procedures to perform dam rehabilitation analysis in aging
TRANSCRIPT
Procedures to Perform Dam Rehabilitation Analysis in Aging Dams
Michael A. Bliss
Thesis submitted to the faculty of the Virginia Polytechnic Institute and State University in partial fulfillment of the requirements for the degree of
Master of Science
In Civil and Environmental Engineering
David F. Kibler (Chair) William E. Cox
Joseph E. Dove
18 May 2006 Blacksburg, Virginia
Keywords: Dam Rehabilitation Analysis, Hydrologic and Hydraulic Analysis, Incremental Economic Analysis, Linear Programming, Dam Safety.
© 2006, Michael A. Bliss
ii
Procedures to Perform Dam Rehabilitation Analysis in Aging Dams
Michael A. Bliss
(ABSTRACT)
There are hundreds of existing dams within the State of Virginia, and even thousands
more specifically within the United States. A large portion of these dams do not meet
the current safety standard of passing the Probable Maximum Flood. Likewise, many of
the dams have reached or surpassed the original design lives, and are in need of
rehabilitation. A standard protocol will assist dam owners in completing a dam
rehabilitation analysis. The protocol provides the methods to complete the hydrologic,
hydraulic, and economic analysis. Additionally, alternative augmentation techniques are
discussed including the integration of GIS applications and linear programming
optimization techniques. The standard protocol and alternative techniques are applied
to a case study. The case study includes a set of flood control dams located in the
headwaters of the South River watershed in Augusta County, VA. The downstream
impacts of the flood control dams on the city of Waynesboro are demonstrated through
the hydrologic and hydraulic analysis.
iii
Table of Contents Abstract�������������������������������� ii Table of Contents���������������������������.. iii List of Figures�����������������������������. v List of Tables�����������������������������.. vi Acknowledgement���������������������������.. vii Dedication������������������������������� viii Chapter 1: Introduction������������������������� 1
1.1 Problem Background��������������������� 1 1.2 Statement of Objectives�������������������.. 2 1.3 General Framework Description���������������� 3 1.4 Introduction to South River Watershed�������������. 4 1.5 Outline��������������������������� 4
Chapter 2: Related Works�����������������������.. 7 2.1 Dam Safety������������������������� 7 2.2 Risk Analysis������������������������. 10 2.3 Probable Maximum Floods������������������. 11
2.4 Linear Programming���������������������. 13 2.5 Dam Remediation Strategies�����������������.. 14
Chapter 3: Hydrologic Model for Upper South River and Application to Dam Removal Question�� 17
3.1 South River Watershed�������������������� 18 3.2 Required Data for Model Creation���������������. 20
3.2.1 Watershed Parameters���������������. 20 3.2.2 Channel Properties����������������� 21 3.2.3 Reservoir and Dam Properties������������. 22 3.2.4 Reservoir Rating Table���������������.. 25 3.2.5 Rainfall Data from IFLOWS Gages����������. 26 3.2.6 Surveyed High Water Marks from Recent Storms���� 27 3.2.7 Lyndhurst Gaging Station Stream Flows�������� 27
3.3 Hydrologic Model Creation������������������.. 29 3.3.1 Basin Model Creation���������������� 30
3.3.1.1 Sub-basin Icon Data������������� 30 3.3.1.2 Reach Icon Data��������������.. 31 3.3.1.3 Reservoir Icon Data�������������. 32
3.3.2 Weather Model Creation��������������� 33 3.3.2.1 User Hyetographs�������������� 33 3.3.2.2 NRCS Hypothetical Storms���������� 36
3.4 Model Calibration����������������������.. 36
iv
3.5 Simulating the Results of Dam Removal..������������ 43 3.6 Summary�������������������������� 47
Chapter 4: Traditional Economic Analysis of Dam Rehabilitation by Flood Damage Curve Integration��� 49
4.1 General Approach to Economic Analysis������������.. 49 4.2 Specific Steps to an Economic Analysis������������� 53 4.3 Federal Planning Guidance������������������. 57 4.4 Case Study Economic Analysis����������������.. 58 4.5 Summary of Traditional Economics Analysis����������� 67
Chapter 5: Use of GIS Software as a Hydro-economic Tool in Dam Rehabilitation Analysis���.. 68
5.1 Overview of GIS as a Tool for Analysis�������������. 68 5.2 Discussion of Existing Relevant GIS Software����������. 70 5.3 Automating the Economic Analysis��������������� 73 5.4 FEMA�s HAZUS Multi-Hazard Model��������������. 74 5.5 Case Study Application of HAZUS-MH Software���������. 76 5.6 Summary of Integration of GIS Software with Rehabilitation Analysis��... 85
Chapter 6: Linear Programming as an Alternative Analysis Technique����.. 87
6.1 An Alternative Economic Analysis for Dam Rehabilitation�����.. 88 6.2 Application of Linear Programming��������������� 93 6.3 Expansion of Alternative Economic Analysis Through Linear Programming���... 96
6.3.1 Model Formulation�����������������.. 96 6.3.2 Test Example�������������������.. 100 6.3.3 Results from Simulation Runs������������.. 103 6.3.4 Discussion of New Linear Program Techniques����� 104
6.4 Summary��������������������������. 105 Chapter 7: Summary, Conclusions, and Recommendations���������.. 107 7.1 Summary�������������������������� 107 7.2 Conclusions������������������������... 109 7.3 Recommendations���������������������� 110 . Bibliography������������������������������ 112 Appendices Appendix A HEC-HMS Data�������������������.. 115 Appendix B South River Model Output Data������������... 136 Appendix C Linear Programming Test Example�����������. 139 Vita���������������������������������� 148
v
List of Figures
Figure 1.1: South River Watershed, Sub-basins and Dams���������.. 5 Figure 2.1: Taum Sauk Reservoir Breach; �Reprinted with permission of the St. Louis Post-Dispatch, copyright 2005.� Graphic from the news article: �Swept away, rescued more than a billion gallons of water��, December 15, 2005, Todd C. Frankel and Tim Rowden����������. 8 Figure 2.2: Extreme 12 hour Historical Storms in U.S. ������������.. 13 Figure 2.3: Parapet Wall Remediation (USACE, 2004)�����������. 15 Figure 2.4: Articulated Blocks in place on VA Tech Campus��������� 16 Figure 3.1: South River Watershed, Sub-basins and Dams���������. 19 Figure 3.2: Cross Section Template�������������������. 22 Figure 3.3: Robinson Hollow Dam, Upstream Side Reservoir��������. 23 Figure 3.4: Canada Run Inlet Structure������������������ 23 Figure 3.5: Happy Hollow Outlet Structure����������������.. 23 Figure 3.6: Robinson Hollow Original Plan View�������������� 24 Figure 3.7: Lofton Lake Auxiliary Spillway����������������.. 24 Figure 3.8: IFLOWS Gage at Stoney Creek Dam�������������. 26 Figure 3.9: Hurricane Isabel Hydrograph����������������� 28 Figure 3.10: HEC-HMS Primary Menu Screen��������������� 29 Figure 3.11: HEC-HMS Basin Model Editing Screen������������. 30 Figure 3.12: Reach Editor Screen, Basin Model��������������. 32 Figure 3.13: Reservoir Editor Screen, Basin Model������������� 33 Figure 3.14: Meteorological Model Editor, HEC-HMS������������ 34 Figure 3.15: South River Watershed, Rainfall Data Applied to Sub-basins for HEC-HMS Model��������������������������. 35 Figure 3.16: South River Watershed, HEC-HMS Schematic Diagram����� 37 Figure 3.17: South River Watershed, Landuse within Watershed������� 40 Figure 3.18: South River Watershed, NRCS Soil Curve Number Data for Sub-basins����������������������������� 41 Figure 3.19: Real Time Data from USGS on 29 NOV 05 Storm�������... 43 Figure 3.20: Q2 Side by Side Comparison at Dam Sites����������� 44 Figure 3.21: Q100 Side by Side Comparison at Dam Sites���������� 45 Figure 3.22: South River Watershed, Reduction of Discharge by Dams for Q100. 46 Figure 3.23: Gage Height Comparison������������������.. 46 Figure 4.1: Example Economic Benefit Determination�����������.. 50 Figure 4.2: Economic Analysis Flow Chart����������������.. 56 Figure 4.3: NRCS Damage Frequency Curve (Faulkner, 2006)�������.. 63 Figure 5.1: Augusta County, VA GIS Web-site��������������� 70 Figure 5.2: HAZUS-MH Start Menu�������������������.. 74 Figure 5.3: Augusta County Study Region in HAZUS-MH���������� 76 Figure 5.4: Census Blocks in HAZUS-MH����������������... 77 Figure 5.5: Stream Network in HAZUS-MH����������������. 78 Figure 5.6: Flood Inundation Zone for Hillsborough, NC����������.. 79 Figure 5.7: Common Reach for Inch Branch and Toms Branch Dams����.. 81 Figure 5.8: Comparison of HAZUS-MH and NRCS Flood Zones������� 82 Figure 5.9: Example Damage HAZUS-MH Damage Report��������� 83 Figure C.1: Regression Plot for People at Risk Parameter���������.. 139 Figure C.2: Regression Plot for Damage without Modification��������. 140 Figure C.3: Regression Plot for Damage with Modification���������.. 141 Figure C.4: Regression Plot for Modification Cost v. % PMF��������� 138
vi
List of Tables
Table 3.1: South River Watershed Data�����������������.. 20 Table 3.2: South River Manning�s n Values���������������� 21 Table 3.3: Lyndhurst GS Data���������������������... 28 Table 3.4: Hurricane Isabel Rainfall�������������������. 36 Table 3.5: Initial Simulation Runs��������������������. 38 Table 3.6: Simulation Changes���������������������. 39 Table 3.7: Calibration Results���������������������� 42 Table 4.1: Example Economic Analysis�����������������... 53 Table 4.2: NRCS Damage Summations (Faulkner, 2006)���������� 62 Table 4.3: NRCS Tabulated Data for Figure 4.3 Damage Frequency Curve (Faulkner, 2006)������������������������� 63 Table 4.4: NRCS Average Annual Damages for Sponsor Breaches (Faulkner, 2006)������������������������� 64 Table 4.5: NRCS Average Annual Damages for Toms Creek Rehab. (Faulkner, 2006)������������������������� 65 Table 4.6: NRCS Incremental Analysis on Sponsor Breaches (Faulkner, 2006).. 66 Table 4.7: NRCS Incremental Analysis on Rehabilitation Options (Faulkner, 2006)������������������������� 66 Table 5.1: Lyndhurst Gaging Station Comparison�������������. 80 Table 5.2: HAZUS-MH Comparison to HEC-HMS at Dam Sites�������. 81 Table 5.3: Flood Inundation Comparison�����������������. 82 Table 5.4: Property Exposure Estimates Comparison������������84 Table 5.5: Total Structure Damages Comparison�������������.. 85 Table 6.1: South River LS and LM Calculations��������������� 90 Table 6.2: South River LCS and LCM Calculations�������������� 91 Table 6.3: LB Results�������������������������.. 91 Table 6.4: South River Economic Calculations��������������.. 92 Table 6.5: Hypothetical Data for South River Dam Rehabilitations������. 94 Table 6.6: Summary of Results���������������������. 103 Table A.1: South River Watershed Sub-Area Data������������� 115 Table A.2: South River Manning�s n Values���������������� 117 Table A.3: Back Creek Manning�s n Values���������������� 117 Table A.4: South River Cross Section Data���������������� 118 Table A.5: Rating Table Data����������������������. 122 Table A.6: IFLOWS Rainfall Data��������������������.. 128 Table A.7: Hurricane Isabel High Water Marks��������������... 134 Table B.1: Simulation Output, CN = 65������������������. 136 Table B.2: Simulation Output, CN = 60������������������. 137 Table B.3: Simulation Output, CN = 55������������������. 138 Table C.1: People at Risk (PAR) Regression���������������.. 139 Table C.2: Flood Damage Regressions������������������ 140 Table C.3: Construction Cost Regression����������������� 141 Table C.4: Run#1: Original Data; Not Feasible��������������.. 142 Table C.5: Run#2: Flood Damage Switched; Not Feasible���������.. 143 Table C.6: Run#3: Flood Damage Switched, no construction costs; Feasible Solution������������������������... 144 Table C.7: Run#4: Additional Condition Xs > 25; Feasible Solution������. 145 Table C.8: Run#5: PARM is reduced to zero to check LB; Feasible Solution��.. 146 Table C.9: Run#6: Take PAR out of equation, Economic only; Feasible Solution 147
vii
Acknowledgements
I want to thank Dr. Kibler for providing mentorship and support through my
studies the past two years. I�m honored to have been associated with such an
outstanding professional who genuinely supports anyone he comes in contact with. I am
also grateful for the assistance from Dr. Cox and Dr. Dove, who have also provided
great insight to me.
I received much assistance from several agencies in providing pivotal data for
the development of the South River case study. I would like to thank Mr. Matthew
Lyons, State Conservation Engineer, Natural Resources Conservation Service (NRCS),
in providing the NRCS dam rehabilitation proposal for the South River watershed. Also
for the detailed economic information provided to me by Mr. David Faulkner, NRCS
economist. Mr. Fred Garst, GIS Analyst, NRCS, provided me with applicable GIS data
files to South River watershed products. Finally, I would like to thank Mr. Otis Bilkins
from the Headwaters Water and Soil Conservation District for providing me with critical
high water marks from major storm events.
Finally, I want to thank my family who support me everyday. My wife and
children mean the world to me, and I couldn�t have finished this without sacrificing time
away from them.
viii
Dedication
I dedicate this work to my soldiers of B Company, 11th Engineer Battalion, who I
am humbled and privileged to have led into battle during the start of Operation Iraqi
Freedom in 2003. They were the finest unit a commander could ever want, and they
fought with the utmost heroism and honor. We think daily of our fallen Bulldogs:
Bulldog 2-7: SFC Paul Smith (KIA, 04 APR 03) (Medal of Honor Recipient)
Bulldog 2-3: SSG Lincoln Hollinsaid (KIA, 07 APR 03)
Bulldog 1-6D: PFC Jason Meyer (KIA, 07 APR 03)
They are not forgotten!
Chapter 1: Introduction 1
Chapter 1: Introduction
1.1 Problem Background
There are hundreds of existing dams within the State of Virginia, and even
thousands more within the United States. The issue of dam safety, with respect to the
aging inventory of the existing dams, is an ongoing struggle that garnered national
interest back in the 1970s. The U.S. Army Corps of Engineers (USACE), mandated by
Congress, inspected over 8,000 non-federal dams in the late 1970s and early 1980s.
Almost one third of the dams did not meet the current Probable Maximum Flood (PMF)
design criteria (USACE, 1982).
Even with national interest for what is now over 30 years, the problem remains a
huge issue. The magnitude of the issue is best highlighted by the following statements
taken from the American Society of Civil Engineers (ASCE) 2005 �Report Card for
America's Infrastructure� (ASCE, 2005):
• Since 1998, the number of unsafe dams has risen by 33% to more than 3,500.
• The number of dams identified as unsafe is increasing at a faster rate than those being repaired.
• Such dam failures as Silver Lake Dam in Michigan in 2003 ($100 million in
damages and economic losses of $1 million per day) and the Big Bay Lake Dam in Mississippi in March 2004 (100 homes destroyed) are current reminders of the potential consequences of unsafe dams.
• The total investment to bring U.S. dams into safety compliance or to remove
obsolete dams tops $30 billion. The ASCE Report Card also states that in general dams owned by government agencies
are as expected in better condition then privately owned dams. Economic
considerations become extremely critical for privately owned dams. These independent
dam owners often do not possess the necessary capital to remediate aging dams to
meet current safety standards.
Chapter 1: Introduction 2
A recent newspaper article for the Roanoke Times exemplifies the dilemma
facing private dam owners. The article is about the Rainbow Forest Lake in Roanoke,
Virginia that is owned by a private home owners� association. The reservoir dam has
existed safely for over 45 years, included during the flood of record in 1985. However,
the dam does not meet the emergency spillway requirement of passing 75% of the PMF
for its size classification. The home owner�s association, with only about 100 members,
is faced with a few courses of actions. The cheapest option, at $41,000, is draining the
lake which would significantly impact the appeal of the lakeside property. A full
remediation project of the emergency spillway is estimated to cost $178,400. Even with
the complete remediation, there is not a guarantee that future changes will not be
needed based upon the continually changing hydrologic conditions in the watershed.
(Poindexter, 2005)
In order to proceed with dam rehabilitation analysis, dam owners perform a
detailed incremental hazard evaluation of the dam. This evaluation quantifies the risks
involved with courses of actions, as well as assesses the economic impacts of the same
courses of actions. A general framework for a procedure to complete this analysis could
greatly benefit the dam owners. Such a framework would demonstrate to the owners
methods to complete the incremental risk analysis. This general framework is the
overall focus for this thesis.
1.2 Statement of Objectives
With the background problem explained, there are two main objectives that
guided this work: 1. Develop a standard protocol to assist dam owners in performing decision
analysis for dam rehabilitation for dams that are out of safety compliance.
2. Develop a method to prioritize courses of actions for dam remediation.
Chapter 1: Introduction 3
The desired standard protocol is a needed framework for dam owners to implement in
completing dam rehabilitation analysis. The second objective is to demonstrate different
methods of performing the economic risk analysis in evaluation of the rehabilitation
courses of actions.
1.3 General Framework Description
The analysis process from a general framework perspective is not intricate by
nature. The problem(s) is defined to include an area of interest with existing structures.
In this case, an aging dam(s) is not in compliance with existing Dam Safety regulations,
is in need of repairs or rehabilitation, or possibly has exceeded the original project
design life. Either way, the initial step in the process is to perform hydrology & hydraulic
(H&H) analysis in order to represent the past, current, and future conditions of the
dam(s) in question. Potential remediation courses of actions are then considered and
monetary amounts of project benefits and costs are calculated.
Using the project benefits and costs from the H&H analysis, economic analysis is
then performed in an iterative manner to rank the courses of actions, and thus allow for a
decision to be made. The Economic analysis may lead to infeasible situations in which
the course of action must be changed, and the H&H analysis redone. Eventually, the
desired end state is achieved, and a decision for future work is made. What is a simple
description of the process requires complicated approaches, techniques, and
assumptions to reach the desired end-state of a recommended course of action to solve
the problem. The process is also time consuming and rigorous due to the complexity in
attempting to replicate real world conditions.
Chapter 1: Introduction 4
1.4 Introduction to South River Watershed
To demonstrate the complexity of the analysis process, a case study watershed
of the headwaters portion of the South River in Augusta County, Virginia was selected
as the case study watershed of interest for this thesis. Within the South River
Watershed (SRW), the Headwaters Soil & Water Conservation District (HSWCD)
maintains 12 existing agricultural flood control dams. All but two of the dams were built
in the 1950s, and therefore are candidates for rehabilitation. The dams are primarily
used for flood control purposes and benefit the local town of Waynesboro, VA and its
surrounding areas (See Figure 1.1) The 12 dams were originally planned, funded, and
constructed by the former Soil Conservation Service (SCS), now the National Resources
Conservation Service (NRCS), under the 1954 Watershed Protection and Flood
Prevention Act (Public Law 83-566, 1954). As will be further detailed, a simulation
model for the entire watershed was initially created to assess the impacts of the 12 dams
on the city of Waynesboro. Later work narrowed the focus onto three of the dams
currently being considered for dam rehabilitation through the NRCS.
1.5 Outline
This thesis is organized into six remaining chapters. The next chapter is a review
of related works and relevant references for this thesis. The initial step for completing
the incremental risk analysis is the hydrology and hydraulic analysis in order to represent
the watershed of interest. Incremental risk analysis is defined as the difference in
impacts incurred from any changes that are made, and the current condition of the
hydraulic structure (Interagency Committee on Dam Safety (ICDS), 2004b). The H&H
analysis preformed for the South River Watershed is presented in Chapter 3. The H&H
analysis must be linked to Economic Analysis in order to arrive at
Cha
pter
1: I
ntro
duct
ion
5
Chapter 1: Introduction 6
recommended courses of action. Chapter 4 provides a discussion of traditional
economic analysis techniques, and a review of the NRCS�s recently completed analysis
within the South River watershed. With today�s continual advancement in Geographic
Information Systems (GIS) software and GIS data, new analysis should incorporate the
available information to assist with the rehabilitation analysis. Chapter 5 presents a
discussion of potential uses of existing GIS software tools, and focuses in on evaluating
the Federal Emergency Management Agency�s (FEMA) risk mitigation software HAZUS-
MH. Incorporating data from Chapter�s 3 and 4, Chapter 6 discusses Linear
Programming techniques as an optimization decision making tool. Finally, closing
remarks and conclusions are summarized in Chapter 7.
Chapter 2: Related Works 7
Chapter 2: Related Works
The topic of dam rehabilitation assessment and analysis encompasses several
different functional areas that are necessary to achieve a complete representation of the
hydraulic structures of interest. There are different facets that must be accounted for
while executing a decision making process for dam rehabilitation. A major factor in this
regard is dam safety as it pertains to the protection of the general public. There are also
several different guideline documents at different levels of government, like Federal
government regulations vs. State regulations for dam construction. The purpose of this
chapter is to summarize these important sources of information.
We begin with the topic of dam safety, which is an important part of dam
rehabilitation. As part of the decision making process of dam rehabilitation, risk analysis
becomes the next area of emphasis for information. Following after this topic, is the
concept of the probable maximum flood (PMF) which is a critical design metric for dam
safety. Next we present the mathematical optimization technique of linear programming.
We briefly comment on the rehabilitation material like roller compacted concrete (RCC).
Finally, we conclude with some key information sources provided for the South River
watershed.
2.1 Dam Safety
As mentioned in the Introduction, a current assessment of the problem the
American Society�s of Civil Engineer�s Infrastructure released in March of 2005
highlights the need for rehabilitation of thousands of dams across the United States
(ASCE, 2005). Additionally, the issue faced by private dam owners is demonstrated by
the news article published in the Roanoke Times in January 2005 (Poindexter, 2005).
Finally, a vivid reminder of the importance of dam safety is demonstrated by the
Chapter 2: Related Works 8
catastrophic failure of the Taum Sauk Hydroelectric Plant�s Reservoir in Lesterville, MO
on December 13, 2005 (Frankel and Rowden, 2005). This horrific event sent a 10 ft high
wall of water through a nearby camp ground that was (fortunately) occupied only by the
Park Ranger�s family, all of whom were rescued safely. (See Figure 2.1)
Figure 2.1: Taum Sauk Reservoir Breach; �Reprinted with permission of the St. Louis Post-Dispatch, copyright 2005.� Graphic from the news article: �Swept away, rescued more than a billion gallons of water��, December 15, 2005, Todd C. Frankel and Tim Rowden�
John Peterson, formally of the U.S. Dept. of Agricultural, presented a paper
during the 2004 International Conference on Geosynthetics and Geoenvironmental
Engineering (Bombay, India), that included a good historical background for flood control
legislation in the United States (Peterson, 2004). Interestingly, he authored the Public
Chapter 2: Related Works 9
Law Statue 106-472 (PL 114, 2000) in 2000 that allowed for federal money to be used to
rehabilitate dams that were built by the Soil Conservation Service (now the National
Resources Conservation Service). This public law does not help all of the dam owners
in Virginia of course, but the dams in the South River Watershed actually are impacted
by this public law. Peterson also references the U.S. Bureau of Reclamation�s (BUREC)
Risk Based Profiling System in his paper as a systematic approach to prioritizing efforts
for rehabilitation.
The current Federal Government guidance for Dam Classification is Technical
Report 333 by FEMA (ICDS, 2004b). Originally, published in 1998 and updated in 2004,
the report states that all dams should be classified into one of three categories: High,
Significant, or Low hazard. To eliminate the gray area between High and Significant
classifications, dams are classified as High if one loss of life is probable from a dam
failure. A companion document also published during the same time is Technical Report
94 by FEMA (ICDS, 2004a). FEMA 94 gives in-depth details on how to select the Inflow
Design Floods through the incremental hazard evaluation process. Both of these FEMA
documents along with three other documents on Dam Safety were direct products of the
National Dam Safety Program Act of 1996.
The original overarching dam safety guidance traces back to the research
completed in the late 1970s and early 1980s as a result of President Carter�s influence
and concern for Dam Safety. The first publication from the National Research Council�s
Committee on the Safety of Existing Dams was published in 1983 (NRC, 1983). The
committee recognized the need to perform risk-based decisional analysis because of the
limited capital always available for rehabilitation. The described risk analysis is not only
technically based, but also must be economics-based. The second publication is the
National Research Council�s 1985 publication on the Safety of Dams (NRC, 1985). This
book includes an entire chapter on how to perform Risk Analysis while designing a dam.
Chapter 2: Related Works 10
Also, the committee acknowledged risk-based decisions were not commonly used prior
to 1985, but recognized the value of performing these types of analyses.
2.2 Risk Analysis
The United States Society on Dams (USSD) recognized the important aspects of
performing risk analysis. In 2003, the USSD published a discussion white paper: �Dam
Safety Risk Assessment: What Is It? Who�s Using It and Why? Where Should We Be
Going With It?� The purpose was to provide some uniform guidance for dam owners.
As previously mentioned, the BUREC published an updated Risk Based Profiling
System (RBPS) in 2001 (Cyganiewicz and et al., 2005). This systematic approach
allows for a rapid assessment of a particular dam in order to set remediation priorities
amongst multiple dams. The approach solves the following equation:
Risk = (Probability of Load)(Probability of Adverse Action)(Consequences).
Each parameter is evaluated and assigned points based upon a 1000 point maximum.
This assessment is particularly useful when management of limited funds is critical to
maximize the benefits of committed capital. The assessment is rapid in that a field
engineer can complete the assessment in a one to two day time period. The RBPS
incorporates the BUREC standard for estimating loss of Life (Graham, 1999). This
standard makes an assessment of the Population at Risk (PAR) given a certain warning
time of the emergency, and the population residing in the particular flood plain.
A comprehensive examination of estimating loss of life was completed by Duane
McClelland and David Bowles from the Institute of Dam Safety Risk Management, Utah
State University. The final paper was prepared for the Institute for Water Resources, of
the USACE (Bowles and McClelland, 2002). McClelland and Bowles reviewed the
current practices for estimating loss of life. They began with Brown and Graham�s work
at the Bureau of Reclamation in the early 1980s. Their research became the BUREC
Chapter 2: Related Works 11
standard. Brown and Graham performed regressions on known dam failures to create
general equations for estimating PAR. McClelland expanded upon Brown and Graham�s
pioneering work (Dekay and McClelland, 1991). They included a few additional dam
failures that Brown and Graham omitted to generate two additional equations for dam
situations where the watershed is within a steep valley.
McClelland and Bowles additionally reviewed a more recent approach used by
the completed by BC Hydro (B. A. and H. BAI, 2001) that attempts to go beyond
statistical regressions for estimating Loss of Life. They�ve created a model based upon
probabilities that a person in a particular area will survive the flood wave from a dam
break. The model is more complex in that the warning time is combined with flood wave
routing, and probability rules are applied to each individual population. This method is
still being developed by BC Hydro, but the potential to provide a more accurate model
beyond derived equations is encouraging.
The first major approach to risk analysis was provided by a committee organized
by the American Society of Civil Engineers (ASCE Task Committee, 1988). This task
force�s primary goal was to evaluate and provide a uniform way to select of selecting the
safety design flood. This committee was formed in response to the risk analysis
approaches presented by the National Research Council�s published work in the 1983
and 1985 on Dam Safety. The ASCE report did provide a thorough approach to risk
analysis, but provided dam owners with a good reference guide for future design work.
2.3 Probable Maximum Floods
The first three references involving the Probable Maximum Flood (PMF) argue
against the validity and purpose of the PMF being used as the design criteria for dams.
Lave et al. (1990b) argue the extremely low probability of the PMF being exceeded and
causing economic damages is not worth the construction costs of retrofitting an existing
Chapter 2: Related Works 12
dam. A companion article, also by Lave et al. (1990a), provided a case study
rehabilitation project of a dam. Lave et al. described how for the case study dam the
emergency spillway was never used in 25 years of operation. Yet to meet the current
PMF required standard, the dam was modified. The large rehabilitation costs only
yielded small economic benefits.
A follow up to Lave et al. (1990b) culminated with a discussion paper published
by Graham (2000) that proposes a procedure for evaluating dam modifications. Graham
(2000) recognized that economic analysis must be performed. Fundamentally, this
analysis should answer the following question: Is spending construction costs going to
be exceeded by the benefits gained? This is typically not an easy issue to address as
the value of human life must be estimated. Graham (2000) also argues that meeting the
PMF design standard is not always the best course of action of many dam projects.
However, this discussion paper provides a logical mathematical framework that can be
used as a basis for completing the economic analysis of a water resources project.
Harrison (2000) and (2003) demonstrated that PMPs and PMFs do happen in the
United States. There are five storms in the Mid-Atlantic region where for a 10 square
mile area, 75% of the calculated PMP was observed (Figure 2.2). For one 12 hour
storm in Smethport, PA, the PMP was exceeded by 19% (Harrison, 2000). It is also
showed that calculated PMFs for Northern Appalachian, Central Appalachian, and South
Central Texas regions are observed frequently (Harrison, 2003).
Chapter 2: Related Works 13
Figure 2.2: Extreme 12 hour Historical Storms in U.S.
2.4 Linear Programming
Linear programming is a solution technique for problems that involve multiple
courses of action that are in competition for limited resources. A goal that is usually
desired is to maximize profits or minimize production costs. Within the confines of the
problem, the limited resources translate to constraints that must be addressed within the
linear program. Through formulation of a linear program an �optimal� solution can be
found by solving mathematical equations to achieve the desired goal.
