lifted during design flood above revised MWL. Planning needs
to be carried out accordingly.
Cross section of dam is required showing Gates at both +114’ & 103’ levels.
The track of all the gates should extend above the revised MWL.
The specification drawings need to be revised as per site visit report and discussions,
including earlier communicated observations.
3rd Construction Site Visit Report.
Observations:
CPMU monitored various on-going works including water loss testing and mixing of
grout. The Contractor is conducting his work using best construction practices and
scheduling of activities including multiple drilling operations which are being carried out
on a night shift.
An inspection of the upstream face revealed that a set of masonry steps has pulled
away from the dam body and needs to be thoroughly inspected and a design developed
to mitigate possible collapse of the stairway and potential damage to the dam body.
This needs to be accomplished on an accelerated schedule to ensure the large
exposed surface area of the dam body behind the stairs in treated in a timely manner. Upstream face treatment including raking and pointing of masonry using PICC
cementitious cement and nipple grouting of cavities. Status report from Contractor on
file. Documents available for review.
Works are well-documented with OK card systems in place to ensure all steps are
taken during implementation of the various scopes of work.
Justifications for increase in scope and costs are in order and technically correct.
ESMF and HSE/PPE OK system tracking mitigation requirements outlined in proposal.
4th Construction Site Visit Report.
Observations:
Upstream face treatment including raking and pointing of masonry using PICC
cementitious cement and nipple grouting of cavities was inspected. Work has been
implemented as per contract. Status report from Contractor on file. Documents
available for review. Extension of pier grouting is being taken up to extend depth of
grouting from the current limit of the gates to 3 to 4 meters downstream to complete
filling of voids noted during previous inspections.
Works are well-documented with OK card systems in place to ensure all steps are
taken during implementation of the various scopes of work.
Justifications for increase in scope and costs are in order and technically correct.
CPMU recommends the additional items in the variation order are taken up to ensure
addressing all the structural enhancements necessary to successfully implement the
project
ESMF and HSE/PPE OK system tracking mitigation requirements outlined in proposal.
5th Construction Site Visit Report
Observations:
Two points are brought out emphasizing additional work that CPMU recommends being taken
up as schedule and budget allow:
Completed between CH +760 to CH 2+100 m from levels +70 to +125 and above level
+125 in place of shotcreted. Submitted EFI proposal for approval of excess quantity
already pointed and balance area to be done.
Project Rehabilitation Report of KRS Dam
36 | P a g e
Primary holes at 12 m c/c at 1.30 m d/s of u/s face, secondary holes at 12 m c/c
(staggered to primary holes) at 1.50 m d/s of primary holes and tertiary holes in row
between primary & secondary holes at 6.00 m c/c (staggered to primary & secondary
holes) completed. EFI proposal submitted for excess quantity executed and quantity to
be executed for extended tertiary holes at 1.50 m c/c as Lugeon values are not in
permissible limit even after three rows of grouting. Also proposed for grouting between
CH +600 m and +750 m and between CH 2+100 m & CH 2+540 m.
No work is carried out after last site inspection made on 7.6.2017 and the status of works
is the same as it was on 7.6.17.
The contract provides for PICC mortar pointing to u/s dam face between CH +750 to CH
+2100, for full area from levels +50 to +80, 35% area from levels +80 to +125 and for full
area from levels +125 to 130. During execution of works, it was noticed that most of the
surkhi mortar joints between levels +80 and +125 are in dilapidated condition or have
developed cracks or peeled off. Hence full area is pointed from levels +70 to +125 and
above FRL level instead of shotcreting. Total quantity of pointing executed as of to date is
40,265 sqm. against BoQ quantity of 26,800 sqm., which is 50% more than BOQ quantity.
Provision is made for dam body grouting by drilling primary holes at 12 m c/c and
secondary holes at 6 m c/c & 40% of primary & secondary holes for tertiary holes. The
permeability values before grouting were ranging from 1.86 Lugeons in rock to 29.83
Lugeons in masonry. After grouting 106 primary holes, 108 secondary holes and 220
tertiary holes at 3 m c/s, the Lugeon values in the three test holes ranged from 4.85 to
19.33.
The average grout intake in primary holes is 171.77 kg/m, in secondary holes 143.08
kg/m and in tertiary holes it is 81.25 kg/m. The overall average grout intake is 121.88
kg/m.
Sl. No.
Observation / Deficiency 15.12.2016 Remarks
1
Masonry stairway attached to upstream face of dam body has a failed foundation. Stones and mortar may be pulled out from dam body
Design for stabilization / removal of stairs and repair of dam body face.
2 Rubble from construction is stockpiled to the upstream face of the dam
Rubble needs to be removed to accommodate raking and pointing of upstream face
3 Contract requires underwater raking and pointing. No method provided
it is ascertained that the present contract does not provide for under water pointing item. Planning to include pointing of the area below water level up to Level +12 level in DRIP-2 works.
4
Upstream face not completely covered in scope for raking and pointing. Only 60% of face under contract. lA requesting an additional 261% financial increase to cover all the upstream face including underwater works.
Requires WB approval
Project Rehabilitation Report of KRS Dam
37 | P a g e
8.4 Summary of Compliance by SPMU
Compliance letter received from SPMU against the CPMU experts’ comments during
construction site visits is attached in Annex E.
8.5 Summary of any Special Visits made by CWC/World Bank/Expert
Committee
Observations/recommendations and compliance of Design Team from Gates
(E&NE), CWC during the inspection of Krishnarajasagar (KRS) dam, Karnataka on
02.07.2015 are attached at Annex E.
8.6 Summary of Technical Assistance provided by CPMU
Review of PST. Review of design flood.
Review of Dam Break Analysis and Inundation maps prepared by SPMU.
Provided technical guidance on maintaining quality of works as per design, contract agreement technical specification and best engineering practices.
9. ENVIRONMENTAL AND SOCIAL MANAGEMENT
FRAMEWORK (ESMF)
9.1 Basic Details
Sl. No.
Item Yes / No Remarks
a. ESMF Issue Identified in PST Yes
b. Mitigation Measures Proposed Yes
c. Any Rehabilitation and Resettlement involved No
d. Site Visit Date of CPMU E&S Specialists -
e. Site Visit Report of CPMU E&S Specialists -
9.2 Summary of Observations
ESMF management during implementation was generally satisfactory but site photo
records show that PPE was sometimes not used during construction.
9.3 Details of ESMF/EIA study (if any)
Nil.
10. OTHER NON-STRUCTURAL INTERVENTIONS
10.1 Basic Details
Sl. No.
Item Yes / No Remarks
a
Emergency Action Plan (EAP)
(i) EAP Available at Site
(ii) EAP Prepared under DRIP
(iii) EAP Published
No
Yes
No
Inundation map prepared by SPMU was reviewed by CPMU.
Draft EAP is also Prepared by SPMU and reviewed by CPMU
Project Rehabilitation Report of KRS Dam
38 | P a g e
Sl. No.
Item Yes / No Remarks
(iv) Stake holder consultations
No
the comments of CPMU sent to SPMU via Transmittal Reference No. 8242 / 21-04-2020 for finalization and publication.
b. O&M Manual availability Yes O&M manual was prepared by SPMU as per DRIP guidelines, reviewed by CPMU and published.
c. Inflow Forecasting No
d. DHARMA Implementation Yes In progress
e. Siren No Needs to be installed
10.2 Summary of Observations
Nil
11. PENDING REHABILITATION WORKS
11.1 Details of pending works
i. Finalization of EAP.
ii. Completion of data entry into DHARMA.
iii. Completion of on-going work for replacement of 136 gates.
iv. Carrying out detailed flood routing and come up with structural and non-
structural measures to accommodate the revised design flood under DRIP II.
11.2 Further course of action
Pending action stated above should be completed.
12. REFERENCES
i. PST
ii. DSRP report
iii. Construction site visit report.
iv. Information received from SPMU from time to time
v. Completion Certificate.
vi. World Bank approval
vii. Compliance against various Observations/Comments from SPMU.
