project rehabilitation report of upper mullamari dam,
TRANSCRIPT
Project Rehabilitation Report
of Upper Mullamari Dam, Karnataka Water Resources Department
Doc. No.: CDSO_DSR_PRR_ KA06MH0153_KaWRD_v1.0
April 2019
Central Water Commission
Ministry of Water Resources,
River Development & Ganga Rejuvenation
Government of India
Project Rehabilitation Report of Upper Mullamari Dam
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Upper Mullamari Dam
Quality Control:
Version Date Writers/Contributors Checked by
1 25/04/2019 Dr. Hadush S Hagos (HSH) Pankaj Kumar Awasthi (PKA Anil Kumar Verma (AKV)
Rajiv Kumar Sawarn
Issued/Copied to:
I/C Date Name Organisation
Issued 25/04/2019 Shri. Pramod Narayan Central Water Commission
Project Rehabilitation Report of Upper Mullamari Dam
Abbreviations
DRIP Dam Rehabilitation & Improvement Project
CWC Central Water Commission
CPMU Central Project Management Unit
CSV Construction Site Visit
SPMU State Project Management Unit
IA Implementation Agency
PIC Project Identification Code
DSRP Dam Safety Review Panel
PST Project Screening Template
DFR Design Flood Review
MSL Mean Sea Level
FRL Full Reservoir Level
MWL Maximum Water Level
TBL Top Bund Level (Top Level of Dam)
MDDL Maximum Draw Down Level
LSL Lowest Sill Level
DSL Dead Storage Level
U/S Upstream
D/S Downstream
El. Elevation
L/B Left Bank
R/B Right Bank
PMF Probable Maximum Flood
SPF Standard Project Flood
CD Works Cross Drainage Works
VRB Village Road Bridge
WBM Water Bound Macadam
NDT Non Destructive Testing
DHARMA Dam Health And Rehabilitation Monitoring Application
O & M Operation and Maintenance
EAP Emergency Action Plan
Project Rehabilitation Report of Upper Mullamari Dam
ESMF Environmental and Social Management Framework
E & S specialists Environmental and Social Specialists
HM Works Hydro-Mechanical Works
EM Works Electro-Mechanical Works
SCADA Supervisory Control and Data Acquisition System
DG Set Diesel Generator Set
MW Mega Watt
MU Million units
Ha Hectare
MCM Million Cubic Metre
Deg. Degree
Min. Minute
Sec. Second
CM Construction management
QC Quality control
m meter
m3 Cubic meter
m3/sec Cubic meter per second
Km2 Square kilometre
Mcm Million cubic meter
TNWRD Tamil Nadu Water Resource Department
TANGEDCO Tamil Nadu Generation and Distribution Corporation
KWRD Kerala Water Resource Department
KSEB Kerala State Electricity Board
MPWRD Madhya Pradesh Water Resource Department
UJVNL Uttarakhand Jal Vidyut Nigam Limited
DVC Damodar Valley Corporation
Project Rehabilitation Report of Upper Mullamari Dam
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Upper Mullamari Dam
DRIP Component Wise Project Cost
KaWRD Initial/Revised Projects & Cost
BACKGROUND
In April 2012, the Central Water Commission
(CWC) with assistance from the World Bank,
embarked upon a six year Dam
Rehabilitation and Improvement Project
(DRIP) at a preliminarily estimated initial cost
of Rs.2100 Crore targeting rehabilitation and
improvement of about 250 dams initially of
six, later of nine implementing agencies -
namely: MPWRD, OWRD, TNWRD,
TANGEDCO, KWRD, KSEB, KaWRD,
UJVNL and DVC.
In June 2018, the project was extended by
two years, until June 2020. The current
revised cost for DRIP is Rs.3466 Crore out of which Rs. 2920.5 Crore is allocated for
Component 1 (Rehabilitation and Improvement of Dams and Associated Appurtenances),
Rs.232.5 Crore for Component 2 (Dam Safety Institutional Strengthening), and Rs.313 Crore
for Component 3 (Project Management). Appropriate assistance is also provided under
DRIP to develop O & M Manuals and Emergency Action Plans (EAP) for these dams. The
project also promotes new technologies and improves institutional capacities for dam safety
evaluation and implementation at the Central and State levels as well as in some identified
premier academic and research institutes in the country. The actual total number of dams
under DRIP stands at 223.