Null and Lund (2005) describes how optimization linear programming was used
to justify the decommissioning of a reservoir for the Hetch Hetchy water supply system in
the Yosemite National Park. The course of action to remove the dam was proven not to
Chapter 2: Related Works 14
have an impact on the water supply system�s ability to meet future year 2100 city
demands. The author�s method of justification for dam removal may prove to be useful
for certain situations.
Lund (2002) is focused on Risk-based Optimization with Floodplain Planning
(Lund, 2002). The author approaches the long standing issue of integrating economical
issues with permanent and emergency flood control options. A two part general linear
program is formulated that allows for the permanent and emergency courses of actions.
This general linear program must then be applied to a given situation by creating the
constraints.
Finally the textbook, �Operations Research: Principles and Practices� provides
the background mathematical method of linear programming formulation (Ravindran et
al., 1987). This background contained within the textbook gives in depth instruction on
developing linear programs and integer programs for the purpose of modeling complex
systems.
2.5 Dam Remediation Strategies
Roller Compacted Concrete (RCC) is extremely relevant for current dam
construction, regardless if it is a new project or a repair of an existing structure. All three
of the sources support the use of RCC in water resource projects because of its ease of
placement; it can be mixed on site, and the lasting physical properties of the end
product. Bass (2000) and (2003) demonstrate the usefulness of RCC. The United
States Society on Dams (USSD) also recognized the value of using RCC in dam
projects. They published a reference book on RCC, with an entire section on dam
rehabilitation (Obermeyer and Johnson, 2003).
While RCC can be used to armor the entire dam or a spillway, RCC can also be
used to raise the height of the dam which is a remediation technique. Raising the dam
Chapter 2: Related Works 15
can also be accomplished with mechanically stabilized soils up to 10 to 15 feet. Another
technique is constructing a parapet concrete wall on the crest of an existing dam. The
USACE Engineer Manual for design of dams states that in general the most cost
effective technique to raise a dam is the parapet wall (USACE, 2004). Figure 2.3 is an
example of a parapet wall looks like (USACE, 2004).
Figure 2.3: Parapet Wall Remediation (USACE, 2004)
Similar to armoring a spillway with RCC, another technique is to use an
articulated concrete block (ACB) mat system. The ACB requires a geotextile fabric
under layment, and typically is covered with a grass and topsoil over layment. The
middle section includes concrete blocks that are geometrically shaped in order to
interlock in a set pattern (See Figure 2.4). The entire matrix is more stable then a typical
grass lined spillway, and the construction costs can be considerably less (NRCS, 2005).
Chapter 2: Related Works 16
Figure 2.4: Articulated Blocks in Place on VA Tech Campus
Chapter 3: Hydrologic Model for Upper South River 17 and Application to Dam Removal Question
Chapter 3: Hydrologic Model for Upper South River and Application to Dam Removal Question
To begin a dam rehabilitation process, one must first evaluate the existing
conditions. The process begins with the physical characteristics of the dam itself, such
as the intake and outlet structures, the storage capacity behind the dam, and the
structural integrity of the dam. They all must be assessed and quantified. The
characteristics of the watersheds upstream and downstream of the hydraulic structure
must be determined. The existing intermittent creeks, streams, and main channel
reaches must be characterized by channel geometry, slope, roughness, etc. The
necessary information requirements are significant, but there is a valid end state result
from obtaining the data. That end state is a working model representing the existing
conditions within the study area of interest. Establishing the current conditions is critical
in order to perform analysis on proposed future work to fix problems occurring with a
dam in question.
There are numerous hydrologic and hydraulic simulation programs existing in
today�s industry. Many generally accepted models are products of Federal Government
Agencies, such as the U.S. Army Corps of Engineers (USACE), Bureau of Reclamation
(BUREC), and National Resources Conservation Service (NRCS), all of whom manage
numerous existing dams across the United States. The model to be discussed in this
chapter is the USACE�s Hydrologic Engineering Center � Hydrologic Modeling System
(HEC-HMS). A widely accepted simulation program, HEC-HMS is capable of
transforming a prescribed precipitation event into surface water run-off hydrographs, and
routing the corresponding river flood hydrographs through the entire watershed.
Additionally, the model simulates various hydraulic structures present within the
watershed, as well as the situation where the structures are removed.
Chapter 3: Hydrologic Model for Upper South River 18 and Application to Dam Removal Question
3.1 South River Watershed
As previously stated, the South River Watershed near Waynesboro, VA is used
as a case study. There was a dual purpose for the selection of this watershed. The first
purpose fulfilled a request of the co-sponsors, the Headwaters Soil & Water
Conservation District (HSWCD) and the city of Waynesboro, that we analyze the 12
existing dams in the watershed. Their specific request was to evaluate the downstream
hydrologic impacts of the 12 dams on the city of Waynesboro during flooding events.
The second purpose narrows the area of interest to the watersheds specifically involved
with 3 of the dams currently being considered for rehabilitation. These purposes are
linked to a common interest. The demonstrated impacts of the city of Waynesboro could
lend critical public support for the proposed rehabilitation of the 3 dams.
The headwater portion of the South River (Upper South River) is comprised of a
watershed drainage area of about 126 square miles. The watershed is further divided
into 69 sub-basins raging from 0.1 to 4.6 square miles (See Figure 3.1). The 12
Agricultural Flood Protection Dams regulate only 12 sub-basins out of the 69 total, or
27% of the 126 square mile drainage area. The 12 dams were originally planned,
funded, and constructed by the former Soil Conservation Service (SCS), now the
National Resources Conservation Service (NRCS), under the 1954 Watershed
Protection and Flood Prevention Act (PL 83-566, 1954). They were all completed in the
1950s to early 1960s, and were built to a 50 year design life that is currently exceeded
on several of the dams. Under PL 83-556, the SCS was empowered to build dams to
provide flood protection for agricultural lands, and then turn over the dams to local
entities to maintain. Hence, the Headwaters Soil & Water Conservation District, along
with the City of Waynesboro, currently is responsible for most of these 12 dams. As
would be expected many of the aging dams require significant upgrades to meet current
Virginia Dam Safety Regulation standards. Also under the 2000 Watershed
Cha
pter
3: H
ydro
logi
c M
odel
for U
pper
Sou
th R
iver
19
an
d Ap
plic
atio
n to
Dam
Rem
oval
Que
stio
n
Chapter 3: Hydrologic Model for Upper South River 20 and Application to Dam Removal Question
Rehabilitation Bill (PL 106-472, 2000), the 12 dams qualify for partial Federal Funding to
rehabilitate the dams, but still require 35% funding by the local entity. Therefore,
knowing the impact of the 12 dams on the greater city of Waynesboro is important to
gain the required 35% local funding (Peterson, 2004).
3.2 Required Data for Model Creation
3.2.1 Watershed Parameters
The model parameter data pertaining to current conditions was obtained from
several different sources. A logical starting point is defining the watershed parameters
for each of the 69 sub-basins comprised within the entire South River Watershed. The
state of Virginia NRCS Conservation Engineering Office provided the data for the 69
sub-basins, based upon hydrologic analysis performed in 1991 (NRCS, 2005). Table
3.1 is an excerpt for three sub-areas taken from that report:
Table 3.1: South River Watershed Data
Sub Area
Drainage Area
SCS Curve #
Initial Infiltr. T conc.
Reach Length
Elev Drop
Reach
Reach Channel
Slope (#) (Sq Mi) (#) (in) (hr) (ft) (ft) (ft/ft) 1 3.41 66 1.030 1.51 - - - 2 2.72 66 1.030 1.41 - - - 3 0.42 66 1.030 0.55 4050 48 0.012
The previous NRCS work provided drainage area, the Soil Conservation Service (SCS)
Curve Number, time of concentration, and, if applicable, the length of main channel
reach within each of the 69 sub-basins.
The drop in elevation of the main channel was obtained from two resources. The
primary resource was the major flood study of record for the South River Watershed that
was completed in 1974 (SCS, 1974). This study�s purpose was to map the flood
inundation zones within the watershed as a prelude to establishment of flood insurance
Chapter 3: Hydrologic Model for Upper South River 21 and Application to Dam Removal Question
rate maps. Detailed elevations of the channel bed are presented in this study. If a reach
was not on the main channel included in the study, channel depths were extrapolated
from a topographic map. Explanation of each of the above parameters, including how to
compute the depth of initial infiltration, will be discussed in the Model Creation section.
3.2.2 Channel Properties
There are 42 reaches within the 69 sub-areas that comprise the watershed.
Some of the reaches constitute main channels of the South River and Back Creek, while
others are secondary connecting streams. The Manning�s �n� Values, representing the
characteristic roughness of the channel beds, were also obtained from the 1974 flood
study. These values are compiled by cross section on the main channels of the South
River and Back Creek. Table 3.2 is an excerpt from Table A.2 in Appendix A. Tables
A.2 and A.3 compiled all the given �n� values for which averages were obtained.
Table 3.2: South River Manning's n Values
Section Description
Main Channel
n
Left Bank
n
Right Bank
n 419 Right after Canada Run SA38 0.069 0.053 0.053 420 Before RR in SA 38 0.069 0.078 0.060
Another important channel property contained in the flood study was an example
cross section for the typical reach within the South River watershed. The basic cross
section became the template for each of the reaches within the watershed (See Figure
3.2). The cross section was adjusted two ways to better replicate the geographic
location of the reaches. The first adjustment was for the actual channel bed elevation at
the beginning of the reach from Table A.1. The second adjustment was to the width of
the main channel. The width of the main channel was changed depending on where it
fell within the watershed. For example, a reach closer to the headwaters would not be
as wide as a reach near the bottom of the watershed (See Table A.4 for section data.)
Chapter 3: Hydrologic Model for Upper South River 22 and Application to Dam Removal Question
Reach #9 Cross Section
14621464146614681470147214741476
0 100 200 300
Distance (feet)
Elev
atio
n (fe
et)
Series1
Figure 3.2: Cross Section Template
3.2.3 Reservoir and Dam Properties
The 12 agricultural flood control dams must be represented in the hydrology
models. A basic understanding of the structures themselves is required in order to
explain the needed parameters to input into the simulation model. The first part of this
section details the basic components of the dams within the South River Watershed.
All of the 12 dams are earthen, ranging from heights of 25 to 91 feet (See Figure
3.3). The surface area of the normal pool for the reservoirs varies from 5 to 11 acres.
During flood events the storage capacity of the reservoirs increases to a range of 223 to
1052 acre-feet. Since all of the dams were constructed by the SCS over a 10 year
period, the dams are all similar in design. Each includes a sedimentation pool upstream
of the dam, an intake structure, a principal spillway outlet structure, and an at least one
auxiliary spillway.
Chapter 3: Hydrologic Model for Upper South River 23 and Application to Dam Removal Question
Figure 3.3: Robinson Hollow Dam, Upstream Side Reservoir
All of the dams include a concrete single stage inlet tower (See Figure 3.4).
Water enters the intake tower from side inlets controlling the normal pool level for the
reservoirs. The principal spillway on all of the dams is a 24 inch diameter pipe, ranging
from 175 to 525 feet in length. The pipes run through the center of the dam to an outlet
pool. The outlet structure in most of the dams is simply the principal spillway pipe
releasing into a rip-rap lined receiving pool (See Figure 3.5).
Figure 3.4: Canada Run Inlet Structure Figure 3.5: Happy Hollow Outlet Structure
The auxiliary spillways, also called emergency spillways, are all grass lined
channel by-passes on either one side or both sides of the dam itself. The primary
purpose of these spillways is to safely pass extreme flood waves in order to protect the
Chapter 3: Hydrologic Model for Upper South River 24 and Application to Dam Removal Question
dam from overtopping which could cause catastrophic structural failure. Figure 3.6
shows the design plan view for the Robinson Hollow Dam from the original design
documents. The auxiliary spillway is highlighted with hatches beside the dam.
Figure 3.6: Robinson Hollow Original Plan View
Some of the spillways are quite large as the design required a smaller depth within
the channel, but the volume of water to pass was large. To compensate for a depth
restriction, the spillway width is increased. This is shown in Figure 3.7:
Figure 3.7: Lofton Lake Auxiliary Spillway
Chapter 3: Hydrologic Model for Upper South River 25 and Application to Dam Removal Question
3.2.4 Reservoir Rating Table
The key to understanding how water flows through the reservoirs begins with
quantifying the storage capacity of the reservoir. This quantification involves knowing
the geometry of the reservoir pond, and then calculating the volume of impounded water
to obtain the total capacity. Unfortunately, the volume never remains constant as the
height of water in the reservoir is always changing during a storm event. To overcome
this, a relationship is developed between the reservoir surface elevation (usually in feet
of water behind the dam) and the storage capacity (usually in acre feet) (Mays, 2001).
The second part of understanding the reservoir is the amount of discharge that
occurs from both the principal and the auxiliary spillways. The flow rate through the
spillways is a function of the geometry of the spillway, and the head difference between
headwater and tail water pools. The total head in this case is usually the elevation head
of the headwater pool, since there is rarely a tail water pool below the dam. Another
relationship can then be generated relating the reservoir surface height to the flow rate
out the spillways. Not every dam has a continuous flow rate out of the principal spillway.
In some cases the reservoirs must reach an initial height before the spillway begins to
discharge. The discharge relationship accounts for such nuances, and incorporates
different discharge rates at different reservoir elevations (Mays, 2001).
The storage capacity and discharge relationships are combined into what is
called a rating table. The common factor between the two relationships is the water
surface height of the reservoir. Rating tables can be generated if the engineering data
for the dam and the reservoir is provided. For the South River case study, the NRCS
provided the rating tables for all 12 of the dams (NRCS, 2005). The original data tables
are compiled in Table A.5.
Chapter 3: Hydrologic Model for Upper South River 26 and Application to Dam Removal Question
3.2.5 Rainfall Data from IFLOWS Gages
In order to calibrate the model, rainfall data from past storm events is required.
Fortunately, there are six Integrated Flood Observing and Warning System (IFLOWS)
rain gages located within the watershed. The IFLOWS program is managed by the
National Weather Service and is meant to assist local officials in predicting floods. Five
of the IFLOWS rainfall gages are co-located on reservoirs, and the other is located near
the Canada Run Dam. The gages provide real time rainfall data at these locations, and
for the five co-located ones, the water level height in the reservoir is also monitored.
Figure 3.8 is a picture of the IFLOWS gage at the Stoney Creek Dam:
Figure 3.8: IFLOWS Gage at Stoney Creek Dam
The real time IFLOWS web-site is found at the following address:
http://www.afws.net/ . Following the map links to Virginia, and then Augusta County, the
past 24 hour data is viewable. Additionally, the historical data beginning in 2001 is
maintained in a rainfall archive. Therefore for recent rainfall events, hourly rainfall data
can be compiled into rainfall hyetographs. For model calibration, three recent storms
were used: 1. Hurricane Isabel, 18 September 2003. 2. Hurricane Jeanne, 28
Chapter 3: Hydrologic Model for Upper South River 27 and Application to Dam Removal Question
September 2004. 3. Hurricane Frances, 08 September 2004. One additional storm that
occurred on November 29, 2005 was also used to confirm the model calibration. The
compiled rainfall data is shown in Table A.6 in Appendix A.
3.2.6 Surveyed High Water Marks from Recent Storms
The HSWCD provided additional key data for the above recent storms in the form
of surveyed high water marks at the reservoirs. Due to the severity of these storms,
HSWCD personnel recorded the elevations left by the debris lines in the reservoir and,
when applicable, the auxiliary spillway. The data for Hurricane Isabel proved to be most
complete, and also corresponded to the largest storm out of the four selected. The
Isabel data became important for model calibration. The Hurricane Isabel high water
mark data is included in Table A.7 of Appendix A.
3.2.7 Lyndhurst Gaging Station Stream Flows
The final link for model calibration is stream flow data for the South River.
Fortunately, like the IFLOWS rainfall gages, the watershed includes a U.S. Geological
Survey (USGS) stream gage station within the city limits of Waynesboro, VA. The
USGS tracking number for the gage is #0126000, and is called �South River Near
Waynesboro, VA.� The South River passes under the Lyndhurst Street bridge right near
the location of the gage. Consequently, the gage is also referred to as the Lyndhurst
Gaging Station. The real time data for the gage is available at the USGS web-site:
http://waterdata.usgs.gov/va/nwis/uv/?site_no=01626000&PARAmeter_cd=00065,00060,62620,00062.
The historical data is archived for the Lyndhurst Gaging Station at the Richmond
USGS office. The flow data corresponding to the selected IFLOWS storms was
obtained. The data was a time series hydrograph, in which the flow was given in cubic
feet per second. The critical information to compare was the magnitude of the peak of
the hydrograph, and the timing of the peak. The peak flow rate and timing will assist
Chapter 3: Hydrologic Model for Upper South River 28 and Application to Dam Removal Question
with model calibration. Refer to Table 3.3 for the summary data, and Figure 3.9 for the
Hurricane Isabel Hydrograph.
Figure 3.9: Hurricane Isabel Hydrograph
Table 3.3: Lyndhurst GS Data
Storm Peak Q
(cfs) Time Isabel 13,800 19 0400 SEP 03
Jeanne 6460 28 1530 SEP 04 Frances 1380 08 2145 SEP 04
29-Nov-05 4720 29 1500 NOV 05
Chapter 3: Hydrologic Model for Upper South River 29 and Application to Dam Removal Question
3.3 Hydrologic Model Creation
The next step following the gathering of required information was to input into the
HEC-HMS simulation program to construct the watershed model. Every HEC-HMS
model requires three separate components in order to execute a simulation: the Basin
Model, the Meteorological Model, and the Control (See Figure 3.10).
Figure 3.10: HEC-HMS Primary Menu Screen
The Control simply sets a reference date, a time period for the simulation, and the
computational time step. To be consistent with time sensitive data like the rainfall and
stream flow data, the control time periods were adjusted to reflect the true time of the
rainfall event. When design storms were used, the present time period was used for the
Control. (Scharffenburg and Felming, 2005)
The Basin Model represents the physical watershed to be modeled, and requires
the most robust data. The Meteorological Model replicates the storm event, and how the
rainfall is distributed across the watershed with respect to time. Both the Basin Model
and Meteorological Models require further explanation in the next sections.
Chapter 3: Hydrologic Model for Upper South River 30 and Application to Dam Removal Question
3.3.1 Basin Model Creation
The Basin Model for the entire watershed including the reservoirs was first
generated. To begin, a new Basin Model was created within HEC-HMS. HEC-HMS
automatically brings up a working schematic pallet for editing (Figure 3.11). For this
model, only four component icons were used: the sub-basins, reaches, junctions, and
reservoirs. The sub-basins correspond to the 69 sub-areas within the entire watershed.
The reaches are the main channel streams or rivers passing through a given sub-basin.
The junctions represent starting and ending points for the reaches. As seen in Figure
3.11, multiple reaches can enter a junction or node. Junctions do not require data, and
are merely a merging point within the simulation. Once all of the icons are drawn onto
the Basin Model Screen, necessary data must be entered for the icons to correctly
replicate the watershed system.
Figure 3.11: HEC-HMS Basin Model Editing Screen
3.3.1.1 Sub-basin Icon Data
The sub-basin data from Table A.1 must be entered for each of the sub-basins.
The first part of the sub-basin data involves the amount of water that is absorbed into the
soil. In this case, the SCS Rainfall-Runoff Relation was used, based upon the known
Chapter 3: Hydrologic Model for Upper South River 31 and Application to Dam Removal Question
Curve Numbers for the sub-basins. HEC-HMS requires the CN and the Initial
Abstraction (Ia) amount. Ia is found by the following equation (Mays, 2001):
Ia = 0.2 x S, where S = 1000 / CN � 10.
With the amount of run-off established from the CN, the run-off must be
transformed to a hydrograph. For this part, the SCS synthetic unit hydrograph method
was used. Synthetic hydrographs are constructed within the simulation program based
upon the Time of Concentration (Tc) parameter. The Tc represents the longest time of
travel from the ridge to outlet within the sub-basin taken by a single drop. One final part
that must be accounted for is the base flow rate within the sub-basins. Since, this is
typically only a small portion of the storm hydrographs a modest assumption of 0.5 cubic
feet per second was used for the entire watershed (Mays, 2001).
3.3.1.2 Reach Icon Data
The reaches, representing streams and river channels, are important in
transporting the sub-basin run-off down stream. The reaches replicate what the channels
do in the real world. All of the sub-basins in the model are assumed to drain to a single
point, represented by the junctions. With the exception of the 69th sub-basin, all of the
sub-basins are then routed along a reach between two junctions. The 69th sub-basin
links to the final junction of the model, but would be further routed to the next sub-basin
downstream. The HEC-HMS simulation first transforms the surface run-off to a
hydrograph at the assigned junction, and this hydrograph must be routed through the
reaches to final junction.
HEC-HMS is capable of several different methods of routing a hydrograph within
a reach. For this simulation, we chose to use the Muskingum-Cunge 8 Point method.
The Muskingum-Cunge method is a variation of the kinematic wave method which
incorporates the Muskingum method of routing (Mays, 2001). The method relies upon
derived Muskingum coefficients for each channel in order to perform the routing. The 8
Chapter 3: Hydrologic Model for Upper South River 32 and Application to Dam Removal Question
Point part of the method, extrapolates the Muskingum coefficients from the known
channel cross sections in Table A.4 (See Figure 3.12).
Figure 3.12: Reach Editor Screen, Basin Model
The reach length from Table A.1 must be included for the routing. The energy
slope was assumed to be equivalent to the slope of the channel bed, also included in
Table A.1. The final information is the channel roughness characteristic represented by
average Manning�s �n� values from Tables A.2 and A.3.
3.3.1.3 Reservoir Icon Data
The key information for the reservoirs already mentioned before is the rating
table. The rating table becomes the basis for the routing of a hydrograph into the
reservoir and through the outlet structures. The HEC-HMS program performs a level
pool routing of the inflow hydrograph based upon the inputted rating table. The only
other requirement to begin the process is to establish the Normal Pool elevation of the
Chapter 3: Hydrologic Model for Upper South River 33 and Application to Dam Removal Question
reservoir surface water. This is the assumed starting point for the routing (See Figure
3.13).
Figure 3.13: Reservoir Editor Screen, Basin Model
3.3.2 Weather Model Creation
The last component needed to complete a HEC-HMS simulation is the Weather
Model. Weather Models represent the precipitation event within the model. There exists
within HEC-HMS eight different methods to create a precipitation event (Scharffenburg
and Felming, 2005). For this case study, only two methods were used: 1. User
Hyetographs (actual rainfall gage data) 2. NRCS Hypothetical Storm.
3.3.2.1 User Hyetographs
For the User Hyetographs approach, the rainfall data gathered from the NOAA
IFLOWS gages was used. One rainfall gage was created for the six gages within the
watershed for each storm event. The 15 minute increment rainfall data was manually
Chapter 3: Hydrologic Model for Upper South River 34 and Application to Dam Removal Question
inputted into HEC-HMS using the Precipitation Gage Manager tool. The rainfall data
was checked after the first simulation runs to confirm accuracy of the data. The
accuracy can be checked by comparing the total rainfall amount in the simulation to the
known amount in the data. Any discrepancies were adjusted when encountered.
The creation of the rainfall gages doesn�t constitute a complete Weather Model.
The second step is to create one Weather Model for the separate storm events. In
choosing the User Hyetograph method, a list of the sub-basins within the watershed is
brought up in the editor screen (See Figure 3.14). Each of the sub-basins must be
associated with a rainfall gage in order to complete a Weather Model. There are many
established techniques for rainfall distribution, such as Mean Aerial Precipitation or
Thiessen Polygons. For this case study the rainfall amounts were spatially similar (one
exception will be discussed in the Model Calibration section). Therefore, gages were
assigned to sub-basins based upon geographic proximity. Figure 3.15 shows how the
gages were assigned to the sub-basins within the storm Weather Models.
Figure 3.14: Meteorological Model Editor, HEC-HMS
Cha
pter
3: H
ydro
logi
c M
odel
for U
pper
Sou
th R
iver
35
an
d Ap
plic
atio
n to
Dam
Rem
oval
Que
stio
n
Chapter 3: Hydrologic Model for Upper South River 36 and Application to Dam Removal Question
3.3.2.2 SCS Hypothetical Storm
The second approach used for the Weather Model is the NRCS Hypothetical
Storm method. This method uses the synthetic method for generating a synthetic storm
based upon a given amount of precipitation. For the South River Watershed, the Type II
hyetograph is appropriate. The rainfall depths were obtained from the National Weather
Services (NWS) NOAA Atlas 14. The NOAA Atlas 14 compiles the precipitation
frequency data for the United States. The rainfall depths for a given return period were
determined based upon the Stuart�s Draft location, located in the center of the
watershed. The rainfall depths can be downloaded from the NWS web-site:
http://hdsc.nws.noaa.gov/hdsc/pfds/index.html. Five weather models were created for the 2,
10, 50, 100, and the 500 year return periods.
3.4 Model Calibration
The finished HEC-HMS model is represented in the schematic shown in Figure
3.16. With the model complete for the case study, simulations could now be run. The
largest of the storms, Hurricane Isabel, was the first Weather Model used. As previously
mentioned, there was a problem with the Hurricane Isabel gage data. During Isabel, the
Upper Sherando IFLOWS gage registered 20 inches of rain, an extreme amount. As
shown in Table 3.4, the other gages only recorded from 6.5 to 9 inches of precipitation
during the same event.
Table 3.4: Hurricane Isabel Rainfall
IFLOWS Gages ID # Total (in)
Toms Branch 1200 6.92 Sherando 1201 8.44 Robinson Hollow 1202 7.08 Stoney Creek 1207 6.59 Upper Sherando 1240 20.12 Mills Creek 1248 9.04 Pavg 7.614
Cha
pter
3: H
ydro
logi
c M
odel
for U
pper
Sou
th R
iver
37
an
d Ap
plic
atio
n to
Dam
Rem
oval
Que
stio
n
Chapter 3: Hydrologic Model for Upper South River 38 and Application to Dam Removal Question
Applying the Upper Sherando gage data to the Upper Sherando Reservoir sub-basin
yielded a flood wave peak that was over five feet higher then what was actually
observed (compared to surveyed debris lines). Additionally, when applying the same
rainfall over surrounding sub-basins, the total flow observed at the Lyndhurst Gaging
Station (Junction 42 in the model) was over 50,000 cubic feet per second (cfs). This
drastically exceeded the recorded observed peak flow by the USGS gage of 13,800 cfs.
To alleviate this issue of extreme isolated rainfall, the Upper Sherando Gage data
was ignored. The Mills Creek gage data was applied instead as shown in Figure 3.15.
The appropriate changes were made in HEC-HMS, and the simulation model was rerun
for Hurricane Isabel. The results of this run were lower, with a total flow of 28,840 cfs.
This is more reasonable, but the target flow of 13,800 was again greatly exceeded. At
this point, Hurricanes Jeanne and Frances were run to confirm any similar observations.
As shown in Table 3.5, all of the storm events were coming in higher then the observed
flows at the Lyndhurst Gaging Station, and the timing of the peaks were slightly off.
Consequently, other changes to the model were needed in order to calibrate the model.
Table 3.5: Initial Simulation Runs
Storm Actual Observed
(Target) Simulation #1 Original Data;
(No Changes)
Peak Q
(cfs) Time Peak Q
(cfs) Time %Difference Isabel 13,800 19 0400 SEP 03 28840 19 0230 SEP 03 2.09
Jeanne 6460 28 1530 SEP 04 11185 28 1530 SEP 04 1.73 Frances 1380 08 2145 SEP 04 7925 08 2045 SEP 04 5.74
Based upon the obtained data, the Curve Number (CN) was the other key model
parameter that when adjusted could lower the flow rates enough. The individual curve
numbers for the South River Watershed average to a value of 65. The entire 69 sub-
basins� CNs were lowered from the average 65 to 55, and then to 45. In comparing the
simulation results to the target flows in Table 3.5, the best matches were for the CN
average of 45, as shown in Table 3.6:
Chapter 3: Hydrologic Model for Upper South River 39 and Application to Dam Removal Question
Table 3.6: Simulation Changes
Storm Simulation #2
(CN = 50; SAs above Dams Original Data) Simulation #3
(CN = 45; SAs above Dams Original Data)
Peak Q
(cfs) Time %Difference Peak Q
(cfs) Time %Difference Isabel 17185 19 0400 SEP 03 1.25 13571 19 0415 SEP 03 0.98
Jeanne 3662.7 28 1530 SEP 04 0.57 2375 28 1530 SEP 04 0.37 Frances 2994 08 2045 SEP 04 2.17 2057 08 2045 SEP 04 1.49
A NRCS Curve Number of 45 is extremely low and is not reflective of the actual
conditions. To confirm this, the land use map, in Figure 3.17, was compared with the
corresponding CN map, Figure 3.18. In Figure 3.17, the darker shaded areas represent
more urbanized terrain closer to the city of Waynesboro. The lighter shades
corresponded to the areas located within the George Washington National Forest. In
checking the NRCS-provided curve numbers in Figure 3.18, it was found that the higher
curve numbers (shown in darker shades) matched the urbanized areas of the land use
map. Therefore, without a more detailed analysis, the provided curve numbers were
assumed to be fairly representative of the real conditions.
The calibration issue remained a problem, as the model output was still not
matching the observed storms. Another potential explanation for the discrepancies is
the topic of antecedent moisture. The concept when applied verifies what the moisture
conditions were prior to the storm event. The storm conditions are segregated into three
categories: normal, extremely dry, or extremely saturated. The NRCS Curve Number
can be changed significantly based upon the antecedent moisture conditions. For the
arid situation, if there was less then 1.4 inches of rain observed 5 days prior to the storm
event during the growing season, then a CN of 65 could be lowered to 45 (McCuen,
2005). In checking the storms, Hurricanes Isabel and Jeanne met this criterion. The
observed antecedent moisture for the storms was less them 1.4 inches of rain, thus
justifying the lowering of the CN from 65 to 45.