Project Rehabilitation Report of KRS Dam
39 | P a g e
Annex A: PST Approval Letter
Project Rehabilitation Report of KRS Dam
40 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of KRS Dam
41 | P a g e
Project Rehabilitation Report of KRS Dam
42 | P a g e
Project Rehabilitation Report of KRS Dam
43 | P a g e
Annex B: Drawings issued for
Rehabilitation measures
Project Rehabilitation Report of KRS Dam
44 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of KRS Dam
45 | P a g e
Project Rehabilitation Report of KRS Dam
46 | P a g e
Project Rehabilitation Report of KRS Dam
47 | P a g e
Project Rehabilitation Report of KRS Dam
48 | P a g e
Project Rehabilitation Report of KRS Dam
49 | P a g e
Project Rehabilitation Report of KRS Dam
50 | P a g e
Project Rehabilitation Report of KRS Dam
51 | P a g e
Annex C: Completion Certificate
Project Rehabilitation Report of KRS Dam
52 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of KRS Dam
53 | P a g e
Project Rehabilitation Report of KRS Dam
54 | P a g e
Project Rehabilitation Report of KRS Dam
55 | P a g e
Project Rehabilitation Report of KRS Dam
56 | P a g e
Project Rehabilitation Report of KRS Dam
57 | P a g e
Annex D: Photographs Before and
After Rehabilitation Works
Project Rehabilitation Report of KRS Dam
58 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of KRS Dam
59 | P a g e
Project Rehabilitation Report of KRS Dam
60 | P a g e
Project Rehabilitation Report of KRS Dam
61 | P a g e
Project Rehabilitation Report of KRS Dam
62 | P a g e
Project Rehabilitation Report of KRS Dam
63 | P a g e
Project Rehabilitation Report of KRS Dam
64 | P a g e
Project Rehabilitation Report of KRS Dam
65 | P a g e
Project Rehabilitation Report of KRS Dam
66 | P a g e
Project Rehabilitation Report of KRS Dam
67 | P a g e
Few Photographs of Ongoing HM works (Replacemnt of 136 surplus release sluice gates)
Project Rehabilitation Report of KRS Dam
68 | P a g e
Project Rehabilitation Report of KRS Dam
69 | P a g e
Annex E: Compliance as Received
from Project Authorities
Project Rehabilitation Report of KRS Dam
70 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of KRS Dam
71 | P a g e
COMPLIANCE TO OBSERVATIONS / RECOMMENDATIONS MADE BY SRI.R.K MALHOTRA,
BANK CONSULTANT, WORLD BANK DURING THE MEETING HELD DELHION 15TH& 16TH
JUNE 2015
Sl.
No.
OBSERVATIONS /
RECOMMENDATIONS
COMPLIANCE BY PROJECT
AUTHORITIES
A
(i)
DSRP Recommendations vide Page 64,
Item No. 17:“ Series of inclined holes of
at least 150 mm dia spaced at 20 m
centre to centre be drilled from
downstream face through the body of the
dam and up to the foundation to provide
means of drainage”. There being no
foundation gallery in this dam, provision
of the DSRP’s suggested drainage holes
is considered essential to release the
uplift pressure.
Inclined Bore holes from the downstream
face of the dam are suggested by the DSRP
and the project authorities of KRS dam
have expressed their apprehensions before
the Technical Committee (T.C) during their
visit with respect to stability if we have
inclined bore holes in 100 years old dam.
The T.C opined that there is no necessity of
inclined bore holes as the authorities have
not experienced the effect of uplift pressure
ever since. Hence this item is dropped.
(ii) DSRP Recommendations vide Page 64,
Item xv. “Undertaking drilling of core
holes in the body of the dam up to few
metres into the foundation to assess the
in situ properties of the masonry and the
mortar including masonry permeability
and uplift pressure etc”. This provision
should be made, being essential to
assess the condition of the dam body.
This will also help in the assessment of
the discontinuities / voids/ cracks/ cavities
in the dam body besides appropriate
assessment of grout intake in the various
sections of the dam body. In this
context,provision of 6 bore holes of 150
mm dia between 750 m to 2100m is
considered to be adequate. Cores from
these bore holes shall provide the
needed guidance. Also, it is suggested to
make provision for the ‘bore hole video-
graphy’ for ensuring realistic situation of
the dam body with respect to the
information provided by the cores.
The provision for drilling of 6 core holes of
150 mm dia between 750 m to 2100m
including bore hole video-graphy has been
now made in the estimate. In the mean
time the EGIS is recommended an another
bore hole at Ch: 2120 m. where
downstream springs erupt when RWL
reaches El.744m and accordingly total 7
core holes are included in the proposed
PST.
(iii) DSRP Recommendations vide Page 71,
Item No.12. The Dam Safety Review
Panel has
recommended that in addition to the
treatment of the upstream face through
raking and pointing of masonry joints in
the reaches proposed to be treated, the
treated portions should be covered with
shot creting (8 to 10 cm thick) over steel
mesh fixed to the upstream face of the
dam. The project authority has not made
any provision of shot creting. The PST
envisages treatment of the upstream face
from El +70 ft to + 80 ft (associated with
wide opening of joints and occurrence of
cavities) and from El +125 ft to +130 ft ,
As recommended, the provision for
providing “Fibre Shot Crete” (8cm thick)has
been made
in the estimate. The cost of this item is
worked out based on the data rate. The
cost of this item is included in the Sub
Estimate NO.1 at Item No 11.
Project Rehabilitation Report of KRS Dam
72 | P a g e
Sl.
No.
OBSERVATIONS /
RECOMMENDATIONS
COMPLIANCE BY PROJECT
AUTHORITIES
being associated with opening of joints
due to splashing of water. It is suggested
that shot crete be provided at least over
the treated reach from El +125 ft to +130
ft since this reach is reported to be in the
zone of severe splashing of water. Also
that, “fibre shot crete” (8 cm thick) be
provided instead of the DSRP’s
suggested plain shotcrete with steel
mesh. The fibre shot crete has several
advantages over the plain shot crete with
steel mesh. Design mix of the fibre shot
crete has been provided to Mr. Gowda,
Executive Engineer
B Treatment of upstream Face. The PST
envisages treatment of the upstream face
only at 2 levels ( from + 70 ft to + 80 ft;
and from +125 ft to +130 ft) and no
treatment has been proposed in the
intervening levels / reach. To the specific
query, Mr. Gowda, Executive Engineer
intimated to the Bank Consultant that the
intervening reach is also associated with
open masonry joints and cavities though
the extent of such open joints & cavities
was somewhat less than those in the
reaches + 70 ft to +80 ft / +125 ft to +130
ft. Now that the reservoir level is around
77 ft, the extent of the open joints/
cavities existing in the intervening reach
above + 80 ft level should be realistically
examined by Mr. Gowda, Executive
Engineer and the provision for treatment
to the extent required in the intervening
reach should be made in the PST.
The upstream face of the dam is inspected
by the team of Project Officers and
observed many number of openings/cavities
on the upstream face of the dam after
inspection of higher authorities it is
concluded to include the entire area from
+50' to +70' between chainages 750 to
2100 m & 35% of the remaining exposed
area of on the exposed area of the dam ,
accordingly the area between +50' to +70'
from Ch. 750 to Ch 2100 works out to 8100
sqm & 35% of the remaining exposed area
of 30350.07 sqm works out to 10623 sqm
(say 10600 sqm) is considered for
horizontal grouting & included in the PST.
The cost of treatment of both horizontal
grouting and pointing are included in the
Sub Estimate NO.1 at Item No 1,2&3.
C Drilling and Grouting. In the Estimate
submitted earlier at Sub-Estimate No. 1,
Pages 109 – 110 indicates the following:
(i) Item No. 4-A &4-B. Drilling of 47 mm
(Bx) core holes is envisaged. The correct
nomenclature should be 51 mm(Ax). It is
also noted that no mention is made for
“washing and conducting water loss
tests” in the holes. These being important
activities should be appropriately
included.
As suggested nomenclature from 47 mm
(Bx) (As per WRD SR 8.11.2, Page-150) is
changed to 51-57mm (Ax). Also washing
bore holes and conducting water loss tests
are included in the detailed specification.
Project Rehabilitation Report of KRS Dam
73 | P a g e
Sl.
No.
OBSERVATIONS /
RECOMMENDATIONS
COMPLIANCE BY PROJECT
AUTHORITIES
(ii) Item No. 5 It is noted that grouting is
envisaged to be done through primary
holes spaced at 6 m centres. No
provision is made for secondary holes.