The Implementing Agencies for DRIP are the Water Resources Departments and State
Electricity Boards in the participating States and Damodar Valley Corporation (DVC) with
Central Water Commission at Central Level. State Implementing Agencies are responsible
for implementation of works of dams under their charge. Co-ordination and management of
such works within a State rests with the
concerned State Project Management
Unit (SPMU). Overall project oversight
and coordination is carried out by Central
Project Management Unit (CPMU) headed
by the Project Director with assistance of
an Engineering and Management
Consultant.
Karnataka Water Resource Department
(KaWRD) joined DRIP in August 2014
with initial number of dams totalling 31.
Later, KaWRD dropped 9 dams and
continuing in DRIP with 22 dams.
Preliminarily estimated initial DRIP project
cost for KaWRD was Rs.276.1 Crore and
the revised actual current project cost is
Rs.581.2 Crore.
Project Rehabilitation Report of Upper Mullamari Dam
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Upper Mullamari Dam
Table of Contents
Abbreviations ........................................................................................................... 4
1. EXECUTIVE SUMMARY .................................................................................. 1
2. PROJECT DETAILS ......................................................................................... 2
2.1 Project Description .......................................................................................................... 2
2.2 Project Location ............................................................................................................... 2
2.3 Project Benefits ................................................................................................................ 2
2.4 Dam and Reservoir Features (Before rehabilitation under DRIP) ............................... 3
2.5 Any Emergency Spillway, Fuse Plug etc. ...................................................................... 4
2.6 Details of previous dam incidents, if any ...................................................................... 4
2.7 PST Details ....................................................................................................................... 4
2.8 DSRP, CPMU and World Bank Recommendations and Compliance ......................... 5
2.9 Scope of Rehabilitation Works as per PST ................................................................... 5
2.10 Drawings ......................................................................................................................... 20
3. DAM VISITS (PST STAGE) ............................................................................ 27
3.1 Dam Inspections ............................................................................................................ 27
3.2 Summary of observations made by CPMU ................................................................. 27
4. DESIGN FLOOD REVIEW (DFR) ................................................................... 27
4.1 DFR Outcome ................................................................................................................. 27
4.2 Brief Summary of Review.............................................................................................. 27
4.3 Recommendations ......................................................................................................... 27
5. REHABILITATION WORKS CARRIED OUT ................................................. 28
5.1 Summary of Investigations ........................................................................................... 28
5.2 Main Dam Works ............................................................................................................ 28
5.3 Basic facilities ................................................................................................................ 28
6. INSTRUMENTATION ..................................................................................... 28
6.1 List of existing instruments installed in dam and their condition ............................ 28
6.2 Details of new instruments installed ........................................................................... 28
6.3 CPMU Recommendations ............................................................................................. 28
7. PROCUREMENT OF WORKS ....................................................................... 29
7.1 Package wise details ..................................................................................................... 29
7.2 Details of Bidding process............................................................................................ 30
7.3 Reason for Variation, if any .......................................................................................... 30
7.4 Litigation / Arbitration, If Any ....................................................................................... 30
8. THIRD PARTY CONSTRUCTION SUPERVISION VISITS BY CPMU ........... 30
Project Rehabilitation Report of Upper Mullamari Dam
8.1. Summary of Visits undertaken .................................................................... 30
8.2. Summary of Third Party Material Testing ................................................... 30
8.3. Summary of Major Recommendations ........................................................ 30
8.4. Summary of Compliance by SPMU ............................................................. 33
8.5. Summary of any Special Visits made by CWC/World Bank/Expert
Committee ..................................................................................................... 33
8.6. Summary of Technical Assistance provided by CPMU ............................. 33
9. ENVIRONMENTAL AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) 33
9.1 Basic Details ................................................................................................................... 33
9.2 Summary of Observations ............................................................................................ 33
9.3 Details of ESMF/EIA study (if any) ............................................................................... 33
10. OTHER NON-STRUCTURAL INTERVENTIONS ........................................... 37
10.1 Basic Details ................................................................................................................... 37
10.2 Summary of Observations ............................................................................................ 37
11. PENDING REHABILITATION WORKS .......................................................... 37
11.1 Details of pending works .............................................................................................. 37
11.2 Further course of action................................................................................................ 37
12. REFERENCES ............................................................................................... 37
Annex A: PST Approval Letter .............................................................................. 39
Annex B: Drawings issued for Rehabilitation measures .................................... 43
Annex C: Completion Certificate .......................................................................... 49
Annex D: Third Party QC Tests ............................................................................. 55
Annex E: ESMF OK Card ....................................................................................... 59
Annex F: Photographs Before and After Rehabilitation Works ......................... 63
Project Rehabilitation Report of Upper Mullamari Dam
1 | P a g e
1. EXECUTIVE SUMMARY
This Project Rehabilitation Report (PRR) is for Upper Mullamari Dam, which is one of
the 22 dams under DRIP in Karnataka. The Dam Safety Review Panel (DSRP)
inspected the dam in July 2015 and recommended both structural & non-structural
measures to be taken up by the dam authorities.