Cha
pter
3: H
ydro
logi
c M
odel
for U
pper
Sou
th R
iver
40
an
d Ap
plic
atio
n to
Dam
Rem
oval
Que
stio
n
Cha
pter
3: H
ydro
logi
c M
odel
for U
pper
Sou
th R
iver
41
an
d Ap
plic
atio
n to
Dam
Rem
oval
Que
stio
n
Chapter 3: Hydrologic Model for Upper South River 42 and Application to Dam Removal Question
The determination of the antecedent moisture conditions left some doubt to
which average SCS CN should be used for the model. To confirm the model calibration
a different way, design storms were used. The simulated discharges Q2, Q10, Q25,
Q100, and Q500 at the model Lyndhurst gaging station were obtained for the average
CNs 55, 60, and 65. The Q2, Q10, Q25, Q100, Q500 were also computed by statistical
flood frequency analysis, based on Log-Pearson Type III distribution and the USGS
historical records for the gaging station. In comparing the simulated with the observed
data, it was found that the simulation results for the average CN of 65 was the best fit
(See Table 3.7).
A final check of the model used an average CN of 65. Rainfall data from a recent
intense storm on November 29, 2005 was used. The model produced a peak flow of
5869 cfs at the Lyndhurst gaging station. Since the storm took place in November, the
dormant season, the antecedent moisture criterion is more stringent at less then 0.5 inch
to meet arid conditions. None of the rainfall gage data met this criterion, so the average
CN of 65 was assumed to be valid. An actual observation by a USGS observer on the
afternoon of the 29th of November, converts to a discharge value of 4720 cfs. The real
time data for the gage continued upwards to a peak of 6600 cfs observed on the USGS
web-site (Figure 3.18). However, this peak was readjusted later by the USGS, to the
lower value of 4720 cfs. In comparison to either value, the model produced a
Table 3.7: Calibration Results Return CN = 55 CN = 60 CN = 65 Historical Period Q (cfs) Q (cfs) Q (cfs) Q (cfs)
Q2 1057 1834 2651 2770 Q10 4182 6063 8077 9568 Q50 11111 14789 18879 21902 Q100 15703 20600 25653 29777 Q500 31942 39145 46847 56810
Chapter 3: Hydrologic Model for Upper South River 43 and Application to Dam Removal Question
reasonable intermediate estimate of 5869 cfs. Thus the model was considered to be
calibrated sufficiently for purposes of this study.
Figure 3.19: Real Time Data from USGS on 29 NOV 05 Storm
3.5 Simulating the Results of Dam Removal
Reiterating the first purpose for creating the model, it is intended to demonstrate
the impacts of the 12 agricultural dams on the watershed. With the difficult part of
validating the simulation model finished, replicating the pre-structure conditions in HEC-
HMS is much simpler. To establish the pre-structure conditions, the reservoir icons in
the HEC-HMS are removed from the simulation. In a sense, they are taken �off-line�,
and do not impact the hydrologic calculations in a simulation run. The HEC-HMS model
now represents the watershed as if the dams were not present. The difference between
Chapter 3: Hydrologic Model for Upper South River 44 and Application to Dam Removal Question
the pre-structure and post-structure discharge rates quantifies the impacts the dams
have on the watershed.
The design storms used to calibrate the model at an average CN value of 65
were used again on the �dams not present� model. Discharge rates were recorded from
the simulation runs for the Q2, Q10, Q25, Q100, and Q500 storm events. In order to
fully assess the impacts of the dams it was necessary to first examine the local area
impacts in the immediate vicinity of the dams. Then flow rates at key junctions along the
downstream reaches were selected in order to allow for a tracking of the diminishing
impacts. Finally, the combined impacts of all 12 agricultural dams were determined at
the Lyndhurst gaging station. All of the simulation output data for average CNs 55, 60,
and 65, for both pre- and post-structure conditions, is presented in Appendix B.
To examine the impacts of the dams the Q2 and Q100 storm events are used to
show the impacts of storms that occur frequently (on average every 2 years), and storms
that occur rarely (on average every 100 years). Figures 3.20 and 3.21 show a side by
side comparison at each of the dams for the Q2 and Q100 storm events. The
comparisons show the dams significantly reduce the flow rates below what would occur
if the dams were not present. Also, the reduction becomes more significant in the
extreme events as the dams reach their full design storage capacity.
Q2 Comparison; CN = 65
050
100150200250300350400
Dams
Q (c
fs) Q2 w Dams
Q2 w/o Dams% Reduction
83% 81%81%
78%
71%87%
58%79%65%
85%82%
74%
Poor C
reek
Lofto
nLak
eSt
oney
Cr.W
ilda La
keCan
ada R
unW
ayne
s Nurs
Up She
rand
oTo
ms Br.
Mills C
r.Hap
py H
ollow
Rob. H
ollow
Inch
Br.
Q2 Comparison; CN = 65
050
100150200250300350400
Dams
Q (c
fs) Q2 w Dams
Q2 w/o Dams% Reduction
83% 81%81%
78%
71%87%
58%79%65%
85%82%
74%
Poor C
reek
Lofto
nLak
eSt
oney
Cr.W
ilda La
keCan
ada R
unW
ayne
s Nurs
Up She
rand
oTo
ms Br.
Mills C
r.Hap
py H
ollow
Rob. H
ollow
Inch
Br.
Figure 3.20: Q2 Side by Side Comparison at Dam Sites
Chapter 3: Hydrologic Model for Upper South River 45 and Application to Dam Removal Question
Q100 Comparison; CN = 65
0500
100015002000250030003500
Dams
Q (c
fs) Q100 w Dams
Q100 w/o Dams
% Reduction
97%97%
97%
95%82%
95%92%
98%
97%97%95%
96%Po
or C
reek
Lofto
nLak
eSt
oney
Cr.W
ilda La
keCan
ada R
unW
ayne
s Nurs
Up She
rand
oTo
ms Br.
Mills C
r.Hap
py H
ollow
Rob. H
ollow
Inch B
r.
Q100 Comparison; CN = 65
0500
100015002000250030003500
Dams
Q (c
fs) Q100 w Dams
Q100 w/o Dams
% Reduction
97%97%
97%
95%82%
95%92%
98%
97%97%95%
96%Po
or C
reek
Lofto
nLak
eSt
oney
Cr.W
ilda La
keCan
ada R
unW
ayne
s Nurs
Up She
rand
oTo
ms Br.
Mills C
r.Hap
py H
ollow
Rob. H
ollow
Inch B
r.
Figure 3.21: Q100 Side by Side Comparison at Dam Sites
In tracking the flow rates moving down stream from the dams, the effect of the
dams diminishes. The reduction percentage decreases as discharge flow moves toward
the Lyndhurst gaging station at the bottom of the watershed. This is directly related to
the increasing flows from the unregulated sub-basins (no dams in the sub-basin) that
merge with the outlet streams from the dams. As shown in Figure 3.1 and stated
previously, only 27% of the entire watershed is regulated by the 12 dams. Figure 3.22
shows how the discharge reduction decreases while moving down stream. The
reductions are represented by circles that are graduated by size, thus a smaller circle
represents smaller reductions.
The final focus is at the Lyndhurst gaging station, which is the officially recognized
site for the city of Waynesboro flood warnings system. Flood stages in Figure 3.23 were
obtained by applying the USGS rating at the Lyndhurst gaging station to the modeled
Q2, Q10, Q50, Q100, and Q500, with the average CN of 65. The highest observed
floods in 1969 and 1985, produced a gage height of 15.3 feet in 1969 and 1985. Based
upon Figure 3.23, these two storms would occur on average about every 40 years.
Chapter 3: Hydrologic Model for Upper South River 46 and Application to Dam Removal Question
Gage Height Comparison at Lyndhurst Gaging Station; CN = 65
0
5
10
15
20
25
30
35
40
45
50
2 10 50 100
500
Flooding Return Period
Gag
e H
eigh
t (ft)
Gage Height w Dams
Gage Height w/o Dams
Jeanne, SEP 04
Frances, SEP 04
29 NOV 05
Flood Stage 9.5'
Isabel, SEP 03
Major Flood 13'05 NOV 85
Figure 3.23: Gage Height Comparison
Chapter 3: Hydrologic Model for Upper South River 47 and Application to Dam Removal Question
The recent hurricane storm events highlighted in Figure 3.23 (Isabel, Jeanne,
Frances) are intended to show the impacts of the existing dams during actual storms.
Hurricane Isabel produced an observed high water mark of 13.6 feet at the Lyndhurst
Gaging Station, corresponding to a return period of about 30 years. If the dams were not
present this high water mark would have been about 16.5 feet, corresponding to a 50-
year flood with the dams in place, as indicated in Figure 3.23. In other words, the same
flood that used to occur on average every 30 years without the dams now can be
expected to occur on average just once every 50 years.
We can look at the 100-year flood in a similar way. From Figure 3.23, one sees
that the simulated 100 year flood peak �with dams� occurs at a gage height of
approximately 22 feet. Transferring this gage height horizontally to the upper �without
dams� curve, a gage height of 22 feet would occur on average every 50 years. Thus,
the effect of the dams is to reduce what used to be the 100 year flood stage (before
dams) back to the 50 year flood stage.
3.6 Summary
After the first purpose of creating the HEC-HMS model was accomplished, the
impacts of the 12 dams were demonstrated. The 12 dams in the upper South River
watershed effectively reduce flood events in areas located immediately below the dam
structures. The results coincides with the original NRCS/SCS purpose of providing flood
protection for agricultural lands. The flood reduction benefit of the 12 dams diminishes
as we move downstream approaching Waynesboro. However, the dams do provide a
significant flood reduction at Lyndhurst gaging station that undoubtedly extends well into
the city limits. This flood reduction is above and beyond the primary purpose of the
dams as planned for by the SCS in the 1950s.
Chapter 3: Hydrologic Model for Upper South River 48 and Application to Dam Removal Question
The completion of the simulation model also fulfills the second purpose of
performing smaller scaled analysis on three out of the 12 dams: Toms Branch, Inch
Branch, and Robinson Hollow Dams. If only these three dams were to be considered,
the HEC-HMS model could have been significantly scaled back to replicate only the sub-
basins impacted by these dams. The purpose of the model would remain unchanged,
as the impacts of the dams would still need to be shown. However, as will be shown in
the next chapter, any proposed structural changes to the dams must be incorporated
into the simulation model of the entire watershed to show the hydrologic impacts of
making the dam improvements.
Chapter 4: Traditional Economic Analysis of Dam Rehabilitation 49 by Flood Damage Curve Integration
Chapter 4: Traditional Economic Analysis of Dam Rehabilitation by Flood Damage Curve Integration
The significant problems with the current inventory of dams in the United States
were highlighted in Chapter 1. Consequently due to the large number of remediation
projects needed, it can be assumed that projects are being considered for remediation
because of their failure to meet the appropriate dam safety regulation. Because funding
is always a constraint, remediation courses of action must be analyzed economically.
Unlike proposed new water projects, the course of action to �do nothing� is really not an
option. The existing hydraulic structure is known to be out of compliance with
established safety regulations, and it is probable that a controlled breach would have to
be completed by the owner. As a result, the �do nothing� option will have associated
construction costs in order to complete the breach which must be considered during the
economic analysis.
This chapter will begin with a general description of an economic framework used
to assess water projects. A step-by-step description of an economic process will follow
the general description intending to be used as reference tool for future work. The
NRCS�s proposed remediation projects for the Toms Branch, Inch Branch, and Robinson
Hollow Dams requires a discussion of the Federal Government�s water project planning
document Principles & Guidelines (P&G). This will lead to an explanation of the NRCS�s
technique for economic analysis. The chapter will conclude with a summary of the
economic analysis process.
4.1 General Approach to Economic Analysis
Water projects, especially those that are publicly funded, require economic
analysis of the benefits and costs. Since the projects already exist, economic analysis
Chapter 4: Traditional Economic Analysis of Dam Rehabilitation 50 by Flood Damage Curve Integration
may have been done previously. A conventional approach to analyze proposed courses
of action is by means of the benefit-cost ratio and its variations. For water projects,
benefits are measured in flood damages avoided annually as a result of the presence of
the project. This shows the importance of knowing the hydrologic impacts of the dams.
In the South River case study for the flood of record, damages for the �with� and
�without� dams can be established. The net difference between these two conditions is
a net benefit of flood damages avoided (Franzini et al., 1964).
The magnitude of damages avoided changes with the magnitude of the resulting
flood wave from a given storm. Lower probability of occurrence storm events (low risk)
produce higher flood damages, but occur infrequently. Typically, a proposed water
project is intended to meet a certain level of protection, like avoiding damages from the
100 year flood. However, the damages for each return period like Q2, Q10, Q25, Q50,
Q100, and Q500 are determined for each course of action. The flood damage in dollars
is then plotted versus the exceedence probability for the desired course of action and the
�no project� case. The economic benefit is then equal to the area between the two
curves as shown in Figure 4.1 (Franzini et al., 1964).
Damage - Frequency Curves
0
10
20
30
40
50
60
0 50 100
Probability of Exceedence
Dam
age
($10
00)
Natural FlowRegulated Flow
Damages Avoided
Damage - Frequency Curves
0
10
20
30
40
50
60
0 50 100
Probability of Exceedence
Dam
age
($10
00)
Natural FlowRegulated Flow
Damages Avoided
Figure 4.1: Example Economic Benefit Determination
Chapter 4: Traditional Economic Analysis of Dam Rehabilitation 51 by Flood Damage Curve Integration
Determining the flood damages within a watershed is not a simple task. The
flood damages are inherently linked to the flood inundation area resulting from the
routed flood wave. A certain magnitude storm, like the 25 year storm, produces a Q25
flood wave that floods a certain area. To determine the area impacted, hydraulic
simulation programs, like USACE�s HEC-River Analysis System (HEC-RAS) are used to
calculate the water surface profile of the resulting flood wave at known cross sections in
the flood plain. The cross sections are linked to the topography of the river in question,
and the end results are inundation zones for each return period. The final step is to
inventory the existing infrastructure in the inundation area like residential homes,
commercial buildings, highways, bridges, or any other item that might get damaged by
flooding. The extent of monetary damage is usually measured as a function of depth of
inundation. This in turn is usually assessed by established damage curves (like FEMA�s
or USACE�s). For example if a structure is flooded by five feet on the main floor, then
the assigned damage might be 50% of assessed property value (Mays, 2001).
Establishing the infrastructure inventory that is impacted by flooding is no simple
task. The required time and effort is extensive as detailed on-site surveys must be
conducted to establish high water marks from flood waves. The process of gathering the
necessary tax parcel information has improved with the availability of GIS databases, but
this is a function of the local government�s efforts. There are guidelines that are
followed, but the assessment of damages is certainly more an �art� rather than pure
science. For example, trying to predict a local gas station�s loss of business based upon
the 25 year flood as opposed to the 100 year flood is not a black and white calculation.
Creating feasible courses of actions will be iterative in nature. Infeasible courses
of actions can be eliminated, most likely by a simple cost comparison. For example, one
course of action could be to replace the entire dam which would undoubtedly be more
expensive than attempting to remediate the existing dam. For this chapter we assume
Chapter 4: Traditional Economic Analysis of Dam Rehabilitation 52 by Flood Damage Curve Integration
that the best remediation courses of actions were created, and the hydrology and
hydraulic models were completed to reflect the flooding changes caused by the courses
of actions. This leads to an annual sum of damages (flood damages will be reduced, but
not completely eliminated in all projects) and project costs for each course of action.
Likewise, the annual benefits (primarily flood damages avoided) can be summed for
each course of action. Benefit-cost ratios can now be calculated for comparison.
It must be noted that the benefit-cost ratios are not the only indicator that should
be used. An incremental approach can establishes better indicators of which course of
action would be best. The courses of action are placed in increasing order by annual
benefits. Beginning with the course of action that had the lowest benefits, it is compared
to the next course of action. Net change in benefits between the two courses of action is
computed, along with the net change in costs. The following ratio is then computed:
∆ Benefits / ∆ Costs see if ratio is > one.
If the ratio is greater then one, the second course of action is worth the change in
benefits at the set change in costs. This completes one increment of the analysis, and
the analysis continues until one course of action yields a ratio that is less then one. At
this point the second course of action is not worth doing because a dollar of benefit is at
expense of more then a dollar of cost (Franzini, et al, 1964).
Table 4.1 presents out an example of incremental analysis based upon five
possible courses of action. If one were to strictly use the benefit-cost ratio, course of
action II would produce the greatest ratio at 1.35. However, course of action III actually
provides a change in benefits-cost ratio of 1.25 when compared incrementally with
course of action II. Course of action IV only provides a change in benefits-ratio of 0.33,
and therefore should not be selected over course of action III. This demonstrates the
importance of using incremental economic analysis for comparison of the course of
actions (Franzini, et al, 1964).
Chapter 4: Traditional Economic Analysis of Dam Rehabilitation 53 by Flood Damage Curve Integration
Table 4.1: Example Economic Analysis
Courses of
Actions
Annual
Benefits
Annual
Costs
Benefit-
Cost ∆ Benefits ∆Costs ∆ B / ∆ C
(#) ($) ($) (Ratio) ($) ($) (Ratio)
I 150,000 128,104 1.17
60,000 27,944 2.15
II 210,000 156,048 1.35
65,000 52,016 1.25
III 275,000 208,064 1.32
25,000 76,088 0.33
IV 300,000 284,152 1.06
40,000 52,006 0.77
V 340,000 336,158 1.01
4.2 Specific Steps to an Economic Analysis
The following section is intended to layout a step by step process to be used as a
guideline for completing economic analysis for a dam remediation project. The steps are
numbered with additional comments in bullet format. A summary flow chart is shown at
the end of the section (See Figure 4.2).
1. Identify a dam, and the need for remediation of some sort.
2. Establish remediation courses of action, and associated costs. (Iterative process)
• Consider the �controlled breach� course of action for dam remediation.
• Narrow down unrealistic solutions like replacing the entire dam.
3. Establish area of interest.
• Include all relevant watersheds and flooding areas are directly impacted by the
dam. (Chapter 3 analysis)
• Begin with FEMA�s 100 and 500 year flood studies as a starting point.
Chapter 4: Traditional Economic Analysis of Dam Rehabilitation 54 by Flood Damage Curve Integration
4. Generate water surface elevations for the downstream flood waves for each course
of action.
• Complete hydrology and hydraulic calculations, and use accepted simulation
models.
• Transfer water surface profiles to flood inundation maps to determine depth of
flooding at impacted properties.
5. Gather economic data for area of interest.
• Gather tax parcel data for any property that might be impacted by flooding.
Includes property value and structures value. Must adjust to current market value.
• Identify any infrastructure like roads, bridges, retaining walls that might be
impacted by flooding. Obtain construction and replacement costs.
• Identify any commercial property that might be impacted. Estimate potential
business loss per day from closures. Identify structure and property costs.
• Determine if any recreational activities that occur within the area of interest.
Estimate daily value for such activities.
• Acquire census income data to establish income lost by population impacted.
6. Field survey at known junctions the high water bench marks from hydrologic and
hydraulic simulation results.
• Establish the flood inundation zone through bench marks.
7. Survey all structures in flood inundation areas, and establish high water marks.
• Determine the elevation of the point of entry, and establish at what elevation water
enters into the structure.
• Identify structures structure that have basements, as less damage might occur if
the main level is not necessarily flooded first.
Chapter 4: Traditional Economic Analysis of Dam Rehabilitation 55 by Flood Damage Curve Integration
8. Sum up all accounted for damages for each course of action, for each level of
flooding Q2, Q25, Q50, Q100, Q500, etc.
• Include property damages and clean up costs. Adopt structural damage
assessment technique such as based upon �x� water level in the structure�s 1st floor, �x�
percent damage of structure value is incurred. (direct damages)
• Include any revenue lost from businesses. (indirect damages)
• Include loss in property value if the course of action removes a reservoir, if
applicable. (intangible damages)
• Include losing recreational value lost by removing reservoir, if applicable.
• Add detour costs to commuters, if flooding results in closure of main traffic roads.
(secondary damages)
9. Construct Damage Frequency Curves for each course of action. (See Figure 4.1)
10. Compute Average Annual Damages from the Damage Frequency Curves.
• Use integration approximations like trapezoidal rule to determine area under the
curves.
11. Establish damages avoided for remediation courses of actions.
• Subtract course of action damages from the status quo.
12. Conduct incremental analysis for the courses of actions.
• Compute ∆ Benefits / ∆ Costs ratio or other equivalent metric.
• Evaluate and rank courses of action based upon calculated decision metric, like
∆ Benefits / ∆ Costs.
Chapter 4: Traditional Economic Analysis of Dam Rehabilitation 56 by Flood Damage Curve Integration
Identify Remediation Problem1.
Establish Courses of Action2.
Establish Flood Area of Interest3.
Create Flood Water Surface Profiles4.
Gather Economic
Data5.
Establish High WaterMarks on
Cross Sections6.
Survey 1st FloorElevations for
Structures7.
Sum Damages for Return Periods8.
Construct Damage Freq. Curves9.
Compute Average Annual Damages10.
Compute Damages Avoided11.
Complete Incremental Analysis12.
Identify Remediation Problem1.
Establish Courses of Action2.
Establish Flood Area of Interest3.
Create Flood Water Surface Profiles4.
Gather Economic
Data5.
Establish High WaterMarks on
Cross Sections6.
Survey 1st FloorElevations for
Structures7.
Sum Damages for Return Periods8.
Construct Damage Freq. Curves9.
Compute Average Annual Damages10.
Compute Damages Avoided11.
Complete Incremental Analysis12.
Figure 4.2: Economic Analysis Flow Chart
Referring to Figure 4.2, the first four steps entail engineering design work, cost
estimating, and hydrologic simulation analysis. The middle steps (Steps 5-7) can be
completed simultaneously, and are usually the most time consuming. Detail surveying
and gathering economic information is resource and time intensive. The remaining
steps are the steps to complete the economic analysis. The end state of the process is
a rank order of recommended courses of action.
Chapter 4: Traditional Economic Analysis of Dam Rehabilitation 57 by Flood Damage Curve Integration
4.3 Federal Planning Guidance
The case study includes the NRCS�s planning for the three case study dams.
Since the NRCS is a part of the federal Department of Agriculture, the NRCS must follow
the federal planning guidelines for water resources projects. The guideline document
was published in 1983, and is called �The Economic and Environmental Principles and
Guidelines for Water and Related Land Resources Implementation Studies (P&G).� The
NRCS completed the economic analysis for the case study watershed following the P&G
planning guidance.
The P&G planning guidance provides a framework for federal agencies to follow.
All analysis is placed into four categories or �accounts.� The first two are more
economically focused being the national economic development (NED) and the regional
economic development (RED) accounts. The other two accounts include the
environmental quality (EQ) and the other social effects (OSE). The NRCS performed
the economic analysis while adhering to the P&G standard. For the case study the RED
analysis equaled the NED analysis since the case study is a localized project, and really
does not have impact at the national level (WRC, 1983).
NRCS economic analysis was clearly guided by the P&G document in two areas
of emphasis. The first area is computation and assignment of recreational value
associated with the courses of action. The P&G gives step by step instructions on how
to assess recreational benefits from a water resources project. The second area is the
break down of costs between what the federal agency can fund, and what must be
funded by the local entity. The NRCS uses a standard spreadsheet file that breaks
down the costs for each course of action, and further breaks down the cost allocations.
This streamlines the process for the NRCS and ensures the P&G regulation is followed
(Faulkner, 2006).
Chapter 4: Traditional Economic Analysis of Dam Rehabilitation 58 by Flood Damage Curve Integration
4.4 Case Study Economic Analysis
This section details the NRCS�s economic analysis as part of the decision
making process to rehabilitate three of the dams in the South River watershed. The
three dams, Robinson Hollow, Toms Branch, and Inch Branch are all located in the
eastern portion of the watershed. They all discharge to the Back Creek branch of the
South River and are located in the George Washington National Forest. The dams were
originally classified as low hazards back in the 1950s and 60s. Urbanization by the mid-
1980s down stream of the dams impacted the hazard classification of the dams.
Consequently, the dam safety criteria changed for the dams in the late 1980s, and the
dams are now classified as high hazard. The following sub-sections follow the above
general framework to demonstrate how the traditional economic approach is applied.
1. Identify Remediation Problem: The three dams do not meet the Virginia State
regulation for dam safety, as they are unable to safely pass the probable maximum flood
(PMF) through the auxiliary spillway without significant risk of structural failure. The
NRCS determined that under current conditions, the Robinson Hollow, Toms Branch,
and Inch Branch dams could only pass 55%, 60%, and 50% of the PMF respectively
(NRCS, 2005). Since 1987, these dams have been operating under �conditional
permits� from the VA Dam Safety Division.
Further analysis performed by the NRCS included modeling the watersheds with
the NRCS Water Resources Site Analysis Program (SITES). One of the key capabilities
of the SITES simulation program is its ability to model erosion of the auxiliary spillway
during extreme storm events. By providing soil sample data from the spillways, the
NRCS personnel could apply the SITES model to predict severe erosion could occur
during major storm events. Thus not only were the dams unable to pass the PMF, the
Chapter 4: Traditional Economic Analysis of Dam Rehabilitation 59 by Flood Damage Curve Integration
auxiliary spillways might also fail during the same event. This constituted the two key
remediation problems. (NRCS, 2005)
2. Establish Courses of Action: The NRCS ruled out two courses of action rather
quickly. The first one was to relocate or flood proof structures in the breach zones below
the dams. The NRCS determined that it would be infeasible to move or flood proof the
identified 263 structures in the inundation zone below the dams. The second course of
action was the decommissioning of the dams, meaning that the dams would be
completely removed and the area returned to a natural state. The costs associated with
the decommissioning for all three dams totaled around $4.7 million.
This left two other options, to remediate the dams or to �sponsor breach� the
dams. A sponsor breach is simply cutting a notch in the dams to allow water to flow
freely through the dam; in a sense a pre-emptive, controlled breach rather then an
unexpected one. The remediation courses of action were compared to the �sponsor
breach� course of action for the economic analysis.
As discussed in Chapter 2, there are several different techniques for dam
rehabilitation. To meet the PMF standard the dam height can be raised, the auxiliary
spillways increased, or the dam itself could be armored. Combinations of these
techniques allows for large permutations of possible courses of action. These dams are
located in most cases in steeply confined valleys, tied in nicely to large hill masses.
Expansion of the spillways for all three dams would require significant earth moving
operations, and possible blasting of rock. The associated cost quickly rules out this
possibility. Likewise armoring the dam with material like RCC would cost significantly
more then raising the dam. Consequently the NRCS, settled on a combination of raising
the dam with a parapet wall (USACE recommended as most cost effective), and
armoring the auxiliary spillways to prevent erosion.
Chapter 4: Traditional Economic Analysis of Dam Rehabilitation 60 by Flood Damage Curve Integration
There is one additional comment about the courses of actions considered by the
NRCS. Although, one remediation technique was selected for each of the dams and
optimally designed, the three projects were also considered as a whole. The NRCS
considered doing nothing, completing all three, completing combinations, etc. Thus, the
end state economic analysis contained numerous courses of actions for which
incremental analysis could be performed. (NRCS, 2005)
3. Establish Flood Area of Interest: Once the courses of action were determined, the
modifications to the dams could be simulated in the SITES model. Simulating all of the
courses of actions produced flow rates at established junctions. The NRCS chose to
use the SITES simulation software, but the hydrology model presented in Chapter 3
would work also.
4. Generate Water Surface Profiles: The NRCS then converted the flow rates to flood
stages at the junctions by surveying the main channels. The hydraulic simulation
program HEC-RAS was then used by the NRCS to create a flood inundation zone for
each course of action.
5. Gather Economic Data: The lead economist for this NRCS project, David Faulkner
spent significant time and effort gathering necessary economic information in order to
conduct the analysis. He began with the tax parcel information for the 263 homes, 13
business structures, 2 church buildings, and 6 farm buildings. He interviewed local
realtors in order to establish a fair market value amount for replacement costs.
There are 13 bridges and 6 public roads in the inundation zones. Mr. Faulkner
obtained from the appropriate departments of transportation to establish replacement
costs. Mr. Faulkner conducted interviews of the business owners to determine what
amount business income could be loss during flood events. He also checked on the
recreation value of the properties around the reservoirs, and the impacts of losing water
front property.
Chapter 4: Traditional Economic Analysis of Dam Rehabilitation 61 by Flood Damage Curve Integration
This only highlights the extremely thorough efforts performed by Mr. Faulkner to
gather the economic data. His efforts, and any similar future efforts, are time and
resource intensive. The compilation of the data took place over several months. Any
effort to obtain data will not encompass everything, and so reasonable assumptions
must be made to fill in missing gaps in the economic information. (Faulkner, 2006)
6. Survey High Water Marks on Cross Sections. 7. Survey 1st Floor Elevations on
Structures: These two steps can be performed together by methodically working
through the inundation zone. The high water marks from the HEC-RAS simulation were
established on the actual ground at the key junctions. Working from these known high
water marks to a given structure one can determine the high water marks that could be
expected to occur on the property. Water damage within the structure can be
established by comparing the high water marks to surveyed 1st flood elevations. This
process is also time and resource intensive, and likewise took several months to
complete. (Faulkner, 2006)
8. Sum Damages for Return Periods: With the labor intensive portion of the process
complete, the compilation of the data is the next step. For each return period and
course of action the following three categories were totaled: 1. Structure Damages 2.