Secondary holes may also be required for
completion of grouting to achieve the
requisite acceptance level of
impermeability in terms of lugeon values.
In this context, it shall be appropriate to
include the provision of drilling secondary
holes in between the primary holes and
undertaking grouting through these holes.
Accordingly, provision for about 33 %
secondary holes may be made for
estimation purposes.
As suggested, provision for drilling of
secondary holes to an extent of 33% of the
primary holes to access the Lugeon values,
has been made in the estimate. Also the
provision for grouting to these secondary
holes has been made in the estimate. The
cost of drilling secondary bore holes is
worked out based on the WRDO SR 2014-
15 vide Item No.8.11.2 Page No.150.
However, the cost of grouting is worked out
based on the data rate due to non-
availability of any scheduled rates. The
costs of these two items are included in
revised Sub Estimate NO.1 at Item No.
4(A), 4(B)&6.
(iii) Supply & Installation of Upheaval
Gauges. It is essential to install upheaval
gauges prior to the commencement of
pressure washing and grouting of any
hole within about 150 m to monitor
movement, if any, of the dam masonry /
rock mass. This dam being about 100
years old, it is of paramount importance
that the masonry does not get disturbed
during the pressure washing and
pressure grouting operations. Provision
for 9 upheaval gauges should be made in
the PST. An illustrative sketch depicting
an ‘upheaval gauge’ was provided to
MrGowda, Executive Engineer.
The provision for installation of upheaval
gauges prior to the commencement of
pressure washing and grouting of any hole
within about 150 m to monitor movement, if
any, of the dam masonry / rock mass has
been included in the estimate. The cost of
upheaval gauges is worked out based on
the WRDO SR 2014-15 vide Item No.2.9.3
Page No.33. The cost of these items is
included in the revised Sub Estimate NO.1
at Item No.5.
(iv) Test Holes. No provision is presently
made for checking the ‘efficacy of
grouting operations’’. It is essential to do
so. In this context, provision for about 7-
10 % test holes of Nx size be made in the
PST to cover drilling to the specified
depths, water loss tests, and finally
grouting of these holes.
As suggested, provision for drilling of 16
Nos. test holes which forms about 7% of the
primary holes to access the efficacy of
grouting operations has been made in the
estimate. Also the provision for grouting to
these test holes has been made in the
estimate. The cost of drilling test holes is
worked out based on the WRDO SR 2014-
15 vide Item No.8.11.2 Page No.150.
However, the cost of grouting is worked out
based on the data rate due to non-
availability of any scheduled rates. The
cost of these two items are included in
revised Sub Estimate NO.1 at Item No. 6, 7
& 8.
D Consultancy for Supervision of Drilling &
Grouting Operations. Drilling and
Grouting operations are specialized jobs
A provision of about ₹25.00 lakhs be made
for engaging a grouting specialist / reputed
agency well versed in drilling & grouting to
Project Rehabilitation Report of KRS Dam
74 | P a g e
Sl.
No.
OBSERVATIONS /
RECOMMENDATIONS
COMPLIANCE BY PROJECT
AUTHORITIES
requiring specialized skill and practical
knowledge. These operations require
constant attention. In this context, it is
suggested that a provision of about Rs 15
lakhs be made for engaging a grouting
specialist / reputed agency well versed in
drilling & grouting to supervise these
operations on a continuing basis.
supervise these operations on a continuing
basis till the satisfactory completion of the
work.
E Gates. The PST envisages replacement
of all 48 flood gates at Level +103 ft and
all 40 flood gates at +106 ft as well as all
the 48 automatic flood gates at +114 ft
level. It is noted that the Committee
formed by the Managing Director, CNNL
has recommended for replacement of all
these 136 gates with new gates and the
project authority has decided for
independent hoisting arrangement of
these gates to be operated through
remote-control system including the
provision for new embedded parts. This is
acceptable from considerations of overall
operational efficiency.
The Project Authorities while preparing
estimate earlier, it was proposed to replace
all 136 gates (40 gates @ + 106’, 48 gates
@ + 103’ and 48 gates @ + 114’) based on
the committee recommendations headed by
Chief Engineer, Irrigation (South), Mysore.
However, a team of Senior Officers from
CWC headed by Sri.Harkesh Kumar,
Director (Gates), CWC, New Delhi, has
conducted a detailed inspection of all gates
and recommended for replacement of gate
@ + 103’ & + 114’ by a single gate and
replacement of gates @ + 106’ level if the
skin plate is corroded by more-than 25% in
thickness by conducting UT test.
Repair/Replacement of embedded parts in
all gates. As recommended/suggested by
the Gates Expert Committee of CWC,
necessary changes have been made in the
estimate and detailed in Sub Estimate
NO.2. However, CPMU has deputed two
experts Sri. Ajit kumar Sachdev, Hydro-
mechanical expert & Sri.Zika Smilkovic,
Dam Design expert, to assist assessment
and recommendations of the current gates
and hoist arrangements. Both experts
visited the dam on 20/08/2015 and awaiting
their reports for finalizing the design of
hydro-mechanical equipments. The final
cost will be arrived after getting the
clearance from the CWC with respect to
design of hydro mechanical equipments.
F Third Party Inspection Agency. It is
suggested that a reputed inspection
agency should be engaged to supervise
each and every activity covering quality
assurance plan, fabrication, erection,
testing, and commissioning of gates.
Accordingly, a provision of Rs 15.00
lakhs should be made in the PST.
A provision of ₹25.00 Lakhs towards
appointing a reputed inspection agency to
supervise each and every activity covering
quality assurance plan, fabrication, erection,
testing, and commissioning of gates has
been made in the revised estimate.
Project Rehabilitation Report of KRS Dam
75 | P a g e
COMPLIANCE TO OBSERVATIONS/RECOMMENDATIONS OF DESIGN TEAM FROM GATES
(E&NE), CWC DURING THE INSPECTION OF KRISHNARAJASAGAR (KRS) DAM, KARNATAKA
ON 02.07.2015
Sl.
No.
Inspection Note of design team from
Gates (E&NE), CWC on its visit to
KrishnarajaSagar (KRS) Dam,
Observations & Recommendations
COMPLIANCE BY PROJECT
AUTHORITIES
1
+106 level gates:
The skin plate of almost all gates has
developed uniform rusting with general
pitting & scaling. The downstream
components of gate are in good condition
and do not appear to have deteriorated
much in last eight decades (since cast
iron does not rust easily and generally
last longer). Overall, the gates did not
seem to be in severe distress. The skin
plate thickness is 1" as against design
requirement of ½". 1948-handbook states
that that additional ½" thick plate riveted
onto I-joists on rear had been provided in
front of original skin plate to improve gate
strength and overall weight. (Few gates
which had failed during initial years were
replaced with extensively ribbed CI gate
like the one provided in bay no.1 in
1938). Therefore, it is suggested that
ultrasonic thickness testing be performed
on skin plate and in case thickness has
reduced by more than 25%, entire gate
shall be replaced with new gate as the
repair works on cast iron may not yield
desired results. Otherwise, the existing
gates shall be sand blasted and painted
as per existing Standards.
The project Authorities have made
enquiries with 3 agencies who are in this
line of executing UT test. They have
agreed to carry out ultra sound thickness
test on skin plate even under water and
required about 25 to 30 days for completing
the work for 40 gates. Further, project
Authority need about 25 to 30 days to
finalise the agency.
As such we have assumed 50% of gates
that is about 20 gates in which thickness of
skin plate has reduced by more than 25% of
the original thickness of skin plate in view
of long age of gate, heavy rust formation on
upstream of skin plate etc.,
Accordingly, replacement of 20 gates &
refirbification of 20 gates is considered for
estimation purpose. The exact number of
gates to be replaced can be known only
after UT test. In the mean time the project
authority will find agency to conduct UT test
& actual number of gates replaced/
refirbificated will be considered before
placing the proposal for technical sanctions.
If the number of gates to be replaced is
more than 50% based on UT test, the
excess number of gates exceeding 20
gates will be considered out of State
Government Grants.
The cost of replacement of gates is worked
out based on WRD S.R 2014-15. The cost
of refirbification is worked out by assuming
that 30% of cost replacement of these gates
based on WRD S.R 2014-15.