DSRP main recommendations included provision of horizontal collector drain on dam
crest and chute drains on dam d/s slope; repair of disturbed riprap; provisions of
manholes at 100 m c/c at rock toe; installation of V-notch weir; provision of protective
grass on dam downstream slope; repair of rain cuts and gullies on dam downstream
slope; repair of templates on dam upstream slope riprap; dismantle cross wall
constructed upstream of spillway; and repair hoisting system and rubber seals of
irrigation sluice gates. Non-structural measures review of design flood, preparation of
EAP and O&M manual.
The original design flood was 1,053 cumec and the revised design flood (SPF) is
1,340 cumec. Flood routing study for the revised design flood is currently on-going
and the revised MWL will only be known after the flood routing study is completed.
The MWL for the original design flood was at EL 588.60 m and the TBL is at 591.60
m. The freeboard above the original MWL is 3 m. However, the final freeboard needs
to be re-calculated using the MWL for the revised design flood and should fulfil the
minimum recommended 1.50 m for embankment dams as per IS 10635.
Following DSRP recommendations, rehabilitation works carried out under DRIP
included:
Construction of lead off drain on dam crest,
Construction of chute and longitudinal drains on d/s slope of dam,
Construction of riprap template wall,
Repair of existing manhole at toe of dam,
Upstream side revetment correction,
Turfing on d/s slope of dam,
Pit filling below d/s of toe,
Improvements to V-notch weir and d/s side channel clearance,
Construction of approach road.
The rehabilitation works were executed under 1 package at a total completion cost of
Rs. 241.30 Lakhs.
Dam break analysis, inundation maps, EAP and O&M manual are currently being
undertaken by SPMU as per guideline published by CWC under DRIP.
Project Rehabilitation Report of Upper Mullamari Dam
2 | P a g e
2. PROJECT DETAILS
The Upper Mullamari dam is located across Mullamari River near Kherda (B) Village
of Basavakalyan Taluk of Bidar district, Karnataka state at Latitude of 77º22’00” N
and Longitude of 17º42’00” E. It was completed in the year 1983. The project
consists of an earthen dam 810 m long and 4.0 m dam crest width. It has 62 m long
ungated spillway having discharge capacity of 1,053 cumec.
The TBL, FRL, original MWL and Spillway Crest level are at EL 591.60 m, 584.60 m,
588.60 m and 584.60 m, respectively. The gross storage at FRL is 21.22 MCM.
2.1 Project Description
Sl. No.
Item Details
a. Project Identification Code (PIC) KA06MH0153
b. Project Name Upper Mullamari Dam
c. River Basin Krishna
d. Sub River Basin Bhima
e. River/Stream Mullamari
f. Catchment area (km2) 207
g. Year of commencement of project 1978
h. Year of completion of project 1983
2.2 Project Location
Sl. No.
Item Details
a. State Karnataka
b. District Bidar
c. Earthquake Zone II
d. Survey of India Map Ref No’s 56G/2
e. Nearest City Humnabad
f. Nearest Airport Hyderabad
g. Nearest Railhead Kalburgi
h. Name of Immediate U/S Project Nil
i. Name of Immediate D/S Project Lower Mullamari
j. Latitude in Deg., Min, Sec. (North) 77º22’00”
k. Longitude in Deg., Min, Sec. (East) 17º42’00”
2.3 Project Benefits
Sl. No. Item Details
a. Type of Project Irrigation
b. Gross Command Area (Ha) 5465
Project Rehabilitation Report of Upper Mullamari Dam
3 | P a g e
Sl. No. Item Details
c. Culturable Command Area (Ha) 3279
d. Annual Irrigation Potential (Ha) 3279
e. Hydropower –
Installed Capacity (MW) Nil
f. Hydropower –
Firm Power (MW) Nil
g. Hydropower –
Average Annual Generation (MU) Nil
h. Domestic/Municipal/Industrial Water –
Annual Quantum (MCM) Nil
i. Domestic/Municipal/Industrial Water –
Area and Population Benefitted Nil
j. Flood Protection –
Flood Protected Area (Ha) Nil
k. Flood Protection –
Details of Area Benefitted Nil
l. Details of Tourism/Recreational Facilities Nil
2.4 Dam and Reservoir Features (Before rehabilitation under DRIP)
Sl. No.
