pohick creek watershed: dam rehabilitation dredging and lake restoration

53
Green Breakfast Pohick Creek Watershed Dam Rehabilitation Dredging and Lake Restoration September 14, 2013 Stormwater Management

Upload: fairfax-county

Post on 26-Jan-2015

997 views

Category:

News & Politics


1 download

DESCRIPTION

Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration Sept. 14, 2013

TRANSCRIPT

Page 1: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Green Breakfast

Pohick Creek Watershed Dam Rehabilitation Dredging and Lake Restoration September 14, 2013

Stormwater Management

Page 2: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Pohick Creek PL-566 Facilities Dam Rehabilitation

Dredging and Lake Restoration

Page 3: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

PL-566 Facilities Locations

Page 4: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

4

Pohick Creek PL-566 Dams The Natural Resources Conservation Service (NRCS) designed and

built six dams in the Pohick Creek Watershed between 1970 and 1985, under the authority of Public Law 83-566, the Watershed and Flood Prevention Act

The Northern Virginia Soil and Water Conservation District (NVSWCD) and Fairfax County were the project sponsors

Fairfax County owns and maintains the six facilities

The Pohick dams have helped mitigate downstream flood damages and provide improved water quality, wildlife habitat, recreational opportunities, and economic benefits to the residents of Fairfax County, and are a significant asset to the residents who live near the lakes

Page 5: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

PL-566 Dams Auxiliary Spillway Erosion Study • In 1995, partly as a result of the White Oak dam failure, Fairfax County initiated a

spillway erosion study on four of the PL-566 dams (Royal Lake, Woodglen Lake, Lake Barton, and Huntsman Lake)

• The studies indicated remedial measures were required to preclude excessive

headcutting and possible dam failure during the design flow event (PMF)

White Oak Dam in Madison County after June 1995 rainfall event (~18” in 24 hours)

Presenter
Presentation Notes
A Conditional Use Certificate means that the dam no longer meets all the safety criteria established by the State Division of Dam Safety and Floodplain Management. Royal Lake has a vegetated earth auxiliary spillway. Using computer models, it was determined that the auxiliary spillway did not have the soil strength needed to withstand high flows without breaching. The Conditional Use Certificate also notes that the training dike that keeps the water in the auxiliary spillway from eroding the edge of the dam is not high enough. This information was initially identified by studies conducted by the consulting firm Gannett Fleming.
Page 6: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

NRCS Technical and Financial Assistance • Fairfax County and NVSWCD as the original project sponsors requested NRCS

assistance to rehabilitate the four PL-566 facilities (starting with Royal Lake) in 2005

• NRCS developed a rehabilitation plan for Royal Lake in 2006, working collaboratively with Fairfax County, NVSWCD, and a citizen’s task force set up by the Braddock District Supervisor’s office

• After adoption of the rehabilitation plan, NRCS asked Fairfax County and NVSWCD to consider taking the lead on the design and construction effort, with NRCS continuing to provide technical and financial assistance

• NRCS also asked Fairfax County and NVSWCD to provide assistance with the Hydrologic and Hydraulic (H&H) studies required to develop rehabilitation plans for the other facilities (Woodglen Lake, Lake Barton and Huntsman Lake)

Page 7: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

PL-566 Facility Rehabilitation – Royal Lake

• Challenges – First project – significant learning curve for county

and consultant in understanding and utilizing NRCS design standards and specifications

– Tropical Storm Hanna impacts

Page 8: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

PL-566 Facility Rehabilitation – Royal Lake

Page 9: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

9

Tropical Storm Hanna (September 6, 2008) Rainfall Amounts in Fairfax County

Page 10: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

10

Page 11: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Royal Lake September 7 and 8, 2008

Page 12: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

12

Royal Lake ACB installation

Page 13: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Royal Lake Post-Construction

Page 14: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

PL-566 Facility Rehabilitation – Woodglen Lake

NRCS received ARRA funding which accelerated the design schedule somewhat

Unsuitable subgrade material encountered at the end of the new auxiliary spillway exit channel resulted in a field design change for the installation of a subsurface drainage system

Page 15: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

15

PL-566 Facility Rehabilitation – Woodglen Lake

Page 16: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

PL-566 Facility Rehabilitation – Woodglen Lake

Presenter
Presentation Notes
Built in 1973 as a flood-control dam
Page 17: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

PL-566 Facility Rehabilitation – Lake Barton

Preferred concept (ACB armoring) in original NRCS rehabilitation plan was changed at the request of landowners from whom easements were required. A new concept utilizing cutoff walls that resulted in a much smaller tree loss was moved forward

The sediment pool did not meet the minimum 50-year life requirement at the

completion of rehabilitation, and the rehabilitation plan recommended raising the permanent pool elevation by 0.8 feet to achieve the required sediment storage

Because of resident concerns and land rights issues, Fairfax County decided to

dredge Lake Barton to meet the sediment pool capacity requirements NRCS also received ARRA funding for this project which significantly accelerated

the design schedule

Page 18: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

18

Page 19: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

PL-566 Rehabilitation Projects: Cost-Share Funds Received

• 2007/2008: Royal Lake Dam, $1.8 million • 2009/2010: Woodglen Lake Dam, $1.4 million • 2010/2011: Lake Barton Dam, $2.8 million • 2013: Huntsman Lake, $1.8 million (obligated)

Fairfax County and NVSWCD as project sponsors have received approximately $6 million to date for rehabilitation of the PL-566 facilities:

Presenter
Presentation Notes
Built in 1973 as a flood-control dam
Page 20: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Huntsman Lake Dam Rehabilitation Project Background

• Huntsman Lake Dam is regulated by the Virginia Department of Conservation and Recreation (DCR), Division of Dam Safety