The cost of the above is considered under
Sub Estimate No.2
2 Sealing against water leakage is
achieved by means of staunching
arrangement which provides two brass
surfaces to come in contact once the gate
The project Authority will make clear in the
tender schedule about providing suitable
sealing arrangement (Seals on gate shall
be fitted to L or Z-shaped plate bolted to
Project Rehabilitation Report of KRS Dam
76 | P a g e
Sl.
No.
Inspection Note of design team from
Gates (E&NE), CWC on its visit to
KrishnarajaSagar (KRS) Dam,
Observations & Recommendations
COMPLIANCE BY PROJECT
AUTHORITIES
is fully closed. However, the action is not
automatic and in the present case the
gate plates are pushed forward using
screw jacks to abut against embedments.
The metallic seals are never expected to
give water tight joint (design
shortcoming) and it seems water
tightness was not imperative all these
years as there
are numerous anicuts on downstream.
But the situation has been aggravated
due to
Damage/loss of brass beading; both on
staunching plates & embedments leading
to profuse leakages. Divers are normally
deployed to pack the gaps between
staunching plates and embedments with
jute/gunny bags to minimize leakage but
are temporary measure. Further, the
operating mechanism by means of screw
jacks is not user friendly Page 4 of 18 in a
sense that the top plate merely tenoned
to side plates was expected to move
along with side plates when screw jack is
operated. In actual practice, simultaneous
operation of screw jacks is never
achieved and has been further
accentuated by rusting of staunching
plates. Therefore, it is recommended that
the sealing shall be replaced with rubber
seals. To achieve the same, additional
embedment’s with seal seats of AISI 304
(min.width of SS plate 150mm) including
concreting etc. shall be provided on
upstream to suit the site condition. The
seals on gate shall be fitted to L or Z-
shaped plate bolted to gate in place of
staunching plates. Choice of L-shaped
plate with music note type seals OR Z-
shaped plate with angle type seals is left
to discretion of designer. However, it is
felt that angle shaped seals may be more
suitable due to greater pre-compression
available considering varying degree of
corrosion of wheel & its track (if at all
present). Standard engineering practice
of providing suitable taper on top seal
seat with adequate recess in adjoining
concrete shall be ensured during
erection.
gate) on U/s & taper on top seal seat with
adequate recess in adjoining concrete.
The project Authority is requesting the CWC
for providing available drawings if any with
them so has to enable us to enclose the
same in the tender document.
The cost of the above all items is worked
out by assuming that 30% of cost
replacement of this entire sealing
arrangements of gates based on WRD S.R
2014-15.
The cost of the above is considered under
Sub Estimate No.2
Project Rehabilitation Report of KRS Dam
77 | P a g e
Sl.
No.
Inspection Note of design team from
Gates (E&NE), CWC on its visit to
KrishnarajaSagar (KRS) Dam,
Observations & Recommendations
COMPLIANCE BY PROJECT
AUTHORITIES
3 It was informed that the gates sway
during operation against load beyond full
opening.
This is very much expected due to
absence of guide/restraints above top of
vent opening as well as due to single
point gate suspension. The provision of
guiding mechanism on upstream may be
formulated along with new seal
embedments (as explained at sl. no ii) up
to top of vent opening. FromEL118.0' to
EL131.0', the guide anchorages could be
Hilti type expansion anchors. The guide
shoe shall be fitted to new plate meant for
rubber seals.
The project Authority will incorporate in the
tender about providing suitable
*guiding mechanism on upstream up to top
of vent opening. FromEL118.0' to EL131.0'
* guide anchorages
The project Authority request for sending
available drawing with CWC to examine of
providing same in our +106 gate groove &
gate.
The cost is considered under Sub estimate
no 2
4 Leakages were noticed through masonry
behind wheel track in few bays. It is
suggested that the masonry around
wheel track shall be treated with suitable
material (preferably epoxy based) having
excellent bonding properties with
masonry. Wheel track in one of the bay
has developed crack. The same shall be
repaired using metal stitching technique
as field welding of cast iron parts are
difficult.
The project Authority will incorporate in the
tender about treatment with suitable
material (preferably epoxy based) having
excellent bonding properties with masonry
behind wheel trackrepairing of wheel track
wherever required using metal stitching
technique (as field welding of cast iron parts
are difficult)
The cost is considered under Sub estimate-
No.2
5 The cantilevered cast iron wheels are
mounted on brass bush & mild steel
shaft. The broken wheels on a couple of
gates as well severely worn-out wheels
shall be replaced
The project Authority will incorporate in the
tender about replacement of wheels
wherever broken, worn out etc.The cost is
considered under Sub estimate- No.2
6 One of the gate was operated to assess
the hoisting mechanism and the
functioning of
gantry crane was found to be smooth. PA
(Project Authority) informed that no
problems have been reported w.r.t.
gantry in past
The project Authority will utilze the Gantry
for operation of two gates at a time.
7 Though no failures have been reported of
suspension chain in past and may not
occur with periodical examination. But it
is felt that additional wire ropes may be
provided on gate as a precautionary
measure to prevent accidental dropping
of gate due to chain snapping or any
other reasons. OR it is advised that these
gates shall not be used for regulating the
flow (i.e. no partial opening of gate, only
open/shut condition) and shall be latched
The project Authority will incorporate in the
tender about providing Additional wire rope
as suggested.
The cost is considered under Sub estimate-
No.2
Project Rehabilitation Report of KRS Dam
78 | P a g e
Sl.
No.
Inspection Note of design team from
Gates (E&NE), CWC on its visit to
KrishnarajaSagar (KRS) Dam,
Observations & Recommendations
COMPLIANCE BY PROJECT
AUTHORITIES
at top deck level by providing suitable
latching arrangement after full opening
8 Multiple screw jacks were missing or
bent. No action needs to be taken for
replacement of missing/damaged screw
jacks
The project Authority will not taken action
but material will be considered as Scrap.
The cost is considered under Sub estimate
No.2
9 +114 level gates:
These gates are presently inoperative
due to non-functioning of float system.
The automatic hoisting arrangement is in
dilapidated state and it seems that no
efforts have been made in the past to
make them functional. It was informed
that these gates have not been operated
for last many years. The restoration of
automatic float system is not
recommended as its functional reliability
cannot be ensured.
The project Authority had decided for non-
restoration of these gates. As same has
been recommended by CWC, no work will
be under taken.
10 It was informed that the gates are
subjected to severe hammering action
due to wave effect; also resulting in
lateral shift of gate. This is expected as
there is absence of guiding mechanism
and is design deficiency
Noted
11 The gates have developed general
rusting but do not appear to be severely
distressed.
However, there is profuse leakage
through metallic seals on account of
design Deficiency (as elaborated under
sub-heading A), damaged/worn-out brass
beads. Considering the fact that these
gates are required for flood disposal and
doubtful reliability of any restorative
measures if implemented on gate & float,
it is recommended that these gates shall
be combined with +103 level sluice gates
and a single gate of size 10.0' x 21.0' with
appropriate freeboard shall be installed.
The gate shall be regulating type with
upstream sealing (no top seal required)
and skin plate. The gate shall be
fabricated in minimum three pieces (to
keep the wheel load under 6T to suit
existing masonry) and designed as per
latest codes in a manner to preclude
These gates will be combined with +103
level sluice gates and a single gate of size
10.0' x 21.0' with appropriate freeboard will
be provided.
We will incorporate technical specifications
as suggested under +106 & +114 heads in
the tender document. The cost is
considered under Sub estimate No.2
Project Rehabilitation Report of KRS Dam
79 | P a g e
Sl.
No.
Inspection Note of design team from
Gates (E&NE), CWC on its visit to
KrishnarajaSagar (KRS) Dam,
Observations & Recommendations
COMPLIANCE BY PROJECT
AUTHORITIES
vibrations. Independent electrical rope
drum hoist mounted on trestle shall be
provided for operating the new gates.
However, the hoist capacity & self-
closure property of gate shall be
evaluated considering coefficient of
friction for seals as min. 1.0 even if PTFE
cladded seals are preferred (μ value for
rubber on stainless steel varies between
0.65- 1.5). The corrosion resistant wheel
track shall be provided upto EL133.0'
(existing track), but the guide shall be
extended to EL141.75' (top of deck). All
other appurtenants required for gate
including latching/dogging shall be
provided as per standard practices and to
suit existing civil structure.
12 The Gantry crane for +103 level gates
was operated to assess its functioning.