Content Damages 3. Infrastructure Damages. These three categories constitute the
bulk of the assessed damages. (See Table 4.2)
Other lesser damages were also calculated and compiled. Fishing and hunting
recreation activity estimates were completed for each dam using the prescribed method
in the P&G. The decommissioning of the three dams would lower the value of the
properties adjacent to the reservoirs, and so these were accounted for as losses.
Personal and Business Incomes were estimated and included in the total damages.
Finally, the clean up costs and public management of the clean up effort rounded out the
lesser damages accounted for by the NRCS. (Faulkner, 2006)
Chapter 4: Traditional Economic Analysis of Dam Rehabilitation 62 by Flood Damage Curve Integration
9. Construct Damage Frequency Curves: The totaled damages from step 8 are
tabulated against the corresponding storm return period. Interpolation was completed
for the 75 and 400 year return periods to allow for better definition to the damage
frequency curve. The damage frequency curves are then plotted for all of the courses of
action. The NRCS decommissioning of all three dams course of action damage
frequency curve is shown in Figure 4.3, as well as the associated tabulated data in Table
4.3.
Table 4.2: NRCS Damage Summations (Faulkner, 2006)
Chapter 4: Traditional Economic Analysis of Dam Rehabilitation 63 by Flood Damage Curve Integration
Figure 4.3: NRCS Damage Frequency Curve (Faulkner, 2006) (Note: FWOT = Future With Out Treatment; FWT = Future With Treatment)
Stor
m E
vent %
Chance of
Occur-rence
Structure Damages
Content Damages
Private Clean-up
Costs
Public Clean-up
Costs
Lost Business Income
and Personal Income
Disrup-tion of Traffic
and EMS + vehicle damage Costs
Infrastruc-ture Clean-
up and Damage Repair Costs
Agricul- tural
Impacts Debris
Clean-up Costs
Public Admin-stration Costs
Total Damages
1 100% $0 $0 $0 $0 $0 $0 $0 $0 $0 $05 20% $16,053 $8,686 $64 $0 $0 $0 $335 $0 $0 $25,13810 10% $83,277 $50,453 $384 $197 $0 $0 $12,225 $0 $0 $146,53625 4% $237,771 $136,178 $1,440 $247 $0 $0 $73,566 $0 $0 $449,20250 2% $499,224 $274,392 $3,328 $592 $0 $1,350 $185,919 $254 $129 $965,18875 1.33% $729,501 $412,392 $6,432 $1,036 $5,486 $3,412 $274,454 $357 $193 $1,433,263
100 1% $959,778 $549,745 $10,496 $1,578 $27,576 $4,601 $362,988 $460 $515 $1,917,737400 0.25% $1,567,835 $950,220 $33,229 $4,182 $62,752 $7,024 $513,771 $1,107 $1,494 $3,141,614500 0.20% $2,959,810 1825806 $72,576 $8,876 $129,305 $9,446 $921,439 $2,307 $3,220 $5,932,785All n/a $7,053,249 $4,207,872 $127,949 $16,708 $225,119 $25,833 $2,344,697 $4,485 $5,551 $14,011,463
Table 4.3 NRCS Tabulated Data for Figure 4.3 Damage Frequency Curve (Faulkner, 2006)
10. Compute Average Annual Damages: The NRCS examples above in Figure 4.3
and Table 4.3 represent the �status quo� course of action. For the NRCS analysis this
becomes the �natural flow� curve shown in Figure 4.1, or stated differently as the
expected damages if the project was not present. To obtain an estimate of the expected
Chapter 4: Traditional Economic Analysis of Dam Rehabilitation 64 by Flood Damage Curve Integration
annual damages for the status quo case, one has to integrate numerically the area
under the damage probability curve in Figure 4.1. This approach was used by the NRCS
and is shown in Table 4.4. The total estimated average annual damages for the �status
quo� is $162,210.
Table 4.4 NRCS Average Annual Damages for Sponsor Breaches (Faulkner, 2006)
Storm Event
Definition (Years)
Freq of each Storm Event - % Chance of Occurrence
Change in Freq
(Probability)
Damages in Present Values ($)
Average Damages in Present Values ($)
Contribution to Average
Annual Damages ($)
1 100.00% --- $0 --- --- --- --- 0.80 --- $12,569 $10,055 5 20.00% --- $25,139 --- --- --- --- 0.10 --- $85,837 $8,584 10 10.00% --- $146,536 --- --- --- --- 0.06 --- $297,869 $17,872 25 4.00% --- $449,202 --- --- --- --- 0.02 --- $707,194 $14,144 50 2.00% --- $965,187 --- --- --- --- 0.07 --- $1,999,063 $7,994 75 1.33% --- $1,432,939 --- --- --- --- 0.00 --- $1,675,338 $5,584
100 1.00% --- $1,917,737 --- --- --- --- 0.01 --- $3,925,261 $31,402
500 20.00% --- $5,932,784 --- --- Estimated Direct Average Annual Damages: $95,635 Lost Incidental Recreation Value each year: $11,381
Lost Property Value (amortized over perpetuity): $55,193 Total Estimated Average Annual Damages: $162,210
The same process was repeated for each course of action. These become the
�regulated flow� curves in Figure 4.1. The same finite difference method was performed
to compute the average annual damages shown in Table 4.5 for the Rehabilitation of
Tom�s Creek only. The calculated average annual damages totaled $84,920.
Chapter 4: Traditional Economic Analysis of Dam Rehabilitation 65 by Flood Damage Curve Integration
Table 4.5 NRCS Average Annual Damages for Toms Branch Rehab. (Faulkner, 2006) Storm Event
Definition (Years)
Freq of each Storm Event - % Chance of Occurrence
Change in Freq
(Probability)
Damages in Present Values ($)
Average Damages in Present Values ($)
Contribution to Average
Annual Damages ($)
1 100.00% --- $0 --- --- --- --- 0.80 --- $1,638 $1,310 5 20.00% --- $3,276 --- --- --- --- 0.10 --- $36,927 $3,693 10 10.00% --- $70,578 --- --- --- --- 0.06 --- $148,502 $8,910 25 4.00% --- $226,426 --- --- --- --- 0.02 --- $313,259 $6,265 50 2.00% --- $400,093 --- --- --- --- 0.07 --- $541,174 $3,608 75 1.33% --- $682,256 --- --- --- --- 0.00 --- $830,203 $2,767
100 1.00% --- $978,151 --- --- --- --- 0.01 --- $2,241,914 $17,935
500 20.00% --- $3,505,676 --- --- Estimated Direct Average Annual Damages: $44,488 Lost Incidental Recreation Value each year: $4,572
Lost Property Value (amortized over perpetuity): $35,859 Total Estimated Average Annual Damages: $84,920
11. Compute Damages Avoided: The damages avoided represents the area between
the natural flow and regulated curves in Figure 4.1. So for the above example the
difference between the status quo and Tom�s Branch rehabilitation is $162,210 -
$84,920, or $77,290, as shown at the bottom of Table 4.5.
12. Complete Incremental Analysis: The NRCS performed some additional analysis
to establish the best order to decommission the dams, as well as the best order to
rehabilitate the dams. This is a subtle point to note, but there is a project length time for
each course of action that shifts slightly when the annual damages occur. Once the
order was determined, this set the increment analysis order. The NRCS compiled the
average annual costs and benefits similar to Table 4.1, as shown in Tables 4.6 and
Tables 4.7
Chapter 4: Traditional Economic Analysis of Dam Rehabilitation 66 by Flood Damage Curve Integration
Table 4.6 NRCS Incremental Analysis on Sponsor Breaches (Faulkner, 2006)
Structure
Average Annual
Cost (&) Incremental
Cost ($)
Average Annual Benefits
($) Incremental Benefits ($)
Net Average Annual Benefits
($) B/C Ratio
($)
Inch Branch $14,860 --- $1,216 --- -$13,644 0.08
Inch Branch and Robinson Hollow $35,415 $20,555 $2,432 $1,216 -$32,983 0.07
Inch Branch, Robinson Hollow and Toms Branch $58,495 $23,080 $3,614 $1,182 -$54,881 0.06
Table 4.7 NRCS Incremental Analysis on Rehabilitation Options (Faulkner, 2006)
Structure
Average Annual
Cost (&) Incremental
Cost ($)
Average Annual Benefits
($) Incremental Benefits ($)
Net Average Annual Benefits
($) B/C Ratio
($)
Inch Branch $57,536 --- $16,938 --- -$40,598 0.29
Inch Branch and Robinson Hollow $120,548 $63,012 $45,318 $28,380 -$75,230 0.38
Inch Branch, Robinson Hollow and Toms Branch $221,393 $100,845 $120,498 $75,180
-$100,895 0.54
The NRCS chose to use the Benefit to Cost ratio as the metric for the
incremental analysis. So as observed in Table 4.6, the B/C ratio is decreasing as each
dam is decommissioned. This makes sense as the flood benefits of the existing dam are
removed, and each increment would increase the damages. We can observe this in
Table 4.7 where they are increasing with each increment. Based upon the B/C ratio of
0.54 the rehabilitation of all three dams yields the highest benefit to cost ratio.
We can check the NRCS calculations by computing the ∆ (B / C) ratios for the
increments. The ratio for the Robinson Hollow and Inch Branch is 0.44, and for the
Chapter 4: Traditional Economic Analysis of Dam Rehabilitation 67 by Flood Damage Curve Integration
rehabilitation of all three 0.75. Both of the ratios are less then 1, and so the incremental
analysis is supposed to end if the ratio is less then one. This is also the case when
computing the B/C ratio, as the benefits should outweigh the costs. David Faulkner
discussed this exact issue, and explained that special permission was needed in order to
proceed with the recommended course of action that yielded a B/C ratio less then one
(Faulkner, 2006). So, if we ignore the ratios being less then one, either method yields
the same resulting recommendation to rehabilitate all three dams.
4.5 Summary of Traditional Economic Analysis
This chapter provides a general framework that is one way of approaching the
necessary economic analysis for proposed rehabilitation projects. The framework was
first discussed on a conceptual level followed by a step-by-step flow chart shown in
Figure 4.2. The framework was validated by the NRCS case study for the proposed
rehabilitation projects for the Toms Branch, Inch Branch, and Robinson Hollow Dams.
As demonstrated, the NRCS economic analysis fit nicely into the general framework.
As indicated in the discussion of the NRCS benefit-cost ratios, these
rehabilitation projects did not have B/C ratios above one. Yet, the NRCS approved the
recommendation despite the B/C ratios. This is an excellent example of a continuous
debate. The debatable issue is justification of rehabilitation projects to meet the required
design probable maximum flood derived from the theoretical probable maximum
precipitation. In the opinion of the NRCS, the project benefits warranted the additional
cost expenditures. This is supported by the conclusions from Chapter 3 in that the dams
do impact and reduce flooding within the watershed. Therefore, the decision metrics like
the B/C ratios are only tools, and the final decisions must account for all mitigating
factors surrounding the projects in question.
Chapter 5: Use of GIS Software as a Hydro-economic Tool 68 in Dam Rehabilitation Analysis
Chapter 5: Use of GIS Software as a Hydro-economic Tool in Dam Rehabilitation Analysis
In performing rehabilitation analysis from both the engineering and economic
stand points, an individual can benefit from the use of integration of Geographic
Information Systems (GIS). Even if a person were only to perform a watershed
delineation today using a paper map, chances are that paper map was produced from
GIS technology at some point. With the continuous improvement in Geographic
Information Systems (GIS) technology, and the ever increasing number of GIS
databases, ignoring a potential source of information could be counter-productive. With
that said, one must be able to evaluate the credibility of the GIS data source, the
capability of the GIS application software being used, and the extent to which such GIS
applications should be used.
This chapter will discuss the topic of integrating GIS into rehabilitation analysis.
The first section provides an overview of potential GIS software that is available that
might assist with the creation of simulation models. The second section provides a
software specific discussion of products available that could be used in performing
rehabilitation analysis. One particular GIS based simulation software that was evaluated
was the Federal Emergency Management Agency�s (FEMA) risk mitigation software
HAZUS Multi-Hazard (HAZUS-MH). The HAZUS software methodology will be
described as an introduction to its capabilities. Following the introduction to the HAZUS
software, a discussion about the application to the case study will be presented. Finally,
the chapter concludes with summary comments.
5.1 Overview of GIS as a Tool for Analysis By definition, a Geographic Information System database is comprised of data
that is spatially referenced. In creating the HEC-HMS model in Chapter 3, input
Chapter 5: Use of GIS Software as a Hydro-economic Tool 69 in Dam Rehabilitation Analysis
parameters for the sub-basins, like the NRCS curve number, were numerically lumped
together by an accepted approach. In the past, input parameters needed to be lumped
together in order to expedite the modeling process by reducing the amount of data to
input into the simulation, and by reducing the computational time of the models.
Advancement in personal computer technology for processor speeds has negated the
need for smaller models to reduce computational time. However, data input can remain
time-consuming, even by today�s standards.
GIS databases allow users to store large amounts of spatially oriented data, such
as soil types. An engineer can now represent data as distributed parameters rather then
as lumped parameters. Provided the GIS database source is relatively error free,
simulation results can be enhanced using distributed parameters as input data
(Whiteaker et al., 2006). Public GIS sources are becoming widely available. For
example, the USGS alone provides downloadable digital elevation maps (DEMS),
satellite imagery, national atlas roads, counties, topographic quad sheets, and many
other databases.
Recognizing the usefulness of GIS databases, counties and larger cities across
the United States have public accessible GIS internet web-sites. Augusta County in
Virginia, the South River case study county, provides such a web-site as shown in
Figure 5.1 (http://www.co.augusta.va.us/website/AugustaInternetGIS/viewer.htm). These web-
sites function not only as great reference maps, but relevant data can also be obtained
in the data layers. In the Augusta County web-site, critical GIS data on Tax Parcel
information (georeferenced shapes and data information), the 500 year flood plane,
existing structure locations, and the shapes of the existing structures are available. This
data could be directly used in conjunction with the creation of the hydrology model and
the economic analysis discussed in Chapters 3 & 4.
Chapter 5: Use of GIS Software as a Hydro-economic Tool 70 in Dam Rehabilitation Analysis
Figure 5.1 Augusta County, VA GIS Web-Site
5.2 Discussion of Existing Relevant GIS Software
The major purpose of GIS was the expansion of a typical database, like one
might create using a program like Microsoft Access, by linking the data to a geospatial
reference point. Thus, a software program to merge traditional databases with maps
was needed. There are several different commercial software programs that have
evolved that will allow the user to manipulate GIS data. A widely used GIS software
program is produced by the Environmental Systems Research Institute (ESRI),
headquartered in Redlands, California. The ESRI software suite named ArcGIS (version
9.0 or 9.1) provides the necessary programs to view, edit, organize, and analyze GIS
data. All GIS related work performed for this work was completed using the ArcGIS
software suite (Longley et al., 2005).
Mastering the ArcGIS software is only part of the battle to employing the full
potential of available GIS data. The process of gathering the data from the various
sources, like Augusta County and the USGS, requires persistence and patience. Often
Chapter 5: Use of GIS Software as a Hydro-economic Tool 71 in Dam Rehabilitation Analysis
a user remains at the mercy of the local internet connection and the source data server
in being able to download files quickly. The GIS data files are often extremely large and
may require breaking the data into smaller files. Another potential problem in dealing
with GIS data is ensuring the data projection and reference coordinate systems are the
same. Otherwise the different data layers will not be compatible when trying to perform
an analysis. All of these issues are usually mastered by a proficient GIS technician. The
time spent gathering the existing data vastly exceeds anyone trying to conduct new
surveys to obtain all of the same information (Wiley et al., 2005).
The ArcGIS software suite contains applications that can immediate expedite the
hydrologic and hydraulic modeling. For example, having obtained the necessary data
layers, watershed boundaries can be delineated manually, the area can be calculated for
the watershed, the centroid of the watershed can be found, and the longest travel
distance within watershed can be determined. These semi-automated applications are
much more efficient then the original manual methods. Another powerful aspect of the
current ArcGIS software suite is a model creation capability. If a particular order of
applications or data calculation is to be repeated, the user can create a model in visual
basic to accomplish this. For example, once the watershed is delineated manually, a
model could be set up that automatically computes the area, the centroid, and longest
distance travel distance for the watershed (Wiley et al., 2005).
The modeling techniques are encouraged by ESRI, as the ArcGIS software
remains the base platform for the data manipulations. New models are perfected for all
different areas of emphasis like geology, water utilities, groundwater, hydrology, and etc.
ESRI takes full advantage of these products, and markets them as software packages,
training packages, and provides technical support. A relevant hydrology and hydraulic
model marketed by ESRI is called Arc Hydro (CRWR, 2001).
Chapter 5: Use of GIS Software as a Hydro-economic Tool 72 in Dam Rehabilitation Analysis
The Arc Hydro data model performs five different tasks within three broad
hydrology categories called: hydro description, hydro connectivity, and hydro modeling.
The five tasks the data model is capable of performing are: 1. Network. 2. Drainage. 3.
Channels. 4. Hydrography. 5. Time Series. The first three functions establish how
water moves through a given watershed, and outputs parameters that allows for a
simulation model to be created. The Hydrography tool links the data from the first three
functions to map locations remaining consistent with the enhanced spatial reference
gained by using GIS. The Time Series tool ties together the first four functions to create
outflow hydrographs. From the description of the software alone, the potential
usefulness of Arc Hydro as an alternate means of modeling is quite apparent (CRWR,
2001).
The USACE Hydrologic Engineering Center (HEC) has recognized the
importance of geospatial data in its recent model development activities. The HEC
developed two ArcGIS applications for hydrology and hydraulics called HEC-GeoHMS
and HEC-GeoRAS. These two programs work with GIS databases like Arc Hydro, but
with a primary purpose to generate input parameter data for the simulation programs
HEC-HMS and HEC-RAS discussed previously. So, the arduous task of compiling and
inputting data into the hydrology model described in Chapter 3 could potentially have
been streamlined into a more automated method using HEC-GeoHMS (HEC, 2004). On
completing the HEC-HMS work, the engineer could then route along the flood inundation
zone HEC-GeoRAS. The HEC-GeoRAS performs two functions. The first function
being like HEC-GeoHMS in that input parameter data is generated in HEC-GeoRAS for
HEC-RAS. Additionally, the output data from HEC-RAS can then be inputted back into
HEC-GeoRAS in order to visualize the hydraulic routing along the reaches in question
(HEC, 2005).
Chapter 5: Use of GIS Software as a Hydro-economic Tool 73 in Dam Rehabilitation Analysis
Using the above simulation programs as described still requires manual transfer
of input/output data, and therefore could be described as semi-automated. Ideally, one
software package that could accomplish all of the tasks might prove to be quite useful.
The Center for Research in Water Resources (CRWR), of the University of Texas
recently published a way of accomplishing a full automation process using ArcGIS and
the HEC software (Whiteaker, 2006). The researchers demonstrated that Flood
Inundation Maps can be created from NEXRAD rainfall maps and the HEC software
suite. They created a model in GIS that interacts with the four software programs HEC-
HMS, HEC-GeoHMS, HEC-RAS, and HEC-GeoRAS. Their research study and
corresponding analysis is not an exact match for the analysis of dam rehabilitation, but
never the less their approach in gaining a more automated process is quite promising.
5.3 Automating the Economic Analysis
Already highlighted in Chapter 4, the economic analysis process is rigorous and
time consuming. Any potential ways to automate or streamline the process would be
welcome. In the absence of a widely accepted software simulation program, in house
spread sheets are used by agencies like the NRCS (Faulkner, 2006). The NRCS does
have a flood damage assessment software packages called URB1 and ECON2, but they
are extremely outdated. The HEC software for economic flood damage analysis that is
used by USACE Districts is the program HEC-Flood Damage Analysis (HEC-FDA).
HEC-FDA provides a risk based analysis for flood reduction studies that are
performed regularly by USACE offices. The purpose for HEC-FDA is to assist the user
during the feasibility stage of the USACE�s project planning cycle. A user of HEC-FDA
must complete the hydrology and hydraulic analysis in order to generate discharge-
frequency curves and water surface elevation profiles. This mandatory H&H input data
is first coupled with the building inventory, and then the program computes the
Chapter 5: Use of GIS Software as a Hydro-economic Tool 74 in Dam Rehabilitation Analysis
equivalent annual damages for the model situation. HEC-FDA is meant to be a decision
tool. The results are meant to provide a quick assessment in order to determine whether
the project is going to be feasible, and therefore can save USACE planners time by not
continuing to plan projects that are not economically viable. (HEC, 1998)
FEMA wrestled with the same automation issues in designing a GIS based
software that can assist local emergency managers across the United States plan for
natural disasters, like flooding. FEMA�s intent was to provide a software package that
could be used by different levels of experienced users. Therefore the program is
capable of running simulations by personnel who possess very limited knowledge of the
science behind some of the models, like a typical emergency planner, but is also
versatile enough to allow technical experts to provide almost all of the input parameters.
The next section will describe the characteristics of FEMA�s HAZUS-MH model.
5.4 FEMA�s HAZUS Multi-Hazard Model
The FEMA HAZUS Multi-Hazard model
contains three major models for the primary
natural disasters experienced in the U.S.:
earthquakes, winds, and flooding (Figure 5.2).
The model is capable of replicating all three
disasters in a given location; however, the
model is not capable of simultaneously running
more then one disaster. HAZUS-MH is an
interactive GIS application that requires the
ArcMAP 9.0 software platform. Our discussion
only focuses on the flood model. (National
Institute of Building Sciences (NIBS), 2003b) Figure 5.2 HAZUS-MH Start Menu
Chapter 5: Use of GIS Software as a Hydro-economic Tool 75 in Dam Rehabilitation Analysis
A person using the HAZUS-MH flood model is able to create a study area up to
the size of four counties. The software package when distributed by FEMA includes
data files for every county in the United States. After selection of a study area, the
program creates the necessary background GIS layers including county boundaries,
census population blocks, and building inventory databases. The user must provide an
elevation DEM in order for the program to establish the stream network. The stream
network is created similarly as the Arc Hydro�s Network tool. With an overall network
completed, the user establishes specific reaches to analyze. In turn the program
calculates a discharge frequency curve for the desired reaches, and creates flood
inundation polygons with a water surface profile for the reach. This leads to the damage
analysis portion of the flood model. The damage model performs an economic analysis
based upon the flood inundation polygon, and summarizes all of the expected direct and
indirect damages. (NIBS, 2003a)
The HAZUS-MH flood model requires a modest amount of input from the user to
complete a basic flood analysis. This is very close to a fully automated process, but as
such there are many problems in completing the basic level analysis. For instance, the
calculated damages are based upon aggregate 2000 U.S. census data that is compiled
by census blocks, and are not site specific data one could obtain from county tax parcel
databases. However, the flood model is capable of integrating user provided data for
infrastructure and building inventories for completing the damage analysis. This requires
a more sophisticated understanding of the software, and requires more time for data
parameter inputting. The next section will describe how the model was applied to the
South River Case Study as a means of evaluating the flood damage assessment
capabilities of the HAZUS-MH flood model.
Chapter 5: Use of GIS Software as a Hydro-economic Tool 76 in Dam Rehabilitation Analysis
5.5 Case Study Application of HAZUS-MH Software
The potential for HAZUS-MH flood model to assist engineers and economists in
performing rehabilitation analysis was evaluated. To accomplish the evaluation, the
flood model was applied to the same South River case study. This section provides
details as to how the HAZUS-MH software works, as well as some discussion of the
strengths and weaknesses of the program. The desired end state is a comparison of the
damage assessment provided by HAZUS-MH versus comparison to the NRCS�s
assessment discussed in Chapter 4.
The first step in setting up the flood model is to select the study region. By
selecting Augusta County, the user requests the HAZUS-MH upload appropriate data
files for the county (Figure 5.3). Embedded in the flood model is the 2000 U.S. census
data broken into census blocks, in which for the urban setting is equivalent to one city
block. The census data determines the population break-down by annual income as
well as the type of residence found in the census blocks (Figure 5.4). The break-down
percentages of types of residences is determined from another national database that
determines the type of homes, like single family versus apartment complexes. (NIBS,
2003a)
Figure 5.3 Augusta County Study Region in HAZUS-MH
Chapter 5: Use of GIS Software as a Hydro-economic Tool 77 in Dam Rehabilitation Analysis
Figure 5.4: Census Blocks in HAZUS-MH
Although the way HAZUS-MH handles the census data within the blocks is
grounded in reasonable assumptions, they do not represent exact numbers and
locations. They are only aggregate numbers, based upon regional regression equations.
This key point must be understood when interpretation of the output data is completed.
The flood model when operated in the basic 1st level mode, only estimates the structure
inventory. The basic analysis would not provide enough detail to make decisions for
rehabilitation feasibility for a single dam. The real tax parcel information would have to
be inputted, which implies it must be gathered first. However, the basic 1st level analysis
would be more effective on a larger scale where the use of default aggregate numbers
would be mitigated. A large levee system encompassing a county size watershed is an
example where such an analysis might be used.
For any case study that is initiated in the flood model, the initial stream network
must be created for the entire study area. This is performed in the HAZUS-MH program
via raster analysis on the DEM. Without going into further details as to the technical
aspects of the raster analysis, the end result from this step is a network of reaches
Chapter 5: Use of GIS Software as a Hydro-economic Tool 78 in Dam Rehabilitation Analysis
(Figure 5.5). The stream network analysis of course is impacted by the resolution of the
DEM that is inputted into the flood model. In most cases, the stream network does not
perfectly match the existing streams and rivers spatially, but the process does not create
�false� streams either (NIBS, 2003a).
Figure 5.5: Stream Network in HAZUS-MH
The next step in the process is to identify the reaches that the user wants to
analyze; these are called �case studies� in the HAZUS-MH model. For this
demonstration we created two case studies, one for the Toms Branch and Inch Branch
dams. The reaches below the dams were selected all the way down to the Lyndhurst
Gaging station. Once the case study is completed, the software performs a hydrologic
analysis. The hydrologic analysis involves several complex computations that include
generating expected discharges from return period precipitation events, establishing a
flood inundation zone boundary, determining the water surface profile, and the flood
depth (NIBS, 2003a).
Chapter 5: Use of GIS Software as a Hydro-economic Tool 79 in Dam Rehabilitation Analysis
There are some discussion points for the HAZUS-MH hydrologic analysis. The
software program establishes the flow network when it created the stream network. The
primary computation performed during the hydrologic analysis is establishing the
discharge-frequency table. The program uses regional USGS regression equations to
compute discharges for each return period event, for each node of the stream network.
Additionally, the program checks if there are existing USGS gaging stations within the
stream network where a historical statistically-based discharge frequency table is
available. If a USGS gaging station is present, the flood model is extremely accurate in
matching the flood inundation zone to FEMA�s established flood zones as demonstrated
in an example in Hillsborough, NC (See Figure 5.6)
Figure 5.6: Flood Inundation Zone for Hillsborough, NC
More often then not, the study area of interest will not have a USGS gaging
station present for a given case study. The validity and accuracy of the regional
regression equations come into question. There are more accurate methods and
simulation models that perform the hydrologic and hydraulic analysis, like HEC-HMS and
Chapter 5: Use of GIS Software as a Hydro-economic Tool 80 in Dam Rehabilitation Analysis
HEC-RAS. For an advanced user, the HAZUS-MH is versatile in that H&H data from
other sources can be inputted into the model. There is a Flood Information Tool (FIT)
that allows the user to manually generate the flood inundation zone, but this tool requires
that cross channel and water surface profile data be known. The more advanced modes
of the HAZUS-MH require more user inputs and fewer semi-automation options. (NIBS,
2003a)
These inherent capabilities and weaknesses in the hydrologic analysis
notwithstanding, the HAZUS flood model output for the Toms Branch and Inch Branch
Dams was compared with HEC-HMS output presented in Chapter 3. As shown in Table
5.1, the calculated discharges from both dams were equal at each return period. This is
a telling feature of HAZUS, and can be attributed to the fact that the discharges are
routed through flow networks to a final reach, which happens to be the same reach for
both dams (see Figure 5.7). Since the raster analysis methodically computes the
discharge-frequency curve continually through the entire set of reaches, having a
common end reach causes the results to be equal. In comparing the HAZUS-MH to the
HEC-HMS model runs where the dams are present in the model, we see that the
HAZUS-MH results are slightly lower for the Q2 and Q10 events, but are considerably
less at for the Q50, Q100, and Q500 events, as shown in Table 5.1:
Table 5.1: Lyndhurst Gaging Station Comparison
Return HAZUS: Inch
Branch HAZUS: Toms
Branch HEC-HMS Period Q (cfs) Q (cfs) Q (cfs)
Q2 2,879 2,879 2,651
Q10 6,914 6,914 8,077
Q50 13,158 13,158 18,879
Q100 16,582 16,582 25,653
Q500 26,254 26,254 46,847
Chapter 5: Use of GIS Software as a Hydro-economic Tool 81 in Dam Rehabilitation Analysis
Figure 5.7: Common Reach of Inch Branch and Toms Branch Dams
The HAZUS-MH flood model was also checked for performance in the
headwaters reaches where the dams are located. The HAZUS-MH flood model, unlike
HEC-HMS, is not capable of reporting individual reaches when completing a multiple
reach analysis. New case studies were created in which only the reach containing the
dam was selected. The results from the hydrologic analysis for each of the dams are
shown in Table 5.2. The HAZUS-MH flood model results closely matched the HEC-HMS
outputs for the dam sites. Note, this time the HEC-HMS simulation results came from
the �without� dams present. This observation is expected since the flood model does
have a simple approach to simulating the presence of a hydraulic structure that is not
activated in the basic 1st level analysis.