Item Details
a. Full Reservoir Level (m) 584.60
b. Original Maximum Water Level (m) 588.60
c. Gross Reservoir Storage Capacity at FRL (Mm
3 )
21.22
d. Live Storage Capacity (Mm3 ) 18.33
e. Revised Live Storage Capacity, if any
(Mm3 )
-
f. Date of bathymetric survey, if any -
g. Dam Type Zoned Earthfill Dam
h.
Length of Dam at Top (m)
i) Total length of the main dam
ii) Length of embankment dam
iii) Length of masonry/concrete dam
810
810
62 (only side ogee spillway section)
i. Number and length of dykes (No. & m) Nil
j. Top of dam (El. in m.) 591.60
k. Top Level of Upstream Parapet Wall of main dam (El. in m.)
NA
l. Height of Dam (m)
i) Embankment dam – above river bed level (up to dam top without
23.00
Project Rehabilitation Report of Upper Mullamari Dam
4 | P a g e
Sl. No.
Item Details
camber)
ii) Concrete/Masonry dam – above deepest foundation level (up to dam top)
2 (ogee control structure)
m Top width of main dam (m) 4.0
n. Spillway details
i) Location Ungated side saddle
ii) Type of spillway Ogee
iii) Length of spillway (m) 62
iv) Spillway crest level (m) 584.60
v) Type of Gate NA
vi) Number and size of gates (no. and
m. x m.) NA
vii) Number and thickness of piers (no.
and m. x m.) NA
o.
Outlet/Sluice details
i) In Embankment dam
Number
Size (Width (m). x Height (m).)
Location
Invert level El. (m)
Discharging capacity (m3/s)
ii) In Concrete/Masonry dam
Number
Size (m. x m.)
Location
Invert level El. (m)
Discharging capacity (m3/s)
2 (LBC, RBC)
0.80 m x 1.80, 0.80 m x 1.80 m
CH 180 m, CH 558 m
576.06 m, 576.06 m
0.99, 1.62
Nil
Note: All elevations are above MSL
2.5 Any Emergency Spillway, Fuse Plug etc.
Nil
2.6 Details of previous dam incidents, if any
Nil
2.7 PST Details
Sl.
No. Item Date/Cost Remarks
a. PST first received from SPMU 18.12.2015
b. Proposed PST Cost (INR in Lakhs) 335.00
Project Rehabilitation Report of Upper Mullamari Dam
5 | P a g e
c. First review by CPMU 08.01.2016
d. Final review by CPMU 08.01.2016
e. World Bank Approval 14.01.2016 E- mail dated 14/01/2016
f. Approved PST Cost (INR in Lakhs) 335.00
2.8 DSRP, CPMU and World Bank Recommendations and Compliance
2.8.1 DSRP Recommendations and Compliance
Compliance to DSRP recommendations as submitted by SPMU/dam authorities is
shown on pages 6 to 11 below.
2.8.2 CPMU/World Bank Recommendations and Compliance
Compliance letters on CPMU observations during PST stage as submitted by
SPMU/dam authorities is shown on pages 12 to 19 below.
2.9 Scope of Rehabilitation Works as per PST
(a) Remedial Measures (Structural)
i. Construction of lead off drain,
ii. Construction of template wall,
iii. Construction of Manholes,
iv. Upstream side revetment correction,
v. Construction of Turfing on d/s side
vi. Pit filling below d/s of toe of dam
vii. Improvements to V-notch and d/s channel clearance
(b) Basic Facilities
viii. Construction of Approach Road to Upper Mullamari Dam.