The operation was smooth and no
problems have been reported in past as
well. Therefore, it is suggested that this
gantry crane shall be shifted and used for
operating +106 gates as it is identical in
capacity, make & other parameters to the
crane already provided for +106 gates.
However, it may be noted that the C/C
distance of +103 gate is 13.5' while for
+106 gate, it is 12.0'. If any modification
is required for simultaneous handling of 2
alternate +106 level gates with the shifted
crane, it shall be carried out provided it is
feasible. Otherwise the shifted crane shall
be used to handle one gate at a time.
The gantry crane will be shifted and used
for operating +106 gates as suggested.
Modification for lifting two gates at a time
will be examined
General
13 Since there is absence of maintenance
gates for sluices, the painting system for
gates shall be such that it is durable with
long life cycle. In this context, it is advised
that Page 7 of 18 international codes (like
EN ISO-12944) shall also be referred
along with BIS codes. Whichever gives
better durability & longevity shall be
adopted for painting.
Painting system as per international codes
(like EN ISO-12944) as suggested will be
examined at the time of tender
At present for estimation purpose standard
practice and as per WRD Specification
Painting system is considered.
14 The scrap comprising discarded gates
including chains, hoisting arrangement for
Automatic gates, inlet pipe arrangements
to float well, screw jacks (including for
+106 level gates) etc. shall be made part
Considered & Included in Sub-Estimate NO
2
Project Rehabilitation Report of KRS Dam
80 | P a g e
Sl.
No.
Inspection Note of design team from
Gates (E&NE), CWC on its visit to
KrishnarajaSagar (KRS) Dam,
Observations & Recommendations
COMPLIANCE BY PROJECT
AUTHORITIES
of Tender. The bidders shall be asked to
quote price for scrap in their bids.
However, the embedments for +114 level
gates shall not be removed. Further, the
inlet conduits provided in dam feeding
water to float well on rear shall be
plugged suitably after removal of inlet
piping arrangement.
15 Remote operation (like ARMAC, SCADA
based control systems) for proposed new
gates and + 80 level gates shall be made
Considered & Included in Sub-Estimate NO
2
As suggested by the Senior Officers(Gates) of the CWC, provision for replacement/refurbication of
gates is made in the PST. However, CPMU CPMU has deputed two experts Sri. Ajit kumar Sachdev,
Hydro-mechanical expert & Sri.Zika Smilkovic, Dam Design expert, to assist assessment and
recommendations of the current gates and hoist arrangements. Both experts visited the dam on
20/08/2015 and awaiting their reports for finalizing the design of hydro-mechanical equipments. The
provision for gates as per the clearance by the CWC with respect to design hydro mechanic
equipments will be made in the PST.
Project Rehabilitation Report of KRS Dam
81 | P a g e
COMPLIANCE TO THE OBSERVATIONS / RECOMMENDATIONS MADE BY EGIS,
CONSULTANTS TO CWC, WITH RESPECT TO CIVIL WORKS SUB-ESTIMATE -1 OF PST,
DATED 28 AUG 2015
Sl.
No. Observations Compliance
1. Any structural measure required to augment
the discharging capacity to safely pass the
revised design flood should be planned and
taken up in the next phase.
Noted. structural measures for safe
discharge of revived design flood will be
planned and taken up in the next phase
since the revised design flood reviewed and
approved by CWC is 17,010 cumecs.
2. The WB has recommended a series of
boreholes in the masonry structure between
Ch. 800 to 2100 m. be conducted to
understand the existing seepage and
leakage conditions of the masonry structure
and foundation. CPMU recommends an
additional borehole be placed at Ch. 2120
where downstream springs erupt when RWL
reaches El.744m.
As recommended by World Bank, 6 core
holes with bore hole video-graphy in
between Ch. 750 to 2100 m. are provided in
the revised PST. Now an additional core
hole with borehole video-graphy at
chainage 2120 m. where downstream
springs erupt when RWL reaches El.744m
is included in the project and accordingly
the estimated cost is revised.
3. The methodology suggested by CWPRS
may be followed and conformity of the repair
materials i.e.PICC or equivalent UV resistant
materials to BIS and international standards
may be ensured from the manufacturer/
supplier.
The methodology suggested by CWPRS
will be followed meticulously and conformity
of the repair materials i.e., PICC or
equivalent UV resistant materials to BIS and
international standards will be ensured from
the manufacturer/supplier. Accordingly
necessary tests required to ensure the
above is included in the NCB.
4. Extensive investigations including drilling for
Geological and Geotechnical investigations,
testing forassessing the in-situ properties of
masonry, regular chemical analysis of water,
preparation of hydraulic model for energy
dissipation arrangements, Geodetic survey
of the dam, Stability analysis of dam have
been suggested by DSRP and agreed by the
Department. Provision of all these
investigations in the estimate may be
confirmed. These investigations should
precede actual execution of remedial
measures proposed. The results of these
investigations may suggest a need for
additional remedial measures. Provision for
the same may also be made in the estimate.
The grouting material has been identified by
CWPRS after extensive testing. However,
quantities may change depending on the
results of above investigations.
Provision for conducting the extensive
investigations, including drilling for
Geological and Geotechnical investigations,
testing for assessing the in-situ properties of
masonry, regular chemical analysis of
water, preparation of hydraulic model for
energy dissipation arrangements, Geodetic
survey of the dam, Stability analysis of dam
as suggested by DSRP is made in the
estimate. An additional 10% of the cost of
the grouting, is included in the project cost
to meet the cost of additional remedial
measures, if required based on the above
tests. However, the actual quantity of
grouting required for the proposed project
will be considered at the time of execution.
5. Other essential points to consider during final design and preparation of tender documents
include:
Project Rehabilitation Report of KRS Dam
82 | P a g e
Sl.
No. Observations Compliance
6. It is recommended that the SPMU
incorporate the identified mitigation
measures as a part of the tender document
to ensure that environmental mitigation
measures are actually implemented during
construction.
In the PST Page No.222 & 223, it is clearly
mentioned that the proposed DRIP project
is in safe zone & it is free from
environmental & social impact. Hence, no
need of ESMF compliance. However, a
condition to mitigate the impacts at the time
of execution with respect to environmental
& social hazards will be included in the
NCB.
7. At maximum section of the dam, a small
pond (350 meters long by 200 meters wide
and between 3 to 5meters deep) has been
constructed and drainage from the under
sluices is directed into the pond. CPMU
recommends that an underwater camera-
mounted remote operated vehicle (ROV)
investigation of the pond be conducted to
map the basin and any disturbances or
visible areas of turbid water where noted.
This mapping can be used as a baseline for
periodic efforts to monitor dam health and
safety concerns
Provision for procuring ROV with camera
mounted for conducting periodical
underwater investigations of the pond is
made in the PST and the cost of the
equipment is around ₹42.00 lakhs which is
ascertained through internet. This value is
considered only for estimate purpose.
Project Rehabilitation Report of KRS Dam
83 | P a g e
COMPLIANCE TO THE COMMENTS / RECOMMENDATIONS MADE BY THE CPMU OF C.W.C
NEW DELHI, FOR KRS REVISED PST & SITE VISITS
Sl.
No. OBSERVATIONS/
RECOMMENDATIONS
COMPLIANCE BY PROJECT
AUTHORITIES
1 The water level corresponding to the
spillway discharge capacity of 9912 m³/s
has been mentioned as 24.38 m (page 7 of
the PST), without any mention of reference
point.
It is understood from the PST that this is
perhaps with reference to the deepest river
bed level. This may please be clarified in
the PST so that this aspect is clear. The
reference level may also be indicated. In
the same light, reference to gate sills
should be in Elevation above MSL to avert
misunderstandings. Mixing of feet and
meters in any combination can lead to
misinterpretations and worse.
Further it appears that the same correction
is also to be applied to various invert/crest
levels in respect of sluice gates. This may
also be looked into and clarified.
The water level corresponding to the
spillway discharge capacity of 9912 m³/s is
754.32m above MSL. Necessary correction
has been effected in the PST. All levels of
structures are mentioned with reference to
MSL.
2 Both the live and gross storage of the
reservoir have been mentioned as 1369
Mm³. It should be corrected considering
the dead storage.
The live storage capacity of the reservoir is
1275.38Mm3 and gross storage capacity of
the reservoir is 1400 Mm3, .Necessary
correction has been effected in the PST.