• Huntsman Dam is operating under a conditional operation and maintenance (O&M) certificate from DCR because it’s auxiliary spillway can only convey about 50 percent of the flows from the design storm

Presenter
Presentation Notes
Built in 1973 as a flood-control dam
Page 21: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Huntsman Lake Dam Rehabilitation Project Summary of Rehabilitation Plan

Presenter
Presentation Notes
Built in 1973 as a flood-control dam
Page 22: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Huntsman Lake Dam Rehabilitation Project Major Design Elements

Presenter
Presentation Notes
Built in 1973 as a flood-control dam
Page 23: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Huntsman Lake Dam Rehabilitation Project Riser Replacement

Presenter
Presentation Notes
Built in 1973 as a flood-control dam
Page 24: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Huntsman Lake Dam Rehabilitation Project Fish Relocation (May 2013)

Presenter
Presentation Notes
Built in 1973 as a flood-control dam
Page 25: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Lake Dredging and Restoration Lake Sediment

(CY)

Sediment Pool

Capacity (CY)

% sediment pool

expended

Annual Load (CY)

Annual Load (CY/AC)

Lake Barton 32,500 75,000 43.33% 1,100 2.04Huntsman Lake 65,000 295,000 22.03% 2,968 2.00Woodglen Lake 32,500 160,000 20.31% 1,244 1.69

Lake Royal 105,000 416,000 25.24% 4,411 1.88Lake Mercer* 37,000 550,000 6.60% 1,650 0.41

Lake Barton Example

Page 26: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Sources of Sediment

Page 27: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Lake Restoration and Dredging Projects

Project Goals • Restore sediment pool capacity

– Downstream water quality benefits – Aesthetics

• Improve lake water quality and habitat • Provide long term maintenance improvements

Page 29: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Lake Barton Example: Dredging in Progress

Page 30: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Disposal Site – Sediment Reuse

• Topsoil for landfill cover • Topsoil product for resale

Page 31: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Lake Restoration

• In-lake forebay • Wetland planting • Shoreline stabilization • Fish habitat • Fish stocking

Lake Barton: Fish stocking by Virginia Game and Inland Fisheries Fish habitat created from salvaged trees

Page 32: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Shoreline Protection Options

Page 33: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Huntsman Lake Facts

• Drainage area = 1,482 acres (2.3 square miles) • Lake surface area = 28.6 acres • Sediment pool capacity = 295,000 cubic yards (CY) • Current sediment in lake = 65,000 CY • Estimated annual sediment load = 2,970 CY

32.5 feet

65,000 CY

Presenter
Presentation Notes
65,000 CY/295,000 CY = 22 percent full
Page 34: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

2011

Inactive Dewatering

Basin

Page 35: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Sediment Thickness

Page 36: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Water Depth

Page 37: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Huntsman Lake - Forebays bank stabilization

aquatic bench

forebay

forebay berms

maintenance access

sanitary sewer

dam embankment

Page 38: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Woodglen Lake

Page 39: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Woodglen Lake: Sediment Thickness

Page 40: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Woodglen Lake: Water Depth

Page 41: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Royal Lake Facts

• Lake surface area = 38 acres • Sediment pool capacity =

417,000 cubic yards (CY) • Current sediment in lake =

105,000 CY • Estimated annual sediment load

= 4,400 CY • Phased

– 55,000 base dredge – 50,000 additional

55 feet

105,000 CY

Presenter
Presentation Notes
32,500/160,000 = 20.3% Land Use in Drainage Area by Type, Acres and Percentage Residential/Business, 522 acres, 70.5% Woodland, 118 acres, 15.9% Transportation, 79 acres, 10.7% Water, 13 acres, 1.8% Grassland, 8 acres, 1.1% Total = 740 acres Floodpool of Woodglen Lake = 36 acres Land Ownership: Upstream of dam: 79% private, 21% public Downstream of dam: 47% private, 53% public
Page 42: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Royal Lake

Page 43: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Royal Lake: Sediment Thickness

Page 44: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Royal Lake: Water Depth

Page 45: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Page 46: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Proposed Schedule

• Huntsman Spillway Rehabilitation and Dredging: Fall 2013

• Woodglen: Winter 2013 • Royal: Summer 2014

Presenter
Presentation Notes
32,500/160,000 = 20.3% Land Use in Drainage Area by Type, Acres and Percentage Residential/Business, 522 acres, 70.5% Woodland, 118 acres, 15.9% Transportation, 79 acres, 10.7% Water, 13 acres, 1.8% Grassland, 8 acres, 1.1% Total = 740 acres Floodpool of Woodglen Lake = 36 acres Land Ownership: Upstream of dam: 79% private, 21% public Downstream of dam: 47% private, 53% public
Page 47: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Lake Accotink – Fairfax County Park Authority

Page 48: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Lake Accotink Dredge Disposal Site – Concrete Plant

Page 49: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Lake Accotink Dredging Disposal Site at Virginia Concrete

Disposal site during dredging – March 2008 (198,000 cubic yards of dredge material was disposed at this site)

Disposal site 3 months after final site reclamation – July 2009 (Dredging and disposal were completed in 2008. Site reclamation was performed in spring 2009)

Page 50: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Reclaimed Old Concrete Disposal Site

Lake Accotink Dredge Disposal Site

2013

concrete plant

Page 51: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Lake Accotink

2009

Page 52: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Lake Accotink

2010 with lake drained for spillway repairs

Page 53: Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration

Project Contacts

Stormwater Planning Division (703-324-5500) • Matt Meyers • Dipmani Kumar • Martin Chang Partners:

Presenter
Presentation Notes
Built in 1973 as a flood-control dam