Table 5.2: HAZUS-MH Comparison to HEC-HMS at Dam Sites HAZUS: HEC-HMS HAZUS: HEC-HMS Return Inch Branch Inch Branch Toms Branch Toms Branch Period Q (cfs) Q (cfs) Q (cfs) Q (cfs)
Q2 217 232 439 378 Q10 606 717 1,173 1,134 Q50 1,289 1,467 2,402 2,333 Q100 1,651 1,867 3,037 2,975 Q500 3,023 2,981 5,418 4,773
Chapter 5: Use of GIS Software as a Hydro-economic Tool 82 in Dam Rehabilitation Analysis
One final hydrologic discussion is the inundation zones created by the HAZUS-
MH for the Inch Branch and Toms Creak Dams. The NRCS dam rehabilitation analysis
included an estimated breach inundation zone shown yellow in Figure 5.8. In comparing
the HAZUS-MH 500 year flood zone to the NRCS breach zone, there are some good
Figure 5.8: Comparison of HAZU-MH and NRCS Flood Zones
correlations. The differences in the zones are due in part to the magnitude of the Q500
used in HAZUS-MH versus the initial breach discharges used by the NRCS (Table 5.3).
The NRCS breach zone was constructed using much larger initial discharges,
representing the large flood wave created from an unexpected dam break. This type of
event under most situations should create a larger flood inundation zone, as shown in
Table 5.3 in this instance.
Table 5.3: Flood Inundation Comparison
HAZUS-MH 500 yr
flood
NRCS Inch
Branch Dam Break
NRCS Toms
Branch Dam Break
Q (cfs) 26,254 51,000 90,000
Chapter 5: Use of GIS Software as a Hydro-economic Tool 83 in Dam Rehabilitation Analysis
Once the flood inundation zone is created in the HAZUS-MH flood model, the
next step is to compute damages. The flood model begins with comparing the flood
zone boundaries to the census inventory. The depth grid establishes the level of
flooding within a census block, which in turn are translated to damages through the use
of depth to percent damage curves. The damage curves are based upon established
USACE curves, and are adjusted to the region. The user also has the option to modify
the damage curves to reflect local conditions, if so desired. The rest of the process
replicates what was described in Chapter 4 by the NRCS. The flood model is capable of
creating a suite of output reports that can be viewed and printed (Figure 5.9).
Figure 5.9: Example Damage HAZUS-MH Damage Report
Chapter 5: Use of GIS Software as a Hydro-economic Tool 84 in Dam Rehabilitation Analysis
As highlighted previously when performing a 1st level analysis, the structure/
building damages are estimated by the use of aggregate census block data. To assess
the 1st level analysis, the results from HAZUS-MH were compared with the NRCS�s
economic analysis. The property exposure values, based upon the baseline inventories
are shown in Table 5.4. The HAZUS-MH model drastically overestimates the exposed
property value, directly attributable to the estimation method the flood model uses for
inventories. The software program can overcome this issue, but this would require
inputting of real tax parcel information into the model. This also requires additional time
and effort, and a higher level of expertise for the HAZUS-MH model. Obviously, the use
of highly aggregated census block data in HAZUS-MH cannot capture local structural
damages, as it was in the NRCS flood damage evaluation.
Another comparison from an economic stand point was the calculated total
damages caused by the flooding. Table 5.5 shows the calculated damages from the
HAZUS-MH flood model and the NRCS economic analysis. The 500 year damages
from the flood were compared with the sunny day breaches from the NRCS analysis
because the 500-year is believed to represent the extreme event in both methods. At
the extreme events, the estimates were closer, but the return periods are not exactly the
same since the breach events occur at percentages of the PMF. Looking at the Q10,
Q50, and Q100 events, results from the HAZUS-MH flood model are drastically larger
than the NRCS estimates. This matches the observed trend with the building exposure
estimates. Further comparisons can be assumed to yield similar results in the HAZUS-
Table 5.4: Property Exposure Estimates Comparison
HAZUS
Inch Branch NRCS
Inch Branch HAZUS
Toms Branch NRCS
Toms Branch Total Property
Exposure ($1000) 45,831 12,083 81,431 22,083
Chapter 5: Use of GIS Software as a Hydro-economic Tool 85 in Dam Rehabilitation Analysis
MH. Without local input data, the HAZUS-MH model will grossly over-estimate the
damages resulting from a flood.
Table 5.5: Total Structure Damages Comparison Damages ($1000)
Return Period
HAZUS Inch
Branch
NRCS Inch
Branch
HAZUS Toms
Branch
NRCS Toms
Branch Q10 1,200 3 2,040 25 Q50 1,690 439 3,230 959 Q100 2,050 996 3,830 1,872 500yr/Breach 2,800 2,463 5,550 5,707
5.6 Summary of Integration of GIS Software with Dam Rehabilitation Analysis
This chapter was intended to demonstrate the importance of using the large
quantities of information available in GIS databases. From a general information view, it
seems obvious that any planning or decision making process must consider all relevant
data. However, as seen in the previous section, the benefits of using automated GIS-
based software in performing complex hydrologic, hydraulic, and economic analyses can
be debated. Ideally, GIS models would approach full automation, and the results would
be black and white. As demonstrated in using the HAZUS-MH flood model application to
South River, the technology advancement although quite significant, still has room for
improvement.
On the surface, the HAZUS-MH flood model appears to be a nice solution in
automating the rigorous and time consuming task of performing a dam rehabilitation
analysis. However, the use of level-1 automatic data input is highly problematic, since
so little user input is required, and the simulation results do not include enough fidelity
for making a decision on a dam rehabilitation process. Performing the necessary
analysis in order to input data in HAZUS-HM flood model for the hydrologic analysis and
the economic analysis yields minimal added benefits. Since added benefits are minimal,
one would certainly question if the �automated� method is worthwhile. Especially, when
Chapter 5: Use of GIS Software as a Hydro-economic Tool 86 in Dam Rehabilitation Analysis
the reliability of the results is questionable, and would have to be verified through a
second means anyways.
The HAZUS-MH flood model was not originally intended to be used in an intense
civil works feasibility analysis. The model is meant for emergency management and
county level planners to use as a tool for disaster mitigation, and we are not commenting
on the model�s ability to meet this intent. There is some merit in using the model for
some preliminary analysis like establishing the stream network in a GIS format. The
simulation computations of the 100 and 500 year flood inundation zones gives a good
visualization of where the flooding areas might occur based upon topography. Since the
500 year flood inundation zone will be similar to an extreme dam break event, the 500
year flood zone created in GIS could be intersected with the GIS tax parcels, structures,
roads, and bridges to give the engineer reference points for potential damages that
might occur in a breach inundation zone. The next chapter explores the concept of
optimization in selecting a course of action through the method of linear programming.
Chapter 6: Linear Programming as an Alternative Analysis Technique 87
Chapter 6: Linear Programming as an Alternative Analysis Technique
The three South River case study dams are classified as �High� risk by the
NRCS. In the event of a catastrophic failure of any of the dams, it is probable that there
would be at least one life lost due to flooding. The three dams are not in compliance
with the VA Dam Safety Regulation (VDCR, 2004). So, the dam rehabilitation analysis
was forced into two possible solutions. The dams could be �sponsor� breached, or the
dams could be retrofitted to pass the calculated PMF.
The mandatory safety criteria for a �High� risk dam is the passage of the PMF as
stated within the Federal Dam Safety Criteria (NRC, 1985), as well as by the VA Dam
Safety Regulation (§ 4 VAC 50-20). However, if dams are classified as �significant� by
Federal guidance (FEMA 333), or Class III by VA standard, then the passage
requirement can be reduced to as low as ½ the calculated PMF. Justification in the form
an engineer analysis is required to demonstrate that increasing the passage of the ½
PMF to the full PMF does not gain any further reduction in flood damages. This
justification analysis creates the potential need for other analysis tools such as
optimization through Linear Programming techniques. Such a tool would be able to find
the optimal solution based upon the constraints of the problem.
This chapter will begin with an argument presented by Wayne Graham from the
BUREC. As discussed in Chapter 2, his argument focuses on the question: �Is the
benefit of rehabilitating a dam to meet the PMF criteria worth the costs?� Graham puts
forth a simple analysis that can be applied to dams being considered for rehabilitation
(Graham, 2000), and this technique was applied to the South River dams. The next
section introduces Linear Programming techniques and where they could be used to
assist with selection of the best course of action. The following section includes an
Chapter 6: Linear Programming as an Alternative Analysis Technique 88
expansion of Graham�s simple analysis in combination with Linear Programming.
Finally, summary remarks are discussed in the final section of the chapter.
6.1 An Alternative Economic Analysis for Dam Rehabilitation
Graham (2000) articulated an argument that modifying existing dams to meet the
required safety criterion of passing the PMF is more often not worth the large amounts of
project costs. He criticizes the PMF design criterion under the following four concepts
(Graham, 2000):
1. Spillway enlargements can increase downstream flooding resulting in an increase in average annual flood losses. 2. Benefit-cost ratios could be low. 3. Dam safety modifications could cause accidental deaths. 4. The cost-per-life-saved is high. Essentially, Graham (2000) questions the value of safety that is added by rehabilitating a
dam to meet what represents a statistically calculated maximum event. Also in
completing the dam rehabilitation, there could be increases in flood damages during
lesser extreme events that occur more frequently. The model format is based upon not
doing any modification, leaving the �status quo�, in comparison to the proposed
modification:
1. Economic Benefits: EB = ES � EM Where EB = Economic benefits derived from modification ES = Annualized Economic loss by flooding (Status quo) EM = Annualized Economic loss by flooding (Modification plan) 2. Life Benefits: LB = LS � LM - LC Where LB = Life benefits derived from modification LS = Annualized Life loss caused by flooding (Status quo) LM = Annualized Life loss caused by flooding (Modification plan) LC = Annualized Life loss caused from Construction spending (0.14 lives per $100 million expended)
Chapter 6: Linear Programming as an Alternative Analysis Technique 89
3. Cost-per-life-saved = LB is positive Parameter found: (CM � EB) / LB
Benefit-per-life-lost = LB is negative Parameter found: (CM � EB) / LB
Where CM = Cost of Modification
4. Decision Guidance:
a. If EB and LB are negative, reject project.
b. If 0 < EB < CM and LB is negative, reject project.
c. If EB < CM and LB is positive, compute Cost-per-life saved.
d. If EB > CM and LB is negative, compute Benefit-per-life lost.
e. If EB > CM and LB is positive, proceed with project.
Graham�s simple economic analysis incorporates a sensitive subject that is often
avoided by our society: assigning a monetary value to human life. Whether we wish to
address this issue from a monetary stand point or not, the fact remains the public
welfare remains the driving force behind the dam safety. What Graham accounts for is
that historically workers are killed during construction projects, and that this fact should
be accounted for when deciding to initiate a new project.
An example problem was provided by Graham (2000), which is used later in this
chapter to demonstrate an expansion of the above analysis. However, this simple
economic analysis is quite applicable to the South River dams. The Chapter 4 NRCS
economic analysis was completed to support the recommended project proposal to
rehabilitate the three South River dams to meet current the PMF standard. This creates
a question: �Would Graham�s economic analysis when applied to the South River case
study support the NRCS�s conclusion to proceed with the dam rehabilitation?� The rest
of this section seeks to answer this question.
To begin the analysis, the number of residents to be impacted by flooding must
be identified within the flood inundation zone. From the NRCS economic analysis, there
are 191 homes with 955 residents who could be affected by the Toms Branch dam, and
Chapter 6: Linear Programming as an Alternative Analysis Technique 90
72 homes with 360 residents for the Inch Branch and Robinson Hollow dams (NRCS,
2005). Following the procedure in BUREC regulation �A Procedure for Estimating Loss
of Life Caused by Dam Failure (Graham, 1999)�, a regression equation was selected
based upon certain on-site conditions of the dams. For example, the selection criteria
include earthen vs. concrete type of dam, viable emergency action plan in place, dam
visibility during storm events, etc. Accounting for all of the selection criteria, the BUREC
regulation suggested estimating the People at Risk (PAR) by the following equation
(Graham,1999): PAR = (Residents in Flood Zone).6.
Table 6.1 shows the calculated PAR (Sponsor Breach) which would be for the
situation where the dam rehabilitation did not occur. The probability the PMF would
occur in a single year is one chance in 286,000, and the loss of life is either zero or 34 in
the case of the Robinson Hollow Dam. Therefore, the annualized loss of life for flooding,
LS, is 34 divided by 286,000 equaling 0.00012. The available NRCS study did not
include the impacted residents in the flood zone based up the new projected inundation
zone. Even with the rehabilitated dams, some lives would be lost as a result of the
increased flows released by the emergency spillway, and therefore it was assumed the
residents in the flood zone would be decreased to a third of the original number. This
led to the calculation of the PAR (w Rehab) and the LM parameter in Table 6.1 (Graham,
2000)
Table 6.1: South River LS and LM Calculations
Residents in Flood
Zone PAR
(Sp. Breach) LS PAR
(w Rehab) LM Rob. Hollow 360 34 0.00012 18 0.00006 Toms Branch 955 61 0.00021 32 0.00011 Inch Branch 360 34 0.00012 18 0.00006 Combined 1315 74 0.00026 38 0.00013
The next parameters to determine were the lives lost due to construction.
Normally, the Lc parameter impacts only the modification because the �status quo� did
Chapter 6: Linear Programming as an Alternative Analysis Technique 91
not include any construction. For the South River dams, the minimal acceptable action
was to complete a sponsor breach of the dams which did have associated costs. The
NRCS calculated average annual costs for both the Sp. Breach and w Rehab are shown
in Table 6.2 (NRCS, 2005). The LCS and LCM parameters are calculated by multiplying
by the ratio of 0.14 per $100 million.
With the all of the necessary parameters calculated, the Life Benefits, LB could be
calculated. The LB were found by the following formula: LB = LS � LM - LCS - LCM. The
results are shown in Table 6.3. All of the calculated Life Benefits were negative,
meaning the dam rehabilitation projects would not create any Life Benefits. Graham�s
economic analysis usually did not include the LCS parameter. In removing this term, the
Toms Branch Dam now creates a positive Life Benefit.
Table 6.3: LB Results
LB Adjusted
LB Rob. Hollow -0.00004 -0.00002 Toms Branch -0.00003 0.00002 Inch Branch -0.00017 -0.00008 Combined -0.00034 -0.00018
The other part of the analysis is the Economic Benefits, EB. Table 6.4 compiles
the economic parameters that were obtained from the NRCS economic analysis (NRCS,
2005). The Economics Benefits were computed using the following formula: EB = ES �
EM. Individual ES values were assumed, as the NRCS data only provided a combined
annualized flood damages for the status quo. All of the courses of action yielded
Table 6.2: South River LCS and LCM Calculations
Avg Cost
(Sp. Breach) LCS Avg Cost (w Rehab) LCM
Rob. Hollow $14,860 2.08E-05 $57,536 8.06E-05 Toms Branch $35,415 4.96E-05 $63,112 8.84E-05 Inch Branch $58,495 8.19E-05 $100,745 1.41E-04 Combined $108,770 0.000152 $221,393 3.10E-04
Chapter 6: Linear Programming as an Alternative Analysis Technique 92
negative economic benefits, but the combined impacts yielded positive impacts. The
Economic Benefits must then be compared with the Project Costs, CM.
Table 6.4: South River Economic Calculations ES EM EB CM Robinson Hollow $20,276 $84,920 ($64,644) $57,536 Toms Branch $121,658 $126,288 ($4,630) $63,112 Inch Branch $20,276 $128,474 ($108,198) $100,744 Combined $162,210 $38,330 $123,880 $221,392
Following Mr. Graham�s decision guidance, the Robinson Hollow and Inch
Branch Dams proposals should be rejected immediately as both the EB and LB
parameters were negative. For the Toms Branch Dam, the LB was positive if the LCS
parameter was not included, but the EB were negative. Thus, this course of action
should be rejected also. Finally, the combined course of action (rehabilitate all three
dams) yielded a positive EB that was less then the CM. Since the LB was negative, the
computed Cost-per-life saved is approximately $528 million (Graham, 2000).
Graham�s analysis proved to be easily applied to the South River dams situation.
As shown in the results from the South River application, completing the rehabilitation of
just one of the dams would not be a wise investment. What is interesting is that the
NRCS proposal to rehabilitate all three dams will occur at the expense of $528 million for
the amount of lives saved. Likewise, the NRCS computed Benefit-Cost ratios that were
less then one, and thus calculated that project costs would indeed exceed project
benefits. We can conclude that Graham�s method of analysis in this situation is
supported by traditional benefit-cost analysis. This ultimately requires a decision
maker(s) to determine if the cost is worth the added safety measures. Graham would
most likely argue the $528 million is not a wise investment in order to achieve the PMF
standard.
Chapter 6: Linear Programming as an Alternative Analysis Technique 93
6.2 Application of Linear Programming
Obtaining an optimal solution for constrained problems through linear
programming technique is a proven powerful technique. By definition, linear
programming exhibits the following characteristics (Ravindran et al., 1987):
• All decision variables are non-negative. • The desired goal for selecting the optimal solution must be expressed as a linear
function of the decision variables, and is called the objective function. • Constraints are expressed as linear equations or inequalities.
The formulation of the linear program model follows three basic steps, but
requires practice in becoming proficient at application to real problems. The three basic
steps are as follows (Ravindran et al., 1987):
Step 1: Identify the unknown decision variables to be determined, and assign algebraic symbols to represent the variables. Step 2: Identify all known constraints for the given problem, and express them as linear equations or inequalities using the unknown variables. Step 3: Identify the objective function, and represent it as a linear function of the decision variables.
For simple linear programs, the problems can be solved by algebra or by completing row
operations. If numerous constraints or courses of actions are created then an
optimization software program is usually employed. The Solver application contained
within the software program Microsoft Excel is an example of an optimization program.
One application where optimization might have been used was during the
NRCS�s dam rehabilitation design efforts. The selection of the remediation method was
determined from a set of possible solutions. For example there was the �sponsor
breach� course of action, remediation of the dam to pass the PMF course of action, or
even implement a warning system. More specifically, the NRCS design analysis looked
at three specific dam rehabilitation solutions. The NRCS possible solutions included: 1.
Widening the emergency spillway, 2. Raising the height of the dam with a parapet wall,
Chapter 6: Linear Programming as an Alternative Analysis Technique 94
3. Armoring the emergency spillway to resist erosion failure, 4. Combination of the first
three courses of action. The NRCS concluded that the combination of parapet wall and
armoring the emergency spillway was the best recommended course of action. Not
knowing how the NRCS design engineers arrived at this conclusion, the linear
programming technique might have been employed to solve this decision.
The linear programming technique was applied to a hypothetical situation for one
of the South River dams. It is assumed that for the South River dams armoring of the
spillway will need to be completed, whether any action is taken. There is a fixed cost for
armoring the spillway that can be reduced to a unit cost per linear foot of emergency
spillway. The remaining other 3 courses of action remain valid: widening the emergency
spillway, raising the height of the dam, and a combination of the first two. The following
data table would then have to be determined to give a starting point:
Table 6.5: Hypothetical Data for South River Dam Rehabilitation COA 1 COA 2 COA 3
Raise Dam w. Parapet
Wall
Widen the Emergency
Spillway
Combination of Raise &
Widen
Cost per Linear Foot Mod. a1$ b1$ c1$
Increase Q per Linear Foot Mod. a2$ b2$ c2$
Armoring E. Spillway Cost per Linear Foot Mod. a3$ b3$ c3$
Following the linear program formulation steps, step 1 requires identification of
variables for the problem. The above hypothetical data is expressed as a metric by
linear foot of modification. The amount of linear foot modification required for each
course of action is unknown, and therefore becomes logical variables. The variables X1,
X2, and X3 are assigned as unknown variables. For step 2, all constraints on the
problem must be identified and expressed as an equation or inequality. Ideally, the total
cost should equal or be greater then flood reduction benefits to yield a benefit-cost ratio
Chapter 6: Linear Programming as an Alternative Analysis Technique 95
of 1. This sets the first constraint for the problem. The second constraint would be the
increase in discharge, Q which should be greater then or equal to the required Q in order
to pass the PMF. Using the variables the following constraint inequalities are created:
Con1: (A1$ * X1) + (B1$ * X2) + (C1$ * X3) < Flood Reduction Benefits $
Con2: (A2$ * X1) + (B2$ * X2) + (C2$ * X3) > Q, passage of PMF
In order to handle the inequalities, two new variables are introduced, X4 and X5. The X4
and X5 variable represent a large number that when added or subtracted to the function
makes the inequality valid as an equation. This changes Con1 and Con2 to:
Con1: (A1$ * X1) + (B1$ * X2) + (C1$ * X3) - X4 = Flood Reduction Benefits $
Con2: (A2$ * X1) + (B2$ * X2) + (C2$ * X3) + X5 = Q, passage of PMF
To complete Step 3, the objective function must be determined. For this
hypothetical situation, the armoring of the emergency spillway is contingent upon the
width of the emergency spillway. The width of the emergency spillway will vary based
upon the optimal solution, but the goal would be to minimize this cost. Therefore the last
row in Table 6.5 becomes the objective function:
Minimize (Z): (A3$ * X1) + (B3$ * X2) + (C3$ * X3) + 0*X4 + 0*X5
The X4 and X5 variables are also included in the objective function as they were added
into the constraints. They are given a coefficient constant of zero, so as not change the
objective function value.
The final linear program to be solved for the hypothetical South River dam
situation would be:
Minimize (Z): (A3$ * X1) + (B3$ * X2) + (C3$ * X3) + 0*X4 + 0*X5
Subject to:
Con1: (A1$ * X1) + (B1$ * X2) + (C1$ * X3) - X4 = Flood Reduction Benefits $
Con2: (A2$ * X1) + (B2$ * X2) + (C2$ * X3) + X5 = Q, passage of PMF
Chapter 6: Linear Programming as an Alternative Analysis Technique 96
This linear program could then be entered into Excel Solver to determine the optimal
solution values for X1, X2, and X3 that would minimize the Armoring cost. The power of
the linear program technique is that each solution process can be tailored to a given
situation. Thus, the linear programming techniques could be applicable in other areas of
the design process where a best solution analysis is required. The next section shows
how linear programming is used to expand Mr. Graham�s economic analysis.
6.3 Expansion of Alternative Economic Analysis Through Linear Programming
A working model was created by the expansion of Mr. Graham�s economic
analysis approach. The intent was to create a method of reflecting the best of course
action to complete a dam rehabilitation project. Mr. Wayne Graham�s equations were
the basis for which the model was created (Graham, 2000). His published article
included a case study that provided data that was adapted to test the new expansion of
the analysis.
The ultimate goal for the model was to create a linear program that solves a set
of constraints to maximize the Economic Benefits of the proposed remediation project.
As Mr. Graham�s analysis determined, the Economic Benefits should outweigh the
Construction Costs. Coupled with the Economic Benefits is the Life Benefits, which
must be positive in order for a project to be completed. Therefore, the maximization of
economic benefits became the objective function. The model formulation, the test
example, and the final results will be discussed further in the following sections.
6.3.1 Model Formulation
Mr. Graham�s key parameters on which he focuses are the Economic Benefits
(EB) and Life Benefits (LB). The following decision guidance is summarized:
1. If EB and LB are negative, reject project.
2. If 0 < EB < CM and LB is negative, reject project.
Chapter 6: Linear Programming as an Alternative Analysis Technique 97
3. If EB < CM and LB is positive, Compute Cost-per-life saved.
4. If EB > CM and LB is negative, Compute Benefit-per-life lost.
5. If EB > CM and LB is positive, Proceed with project.
The parameter CM represents the construction of cost for the modification of the
existing dam. From the above guidance, the last condition is the most desirable goal in
which a dam owner needs. The dam owners must make a change to the dam in order to
meet the current dam safety restrictions for the type of dam they own. The third and
fourth conditions allow the user to quantify the cost of meeting the safety restrictions by
only partially meeting the fifth condition.
In looking at the fifth condition, the Objective Function logically became to
maximize Economic Benefits (EB):
Objective Function (Z): Maximize EB
The other key part to the fifth condition in the above guidance is the Life Benefits (LB)
must be positive. LB becomes a variable, and by the standard form for linear
programming, all variables must be non-negative.
Constraints for the Objective Function were formulated beginning with the two
key decision variables EB and LB. The first constraint is:
Con1: LS � LM � LC � LB = 0 (1)
Simply stated, life benefits (LB) equal life lost under the status quo (LS), minus life lost
under modification (LM), minus life lost due to construction (LC). The variables LS, LM,
and LC create other constraints, and therefore will be discussed later on.
The second constraint is based upon the Economic Benefits:
Con2: ES � EM � EB = 0 (2)
The Economic Benefits equal the Economic Losses (ES) from the status quo, minus the
Economic Losses (EM) from the modifications. Similarly as with Con1, the additional
variable ES and EM create other constraints to be further discussed.
Chapter 6: Linear Programming as an Alternative Analysis Technique 98
For the variables LS and LM, the loss of life is a function of warning time (WT) and
the number of people at risk (PAR) in the flood plain. As previously discussed, the
BUREC regulation provides guidance for estimating the loss of life (Graham, 1999). The
low and high values for WT are in the situation of where no warning is given or if there
are greater then 90 minutes of WT. In the case of no warning time, the results are
catastrophic and average at 50% loss of life from exposed population. In the case with
greater then 90 minutes of warning, almost all loss of life is avoided, or a 0.2% loss of
life on average. So, WT becomes a constant that is set based upon expected warning
time. However, the PAR remains variable as it depends on the magnitude of the flood in
most cases. So the following constraints were determined:
Con3: LS � WTS x PARS = 0 (3)
Con4: LM � WTM x PARM = 0 (4)
The loss of life due to construction is a function of the construction costs (CM). A
construction life lost constant is determined (CL). This sets the next constraint:
Con5: LC � CL x CM (5)
To get at the variables EM and ES an assumption was made. The value of the
Economic Flood Losses is assumed to be a function of the magnitude of the flood (ie. %
PMF). Therefore, a damage value is estimated for varying flood magnitudes, usually
percentage of the PMF for consistency. Performing a regression on these values, based
on the assumption, the result is an equation for a line. Thus the following constraints
were created:
Con6: -ES + (mS) x (XS) + bS = 0 (6)
Con7: -EM + (mM) x (XM) + bM = 0 (7)
The variables XS and XM represent the percentage of PMF for the status quo and the
modification conditions. The constants mS, bS, mM, and bM are generated from data
and analysis from the status quo and the modification conditions.
Chapter 6: Linear Programming as an Alternative Analysis Technique 99
Similar logic is needed to estimate the people at risk (PAR) variables. As the
magnitude of the flood increases, the PAR should increase. In reality, this is not as
simple as stated because PAR is a function of two factors. The first factor is the
magnitude of the flood that is passed through the dam spillway. In the modification
case, the enlargement of the spillway causes the PAR value to increase due to more
volume of water passed at lower flood conditions. The second factor is the ultimate dam
failure caused by overtopping. As stated above the warning time plays largely into the
amount of people affected also. For simplicity with this linear program formulation, it is
assumed that the above two factors are already calculated to create a single value of
PAR for each flood wave magnitude. Thus a linear regression is performed to give the
following constraints:
Con8: -PARS + (mPARS) x (XS) + bPARS = 0 (8)
Con9: -PARM + (mPARM) x (XM) + bPARM = 0 (9)
The constants mPARS, bPARS, mPARM, and bPARM are generated from data and
analysis from the status quo and the modification conditions.
The next constraint also involved an assumption. The construction cost involves
a certain initial cost to achieve a minimum modification. From that minimum
modification, to achieve the full desired construction result is a function of material and
labor. For example, to raise a dam one foot costs the initial overhead to begin the
project. Each additional foot can be determined largely upon the additional materials
and labor hours required. Again for simplicity, an initial cost is set for the project, and
modification costs are assumed to increase as the percentage of PMF increases. This
set the constraint:
Con10: -CM + (mCM) x (XM) + bCM (10)
The constants mCM and bCM are generated from data and analysis from the status quo
and the modification conditions.
Chapter 6: Linear Programming as an Alternative Analysis Technique 100
One final constraint required was for the variables XS and XM, the percentage of
PMF. These are two variables as they impact differently based upon the comparison of
the status quo versus the modification plan. However, in reality the flood magnitude
would be constant, and thus Xs and Xm must be equal. This leads to the last constraint:
Con11: XS � XM = 0 (11)
In summary the linear program includes the Objective Function, 11 main
constraint equations, and 12 variables. Of course for the standard form, the variables
are assumed to be non-negative which creates an additional 12 constraints. The linear
program is shown below:
Objective Function (Z): Maximize Eb
Subject To: Con1: LS � LM � LC � LB = 0 (1) Con2: ES � EM � EB = 0 (2) Con3: LS � WTS x PARS = 0 (3) Con4: LM � WTM x PARM = 0 (4) Con5: LC � CL x CM (5) Con6: -ES + (mS) x (XS) + bS = 0 (6) Con7: -EM + (mM) x (XM) + bM = 0 (7) Con8: -PARS + (mPARS) x (XS) + bPARS = 0 (8) Con9: -PARM + (mPARM) x (XM) + bPARM = 0 (9) Con10: -CM + (mCM) x (XM) + bCM (10) Con11: XS � XM = 0 (11)
Variables: LS, LM, LC, LB, ES, EM, EB, PARS, PARM, CM, XS, XM > 0
With formulation of a model complete, the next step is to test the model to analyze the
linear program. The next section describes the test model used.
6.3.2 Test Example
Graham (2000) provided a demonstration of the economic analysis. The overall
purpose of his discussion was to show that dam modifications to achieve compliance
with the current dam safety regulations are not a worthy investment. With that objective
in mind, we realize that his example is geared towards demonstrating his purpose.