3 The drawings enclosed are not readable.
Bigger size (minimum A3) and readable
drawings may be enclosed.
Drawing for Sluice sections may also be
enclosed.
Bigger size readable drawings (from size A4
to A2) are enclosed.
Sluice sections drawings are also enclosed.
4 From the dam specific details in Form II, it
is seen that the top level of the dam, FRL
and MWL are all the same, i.e. El.752.25m
(pages 7 and 9 of PST). On page 73 of the
May 2014 DSRP report the crest of the
dam is stated as El. 754.08 meters; this
may be looked into and corrected.
The FRL is at 752.48m above MSL & the
MWL is at754.32m above MSL.
Corresponding data are corrected in the
PST.
5 Hydrology
In the revised design flood study, based on
PMP values received from IMD, a peak
flood of 8539 m³/s has been estimated.
Since this was found to be less than the
original design flood of 9911 m³/s, the
original design flood was retained.
As per the studies conducted by KERS, the
PMF value is 9683m3/s without considering
the effect of interceptions in the estimating
the flood and PMF value is 8539 M3/s
considering the effect of interceptions in
estimating the flood. Both values are much
less than the existing designed spillway
Project Rehabilitation Report of KRS Dam
84 | P a g e
Sl.
No. OBSERVATIONS/
RECOMMENDATIONS
COMPLIANCE BY PROJECT
AUTHORITIES
Subsequently it has been learnt from CWC
that they have carried out a storm study for
the project and obtained PMP values of
17.7 cm for 1-day and 28.6 cm for 2 days.
Estimation of probable maximum flood
hydrographs from the sub-catchments
followed by routing through the channel
reaches and Hemavathy Reservoir carried
out based on these new values by CWC
yielded a peak magnitude of PMF of 16057
m³/s.
capacity of 9911m3/s. However, structural
measures for safe discharge of revived
design flood will be planned and taken up in
the next phase since the revised design
flood reviewed and approved by CWC is
17,010 cumecs.
6
As the revised design flood increases
significantly from the current spillway
capacity (6686 m³/s), reservoir routing
studies should be carried out to establish
the adequacy of freeboard during
passage of the flood peak Consequently,
any Structural measure required to
augment Discharging capacity to safely
pass the revised design flood may be
planned and taken up in the next phase.
The spillway capacity by considering the
operative spillway gates is 6686m3/s (less
than the designed due to defunct of certain
spillway gates) and the same will be
reached to 9794m3/s after implementation
of this DRIP project. However, Structural
measures for safe discharge of revived
design flood will be planned and taken up in
the next phase.
7 Downstream springs are occurring at Ch.
2120m whenever the RWL reaches El.
744.7m. The WB has recommended
provision for borehole videography
between Ch. 750m to 2100m. CPMU
recommends an additional similarly
spaced borehole placed at Ch. 2120 to
better understand the existing condition of
the masonry structure and foundation
where these springs have been observed.
.As recommended by World Bank, 6 core
holes with bore hole video-graphy in
between Ch. 750 to 2100 m. are provided in
the revised PST. Now, an additional core
hole with borehole video-graphy at chainage
2120 m. where downstream springs erupt
when RWL reaches El.744m is included in
the project and accordingly the estimated
cost is revised.
8 It is proposed to carry out re-pointing of
masonry joints on the u/s face of the
Masonry dam above low water level where
ever the pointing has peeled off/come out
using PICC or equivalent as per the
recommendations of CWPRS.
The methodology suggested by CWPRS
may be followed and conformity of the
repair materials i.e. PICC or equivalent UV
resistant materials to BIS and international
standards may be ensured from the
manufacturer/supplier.
It is recommended that CWPRS may be
associated during construction.
Further the type of cement proposed to be
used in grouting of the dam from dam top
The methodology suggested by CWPRS will
be followed meticulously and conformity of
the repair materials i.e. PICC or equivalent
UV resistant materials to BIS and
international standards will be ensured from
the manufacturer/supplier. Accordingly
necessary tests required to ensure the
above is included in the NCB.
It is proposed to appoint CWPRS as
grouting consultants.
53 grade ordinary Portland cement is
proposed for grouting from top of the dam
and necessary corrections have been
incorporated in the PST.
Project Rehabilitation Report of KRS Dam
85 | P a g e
Sl.
No. OBSERVATIONS/
RECOMMENDATIONS
COMPLIANCE BY PROJECT
AUTHORITIES
also needs to be indicated.
All precautions as recommended by the
World Bank with regard to pressures to be
applied and monitoring of movements
using upheaval gauges need to be
followed.
All precautions as recommended by the
World Bank with regard to pressures to be
applied and monitoring of movements using
upheaval gauges will be followed
meticulously.
9 It is seen that as the dam does not have
any foundation/drainage gallery, a series
of inclined holes of at least 150mm dia.
spaced at 20m centre to centre are
proposed to be drilled from the d/s face up
to the foundation for drainage.
In this regard it is felt that the above
drainage holes may not be very useful as
any such drainage holes from the d/s face
are normally not very effective in reducing
uplift pressures and also as the proposed
spacing of drainage holes is too large
(normal spacing is 3m centre to centre). It
is felt that these holes may not be
necessary
The stability of the masonry dam may be
checked as per IS 6512 and IS 1893
assuming extreme uplift in the locations of
normal uplift using the parameters
obtained from proposed investigations/
testing
If required then strengthening of the dam
by addition of buttresses/continuous
concrete lamina on the d/s face could be
considered later.
Inclined Bore holes from the downstream
face of the dam are suggested by the DSRP
and the project authorities of KRS dam have
expressed their apprehensions before the
Technical Committee (T.C) during their visit
with respect to stability if we have inclined
bore holes in 100 years old dam. The T.C
opined that there is no necessity of inclined
bore holes as the authorities have not
experienced the effect of uplift pressure ever
since. Hence this item is dropped.
It is proposed to conduct stability analysis of
the Dam as per IS 6512 and IS 1893 and
strengthening of the Dam by addition of
buttresses/continuous concrete lamina on
the d/s face will be considered in the next
phase if required.
10 The nomenclature of item no.1 of Sub-
Estimate 1 at page 105 of the PST may be
modified and elaborated to cover all the
items proposed to be carried out for clarity
The nomenclature of item no.1 of Sub-
Estimate 1 at page 105 of the PST is
modified and elaborated to cover all the
items proposed to be carried out.
11 Similarly the nomenclature of item no.3 of
Sub-Estimate 2 on Sluice Gates at page
105 of the PST is not clear .The
gates/vents at +103 ft. are seen to be
occurring twice in the nomenclature. The
nomenclature needs to be clearly worded
for the sake of clarity. It is presumed that
the recommendations of the CWC expert
team on gates and the Committee under
Managing Director, CNNL have been duly
CPMU has deputed two experts Sri. Ajit
kumar Sachdev, Hydro-mechanical expert &
Sri.Zika Smilkovic, Dam Design expert, to
assist assessment and recommendations of
the current gates and hoist arrangements.
Both experts visited the dam on 20/08/2015
and awaiting their reports for finalizing the
design of hydro-mechanical equipments.
Project Rehabilitation Report of KRS Dam
86 | P a g e
Sl.
No. OBSERVATIONS/
RECOMMENDATIONS
COMPLIANCE BY PROJECT
AUTHORITIES
considered
The details/type of the new gates and
their hoists as planned may be indicated
Provision for embedded parts and
implications on civil works need to be
appropriately considered.
12
Again, some confusion as sill elevations
based on the foot distance above deepest
river bed elevation is confusing.
Recommend all sill elevations are
referenced in meters above MSL to avert
misinterpretations by reviewers and
contractors.
All sill elevations are corrected to meters
with reference to MSL and are incorporated
in the PST
13 The provision of energy dissipation
arrangements for the waste weir sluices
has been suggested.
However, no provision for its study by
Hydraulic model and subsequent
execution of the energy dissipation
arrangements works has been made
The energy dissipation arrangements for the
waste weir sluices are already proposed in
the state budget.
14 Extensive investigations (Para 2.5.1.1)
including drilling for Geological and
Geotechnical preparation of hydraulic
model for energy dissipation
arrangements, Geodetic survey of the
dam, Stability analysis of dam have been
suggested by DSRP and agreed by the
Department. Provision of all these
investigations (proposed to be outsourced)
in the estimate may be confirmed.
Investigations, testing for assessing the in-
situ properties of masonry, regular
chemical analysis of water These
investigations should precede the actual
execution of remedial measures work. The
results of these investigations may suggest
the need for additional remedial measures.
Provision for the same may also be made
in the Estimates. The grouting material has
been identified by CWPRS after extensive
testing. However, the quantities may
change depending on the results of
investigations.
Provision for conducting the extensive
investigations, including drilling for
Geological and Geotechnical investigations,
testing for assessing the in-situ properties of
masonry, regular chemical analysis of water,
preparation of hydraulic model for energy
dissipation arrangements, Geodetic survey
of the dam, Stability analysis of dam as
suggested by DSRP is made in the
estimate. An additional 10% of the cost of
the grouting, is included in the project cost
to meet the cost of additional remedial
measures, if required based on the above
tests. However, the actual quantity of
grouting required for the proposed project
will be considered at the time of execution.
15 Additional works may be needed in case
the dam is found to be unstable under
various loading conditions as per IS Codes
especially due to change (increase) in
design seismic parameters.
Additional works, if needed due to change
in design seismic parameters will be
proposed under state budget.
16 A boat pond lies at the downstream toe of
the dam and measures approximately 200
Provision for procuring ROV with camera
mounted for conducting periodical
Project Rehabilitation Report of KRS Dam
87 | P a g e
Sl.
No. OBSERVATIONS/
RECOMMENDATIONS
COMPLIANCE BY PROJECT
AUTHORITIES
meters by 350 meters. The estimated
depth of the pond is about 3 to 5 meters.
There has been no investigation as to the
foundation condition of the pond. CPMU
recommends an underwater camera-
mounted ROV investigation of the pond be
conducted to understand the current
condition. CPMU recommends mapping of
the bed of the pond be conducted and
areas and or locations of turbidity,
turbulence of the water and or the current
floor condition be done to form a baseline
for future monitoring of dam behaviour.
underwater investigations of the pond is
made in the PST and the cost of the
equipment is around ₹ 42.00 lakhs which
is ascertained through internet. This value
is considered only for estimate purpose.
17 Instrumentation
There is no drainage and Foundation
Gallery in the body of the dam and
hence limited instrumentation has been
suggested by DSRP (DSRP of 1996, 97,
98 and 2014). However, no provision has
been made in the estimate submitted.
Provision of automatic Reservoir Water
Level Gauge, uplift gauges, V notches for
measurement of quantity of seeping water
at various places, automatic weather
station, etc., may be made.
Provision for providing and fixing Echo
Sounder, DGPS beacon-cum-heading
receiver along with single beam software for
data logging and processing, automatic
Reservoir Water Level Gauge, uplift gauges,
automatic weather station has been made in
the sub estimate-4 under instrumentation.
18 Hydro-Mechanical
Most of the gates need replacement and or
extensive repair. Some of these gates
have already been replaced and the
balance of the gates to be replaced now
has been studied by a committee
constituted by the department. The
provision for the same has been made in
the Estimate
CPMU recommends a more detailed
review of the existing gates and
appurtenant structures be conducted and,
in that light, CPMU will dispatch two
experts in hydro-mechanical and dam
design respectively, to assist assessment
and recommendations of the current gate
and hoist arrangement.
CPMU has deputed two experts Sri. Ajit
kumar Sachdev, Hydro-mechanical expert &
Sri.Zika Smilkovic, Dam Design expert, to
assist assessment and recommendations of
the current gates and hoist arrangements.
Both experts visited the dam on 20/08/2015
and awaiting their reports for finalizing the
design of hydro-mechanical equipments.
19 Environmental
The Attachment 1- Abstract Screening for
ESMF Activities and Categorization is
given but the identification of impacts and
the mitigation measures not provided. The
In the PST Page No.222 & 223, it is clearly
mentioned that the proposed DRIP project is
in safe zone & it is free from environmental
& social impact. Hence, no need of ESMF
compliance. However, a condition to
Project Rehabilitation Report of KRS Dam
88 | P a g e
Sl.
No. OBSERVATIONS/
RECOMMENDATIONS
COMPLIANCE BY PROJECT
AUTHORITIES
proposed activities will have impacts on
environmental components to a certain
extent and it is recommended to be
addressed appropriately in the PST
covering all the individual screening forms
of the ESMF.
mitigate the impacts at the time of execution
with respect to environmental & social
hazards will be included in the NCB
20 Other
EAP has already been prepared (Para
2.3.6). However, provision has been kept
in the Estimate submitted for its review
through outsourcing. Please clarify
EAP has already prepared and this item is
removed from the estimate.
Project Rehabilitation Report of KRS Dam
89 | P a g e
Compliance for the EGIS/CWC - Meeting with project to firm up the proposal of sluice gates at
KRS Dam on December 8th 2015
Sl. No.
EGIS / CWC- RECOMMENDATION PROJECT COMPLIANCE
+114 Gates and Hoist System
1
Replacing the existing battery of gates by a new set of gates designed & fabricated out of stainless steel material as per IS 4622 ( fixed wheel gates ), provision of corrosion resistant material wheels with self- lubricating Lubrite or equivalent bearings, for making these almost maintenance free.
Provided New set of structural steel with self lubrite or equivalent , as gates will be hardly in water for 3-4 months
However SS materials same will be considered looking into the financial implication for implementing SS materials .
2
Providing fabricated guides on both sides & supporting sill (removable) at the bottom by suitably designed channel shaped frames of stainless steel material to be anchored to the civil structure by chemical bonded anchors to properly guide the gate removable supporting sill at the bottom of the gate.
Provided Side guides & Supporting Sill at the bottom of Structural Steel materials by anchoring to civil structure However SS of C section will be adopted
3
Dispensing the original system of pulleys & chains, removing & disposing the unutilised removable components, while leaving pulleys etc. as such as their removal is likely to damage & disfigure the masonry structure.(The removal & replacement of old age pulley system would have required un-necessary disturbing the masonry unique look.)
The components which are embedded in
civil work ( pulleys& chains ) will not be disturbed.
4
Removal of additional gate supporting slings provided for safety of hanging gates against failure of pulling sling resulting in free fall of gates in the reservoir, for their disposal.
The removal and replacement of SUPPORTING
SLINGS will be removed for disposal.
5
Abandoning the use of float, float well Counter weight, & float-well system by isolating the same by delinking of connecting chain sling system. The existing structure to be retained & preserved as Heritage structure & marvel of age old engineering.
The system of Float well Counter weight, & float-well by isolating same by delinking conecting chain sling system will be abandond. The Civil structure will be retained and preserved Heritage structure & marvel of old age engineering.
6
Providing actuation to gate systems through an individual lightweight & compact skid mounted, electrical rope drum hoist conforming to IS 3938 for lifting & lowering the gates. The proposal remained deferred for some additional studies on how to support the hoisting system appropriately on the old & heritage masonry structure to cause the least damaging impact on the aesthetics & outlook of the structure. With this objective another site visit on 19.11.15 was conducted & detailed meetings were held with Director, DRIP to evolve the structural support system on the masonary dam to support the independent hoist systems for individual fixed wheel gates Detailed deliberations led to: v An innovative approach to provide for the load bearing concrete.
We have examined the proposal of laying the RCC beam beneath the existing track and extend the same RCC beam on the Upstream to accommodate the hoist arrangement for both the +103’ and +114’ and to free the gate from hoist arrangement during non -usage and for maintenance by a portal structure provided over the existing rail system for handling the gate for maintenance .
a
Beam structures over the existing piers to be cast & anchored to the existing pier with cantilever projection on u/s to support the
As per the site condition the RCC beam will be provided at 141.75 ‘level and will be projected beyond the face of the dam. Then
Project Rehabilitation Report of KRS Dam
90 | P a g e
Sl. No.