Chapter 6: Linear Programming as an Alternative Analysis Technique 101
However, his example gave a starting point on putting together a test for the linear
program.
The test example is based on some real data and also assumptions made by Mr.
Graham. The example is a Dam located in Colorado that in 1993 was being considered
for a modification project. A new spillway combined with a nine-foot dam heightening
involved a total cost of $31 million. The new spillway was a 200 foot sill, set 45 feet
below the dam crest. Assuming a worst case expected flow out of that spillway, the
calculated discharge rate is approximately 8,800 cubic feet per second (cfs). That is a
large amount flow that is now allowed to pass through the dam. For this example a
Warning Time (WT) of 0.002 was assumed, and the constant for construction losses
(CL) is 0.014.
In the article example, 100,000 people were assumed to be at risk in the
floodplain, which allowed for the simple warning time adjustment to arrive at a single
value PAR value. A single value was not the desired end-state for the model. So data
was created to replicate the PAR for given percentages of the PMF. Taking the 100,000
PAR, assuming the worse case of complete dam failure at 100% PMF, a value of 50,000
lives lost was estimated for the status quo. From there, the values were scaled back as
the percentage of PMF scaled back. In the modification design, the 100% PMF can now
pass. For this case, assuming no warning time also, a value of 1000 lives lost was
assigned. As for the status quo, the values were scaled back as the percentage of PMF
scaled back. Refer to Appendix C for the full data set, the regression plots, and the
derived line equations. This set the constants mPARs, bPARs, mPARm, and bPARm.
The Economic Damages were compiled for both the status quo and the
modification plan. They were annualized in order to allow for easy comparison, and
compiled in Table 2 of Mr. Graham�s article (Graham, 2000). The Annualized Damages
for the modification plan followed a decreasing trend that is expected. The damages in
Chapter 6: Linear Programming as an Alternative Analysis Technique 102
higher magnitude floods are larger, but occur less frequently. For the status quo, the
damages start downward, but then drastically increase in the 75-100 PMF range. The
cause of this is not explained, but one can infer dam failure must be involved. In order to
demonstrate the linear program, a linear downward trend was assumed to simplify the
issue. For future work, two equations would need to be developed: 1. Damages with
dam intact, and 2. Damages with dam failure.
Additional minimal conditions were needed in order to limit the percentage of
PMF for this test example. The damages begin to incur at certain percentages of the
PMF; therefore, a minimum value for XS and XM was needed. This tailors the
generalized linear program to the realistic data. Otherwise the linear program would
most likely optimize the modification plan at zero percent of the PMF. The whole
purpose for the analysis is consistent in that the status quo dam is not in compliance
with current dam regulations, and the modification must reach some percentage of the
PMF being passed. Refer to Appendix 3 for the data set, plots, and the linear regression
equations for the Economic Damages. This data set the values for the constants mS,
bS, mM, and bM.
The final data part needed was the construction cost data. The annualized
yearly construction costs were $1.55 million. An annualized fixed cost of 500,000 was
assumed. This represents a fixed cost that must be overcome to make any modification.
Data points were then generated for the other percentages of PMFs such that the 100%
PMF equaled the total cost of $1.55 million. Refer to Appendix C for the data set, plots,
and the linear regression equations for the Construction Costs. This data set the values
for the constants mCM and bCM.
With the test example set up, the model was then entered into Excel Solver to
run the Model. A total of six different runs were completed in order to demonstrate the
Chapter 6: Linear Programming as an Alternative Analysis Technique 103
capabilities of the linear program, as well as test different conditions. The next section
explains the results.
6.3.3 Results from Simulation Runs
The linear program formulated above for the test example was inputted into
Excel Solver. Refer to Appendix C for the original model, and the model outputs. Six
different runs are summarized in Table 6.6:
Table 6.6: Summary of Results Eb Lb Xs/Xm Feasible
Run # ($) (+ or 0) (%) Solution 1 N/A N/A N/A Not Feasible 2 N/A N/A N/A Not Feasible 3 239750 + (11) 0 Feasible 4 239750 + (39) 25 Feasible 5 239750 + (39) 25 Feasible 6 239750 0 25 Feasible
The first run was the first set of derived conditions loosely based up the test
example from Graham (2000). As expected, there was not a feasible solution found for
the model. This follows Graham�s purpose that completing modifications to dam
spillways are usually not practical. The second run simply switched the Economic
Damages from the two conditions, thus creating a situation where the Damages from the
modification are much less then the status quo. This run also proved to be infeasible as
the construction costs were much too large to overcome.
The third run eliminated the construction costs, thus pushing the model to select
the modification course of action. For this case, the Economic Damages are better
under the Modification Plan, and the cost of the Modification Plan is zero. As expected,
a feasible solution was found. The Economic Value was maximized, Life Benefits were
positive, but the Flood magnitude was zero. To account for the fact that a minimum
Chapter 6: Linear Programming as an Alternative Analysis Technique 104
value for the flood is required, Xs was set at 25%. The model was rerun, and a feasible
solution was found. Interestingly, the magnitude of the Life Benefits increased.
To further test the sensitivity of the model, the fifth and sixth runs set the People
at Risk for the modification plan to zero, and then both PARs at zero. This creates a
situation where the modification plan produces less economic damages and does not
increase the PAR parameter. As expected feasible solutions were found for both of
these runs, and this concluded the sensitivity analysis performed on the new model.
6.3.4 Discussion of New Linear Program Technique
The formulated linear program is an expansion of Graham�s work. The model
was an attempt to apply his technique to more realistic conditions. The model is more
complicated then Graham�s, however simplifying assumptions may prove to be
ineffective when applied to a real case study. The damage curves could be more
complicated, and thus assuming a linear regression equation may introduce
unacceptable error. Also, the uncertainty at arriving at the values for the Flood
Damages and People at Risk creates new areas where this model may not be effective,
or at least may need to be adjusted. These complexities were overcome by making
assumptions in order to create a test example for the model. However since every dam
situation is different, specific analysis must be performed anyways that arguable would
lead to results similar to the assumptions that we made.
The overall goal for the linear program was met in that the economic benefit (EB)
was maximized. The new model was applied to a test situation in which data was
generated from Mr. Graham�s example. Varying the warning time should cause the
model to yield different results, and so becomes a key value that must be selected.
Using the BUREC�s method for estimating the PAR relies heavily on the warning time
prior to the catastrophic event. A modification plan that included a highly reliable warning
Chapter 6: Linear Programming as an Alternative Analysis Technique 105
detection system, coupled with a systematic notification process can drastically
decrease the loss of life caused by major flooding or even dam failure. With warning
system in place the PAR parameter would be reduced, which will increase the
possibilities of achieving positive life benefits (LB).
6.4 Summary
This chapter brings forth two alternative analyses for dam rehabilitation: Mr.
Graham�s economic analysis and linear programming techniques. Both analyses are
meant to be used as supplemental tools that would augment the traditional rehabilitation
analysis presented in Chapter 4. Graham�s analysis, although founded upon criticism of
the PMF design standard, proved to be effective when applied to the South River dams.
Results from the applied analysis showed that the recommended dam rehabilitations of
the three South River dams should not be completed, and the NRCS economic analyses
yielded benefit-cost ratios of less then one. Yet the fact that NRCS went forward with
the recommendation to complete the rehabilitation demonstrates that other
circumstances can factor into the decision to proceed with a project, and that these
analyses are only decision making tools.
The extension of Graham�s analysis through the use of linear programming is a
new concept that needs further testing for real situations. The South River case study
was not a good match for the initial conditions. All three of the dams are classified as
high risk, and so the NRCS design and economic analysis was never intended to reach
a lower design standard than passing the PMF. Consequently, the available economic
data was limited to the 500 year flood, and the breach failure. If we assume the breach
failure occurs at the known percentage of the PMF for the dams (55%, 60%, & 50% for
Robinson Hollow, Toms Branch, and Inch Branch respectively), then we could fit a trend
line from the 500 damages to the damages at the dam failure. This linear function might
Chapter 6: Linear Programming as an Alternative Analysis Technique 106
sufficiently represent the damages, but the best result would be to route the flood waves
for percentages of the PMF and calculate the expected damages.
A similar discussion could be repeated for the expected lives lost from the same
flood waves. Hence, based upon the available data from the South River dams,
significant assumptions would have to have been made in order for the proposed
extension analysis to be applied. These broad assumptions would be similar to the ones
made for Graham�s test example, and so would still remain as a theoretical approach.
The next logical step to validate the extended analysis would be to apply the approach to
a real case study of a �significant� classified dam in need of dam rehabilitation.
Chapter 7: Summary, Conclusions, and Recommendations 107
Chapter 7: Summary, Conclusions, and Recommendations
7.1 Summary
In order to comment on the completion of this thesis, the following original goals
were presented in Chapter 1 as a desired end state:
1. Develop a standard protocol to assist dam owners in performing decision
analysis for dam rehabilitation for dams that are out of safety compliance.
2. Develop a method to prioritize courses of actions for dam remediation.
The 12 step traditional approach discussed in Chapter 4 is the recommended standard
protocol that will assist dam owners in performing decision analysis. This method is by
no means easy or rapid. In fact, it is usually quite the opposite. Even though the process
introduces some �art� in an otherwise scientific approach, the method produces credible
results that can be weighted significantly in making an informed decision.
The continual advancement in GIS and mathematically based simulation models
in analysis areas of hydrology, hydraulics, economics, and optimization has opened the
way for automation in assessing the feasibility of dam rehabilitation. However, as shown
in Chapter 5, the existing programs have many limitations and are concluded to be
inferior to the traditional approach. There certainly is potential gain from employing
existing analysis programs, but at this time these should only augment the traditional
approach.
As for the second goal, the traditional approach to economic analysis also sets
the priority for courses of action. The incremental economic analysis by definition
analyzes the incremental gain or loss between two courses of action. Thus, the courses
of action can easily be ranked based upon the incremental analysis. Linear
programming as shown in Chapter 6 can also be an effective way to prioritize courses of
action. An additional feature of linear programming is that sensitivity analyses can be
Chapter 7: Summary, Conclusions, and Recommendations 108
performed on the recommended course of action by adjusting the constraints for the
given problem.
The Chapter 3 HEC-HMS modeling work performed on the South River
watershed represents the necessary hydrologic analysis that is critical to the economic
assessment of dam rehabilitation. The model work was performed to establish the
impact of the flood control dams on the city of Waynesboro, Virginia. This separate goal
was also achieved, in that the local impacts as well as the down stream impacts were
represented in the modeling results. These results were acknowledged by the
Headwaters Soil & Water Conservation District as being extremely effective in
demonstrating the importance of the flood control dams for the city of Waynesboro.
The HEC-HMS model could be further refined as a future project. The large
scale averaging on certain model input parameters made during the calibration of the
model may prove to be grossly inaccurate at sub-watershed level. For example, the
variations in observed rainfall depth in comparison to location were not well addressed.
Applying a rainfall distribution to the rainfall gage data, and checking against recorded
NEXRAD imagery could enhance the calibration of the model. Additionally, the
watershed parameters can also be spatially distributed using GIS applications. An
interesting question might arise: �By distributing the watershed parameters, are the
model results closer to the observed flows then what was created by the current model?�
Finally, the proposed extension of Graham�s economic analysis through linear
programming is at best a theoretical approach. The application needs further testing on
real examples where dam rehabilitation is being looked at for significant classified dams.
The data requirements may not be attainable without personally performing data
calculations. This problem arises because the economic analyses might not always be
incremented by percentages of the PMF. This might force unwanted assumptions to be
Chapter 7: Summary, Conclusions, and Recommendations 109
made in order for the analysis approach to work, which could detract from the credibility
of the method.
7.2 Conclusions
The following compiled comments represent sequential conclusions presented in
earlier chapters:
• The 12 agricultural flood control dams in the South River watershed effectively
reduce flood events in the immediate localized area below the dams.
• The flood reduction effects of the dams diminish significantly with distance down
stream, and therefore partially impact flooding in Waynesboro, Virginia.
• The upper South River dams effectively meet the original SCS intent of
protecting agricultural lands in the watershed.
• The traditional step-by-step economic process to perform a dam rehabilitation
analysis is one way of completing the necessary economic analysis for a project
proposal.
• The traditional economic analysis is time and resource intensive, and
incorporates several professional disciplines such as engineering and economics.
• The HAZUS-MH model was demonstrated as not versatile enough to perform
dam rehabilitation analysis, nor was the model ever meant to perform such an
analysis.
• The HAZUS-MH model is a GIS application, and therefore does have potential to
assist with defining an initial flood inundation zone as a starting point.
• The HAZUS-MH model achieves semi-automation at the expense of accuracy in
results.
Chapter 7: Summary, Conclusions, and Recommendations 110
• The application of linear programming has demonstrated that linear programming
can be used to enhance a dam rehabilitation analysis through establishing an
optimal solution.
• The expanded Graham�s analysis potentially could assist a rehabilitation analysis
to establish an optimal solution that is less then full PMF, and thus reduce
construction costs.
7.3 Recommendations
The passage of the PMF versus a percentage of the PMF as a dam safety
standard discussion remains a critical issue for a large portion of existing dams. In the
situation of Significant and Low risk classified dams, the passage of the full PMF is not
always required. However, what is required in most cases is an engineering/economic
analysis demonstrating that passage of the percentage of the PMF meets established
safety criteria, and that increasing to the full PMF does not decrease flood damages. A
way of solving such a problem is through an iterative method of designing the structure,
routing the flood wave, and calculating damages for each percentage of PMF increment.
This approach, like the presented traditional economic analysis in Chapter 4 is time and
resource intensive.
The alternative linear programming technique potentially could reduce the time
and effort of the rigorous iterative approach. The solution of the linear program
immediately arrives at the optimal solution, assuming the established constraints
accurately represent the real situation. Validation of the linear program method might
prove to be a very useful technique for dam owners. To accomplish the validation,
several case study dams would be required, preferably not in the same watershed. The
case study dams would need to be Significant or Low risk dams that must be
rehabilitated to meet a certain PMF passage standard.
Chapter 7: Summary, Conclusions, and Recommendations 111
Validation of the linear program could be accomplished using the case study
dams by first completing the rehabilitation analysis through the rigorous iterative
approach. While completing the more traditional approach, the required economic data
will be gathered that could then be used for the alternative linear programming method.
The linear program parameters discussed in Chapter 6 will be obtained from the reduced
economic data. Finally, a comparison of the results from the traditional method versus
the linear programming technique could be made.
Assuming the alternative linear programming technique proved valid for the case
study dams classified as Significant and Low risk, then the question arises: �Are there
High risk dams where a percentage of the PMF may prove to be the optimal solution?�
This question remains the essential one in the argument put forth in Graham (2000).
The new approach may prove to be a justification for requesting an exception to the full
PMF passage requirement on certain qualified dams. Such an exception would reduce
the rehabilitation costs of certain dams, and potentially allow for other aging dams to
also be rehabilitated.
Bibliography 112
Bibliography
American Society of Civil Engineers (2005). "ASCE�s Report Card for America's Infrastructure.� American Society of Civil Engineers, New York, New York. ASCE Task Committee on Spillway Design Flood Selection (1988). "Evaluation Procedures for Hydrologic Safety of Dams." American Society of Civil Engineers, New York, New York. B. A., and H. BAI (2001). "Physically-Based Modeling of Life Safety Considerations in Water Resource Decision-Making." Word Water Conference 2001. Bass, R. P. (2003). "Improving the Safety of Our Dam Infrastructure - RCC Makes the Grade." World Water Congress 2003. Bass, R. P. (2001) "Rehabilitating Dams with Roller Compacted Concrete." World Water Congress 2001. Bowles, D. S., and McClelland, D. M. (2002). "Estimating Life Loss for Dam Safety Risk Assessment -- A Review and New Approach." IWR Report 02-R-3, Institute for Water Resources, U.S. Army Corps of Engineers, Alexandria, VA. Center for Research in Water Resources (2001). ArcGIS Hydro Data Model (Draft), University of Texas, Austin, Texas. Cyganiewicz, J., Dise, K., Hincliff, D., Mayer, D., Muller, B., and Hovenden, C. (2001). "Risk Based Profiling System." U.S. Bureau of Reclamation, Denver, CO. DeKay, M. L., & McClelland, G. H. (1991). "Setting decision thresholds for dam failure warnings: A practical theory-based approach." Tech. Rep. No. 328, Center for Research on Judgment and Policy, University of Colorado, Boulder, CO. Faulkner, D., and Bliss Michael A. (2006). "Personal Interview on NRCS Economic Analysis on South River Dams." Richmond, VA. Frankel, T. C., and Rowden, T. (2005). "Family Survives a Wall of Water." December 15, 2005, St. Louis Dispatch, St Louis, MO. Franzini, J. B., Freyberg, D. L., Linsley, R. K., and Tchobanoglous, G. (1964). Water-Resources Engineering, McGraw-Hill, Inc., New York. Graham, W. J. (1999). A Procedure for Estimating Loss of Life Caused by Dam Failure, Bureau of Reclamation, Dam Safety Office, Denver, Colorado. Graham, W. J. (2000). "Should Dams Be Modified for the Probable Maximum Flood?" Journal of the American Water Resources Association, 36(5), 953-963. Harrison, J. P. (2000). "PMPs Never Happen - or Do They?" Schnabel Engineering Inc. Harrison, J. P., and Paxson, G. P. (2003). "Ballpark PMFs." Schnabel Engineering Inc. Heath, D. C., Stedinger, J. R., and Thompson, K. (1996). "Risk Analysis for Dam Safety: Hydrologic Risk." IWR Report 96-R-13, Institute for Water Resources, U.S. Army Corps of Engineers, Alexandria, VA.
Bibliography 113
Hydrologic Engineering Center (1998). HEC-FDA, Flood Damage Reduction Analysis, User's Manual, U.S. Army Corps of Engineers, Davis, CA. Hydrologic Engineering Center (2002). HEC-GeoRAS, an Extension for support of HEC-RAS using Arc-View, User's Manual, U.S. Army Corps of Engineers, Davis, CA. Hydrologic Engineering Center (2003). Geospatial Hydrologic Model Extension HEC-GeoHMS, User's Manual, U.S. Army Corps of Engineers, Davis, CA. Interagency Committee on Dam Safety (2004a). "Federal Guidelines for Dam Safety: Selecting and Accommodating Inflow Design Floods for Dams." FEMA 94, Federal Emergency Management Agency, Washington, D.C. Interagency Committee on Dam Safety (2004b). "Federal Guidelines for Dam Safety: Hazard Potential Classification System for Dams." FEMA 333, Federal Emergency Management Agency, Washington, D.C. Lave, L. B., and Resendiz-Carrilo, D. (1990a). "Evaluating Dam Safety Retrofits with Uncertain Benefits: The Case of Mohawk Dam (Walhonding River, Ohio)." Water Resources Research, 26(5), 1093-1098. Lave, L. B., Resendiz-Carrilo, D., and McMichael, F. C. (1990b). "Safety Goals for High-Hazard Dams: Are Dams Too Safe?" Water Resources Research, 26(7), 1383-1391. Longley, P. A., Goodchild, M. F., Maguire, D. J., and Rhind, D. W. (2005). Geographic Information Systems and Science, John Wiley & Sons, Ltd, West Sussex, England. Lund, J. R. (2002). "Floodplain Planning with Risk-based Optimization." Journal of Water Resources Planning and Management, 127(3), 202-207. Mays, L. W. (2001). Water Resources Engineering, John Wiley & Sons, Inc., New York. McCuen, R. H. (2005). Hydrologic Analysis and Design, Prentice Hall, Upper Saddle River, New Jersey. National Institute of Building Sciences (2003a). HAZUS Multi-Hazard MR1 Technical Manual, Federal Emergency Management Agency, Washington, D.C. National Institute of Building Sciences (2003b). HAZUS Multi-hazard MR1 User Manual, Federal Emergency Management Agency, Washington, D.C. National Research Council (1983). Safety of Existing Dams: Evaluation and Improvement / Committee on the Safety of Existing Dams, National Academy Press, Washington, D.C. National Research Council (1985). Safety of Dams / Flood and Earthquake Criteria, National Academy Press, Washington, D.C. National Resources Conservation Service (2005). "Supplemental Watershed Plan-Environmental Assessment for the South River Watershed." U.S. Department of Agriculture, Richmond, VA. Null, S., and Lund, J. R. (2005). "Re-Assembling Hetch Hetchy: Water Supply Implications of Removing O'Shaugnessy Dam." Journal of the American Water Resources Association. Obermeyer, J. R., and Johson, D. L. (2003). "RCC Construction for Dam Rehabilitation." , United States Society on Dams, Denver, CO.
Bibliography 114
Poindexter, J. (2005). "Neighborhood will lose popular lake." Roanoke Times, Roanoke, VA. Peterson, J. W. (2004). "Rehabilitating Aging Earthen Dams: Recent United States Experience." International Conference on Geosynthetics and Geoenvironmental Engineering 2004, Bombay, India. Public Law 114 (2000). "Grain Standards and Warehouse Improvement Act of 2000." 114 Stat. 2058. Public Law 83-566 (1954). "The Watershed Protection and Flood Prevention Act." 68 Stat. 666. Ravindran, A., Phillips, D. T., and Solberg, J. J. (1987). Operations Research: Principles and Practices, John Wiley & Sons, New York, New York Scharffenburg, W. A., and Fleming, M. J. (2005). " Hydrologic Modeling System, HEC-HMS User's Manual." CPD-74A, Institute of Water Resources, U.S. Army Corps of Engineers, Davis, CA. Soil Conservation Service (1974). "Flood Hazard Analyses South River." U.S. Department of Agriculture, Richmond, VA. U.S. Army Corps of Engineers (2004). General Design and Construction Considerations for Earth and Rock-Fill Dams, Department of the Army, Washington, DC 20314 U.S. Army Corps of Engineers (1982). Report of the Chief of Engineers to the Secretary of the Army on the National Program of Inspection of Non-Federal Dams, Dept. of the Army, Office of the Chief of Engineers, Washington, D.C. U.S. Society on Dams (2003). "White Paper on Dam Safety Risk Assessment: What Is It? Who�s Using It and Why? Where Should We Be Going With It?" United States Society on Dams, Denver, CO. Virginia Department of Conservation & Recreation (2004). "Virginia Impounding Structures Regulation (Dam Safety)." (§ 4 VAC 50-20), Division of Dam Safety and Floodplain Management, Richmond, VA. Water Resources Council (1983). "Economic and Environmental Principles and Guidelines for Water and Related Land Resources Implementation Studies." , Washington, D.C. Whiteaker, T. L., Robayo, O., Maidment, D. R., and Obenour, D. (2006). "From a NEXRAD Rainfall Map to a Flood Inundation Map." Journal of Hydrologic Engineering, 11(1), 37-45.
Appendix A: HEC-HMS Data
Appendix A: HEC-HMS Data 115
Table A.1: South River Watershed Sub-Area Data
South River Watershed
Sub Area
Drainage Area
SCS Curve #
Initial Infiltr. T conc.
Reach Length
Elev Drop
Reach
Reach Channel
Slope (#) (Sq Mi) (#) (in) (hr) (ft) (ft) (ft/ft) 1 3.41 66 1.030 1.51 - - - 2 2.72 66 1.030 1.41 - - - 3 0.42 66 1.030 0.55 4050 48 0.012 4 3.61 66 1.030 1.54 - - - 5 1.67 68 0.941 0.91 14200 66 0.005 6 3.14 65 1.077 1.40 - - - 7 0.66 66 1.030 1.20 10000 66 0.007 8 0.71 67 0.985 0.99 6400 55 0.009 9 0.99 66 1.030 1.63 - - - 10 2.91 65 1.077 0.98 - - - 11 0.52 65 1.077 1.10 5200 40 0.008 12 2.61 65 1.077 1.77 14000 160 0.011 13 4.23 65 1.077 1.35 - - - 14 0.77 65 1.077 1.17 5200 120 0.023 15 0.68 66 1.030 0.89 5300 36 0.007 16 0.67 67 0.985 0.81 6400 24 0.004 17 2.27 61 1.279 1.27 - - - 18 0.30 66 1.030 0.80 2100 60 0.029 19 0.45 66 1.030 0.49 3400 14 0.004 20 3.43 65 1.077 1.81 - - -
21a 2.70 68 0.941 1.51 10700 39 0.004 21b 3000 8 0.003 22 2.85 65 1.077 1.66 - - - 23 2.79 65 1.077 1.16 - - - 24 1.65 65 1.077 2.02 - - - 25 1.04 66 1.030 1.34 5100 61 0.012 26 0.10 66 1.030 0.53 4500 17.5 0.004 27 0.97 68 0.941 1.36 - - - 28 1.29 69 0.899 0.91 1000 0.5 0.001
29a 3.61 69 0.899 1.26 7000 4.8 0.001 29b 1400 0.2 0.0001 30 3.30 65 1.077 1.75 - - - 31 0.94 65 1.077 0.71 - - - 32 1.15 66 1.030 1.39 12100 239 0.020 33 2.48 65 1.077 1.07 - - - 34 3.66 67 0.985 1.57 20500 438.8 0.021 35 0.82 67 0.985 0.83 4400 2 0.0005 36 1.42 65 1.077 1.16 - - - 37 1.03 66 1.030 1.46 7900 121 0.015 38 0.74 67 0.985 0.77 4800 6 0.001 39 2.85 65 1.077 1.90 - - - 40 0.76 67 0.985 1.08 4200 47 0.011
Appendix A: HEC-HMS Data
Appendix A: HEC-HMS Data 116
Table A.1 (cont.): South River Watershed Sub-Area Data
South River Watershed
Sub Area
Drainage Area
SCS Curve #
Initial Infiltr. T conc.
Reach Length
Elev Drop
Reach
Reach Channel
Slope (#) (Sq Mi) (#) (in) (hr) (ft) (ft) (ft/ft) 41 1.60 67 0.985 1.15 7300 7 0.001 42 1.17 67 0.985 0.82 - - - 43 2.46 67 0.985 1.73 13200 10 0.001 44 2.03 67 0.985 0.91 - - - 45 0.52 67 0.985 0.89 7700 11 0.001 46 2.76 65 1.077 1.04 - - - 47 2.20 65 1.077 0.88 10000 180 0.018 48 2.85 61 1.279 1.63 - - - 49 1.31 65 1.077 0.56 6000 71 0.012 50 1.16 65 1.077 0.76 9100 99 0.011 51 4.40 65 1.077 1.28 16600 238 0.014 52 2.19 65 1.077 1.16 - - - 53 4.56 61 1.279 1.31 - - - 54 1.16 65 1.077 0.88 1900 78 0.041 55 0.83 66 1.030 1.19 8100 56 0.007 56 1.58 65 1.077 1.04 - - - 57 3.70 65 1.077 1.45 - - - 58 1.10 65 1.077 1.25 18900 416 0.022 59 1.64 67 0.985 2.04 10600 65 0.006 60 1.13 65 1.077 0.58 - - - 61 0.69 66 1.030 0.53 5900 159 0.027 62 1.60 66 1.030 1.20 4900 25 0.005 63 2.35 66 1.030 0.97 - - - 64 0.54 66 1.030 0.39 4600 70 0.015 65 2.38 67 0.985 1.04 - - - 66 0.07 67 0.985 0.28 1600 23 0.014 67 0.56 66 1.030 0.47 3900 44 0.011 68 1.42 69 0.899 2.05 7800 31 0.004 69 3.59 68 0.941 1.25 12600 27 0.002
Totals 125.87 65.85507
Appendix A: HEC-HMS Data
Appendix A: HEC-HMS Data 117
Table A.2: South River Manning's n Values
South River Manning's n Values
Section Description
Main Channel
n
Left Bank
n
Right Bank
n 419 Right after Canada Run SA38 0.069 0.053 0.053 420 Before RR in SA 38 0.069 0.078 0.060 421 After RR in SA 38 0.069 0.078 0.060 422 SA 38 0.076 0.050 0.050 430 SA 45, Right Before SR 664 0.072 0.103 0.090 431 SA 45, Right After SR 664 0.072 0.103 0.090 432 SA 45, Just beyond SR 664 0.072 0.103 0.102 433 SA 45, 2000 feet beyond SR 664 0.072 0.087 0.078 434 SA 69, Just Beyond Back Creek 0.076 0.050 0.052 435 SA 69, Just Before SR 650 0.070 0.075 0.078 436 SA 69, Middle of SR 650 0.070 0.075 0.078 437 SA 69, After SR 650 0.070 0.075 0.078 438 SA 69, Near TBM 18 0.073 0.078 0.063
Averages 0.072 0.078 0.072
Table A.3: Back Creek Manning's n Values
Back Creek Manning's n Values
Section Description Main
Channel n Left
Bank n Right
Bank n 310 SA 51 0.068 0.075 0.078 311 SA 55 0.070 0.078 0.070 312 SA 55, SR 610 0.066 0.070 0.078 313 SA 59, Near TBM 213 0.066 0.050 0.060 314 SA 59, Further Down 0.066 0.078 0.050 315 SA 59, Before End 0.066 0.050 0.075 316 SA 61, Beginning 0.066 0.050 0.050 317 SA 61, 0.066 0.050 0.050 318 SA 67 0.066 0.052 0.083 320 SA 68 at SR 624 0.066 0.060 0.063 323 SA 68 at RR 0.073 0.070 0.070
Averages 0.067 0.062 0.066
Appendix A: HEC-HMS Data
Appendix A: HEC-HMS Data 118
Table A.4: South River Cross Section Data Reach Number: 1 Reach Number: 2 Reach Number: 3 Streambed Elevation: 1633 Streambed Elevation: 1585 Streambed Elevation: 1585 Bottom Width: 5 Bottom Width: 5 Bottom Width: 5 Dist Elevation Dist Elevation Dist Elevation Station 1 0 1644 Station 1 0 1596 Station 1 0 1596 Station 2 50 1639 Station 2 50 1591 Station 2 50 1591 Station 3 150 1638 Station 3 150 1590 Station 3 150 1590 Station 4 152 1633 Station 4 152 1585 Station 4 152 1585 Station 5 157 1633 Station 5 157 1585 Station 5 157 1585 Station 6 159 1638 Station 6 159 1590 Station 6 159 1590 Station 7 259 1639 Station 7 259 1591 Station 7 259 1591 Station 8 309 1644 Station 8 309 1596 Station 8 309 1596
Reach Number: 4 Reach Number: 5 Reach Number: 6 Streambed Elevation: 1519 Streambed Elevation: 1700 Streambed Elevation: 1660 Bottom Width: 7 Bottom Width: 5 Bottom Width: 6 Dist Elevation Dist Elevation Dist Elevation Station 1 0 1530 Station 1 0 1711 Station 1 0 1671 Station 2 50 1525 Station 2 50 1706 Station 2 50 1666 Station 3 150 1524 Station 3 150 1705 Station 3 150 1665 Station 4 152 1519 Station 4 152 1700 Station 4 152 1660 Station 5 159 1519 Station 5 157 1700 Station 5 158 1660 Station 6 161 1524 Station 6 159 1705 Station 6 160 1665 Station 7 261 1525 Station 7 259 1706 Station 7 260 1666 Station 8 311 1530 Station 8 309 1711 Station 8 310 1671
Reach Number: 7 Reach Number: 8 Reach Number: 9 Streambed Elevation: 1620 Streambed Elevation: 1500 Streambed Elevation: 1464 Bottom Width: 5 Bottom Width: 7 Bottom Width: 10 Dist Elevation Dist Elevation Dist Elevation Station 1 0 1631 Station 1 0 1511 Station 1 0 1475 Station 2 50 1626 Station 2 50 1506 Station 2 50 1470 Station 3 150 1625 Station 3 150 1505 Station 3 150 1469 Station 4 152 1620 Station 4 152 1500 Station 4 152 1464 Station 5 157 1620 Station 5 159 1500 Station 5 162 1464 Station 6 159 1625 Station 6 161 1505 Station 6 164 1469 Station 7 259 1626 Station 7 261 1506 Station 7 264 1470 Station 8 309 1631 Station 8 311 1511 Station 8 314 1475
Reach Number: 10 Reach Number: 11 Reach Number: 12 Streambed Elevation: 1500 Streambed Elevation: 1440 Streambed Elevation: 1426 Bottom Width: 6 Bottom Width: 10 Bottom Width: 11 Dist Elevation Dist Elevation Dist Elevation Station 1 0 1511 Station 1 0 1451 Station 1 0 1437 Station 2 50 1506 Station 2 50 1446 Station 2 50 1432 Station 3 150 1505 Station 3 150 1445 Station 3 150 1431 Station 4 152 1500 Station 4 152 1440 Station 4 152 1426 Station 5 158 1500 Station 5 162 1440 Station 5 163 1426 Station 6 160 1505 Station 6 164 1445 Station 6 165 1431 Station 7 260 1506 Station 7 264 1446 Station 7 265 1432 Station 8 310 1511 Station 8 314 1451 Station 8 315 1437
Appendix A: HEC-HMS Data
Appendix A: HEC-HMS Data 119
Table A.4 (cont.): South River Cross Section Data Reach Number: 13 Reach Number: 14 Reach Number: 15 Streambed Elevation: 1387 Streambed Elevation: 1440 Streambed Elevation: 1379 Bottom Width: 11 Bottom Width: 7 Bottom Width: 12 Dist Elevation Dist Elevation Dist Elevation Station 1 0 1398 Station 1 0 1451 Station 1 0 1390 Station 2 50 1393 Station 2 50 1446 Station 2 50 1385 Station 3 150 1392 Station 3 150 1445 Station 3 150 1384 Station 4 152 1387 Station 4 152 1440 Station 4 152 1379 Station 5 163 1387 Station 5 159 1440 Station 5 164 1379 Station 6 165 1392 Station 6 161 1445 Station 6 166 1384 Station 7 265 1393 Station 7 261 1446 Station 7 266 1385 Station 8 315 1398 Station 8 311 1451 Station 8 316 1390
Reach Number: 16 Reach Number: 17 Reach Number: 18 Streambed Elevation: 1367 Streambed Elevation: 1366 Streambed Elevation: 1361 Bottom Width: 12 Bottom Width: 12 Bottom Width: 12 Dist Elevation Dist Elevation Dist Elevation Station 1 0 1378 Station 1 0 1377 Station 1 0 1372 Station 2 50 1373 Station 2 50 1372 Station 2 50 1367 Station 3 150 1372 Station 3 150 1371 Station 3 150 1366 Station 4 152 1367 Station 4 152 1366 Station 4 152 1361 Station 5 164 1367 Station 5 164 1366 Station 5 164 1361 Station 6 166 1372 Station 6 166 1371 Station 6 166 1366 Station 7 266 1373 Station 7 266 1372 Station 7 266 1367 Station 8 316 1378 Station 8 316 1377 Station 8 316 1372
Reach Number: 19 Reach Number: 20 Reach Number: 21 Streambed Elevation: 1600 Streambed Elevation: 1800 Streambed Elevation: 1361 Bottom Width: 7 Bottom Width: 7 Bottom Width: 13 Dist Elevation Dist Elevation Dist Elevation Station 1 0 1611 Station 1 0 1811 Station 1 0 1372 Station 2 50 1606 Station 2 50 1806 Station 2 50 1367 Station 3 150 1605 Station 3 150 1805 Station 3 150 1366 Station 4 152 1600 Station 4 152 1800 Station 4 152 1361 Station 5 159 1600 Station 5 159 1800 Station 5 165 1361 Station 6 161 1605 Station 6 161 1805 Station 6 167 1366 Station 7 261 1606 Station 7 261 1806 Station 7 267 1367 Station 8 311 1611 Station 8 311 1811 Station 8 317 1372
Reach Number: 22 Reach Number: 23 Reach Number: 24 Streambed Elevation: 1480 Streambed Elevation: 1359 Streambed Elevation: 1400 Bottom Width: 5 Bottom Width: 15 Bottom Width: 5 Dist Elevation Dist Elevation Dist Elevation Station 1 0 1491 Station 1 0 1370 Station 1 0 1411 Station 2 50 1486 Station 2 50 1365 Station 2 50 1406 Station 3 150 1485 Station 3 150 1364 Station 3 150 1405 Station 4 152 1480 Station 4 152 1359 Station 4 152 1400 Station 5 157 1480 Station 5 167 1359 Station 5 157 1400 Station 6 159 1485 Station 6 169 1364 Station 6 159 1405 Station 7 259 1486 Station 7 269 1365 Station 7 259 1406 Station 8 309 1491 Station 8 319 1370 Station 8 309 1411
Appendix A: HEC-HMS Data
Appendix A: HEC-HMS Data 120
Table A.4 (cont.): South River Cross Section Data Reach Number: 25 Reach Number: 26 Reach Number: 27 Streambed Elevation: 1353 Streambed Elevation: 1346 Streambed Elevation: 1400 Bottom Width: 20 Bottom Width: 25 Bottom Width: 30 Dist Elevation Dist Elevation Dist Elevation Station 1 0 1364 Station 1 0 1357 Station 1 0 1411 Station 2 50 1359 Station 2 50 1352 Station 2 50 1406 Station 3 150 1358 Station 3 150 1351 Station 3 150 1405 Station 4 152 1353 Station 4 152 1346 Station 4 152 1400 Station 5 172 1353 Station 5 177 1346 Station 5 182 1400 Station 6 174 1358 Station 6 179 1351 Station 6 184 1405 Station 7 274 1359 Station 7 279 1352 Station 7 284 1406 Station 8 324 1364 Station 8 329 1357 Station 8 334 1411
Reach Number: 28 Reach Number: 29 Reach Number: 30 Streambed Elevation: 1920 Streambed Elevation: 1910 Streambed Elevation: 1839 Bottom Width: 5 Bottom Width: 5 Bottom Width: 5 Dist Elevation Dist Elevation Dist Elevation Station 1 0 1931 Station 1 0 1921 Station 1 0 1850 Station 2 50 1926 Station 2 50 1916 Station 2 50 1845 Station 3 150 1925 Station 3 150 1915 Station 3 150 1844 Station 4 152 1920 Station 4 152 1910 Station 4 152 1839 Station 5 157 1920 Station 5 157 1910 Station 5 157 1839 Station 6 159 1925 Station 6 159 1915 Station 6 159 1844 Station 7 259 1926 Station 7 259 1916 Station 7 259 1845 Station 8 309 1931 Station 8 309 1921 Station 8 309 1850
Reach Number: 31 Reach Number: 32 Reach Number: 33 Streambed Elevation: 1740 Streambed Elevation: 1580 Streambed Elevation: 1502 Bottom Width: 7 Bottom Width: 5 Bottom Width: 10 Dist Elevation Dist Elevation Dist Elevation Station 1 0 1751 Station 1 0 1591 Station 1 0 1513 Station 2 50 1746 Station 2 50 1586 Station 2 50 1508 Station 3 150 1745 Station 3 150 1585 Station 3 150 1507 Station 4 152 1740 Station 4 152 1580 Station 4 152 1502 Station 5 159 1740 Station 5 157 1580 Station 5 162 1502 Station 6 161 1745 Station 6 159 1585 Station 6 164 1507 Station 7 261 1746 Station 7 259 1586 Station 7 264 1508 Station 8 311 1751 Station 8 309 1591 Station 8 314 1513
Reach Number: 34 Reach Number: 35 Reach Number: 36 Streambed Elevation: 1862 Streambed Elevation: 1446 Streambed Elevation: 1540 Bottom Width: 5 Bottom Width: 15 Bottom Width: 5 Dist Elevation Dist Elevation Dist Elevation Station 1 0 1873 Station 1 0 1457 Station 1 0 1551 Station 2 50 1868 Station 2 50 1452 Station 2 50 1546 Station 3 150 1867 Station 3 150 1451 Station 3 150 1545 Station 4 152 1862 Station 4 152 1446 Station 4 152 1540 Station 5 157 1862 Station 5 167 1446 Station 5 157 1540 Station 6 159 1867 Station 6 169 1451 Station 6 159 1545 Station 7 259 1868 Station 7 269 1452 Station 7 259 1546 Station 8 309 1873 Station 8 319 1457 Station 8 309 1551
Appendix A: HEC-HMS Data
Appendix A: HEC-HMS Data 121
Table A.4 (cont.): South River Cross Section Data Reach Number: 37 Reach Number: 38 Reach Number: 39 Streambed Elevation: 1381 Streambed Elevation: 1470 Streambed Elevation: 1423 Bottom Width: 20 Bottom Width: 5 Bottom Width: 5 Dist Elevation Dist Elevation Dist Elevation Station 1 0 1392 Station 1 0 1481 Station 1 0 1434 Station 2 50 1387 Station 2 50 1476 Station 2 50 1429 Station 3 150 1386 Station 3 150 1475 Station 3 150 1428 Station 4 152 1381 Station 4 152 1470 Station 4 152 1423 Station 5 172 1381 Station 5 157 1470 Station 5 157 1423 Station 6 174 1386 Station 6 159 1475 Station 6 159 1428 Station 7 274 1387 Station 7 259 1476 Station 7 259 1429 Station 8 324 1392 Station 8 309 1481 Station 8 309 1434
Reach Number: 40 Reach Number: 41 Reach Number: 42 Streambed Elevation: 1400 Streambed Elevation: 1356 Streambed Elevation: 1325 Bottom Width: 15 Bottom Width: 30 Bottom Width: 40 Dist Elevation Dist Elevation Dist Elevation Station 1 0 1411 Station 1 0 1367 Station 1 0 1336 Station 2 50 1406 Station 2 50 1362 Station 2 50 1331 Station 3 150 1405 Station 3 150 1361 Station 3 150 1330 Station 4 152 1400 Station 4 152 1356 Station 4 152 1325 Station 5 167 1400 Station 5 182 1356 Station 5 192 1325 Station 6 169 1405 Station 6 184 1361 Station 6 194 1330 Station 7 269 1406 Station 7 284 1362 Station 7 294 1331 Station 8 319 1411 Station 8 334 1367 Station 8 344 1336
Appendix A: HEC-HMS Data
Appendix A: HEC-HMS Data 122
Table A.5: Rating Table Data
Poor Creek Rating Table
Lofton Lake Rating Table
Appendix A: HEC-HMS Data
Appendix A: HEC-HMS Data 123
Table A.5 (Cont.): Rating Table Data
Stoney Creek Rating Table
Lake Wilda Rating Table
Appendix A: HEC-HMS Data
Appendix A: HEC-HMS Data 124
Table A.5 (Cont.:) Rating Table Data
Canada Run Rating Table
Waynesboro Nursery Rating Table
Appendix A: HEC-HMS Data
Appendix A: HEC-HMS Data 125
Table A.5 (Cont.): Rating Table Data
Inch Branch Rating Table
Toms Branch Rating Table
Appendix A: HEC-HMS Data
Appendix A: HEC-HMS Data 126
Table A.5 (Cont.): Rating Table Data
Robinson Hollow Rating Table
Happy Hollow Rating Table
Appendix A: HEC-HMS Data
Appendix A: HEC-HMS Data 127
Table A.5 (Cont.): Rating Table Data
Mills Creek Rating Table
Upper Sherando Rating Table
App
endi
x A
: HEC
-HM
S D
ata
Appe
ndix
A: H
EC-H
MS
Dat
a
12
8
Ta
ble
A.6:
IFL
OW
S R
ainf
all D
ata
Hur
rican
e Is
abel
, Sep
tem
ber,
2003
ID #
10
:00
10:1
5 10
:30
10:4
5 11
:00
11:1
5 11
:30
11:4
5 12
:00
12:1
5 12
:30
12:4
5 13
:00
13:1
5 13
:30
13:4
5
Tota
l To
ms
Bra
nch
1200
0
0 0
0.04
0
0.12
0.
04
0 0
0.04
0
0 0
0 0
0.04
0.28
Sh
eran
do
1201
0
0 0
0 0
0.04
0.
04
0.04
0
0 0
0 0
0 0.
04
0.04
0.2
Rob
inso
n H
ollo
w
1202
0
0 0
0 0.
04
0.08
0
0 0.
04
0 0
0 0
0.04
0.
04
0
0.24
St
oney
Cre
ek
1207
0
0 0
0 0
0.08
0.
04
0 0
0 0.
12
0 0
0 0
0
0.24
U
pper
She
rand
o 12
40
0 0
0 0
0 0.
08
0.04
0
0.04
0
0.04
0
0 0.
04
0.12
0
0.
36
Mill
s C
reek
12
48
0 0
0 0
0 0.
08
0.04
0
0.04
0
0 0
0 0.
04
0.08
0
0.
28
ID
#
14:0
0 14
:15
14:3
0 14
:45
15:0
0 15
:15
15:3
0 15
:45
16:0
0 16
:15
16:3
0 16
:45
17:0
0 17
:15
17:3
0 17
:45
To
tal
Tom
s B
ranc
h 12
00
0.04
0.
08
0.12
0.
04
0.12
0.
16
0.16
0.
16
0.28
0.
16
0.16
0.
04
0.04
0.
04
0.16
0.
08
2.
12
Sher
ando
12
01
0.04
0.
04
0.08
0.
08
0.12
0.
12
0.12
0.
16
0.16
0.
24
0.24
0.
2 0.
28
0.2
0.12
0.
12
2.
52
Rob
inso
n H
ollo
w
1202
0
0 0.
16
0.12
0.
12
0.24
0.
24
0 0.
2 0.
32
0.32
0.
12
0.08
0.
08
0.2
0.08
2.52
St
oney
Cre
ek
1207
0
0.08
0
0 0.
28
0.08
0.
08
0 0.
12
0.12
0.
36
0.16
0.
04
0.08
0.
32
0.16
2.12
U
pper
She
rand
o 12
40
0.12
0.
24
0.24
0.
24
0.13
0.
35
0.35
0
0.58
0.
87
0.87
0.
28
0.15
0.
16
0.6
0.28
5.82
M
ills
Cre
ek
1248
0
0.08
0.
2 0.
08
0.04
0.
24
0.24
0
0.32
0.
4 0.
4 0.
16
0.16
0.
12
0.12
0.
16
3
ID
#
18:0
0 18
:15
18:3
0 18
:45
19:0
0 19
:15
19:3
0 19
:45
20:0
0 20
:15
20:3
0 20
:45
21:0
0 21
:15
21:3
0 21
:45
To
tal
Tom
s B
ranc
h 12
00
0.1
0.1
0 0
0.08
0.
2 0.
12
0.04
0.
12
0.12
0.
12
0.12
0.
12
0.2
0.2
0.2
3.
96
Sher
ando
12
01
0.08
0.
16
0.16
0.
08
0.12
0.
12
0.16
0.
04
0.18
0.
18
0.12
0.
12
0.18
0.
18
0.2
0.2
4.
8 R
obin
son
Hol
low
12
02
0.08
0.
2 0.
12
0 0.
12
0.12
0.
16
0 0.
24
0.2
0.12
0.
1 0.
1 0.
24
0.16
0.
16
4.
64
Ston
ey C
reek
12
07
0.08
0.
08
0 0.
08
0.08
0.
08
0.2
0.04
0.
2 0.
2 0.
12
0.16
0.
2 0.
2 0.
14
0.14
4.12
U
pper
She
rand
o 12
40
0.64
0.
5 0.
35
0.35
0.
55
0.55
0.
71
0 0.
75
0.75
0.
71
0.47
0.
9 0.
9 0.
44
0.44
14.8
3 M
ills
Cre
ek
1248
0.
18
0.3
0.16
0.
08
0.12
0.
12
0.28
0.
04
0.43
0.
25
0.16
0.
3 0.
25
0.25
0.
16
0.16
6.24
ID #
22
:00
22:1
5 22
:30
22:4
5 23
:00
23:1
5 23
:30
23:4
5 0:
00
0:15
0:
30
0:45
1:
00
1:15
1:
30
1:45
Tota
l To
ms
Bra
nch
1200
0.
34
0.34
0.
24
0.2
0.2
0.2
0.08
0.
08
0.27
0.
25
0.24
0.
12
0.16
0.
16
0.08
0
6.
92
Sher
ando
12
01
0.32
0.
4 0.
16
0.2
0.16
0.
12
0.16
0.
16
0.23
0.
25
0.16
0.
08
0.2
0.16
0.
12
0
7.68
R
obin
son
Hol
low
12
02
0.4
0.4
0.28
0.
16
0.04
0.
12
0.12
0.
08
0.08
0.
2 0.
12
0.08
0.
14
0.18
0.
04
0
7.08
St
oney
Cre
ek
1207
0.
3 0.
3 0.
2 0.
2 0.
27
0.2
0.2
0.2
0.2
0.12
0.
08
0.08
0.
06
0.06
0
0
6.59
U
pper
She
rand
o 12
40
0.9
0.9
0.56
0.
55
0.34
0.
36
0.14
0.
14
0.29
0.
47
0.24
0.
04
0.18
0.
14
0.04
0
20
.12
Mill
s C
reek
12
48
0.31
0.
37
0.44
0.
16
0.2
0.2
0.08
0.
08
0.26
0.
26
0.12
0.
08
0.1
0.1
0.04
0
9.
04
App
endi
x A
: HEC
-HM
S D
ata
Appe
ndix
A: H
EC-H
MS
Dat
a
12
9
Tabl
e A.
6 (c
ont.)
: IF
LOW
S R
ainf
all D
ata
H
urric
ane
Isab
el, S
epte
mbe
r, 20
03 (c
ont.)
ID #
2:
00
2:15
2:
30
2:45
3:
00
3:15
3:
30
3:45
4:
00
Tota
l Sh
eran
do
1201
0.
24
0.12
0.
12
0.12
0.
08
0.08
0
0 0
0 0
0 0
0 0
0
8.44
ID #
11
:00
12:0
0 13
:00
14:0
0 15
:00
16:0
0 17
:00
18:0
0 19
:00
20:0
0 21
:00
22:0
0 23
:00
0:00
1:
00
2:00
3:
00
To
ms
Bra
nch
1200
0.
04
0.16
0.
04
0.04
0.
24
0.44
0.
56
0.32
0.
2 0.
44
0.36
0.
6 0.
92
0.56
0.
72
0.32
0
Sh
eran
do
1201
0
0.12
0
0.08
0.
24
0.52
0.
84
0.68
0.
52
0.44
0.
52
0.56
0.
84
0.6
0.56
0.
44
0.48
Rob
inso
n H
ollo
w
1202
0.
04
0.08
0
0.08
0.
24
0.6
0.72
0.
44
0.4
0.4
0.48
0.
6 0.
76
0.64
0.
4 0.
36
0.04
Ston
ey C
reek
12
07
0 0.
12
0.12
0
0.08
0.
44
0.6
0.6
0.24
0.
4 0.
36
0.68
0.
76
0.87
0.
36
0.12
0
U
pper
She
rand
o 12
40
0 0.
12
0.04
0.
16
0.72
0.
83
2.09
1.
19
1.84
1.
81
2.01
2.
05
2.08
0.
98
0.8
0.28
0
M
ills
Cre
ek
1248
0
0.12
0
0.12
0.
32
0.52
0.
96
0.56
0.
72
0.56
0.
72
0.84
1
0.56
0.
52
0.2
0.04
ID
#
4:00
5:
00
Tota
l
Tom
s B
ranc
h 12
00
0 0.
08
6.04
Sher
ando
12
01
0.16
0
7.6
R
obin
son
Hol
low
12
02
0.04
0
6.32
Ston
ey C
reek
12
07
0.04
0
5.79
Upp
er S
hera
ndo
1240
0.
08
0 17
.08
M
ills
Cre
ek
1248
0.
04
0 7.
8
M
ean
6.71
App
endi
x A
: HEC
-HM
S D
ata
Appe
ndix
A: H
EC-H
MS
Dat
a
13
0
Ta
ble
A.6
(con
t.): I
FLO
WS
Rai
nfal
l Dat
a
Hur
rican
e Je
anne
, Sep
tem
ber,
2004
ID #
14
:00
14:1
5 14
:30
14:4
5 15
:00
15:1
5 15
:30
15:4
5 16
:00
16:1
5 16
:30
16:4
5 17
:00
17:1
5 17
:30
17:4
5
Tota
l To
ms
Bra
nch
1200
0
0 0
0 0
0 0
0 0.
01
0.01
0.
01
0.01
0
0 0
0
0.04
Sh
eran
do
1201
0
0 0
0 0
0 0
0 0.
02
0.02
0
0 0
0.02
0.
02
0
0.08
R
obin
son
Hol
low
12
02
0 0
0 0
0 0
0 0
0.02
0.
02
0 0
0.02
0.
02
0 0
0.
08
Ston
ey C
reek
12
07
0 0
0 0
0 0
0 0
0.02
0.
02
0 0
0 0
0 0
0.
04
Upp
er S
hera
ndo
1240
0
0 0
0 0
0.02
0.
02
0.04
0.
04
0.04
0.
04
0 0
0.02
0.
02
0
0.24
M
ills
Cre
ek
1248
0
0 0
0 0.
02
0.02
0
0 0.
02
0.02
0
0 0
0 0
0
0.08
ID #
18
:00
18:1
5 18
:30
18:4
5 19
:00
19:1
5 19
:30
19:4
5 20
:00
20:1
5 20
:30
20:4
5 21
:00
21:1
5 21
:30
21:4
5
Tota
l To
ms
Bra
nch
1200
0
0 0
0 0
0 0
0 0.
02
0.02
0
0 0
0 0
0
0.08
Sh
eran
do
1201
0
0 0
0 0
0.02
0.
02
0 0
0 0
0 0.
02
0.02
0
0
0.16
R
obin
son
Hol
low
12
02
0.02
0.
02
0.02
0.
02
0 0
0 0
0.02
0.
02
0 0
0 0
0 0
0.
2 St
oney
Cre
ek
1207
0
0.02
0.
02
0 0
0 0
0 0.
02
0.04
0.
02
0 0
0 0
0
0.16
U
pper
She
rand
o 12
40
0.02
0.
02
0.02
0.
02
0 0
0 0
0 0
0 0
0 0
0 0
0.
32
Mill
s C
reek
12
48
0 0.
02
0.02
0
0 0
0 0
0.02
0.
02
0 0
0 0
0 0
0.
16
ID
#
22:0
0 22
:15
22:3
0 22
:45
23:0
0 23
:15
23:3
0 23
:45
0:00
0:
15
0:30
0:
45
1:00
1:
15
1:30
1:
45
To
tal
Tom
s B
ranc
h 12
00
0 0
0 0
0.02
0.
02
0 0
0 0
0 0
0 0
0 0
0.
12
Sher
ando
12
01
0 0
0 0
0 0.
02
0.02
0
0 0
0 0
0.02
0.
02
0 0
0.
24
Rob
inso
n H
ollo
w
1202
0
0 0.
02
0.02
0
0 0
0 0
0 0.
02
0.02
0.
04
0.04
0
0
0.36
St
oney
Cre
ek
1207
0
0 0
0 0
0 0
0 0.
02
0.02
0
0 0
0 0
0
0.2
Upp
er S
hera
ndo
1240
0
0 0
0 0
0 0
0 0.
04
0.04
0
0 0
0 0.
02
0.02
0.44
M
ills
Cre
ek
1248
0
0 0
0 0.
02
0.02
0
0 0
0 0
0 0.
02
0.02
0
0
0.24
App
endi
x A
: HEC
-HM
S D
ata
Appe
ndix
A: H
EC-H
MS
Dat
a
13
1
Tabl
e A.
6 (c
ont.)
: IFL
OW
S R
ainf
all D
ata
Hur
rican
e Je
anne
, Sep
tem
ber,
2004
(Con
t.)
ID
#
2:00
2:
15
2:30
2:
45
3:00
3:
15
3:30
3:
45
4:00
4:
15
4:30
4:
45
5:00
5:
15
5:30
5:
45
To
tal
Tom
s B
ranc
h 12
00
0.02
0.
02
0 0
0.16
0.
1 0.
1 0.
04
0 0
0 0
0.04
0.
08
0.08
0.
04
0.
8 Sh
eran
do
1201
0
0 0
0 0.
12
0.04
0.
04
0.08
0
0 0
0 0.
02
0.06
0.
12
0.08
0.8
Rob
inso
n H
ollo
w
1202
0.
06
0.06
0.
04
0 0.
08
0.1
0.1
0.08
0.
04
0.02
0.
02
0 0
0.08
0.
08
0.04
1.16
St
oney
Cre
ek
1207
0.
02
0.02
0
0 0.
1 0.
1 0
0 0
0 0
0 0.
08
0.08
0.
04
0
0.64
U
pper
She
rand
o 12
40
0 0
0 0.
1 0.
14
0.02
0.
02
0 0
0 0
0 0.
18
0.15
0.
15
0.04
1.24
M
ills
Cre
ek
1248
0
0.02
0.
02
0.06
0.
06
0.04
0.
04
0.04
0
0 0
0 0.
04
0.06
0.
06
0.04
0.72
ID #
6:
00
6:15
6:
30
6:45
7:
00
7:15
7:
30
7:45
8:
00
8:15
8:
30
8:45
9:
00
9:15
9:
30
9:45
Tota
l To
ms
Bra
nch
1200
0.
08
0.08
0.
04
0 0.
16
0.2
0.08
0.
38
0.41
0.
16
0.16
0.
04
0.06
0.
1 0.
04
0
2.79
Sh
eran
do
1201
0.
04
0.04
0.
04
0 0.
18
0.2
0.06
0.
21
0.15
0.
15
0.28
0.
12
0.04
0.
04
0.08
0.
08
2.
51
Rob
inso
n H
ollo
w
1202
0.
04
0.04
0.
08
0.08
0.
2 0.
3 0.
06
0.18
0.
29
0.28
0.
28
0.08
0.
14
0.18
0.
04
0
3.43
St
oney
Cre
ek
1207
0.
04
0.04
0
0 0.
08
0.08
0.
08
0.1
0.18
0.
1 0.
14
0.08
0
0 0
0
1.56
U
pper
She
rand
o 12
40
0.08
0.
08
0.08
0.
04
0.16
0.
2 0.
11
0.4
0.4
0.4
0.28
0.
04
0.04
0.
08
0.08
0
3.
71
Mill
s C
reek
12
48
0.06
0.
06
0.04
0
0.08
0.
08
0.08
0.
1 0.
06
0.06
0.
06
0.04
0.
06
0.02
0.
04
0
1.56
ID #
10
:00
10:1
5 10
:30
10:4
5 11
:00
11:1
5 11
:30
11:4
5 12
:00
12:1
5 12
:30
12:4
5 13
:00
13:1
5 13
:30
13:4
5
Tota
l To
ms
Bra
nch
1200
0.
02
0.02
0.
02
0.02
0.
57
0.41
0.
41
0.35
0.
37
0.33
0.
33
0.04
0.
08
0.04
0.
04
0
5.84
Sh
eran
do
1201
0
0 0
0 0.
57
0.37
0.
37
0.39
0.
5 0.
4 0.
4 0.
04
0.1
0.1
0.04
0
5.
79
Rob
inso
n H
ollo
w
1202
0.
04
0.04
0.
04
0.04
0.
33
0.43
0.
43
0.47
0.
34
0.4
0.4
0.08
0.
08
0.08
0
0
6.63
St
oney
Cre
ek
1207
0.
03
0.03
0.
03
0.03
0.
06
0.14
0.
1 0.
1 0.
06
0.25
0.
25
0.08
0.
02
0.06
0.
04
0
2.84
U
pper
She
rand
o 12
40
0.06
0.