EGIS / CWC- RECOMMENDATION PROJECT COMPLIANCE
compact hoist systems. This would require removal of one stone support from each side of the pier from under the stone beams supporting the crane rails for casting concrete beam with overhang on u/s side for supporting the rope drum hoists.
the gate cannot be lifted above the newly casted beam and approach for the gate maintenance is constrained. Further the portal provided should be capable of taking the gate from EL141.75 ‘and turn by 180 degree and store at 124 ‘ level as there is no space at EL 141.75’. In view of the above constrain it is proposed to provide hoist on the common Hoist bridge mounted on the columns. In this proposal the columns will be proposed by casting RCC foundation in the existing recess of the +103’ gate groove on piers without disturbing the existing stone masonry. With this arrangement gate can be lifted above the pier for maintenance and can be dogged within the groove during long non- use and this arrangement is in line with the present +80’ vents. Under the circumstances explained above we request to examine this proposal for adoption. This will least damage the masonry structure .The aesthetics and outlook will not change and will be in line with the +80’ vent which are recently innovated.
b
Suitable dogging arrangements shall be provided under this hoist supporting structure for facilitating freeing the gate from the hoist during long periods of non-usage & also for facilitating removal & lifting of the hoists from its base for any intended maintenance
requirements on the gates.
Suitable dogging arrangement shall be provided
under hoist supporting structure for faacilating
the gate from hoist.
c
For facilitating this a portal structure crane shall be provided over the existing rail system for handling the removal of hoist & gates for maintenance as & when required. Moreover the ropes & rope drums for +114 gates shall be such as will allow these gates to be lowered to the sluice + 103 ground level for any maintenance jobs as & when essential during the lean periods.
A Portal crane will be provided for handling hoists & gates for maintainance of +114 gates The rope & rope drums for +103 gates shall be placed on similar way.
d
Considering the age of the Surkhi mortar structure, the most challenging work shall be to handle the work of installation/ modification work of gate grooves & provision of embedment in the civil structure for the proposed new gates without affecting the integrity of the civil structure.
Work of installation / modification of gate and hoist will be handled without affecting the integrity of the masonry structure considering age of dam for the proposed New gates . Precautionary method will be adopted and methodology /experience gained during execution of +80’ vents will be given as guidelines for the executing agency
e
The proposed methodology for the civil structure has been broadly discussed & envisaged & the project has been advised to prepare the detailed methodology based on their past experience gained on earlier modified gate installations at + 80 & other locations as a guideline for the executing agency for preparation of bid document and submission to
Work of installation / modification of gate and hoist will be handled without affecting the integrity of the masonry structure considering age of dam for the proposed New gates . Precautionary method will be adopted and methodology /experience gained during execution of +80’ vents will be given as guidelines for the executing
Project Rehabilitation Report of KRS Dam
91 | P a g e
Sl. No.
EGIS / CWC- RECOMMENDATION PROJECT COMPLIANCE
CPMU for review. agency
103 &106 Gates & Hoists
1
The scheme of the proposed replacement of cast iron gates & embedded parts for +103 & +106 gates by structural steel wheeled gates as per IS 4622 along with their embedded parts has already been cleared.
The Embedded parts and wheeled gate for 103 & +106 gates ( Structural steel ) will designed as per IS 4622.
2
Project had all along been requesting for provision of independent rope drum hoists over trestles for all the gates. Keeping in view the requirement for independent hoist driven gates at these locations, the same was also agreed to with a centralised control room for
operation of all the gates on these sluices with the exception that hoist light weight, compact, skid mounted electric wire rope hoists conforming to IS 3938-1983 to be adopted for +114, +103 gates & also
for +106 gates at the top of dam structures (without use of trestles) to be mounted on the same pattern as for the +114 gates.
The rollers will be out of cast steel with anti-friction bearing and will be replaced as per the proposal.
The Independent rope drum hoist will be mounted on pier and designed for a IS 6938 and is operated by central control remote system for +114, +103 & +106 gates
3938 -1983.
Maintenance provision:
For facilitating this a portal structure crane shall be provided over the existing rail system for handling the removal of hoists & gates for maintenance of gates & hoists at +103 & +114 gate installations along with a similar separate portal structure for maintenance of
+106 gate installations. Moreover the ropes & rope drums for +114 gates shall be such as will allow these gates to be lowered to the sluice + 103 ground level for any maintenance jobs as & when essential during the lean periods, if so required.
A Portal structure crane shall be provided for existing rail system for handling for maintenance of +103 , +114 and also for +106 hoists & gates. With this portal the hoist is to be freed from the gate and gate is to be lifted above the pier for maintenance. Only one gate at a time can be taken up for maintenance. It is empathized the time required for maintenance of 48 gates may be high. If the hoist is on the individual hoist bridge then the maintenance will be quicker and easier as the hoist and gate need not be freed to take out gate from the vent. We request to examine to adopt hoist and hoist bridge mounted on the column. This will not affect aesthetes and outlook of the dam. Further we will have similar look from +106’ to end of dam i.e. including recently renovated vent +80’. Illumination to the hoist will be further attractive.
Project Rehabilitation Report of KRS Dam
92 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of KRS Dam
93 | P a g e
Annex F: DBA and Inundation Maps
Project Rehabilitation Report of KRS Dam
94 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of KRS Dam
95 | P a g e
Project Rehabilitation Report of KRS Dam
96 | P a g e
Project Rehabilitation Report of KRS Dam
97 | P a g e
Project Rehabilitation Report of KRS Dam
98 | P a g e
Project Rehabilitation Report of KRS Dam
99 | P a g e
Project Rehabilitation Report of KRS Dam
100 | P a g e
Project Rehabilitation Report of KRS Dam
101 | P a g e
Project Rehabilitation Report of KRS Dam
102 | P a g e
Project Rehabilitation Report of KRS Dam
103 | P a g e
Project Rehabilitation Report of KRS Dam
104 | P a g e
Project Rehabilitation Report of KRS Dam
105 | P a g e
Project Rehabilitation Report of KRS Dam
106 | P a g e
Project Rehabilitation Report of KRS Dam
107 | P a g e
Project Rehabilitation Report of KRS Dam
108 | P a g e
Project Rehabilitation Report of KRS Dam
109 | P a g e
Project Rehabilitation Report of KRS Dam
110 | P a g e
Project Rehabilitation Report of KRS Dam
111 | P a g e
Project Rehabilitation Report of KRS Dam
112 | P a g e
Project Rehabilitation Report of KRS Dam
113 | P a g e
Project Rehabilitation Report of KRS Dam
114 | P a g e
Project Rehabilitation Report of KRS Dam
115 | P a g e
Project Rehabilitation Report of KRS Dam
116 | P a g e
Project Rehabilitation Report of KRS Dam
117 | P a g e
Project Rehabilitation Report of KRS Dam
118 | P a g e
Project Rehabilitation Report of KRS Dam
119 | P a g e
Project Rehabilitation Report of KRS Dam
120 | P a g e
Project Rehabilitation Report of KRS Dam
121 | P a g e
Project Rehabilitation Report of KRS Dam
122 | P a g e
Project Rehabilitation Report of KRS Dam
123 | P a g e
Project Rehabilitation Report of KRS Dam
124 | P a g e
Project Rehabilitation Report of KRS Dam
125 | P a g e
Project Rehabilitation Report of KRS Dam
126 | P a g e
Project Rehabilitation Report of KRS Dam
127 | P a g e
Project Rehabilitation Report of KRS Dam
128 | P a g e
Project Rehabilitation Report of KRS Dam
129 | P a g e
Project Rehabilitation Report of KRS Dam
130 | P a g e
Project Rehabilitation Report of KRS Dam
131 | P a g e
Project Rehabilitation Report of KRS Dam
132 | P a g e
Project Rehabilitation Report of KRS Dam
133 | P a g e
Project Rehabilitation Report of KRS Dam
134 | P a g e
Project Rehabilitation Report of KRS Dam
135 | P a g e
Project Rehabilitation Report of KRS Dam
136 | P a g e
Project Rehabilitation Report of KRS Dam
137 | P a g e
Project Rehabilitation Report of KRS Dam
138 | P a g e
Project Rehabilitation Report of KRS Dam
139 | P a g e
Project Rehabilitation Report of KRS Dam
140 | P a g e
Project Rehabilitation Report of KRS Dam
141 | P a g e
Project Rehabilitation Report of KRS Dam
142 | P a g e
Project Rehabilitation Report of KRS Dam
143 | P a g e
Project Rehabilitation Report of KRS Dam
144 | P a g e
Project Rehabilitation Report of KRS Dam
145 | P a g e
Project Rehabilitation Report of KRS Dam
146 | P a g e
Project Rehabilitation Report of KRS Dam
147 | P a g e