06
0.06
0.
06
0.28
0.
35
0.36
0.
55
0.41
0.
35
0.35
0.
12
0.04
0.
02
0.02
0
6.
8 M
ills
Cre
ek
1248
0.
01
0.01
0.
01
0.01
0.
24
0.06
0.
06
0.08
0.
16
0.08
0.
08
0.04
0.
1 0.
08
0.06
0
2.
64
App
endi
x A
: HEC
-HM
S D
ata
Appe
ndix
A: H
EC-H
MS
Dat
a
13
2
Tabl
e A.
6 (c
ont.)
: IF
LOW
S R
ainf
all D
ata
Hur
rican
e Fr
ance
s, S
epte
mbe
r, 20
04
ID
#
5:00
5:
15
5:30
5:
45
6:00
6:
15
6:30
6:
45
7:00
7:
15
7:30
7:
45
8:00
8:
15
8:30
8:
45
To
tal
Tom
s B
ranc
h 12
00
0.08
0.
04
0.04
0.
08
0.04
0.
02
0.02
0.
04
0.08
0.
04
0.04
0.
16
0.28
0.
2 0.
2 0.
12
1.
48
Sher
ando
12
01
0
Rob
inso
n H
ollo
w
1202
0.
04
0.02
0.
02
0.1
0.1
0.1
0.1
0.12
0.
18
0.18
0.
2 0.
08
0.57
0.
5 0.
47
0.35
3.13
St
oney
Cre
ek
1207
0
0 0
0.06
0.
06
0.06
0.
06
0.08
0.
06
0.06
0.
08
0 0.
22
0.22
0.
32
0.2
1.
48
Upp
er S
hera
ndo
1240
0.
06
0.06
0.
04
0.12
0.
12
0.08
0.
08
0.04
0.
3 0.
3 0.
24
0 0.
7 0.
84
1.1
0.71
4.79
M
ills
Cre
ek
1248
0.
04
0.02
0.
02
0.04
0.
04
0.04
0.
04
0.04
0.
14
0.14
0.
16
0 0.
32
0.32
0.
44
0.32
2.12
ID #
9:
00
9:15
9:
30
9:45
10
:00
10:1
5 10
:30
10:4
5 11
:00
11:1
5 11
:30
11:4
5 12
:00
12:1
5 12
:30
12:4
5
Tota
l To
ms
Bra
nch
1200
0.
2 0.
32
0.24
0.
12
0.06
0.
06
0 0
0.24
0.
24
0.12
0.
04
0.02
0.
02
0 0
3.
16
Sher
ando
12
01
0
Rob
inso
n H
ollo
w
1202
0.
3 0.
29
0.08
0
0.06
0.
06
0 0
0.3
0.3
0.28
0.
04
0.06
0.
06
0 0
4.
96
Ston
ey C
reek
12
07
0.1
0.1
0.04
0
0.04
0.
04
0 0
0.02
0.
02
0 0
0.02
0.
02
0 0
1.
88
Upp
er S
hera
ndo
1240
0.
3 0.
42
0.24
0.
12
0.12
0.
12
0.12
0
0.1
0.1
0.08
0.
08
0 0
0 0
6.
59
Mill
s C
reek
12
48
0.3
0.26
0.
04
0 0.
04
0.04
0.
04
0 0.
2 0.
2 0.
2 0.
04
0 0
0 0
3.
48
ID
#
13:0
0 13
:15
13:3
0 13
:45
14:0
0 14
:15
14:3
0 14
:45
15:0
0 15
:15
15:3
0 15
:45
16:0
0 16
:15
16:3
0 16
:45
To
tal
Tom
s B
ranc
h 12
00
0.02
0.
02
0 0
0 0
0 0.
04
0.04
0.
04
0.04
0
0.16
0.
16
0.28
0.
12
4.
08
Sher
ando
12
01
0
Rob
inso
n H
ollo
w
1202
0.
06
0.06
0
0 0.
04
0.04
0
0.18
0.
18
0.12
0.
12
0 0.
2 0.
2 0.
4 0.
28
6.
84
Ston
ey C
reek
12
07
0.02
0.
02
0 0
0.02
0.
02
0 0
0.16
0.
16
0 0
0.16
0.
16
0.16
0.
16
2.
92
Upp
er S
hera
ndo
1240
0
0 0
0 0
0 0
0 0.
08
0.08
0.
04
0 0.
44
0.5
0.86
0.
39
8.
98
Mill
s C
reek
12
48
0 0
0 0
0 0
0 0
0.04
0.
04
0 0
0.25
0.
27
0.28
0.
2
4.56
ID #
17
:00
17:1
5 17
:30
17:4
5 18
:00
18:1
5 18
:30
18:4
5 19
:00
19:1
5 19
:30
19:4
5 20
:00
20:1
5 20
:30
20:4
5
Tota
l To
ms
Bra
nch
1200
0.
1 0.
1 0
0 0.
04
0.04
0.
08
0.08
0.
2 0.
2 0
0 0
0 0
0
4.92
Sh
eran
do
1201
0 R
obin
son
Hol
low
12
02
0.18
0.
17
0 0
0 0
0.2
0.2
0.2
0.11
0.
08
0 0
0 0
0
7.98
St
oney
Cre
ek
1207
0
0 0
0 0.
24
0.24
0.
48
0.2
0.4
0 0
0 0
0 0
0
4.48
U
pper
She
rand
o 12
40
0 0
0 0
0.14
0.
14
0.28
0.
28
0.04
0.
04
0 0
0 0
0 0
9.
9 M
ills
Cre
ek
1248
0.
02
0.02
0
0 0.
06
0.06
0.
12
0.12
0.
02
0.02
0
0 0
0 0
0
5
App
endi
x A
: HEC
-HM
S D
ata
Appe
ndix
A: H
EC-H
MS
Dat
a
13
3
Tabl
e A.
6 (c
ont.)
: IF
LOW
S R
ainf
all D
ata
N
ovem
ber 2
9, 2
005
Stor
m
ID
#
18:0
0 19
:00
20:0
0 21
:00
22:0
0 23
:00
0:00
1:
00
2:00
3:
00
4:00
5:
00
6:00
7:
00
8:00
9:
00
To
tal
Tom
s B
ranc
h 12
00
0 0.
04
0 0
0.04
0.
12
0.24
0.
2 0.
4 0.
2 0.
28
0.12
0.
08
0.04
0.
2 0.
4
2.36
Sh
eran
do
1201
0
0 0.
08
0 0.
04
0.08
0.
16
0.08
0.
24
0.12
0.
16
0.12
0.
16
0.08
0.
24
0.4
1.
96
Rob
inso
n H
ollo
w
1202
0
0.04
0.
04
0 0
0.04
0.
12
0.12
0.
32
0.16
0.
16
0.08
0.
08
0.04
0.
12
0.32
1.64
St
oney
Cre
ek
1207
0
0 0.
04
0 0.
04
0 0
0 0.
04
0 0
0 0.
04
0 0.
04
0.04
0.24
U
pper
She
rand
o 12
40
0 0
0 0.
04
0.08
0.
28
0.36
0.
32
0.84
0.
48
0.28
0.
36
0.24
0.
2 0.
52
0.56
4.56
M
ills
Cre
ek
1248
0
0.08
0.
04
0 0.
04
0.08
0.
16
0.16
0.
28
0.16
0.
24
0.12
0.
16
0.08
0.
24
0.4
2.
24
ID
#
10:0
0 11
:00
12:0
0 13
:00
14:0
0 15
:00
16:0
0 17
:00
18:0
0 19
:00
20:0
0
To
tal
Tom
s B
ranc
h 12
00
0.28
0.
24
0.24
0.
36
0.68
0.
12
0.08
0.
12
0.12
0
0
4.
6 Sh
eran
do
1201
0.
32
0.4
0.28
0.
24
1.1
0.12
0.
08
0.12
0.
16
0.04
0
4.82
R
obin
son
Hol
low
12
02
0.28
0.
2 0.
12
0.24
0.
79
0.2
0.12
0.
04
0.16
0
0
3.
79
Ston
ey C
reek
12
07
0.04
0
0.08
0.
04
0.44
0.
08
0 0.
04
0.16
0
0
1.
12
Upp
er S
hera
ndo
1240
0.
24
0.04
0.
16
0.08
0.
16
0.12
0.
08
0.24
0
0 0
5.68
M
ills
Cre
ek
1248
0.
4 0.
36
0.36
0.
36
0.91
0.
04
0.16
0.
36
0.12
0
0
5.
31
App
endi
x A
: HEC
-HM
S D
ata
Appe
ndix
A: H
EC-H
MS
Dat
a
13
4
Ta
ble
A.7:
Hur
rican
e Is
abel
Hig
h W
ater
Mar
ks
App
endi
x A
: HEC
-HM
S D
ata
Appe
ndix
A: H
EC-H
MS
Dat
a
13
5
Tabl
e A.
7 (C
ont.)
Hur
rican
e Is
abel
Hig
h W
ater
Mar
ks
App
endi
x B
: Sou
th R
iver
Mod
el O
utpu
t Dat
a
Appe
ndix
B: S
outh
Riv
er M
odel
Out
put D
ata
136
Tabl
e B
.1:
Sim
ulat
ion
Out
put,
CN
= 6
5
C
N =
65
Dis
char
ge in
cfs
; Dam
s Pr
esen
t D
isch
arge
in c
fs; w
ith o
ut D
ams
Pres
ent
# D
ata
Poin
t Q
2 Q
10
Q50
Q
100
Q50
0 Q
2 Q
10
Q50
Q
100
Q50
0 1
Poo
r Cre
ek D
am
42
52
59
62
520
247
748
1521
19
34
3095
2
Junc
tion
3 86
2 25
25
5177
66
05
1075
0 10
64
3210
66
12
8420
13
754
3 Lo
fton
Lake
Dam
52
60
67
70
40
1 28
7 88
7 18
10
2302
36
73
4 S
tone
y C
reek
Dam
49
59
67
70
57
7 33
3 10
07
2049
26
06
4169
5
Junc
tion
4 12
85
3442
69
26
9140
15
109
1682
58
23
1221
6 15
740
2589
8 6
Wild
a La
ke D
am
48
57
65
68
427
188
565
1162
14
81
2376
7
Junc
tion
9 13
21
3541
70
89
9290
15
444
1756
61
08
1291
2 16
555
2775
5 8
Junc
tion
14
1599
47
43
1044
3 13
825
2408
6 20
80
7287
16
522
2159
7 36
832
9 C
anad
a R
un D
am
43
48
59
176
772
124
377
769
978
1562
10
W
ayne
sbor
o N
urse
ry D
am
39
48
57
60
398
186
547
1115
14
20
2273
11
Ju
nctio
n 23
17
97
5683
13
257
1774
1 32
327
2265
80
19
1896
0 25
272
4459
0 12
Ju
nctio
n 26
18
59
5956
13
778
1849
4 33
672
2314
81
44
1918
2 25
727
4513
0 13
U
pper
She
rand
o D
am
84
99
115
121
537
200
617
1253
15
94
2565
14
Ju
nctio
n 29
67
6 20
34
4498
59
16
9731
71
3 21
48
4647
60
98
1025
5 15
To
ms
Cre
ek D
am
46
55
63
66
470
378
1134
23
33
2975
47
73
16
Mills
Cre
ek D
am
79
83
89
92
1021
28
0 83
7 17
16
2187
35
05
17
Hap
py H
ollo
w D
am
33
55
61
64
73
152
484
992
1262
20
16
18
Junc
tion
36
1445
42
33
9929
13
117
2181
4 18
85
5651
13
743
1816
2 30
178
19
Rob
inso
n H
ollo
w
44
51
58
60
262
234
721
1469
18
67
2978
20
In
ch B
ranc
h 44
51
57
60
14
6 23
2 71
7 14
67
1867
29
81
21
Junc
tion
38
1564
45
48
1059
2 13
695
2296
2 21
45
6540
16
050
2098
8 35
572
22
Junc
tion
42
2651
80
77
1887
9 25
653
4684
7 31
30
1119
5 27
022
3639
6 66
305
App
endi
x B
: Sou
th R
iver
Mod
el O
utpu
t Dat
a
Appe
ndix
B: S
outh
Riv
er M
odel
Out
put D
ata
137
Tabl
e B
.2:
Sim
ulat
ion
Out
put,
CN
= 6
0
C
N =
60
Dis
char
ge in
cfs
; Dam
s Pr
esen
t D
isch
arge
in c
fs; w
ith o
ut D
ams
Pres
ent
# D
ata
Poin
t Q
2 Q
10
Q50
Q
100
Q50
0 Q
2 Q
10
Q50
Q
100
Q50
0 1
Poo
r Cre
ek D
am
40
49
57
60
298
157
561
1247
16
27
2712
2
Junc
tion
3 55
3 19
12
4209
55
37
9424
64
7 24
07
5386
70
73
1206
2 3
Lofto
n La
ke D
am
50
58
65
68
219
177
662
1483
19
35
3226
4
Sto
ney
Cre
ek D
am
46
56
65
68
320
211
755
1680
21
91
3653
5
Junc
tion
4 82
1 27
33
5681
74
18
1319
4 11
13
4312
99
04
1306
9 22
652
6 W
ilda
Lake
Dam
46
54
63
66
24
2 11
8 42
4 94
7 12
40
2081
7
Junc
tion
9 86
4 28
02
5806
76
05
1342
5 11
22
4427
10
434
1385
7 24
125
8 Ju
nctio
n 14
10
65
3686
83
66
1127
8 20
717
1318
52
86
1321
0 17
786
3182
9 9
Can
ada
Run
Dam
38
46
54
80
55
8 78
28
2 63
0 82
2 13
72
10
Way
nesb
oro
Nur
sery
Dam
37
46
54
58
24
7 11
9 41
2 91
3 11
92
1993
11
Ju
nctio
n 23
12
24
4254
10
484
1438
2 27
221
1484
57
81
1509
3 20
525
3826
0 12
Ju
nctio
n 26
12
76
4419
10
908
1499
4 28
392
1526
58
98
1524
4 20
918
3870
8 13
U
pper
She
rand
o D
am
81
95
111
117
299
132
464
1028
13
40
2241
14
Ju
nctio
n 29
42
3 14
30
3673
48
72
8490
46
8 15
15
3794
49
98
8882
15
To
ms
Cre
ek D
am
44
53
61
64
259
236
850
1903
24
91
4179
16
M
ills C
reek
Dam
78
82
87
90
61
9 17
7 62
7 14
02
1833
30
70
17
Hap
py H
ollo
w D
am
20
53
59
62
70
90
358
811
1060
17
70
18
Junc
tion
36
951
3107
78
58
1073
6 18
946
1335
40
93
1101
0 14
805
2688
8 19
R
obin
son
Hol
low
42
49
56
58
15
2 14
4 53
8 12
04
1570
26
16
20
Inch
Bra
nch
43
49
55
58
63
144
534
1200
15
68
2616
21
Ju
nctio
n 38
10
82
3345
84
34
1147
4 20
195
1491
47
83
1266
3 17
245
3065
0 22
Ju
nctio
n 42
18
34
6063
14
789
2060
0 39
145
2036
80
75
2128
4 29
410
5584
6
App
endi
x B
: Sou
th R
iver
Mod
el O
utpu
t Dat
a
Appe
ndix
B: S
outh
Riv
er M
odel
Out
put D
ata
138
Tabl
e B
.3:
Sim
ulat
ion
Res
ults
, CN
= 5
5
C
N =
55
Dis
char
ge in
cfs
; Dam
s Pr
esen
t D
isch
arge
in c
fs; w
ith o
ut D
ams
Pres
ent
# D
ata
Poin
t Q
2 Q
10
Q50
Q
100
Q50
0 Q
2 Q
10
Q50
Q
100
Q50
0 1
Poo
r Cre
ek D
am
37
46
55
58
153
78
376
957
1297
22
98
2 Ju
nctio
n 3
306
1304
32
59
4384
79
35
322
1628
41
36
5606
10
165
3 Lo
fton
Lake
Dam
48
55
63
66
72
84
43
7 11
35
1540
27
34
4 S
tone
y C
reek
Dam
43
53
62
65
77
10
5 50
6 12
90
1746
30
95
5 Ju
nctio
n 4
479
1879
44
16
5918
11
043
519
2933
75
63
1032
3 18
876
6 W
ilda
Lake
Dam
42
51
60
63
10
5 58
28
6 72
1 98
2 17
55
7 Ju
nctio
n 9
514
1951
44
95
6050
11
043
567
2980
79
23
1088
6 20
311
8 Ju
nctio
n 14
65
2 25
14
6275
87
53
1699
7 75
6 35
41
9791
13
853
2643
4 9
Can
ada
Run
Dam
21
45
51
55
31
8 38
18
8 48
3 65
5 11
62
10
Way
nesb
oro
Nur
sery
Dam
34
43
52
55
12
5 62
28
1 70
1 94
9 16
85
11
Junc
tion
23
783
2878
78
38
1100
4 22
095
845
3799
11
133
1580
3 31
523
12
Junc
tion
26
791
2993
81
87
1150
4 23
110
868
3863
11
273
1600
8 31
983
13
Upp
er S
hera
ndo
Dam
47
89
10
5 11
2 12
7 67
31
3 79
1 10
70
1893
14
Ju
nctio
n 29
21
2 94
5 27
92
3832
70
83
228
990
2866
39
57
7333
15
To
ms
Cre
ek D
am
41
50
58
62
68
117
574
1449
19
73
3526
16
M
ills C
reek
Dam
41
80
85
88
30
3 89
42
5 10
70
1454
25
93
17
Hap
py H
ollo
w D
am
11
52
57
59
67
41
231
617
841
1498
18
Ju
nctio
n 36
54
2 20
30
5792
82
16
1573
7 70
9 28
49
7972
11
516
2187
5 19
R
obin
son
Hol
low
36
47
54
56
62
68
35
6 92
2 12
51
2218
20
In
ch B
ranc
h 32
46
53
56
62
68
35
3 91
7 12
46
2216
21
Ju
nctio
n 38
64
6 22
23
6216
88
04
1677
9 80
9 32
45
9181
13
232
2567
6 22
Ju
nctio
n 42
10
57
4182
11
111
1570
3 31
942
1118
52
74
1558
2 22
440
4541
0
Appendix C: Linear Programming Test Example Data
Appendix C: Linear Programming Test Example Data 139
Flood Plain PAR= 100000Ls Max = 50000 Lm Max 1000
% PMF PAR w/o Mod PAR w Mod 0 0 0 15 0 0 25 0 50 50 30,000 200 75 40,000 400
100 50,000 1,000
People at Risk (PAR) Regression
y = 577.65x - 5512.9
y = 9.404x - 140.34
-10,0000
10,00020,00030,00040,00050,00060,000
0 50 100 150
% PMF
Peop
le a
t Ris
k PAR w /o Mod
PAR w Mod
Linear (PAR w /oMod)
Linear (PAR wMod)
Figure C.1: Regression Plot for People at Risk Parameter
Appendix C: Linear Programming Test Example Data
Appendix C: Linear Programming Test Example Data 140
Table C.2: Flood Damage Regressions
Annualized
% PMF Flood Q (cfs)
Existing Damage
Post Construction
Damage 0 0 0 0
15 99000 0 0 25 166000 0 240000 50 331000 18000 229000 75 497000 14000 26700 100 662700 11,200 6600
Flood Damage Without Modification
y = -136x + 24600
05000
100001500020000
0 50 100 150
% PMF
Ann
ualiz
ed
Dam
age
($)
Status Quo
Linear (Status Quo)
Figure C.2: Regression Plot for Damage without Modification
Flood Damage With Modificationy = -3610x + 351200
-100000
0
100000
200000
300000
0 50 100 150
% PMF
Ann
ualiz
ed D
amag
e ($
) Series1
Linear (Series1)
Figure C.3: Regression Plot for Damage with Modification
Appendix C: Linear Programming Test Example Data
Appendix C: Linear Programming Test Example Data 141
Table C.3: Construction Cost Regression
Total $ 31,000 Fixed $ 500,000Annualized 1,550,000 Variable $ 1,050,000
% PMF Cost
Annualized 0 0 15 600,000 25 750,000 50 900,000 75 1,250,000
100 1,550,000
Modification Cost vs % PMF
y = 10923x + 431085
0
500,000
1,000,000
1,500,000
2,000,000
0 50 100 150
% PMF
Ann
ualiz
ed C
ost (
$)
Series1
Linear (Series1)
Figure C.4: Regression Plot for Modification Cost v. % PMF
Appendix C: Linear Programming Test Example Data
Appendix C: Linear Programming Test Example Data 142
Table C.4: Run #1: Original Data; Not Feasible
Max Z: Eb 239750 Variables Constraints Ls 11.0258 Ls-Lm-Lc-Lb = 0 Con1 0Lm 0.28068 Es-Em-Eb = 0 Con2 0Lc 10.74512 Ls-Wt*PARs = 0 Con3 0Lb 0 Lm-Wt*PARm = 0 Con4 0Es 24600 Lc-Cl*Cm = 0 Con5 0Em 24600 -Es+mS*Xs+bS = 0 Con6 0Eb 0 -Em+mM*Xm+bM = 0 Con7 0
Cm 76.75086 -PARs+mPARs*Xs+bPARs = 0 Con8 0
Xs 0
-PARm+mPARm*Xm+bPARm = 0 Con9 0
Xm 0 -Cm+mCm*Xm+bCm = 0 Con10 0PARs 5512.9 Xs-Xm = 0 Con11 0PARm 140.34 All variables are non-negative Constants Wt 0.002 CL 0.14 mS -136 bS 24600 mM -3610 bM 351200 mPARs 577.65 bPARs 5512.9 mPARm 9.404 bPARm 140.34 mCm 10923 bCm 431085
Appendix C: Linear Programming Test Example Data
Appendix C: Linear Programming Test Example Data 143
Table C.5: Run #2: Flood Damage Switched; Not Feasible Max Z: Eb 239750 Variables Constraints Ls 11.0258 Ls-Lm-Lc-Lb = 0 Con1 0Lm 0.28068 Es-Em-Eb = 0 Con2 0Lc 10.74512 Ls-Wt*PARs = 0 Con3 0Lb 0 Lm-Wt*PARm = 0 Con4 0Es 351200 Lc-Cl*Cm = 0 Con5 0Em 24600 -Es+mS*Xs+bS = 0 Con6 0Eb 326600 -Em+mM*Xm+bM = 0 Con7 0
Cm 76.75086 -PARs+mPARs*Xs+bPARs = 0 Con8 0
Xs 0
-PARm+mPARm*Xm+bPARm = 0 Con9 0
Xm 0 -Cm+mCm*Xm+bCm = 0 Con10 0PARs 5512.9 Xs-Xm = 0 Con11 0PARm 140.34 All variables are non-negative Constants Wt 0.002 CL 0.14 mS -3610 bS 351200 mM -136 bM 24600 mPARs 577.65 bPARs 5512.9 mPARm 9.404 bPARm 140.34 mCm 10923 bCm 431085
Appendix C: Linear Programming Test Example Data
Appendix C: Linear Programming Test Example Data 144
Table C.6: Run #3: Flood Damage Switched, no construction costs; Feasible Solution Max Z: Eb 239750 Variables Constraints Ls 11.0258 Ls-Lm-Lc-Lb = 0 Con1 0Lm 0.28068 Es-Em-Eb = 0 Con2 0Lc 0 Ls-Wt*PARs = 0 Con3 0Lb 10.74512 Lm-Wt*PARm = 0 Con4 0Es 351200 Lc-Cl*Cm = 0 Con5 0Em 24600 -Es+mS*Xs+bS = 0 Con6 0Eb 326600 -Em+mM*Xm+bM = 0 Con7 0
Cm 0 -PARs+mPARs*Xs+bPARs = 0 Con8 0
Xs 2.71E-20
-PARm+mPARm*Xm+bPARm = 0 Con9 0
Xm 0 -Cm+mCm*Xm+bCm = 0 Con10 0PARs 5512.9 Xs-Xm = 0 Con11 0PARm 140.34
All variables are non-negative
Constants Wt 0.002 CL 0.14 mS -3610 bS 351200 mM -136 bM 24600 mPARs 577.65 bPARs 5512.9 mPARm 9.404 bPARm 140.34 mCm 0 bCm 0
Appendix C: Linear Programming Test Example Data
Appendix C: Linear Programming Test Example Data 145
Table C.7: Run #4 Additional Condition Xs > 25; Feasible Solution Max Z: Eb 239750 Variables Constraints Ls 39.9083 Ls-Lm-Lc-Lb = 0 Con1 0Lm 0.75088 Es-Em-Eb = 0 Con2 0Lc 0 Ls-Wt*PARs = 0 Con3 0Lb 39.15742 Lm-Wt*PARm = 0 Con4 0Es 260950 Lc-Cl*Cm = 0 Con5 0Em 21200 -Es+mS*Xs+bS = 0 Con6 0Eb 239750 -Em+mM*Xm+bM = 0 Con7 0
Cm 0 -PARs+mPARs*Xs+bPARs = 0 Con8 0
Xs 25
-PARm+mPARm*Xm+bPARm = 0 Con9 0
Xm 25 -Cm+mCm*Xm+bCm = 0 Con10 0PARs 19954.15 Xs-Xm = 0 Con11 0PARm 375.44 All variables are non-negative Xs > 25 Constants Wt 0.002 CL 0.14 mS -3610 bS 351200 mM -136 bM 24600 mPARs 577.65 bPARs 5512.9 mPARm 9.404 bPARm 140.34 mCm 0 bCm 0
Appendix C: Linear Programming Test Example Data
Appendix C: Linear Programming Test Example Data 146
Table C.8: Run #5: PARM is reduced to zero to check impact on LB; Feasible Solution Max Z: Eb 239750 Variables Constraints Ls 39.9083 Ls-Lm-Lc-Lb = 0 Con1 0Lm 0 Es-Em-Eb = 0 Con2 0Lc 0 Ls-Wt*PARs = 0 Con3 0Lb 39.9083 Lm-Wt*PARm = 0 Con4 0Es 260950 Lc-Cl*Cm = 0 Con5 0Em 21200 -Es+mS*Xs+bS = 0 Con6 0Eb 239750 -Em+mM*Xm+bM = 0 Con7 0
Cm 0 -PARs+mPARs*Xs+bPARs = 0 Con8 0
Xs 25
-PARm+mPARm*Xm+bPARm = 0 Con9 0
Xm 25 -Cm+mCm*Xm+bCm = 0 Con10 0PARs 19954.15 Xs-Xm = 0 Con11 0PARm 0 All variables are non-negative Xs > 25 Constants Wt 0.002 CL 0.14 mS -3610 bS 351200 mM -136 bM 24600 mPARs 577.65 bPARs 5512.9 mPARm 0 bPARm 0 mCm 0 bCm 0
Appendix C: Linear Programming Test Example Data
Appendix C: Linear Programming Test Example Data 147
Table C.9: Run #6: Take PAR out of equation, Economic Only; Feasible Solution Max Z: Eb 239750 Variables Constraints Ls 0 Ls-Lm-Lc-Lb = 0 Con1 0Lm 0 Es-Em-Eb = 0 Con2 0Lc 0 Ls-Wt*PARs = 0 Con3 0Lb 0 Lm-Wt*PARm = 0 Con4 0Es 260950 Lc-Cl*Cm = 0 Con5 0Em 21200 -Es+mS*Xs+bS = 0 Con6 0Eb 239750 -Em+mM*Xm+bM = 0 Con7 0
Cm 0 -PARs+mPARs*Xs+bPARs = 0 Con8 0
Xs 25
-PARm+mPARm*Xm+bPARm = 0 Con9 0
Xm 25 -Cm+mCm*Xm+bCm = 0 Con10 0PARs 0 Xs-Xm = 0 Con11 0PARm 0 All variables are non-negative Xs > 25 Constants Wt 0.002 CL 0.14 mS -3610 bS 351200 mM -136 bM 24600 mPARs 0 bPARs 0 mPARm 0 bPARm 0 mCm 0 bCm 0
Vita 148
Vita
Major Michael Bliss, U.S. Army, hails originally from Massena, New York. He is
married to Cheria Bliss, and they have three children Cheyennee, Tiyler, and Brandon.
Mike is stationed here in Blacksburg, VA for educational training as part of a utilization in
the U.S. Army Corps of Engineers (USACE). His follow on assignment is Fort Riley,
Kansas in USACE resident office as a project engineer.
Michael�s educational background started at Clarkson University, Potsdam, New
York. He earned a Bachelor of Science in Chemical Engineering in May, 1996. While
stationed at Ft. Leonard Wood Missouri in 2000, Mike earned a Master of Science in
Engineering Management from the University of Missouri at Rolla, Rolla, Missouri.
Major Bliss� army career began when he enlisted in the U.S. Army Reserves in
1992. Completing Army Basic and Advanced Individual Training by the end of 1992, he
accepted an ROTC Scholarship in May of 1993. Mike was commissioned in May 1996,
as a 2nd Lieutenant as an Engineer Officer. His career assignments include various
Company, Battalion, and Brigade level positions.
Michael�s operational deployments include tours in Bosnia-Herzegovina, Kosovo,
and most recently Iraq. Mike deployed his 105 soldier, combat engineer company, B
Company, 11th Engineer Battalion to Kuwait in January 2003 as part of the 3rd Infantry
Division�s preparations for Operation Iraqi Freedom. B Company executed initial
breaches on two lanes into Iraq as part of the 3rd Infantry Division�s assault into Iraq. His
company also executed combat operations in support of Task Force 2-7 Infantry,
culminating with assistance in the seizure of the Baghdad International Airport in April
2003. Mike�s most notable awards include the Bronze Star with �Valor� Device and the
Meritorious Service Medal.