(c) Non-structural Measures
ix. Design flood studies, Flood routing study, Preparation of Emergency Action Plan, Dam break Analysis, Stability Analysis of Dam and Preparation of inundation maps
Project Rehabilitation Report of Upper Mullamari Dam
6 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
7 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
8 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
9 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
10 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
11 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
12 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
13 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
14 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
15 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
16 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
17 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
18 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
19 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
20 | P a g e
2.10 Drawings
Figure 2-1: Index Map of Upper Mullamari Dam.
Project Rehabilitation Report of Upper Mullamari Dam
21 | P a g e
Figure 2-2: Google Map of Upper Mullamari Dam.
Project Rehabilitation Report of Upper Mullamari Dam
22 | P a g e
Figure 2-3: Layout Map of Upper Mullamari Dam.
Project Rehabilitation Report of Upper Mullamari Dam
23 | P a g e
Figure 2-4: Longitudinal Section of Upper Mullamari Dam.
Project Rehabilitation Report of Upper Mullamari Dam
24 | P a g e
Figure 2-5: Typical Cross Section of Upper Mullamari Earth Dam.
Project Rehabilitation Report of Upper Mullamari Dam
25 | P a g e
Figure 2-6: Spillway Plan of Upper Mullamari Dam.
Project Rehabilitation Report of Upper Mullamari Dam
26 | P a g e
Figure 2-7: Spillway Cross Section of Upper Mullamari Dam.
Project Rehabilitation Report of Upper Mullamari Dam
27 | P a g e
3. DAM VISITS (PST STAGE)
3.1 Dam Inspections
Sl. No.
Item Date of visit Remarks
a. Dam Safety Review Panel (DSRP) July 2015
b. Site Visit made by CPMU experts Oct 2015
3.2 Summary of observations made by CPMU
Revised design flood has been estimated as 1340 m3/sec against original value of
1053 m3/sec. Recommended that flood routing studies be carried out to obtain the
revised maximum water level and check adequacy of the freeboard available. Other
observations made by CPMU are as given under section 2.8.2.
4. DESIGN FLOOD REVIEW (DFR)
4.1 DFR Outcome
Sl. No.
Item Original
Value
Revised
Value Remarks
a. Inflow Design Flood (m3/s) 1053 1340 SPF
b. Spillway Capacity / Routed Outflow (m
3/s)
- - Flood routing
study is on-going.
c. Maximum Water Level (m) 588.6 - TBL 591.6
FRL 584.6
4.2 Brief Summary of Review
The original design flood was 1,053 cumec and the revised design flood (SPF) is 1,340 cumec. Flood routing study for the revised design flood is currently on-going and the revised MWL will only be known after the flood routing study is completed. The MWL for the original design flood was at EL 588.60 m and the TBL is at 591.60 m. The freeboard above the original MWL is 3 m. However, the final freeboard needs to be re-calculated using the MWL for the revised design flood and should fulfil the minimum recommended 1.50 m for embankment dams as per IS 10635.
4.3 Recommendations
Structural measures - Nil.
Non-structural measures - EAP.
Project Rehabilitation Report of Upper Mullamari Dam
28 | P a g e
5. REHABILITATION WORKS CARRIED OUT
5.1 Summary of Investigations
Sl. No.
Item Details Remarks
a. Geo-Physical Investigations
NA b. Geo-Technical Investigations
c. Hydraulic Model Studies
d. Under-Water Scanning
5.2 Main Dam Works
Sl. No.
Item Details Remarks
a. Works from hydrological angle Design flood review & flood
routing
Design flood Completed.
Flood routing on-going
b. Resetting of disturbed upstream pitching (rip-rap)
Upstream side revetment correction and construction of
template wall Completed
c. Repairs to d/s toe drains, provision of V-Notches for seepage measurements
Construction of lead off drain at dam top and chute drains
on dam d/s slope Completed
d. Provision for d/s turfing Turfing on d/s dam slope Completed
e. Other miscellaneous works d/s of embankment dam
Repair of existing manholes d/s of dam toe
Pit filling below d/s of toe of dam
Completed
5.3 Basic facilities
S/N Item Details Status
a. b. Roads Construction of approach road Completed
b. c. Others
Improvements to V-notch and d/s channel clearance
Completed
6. INSTRUMENTATION
6.1 List of existing instruments installed in dam and their condition
V-notch weir newly installed.
6.2 Details of new instruments installed
Nil.
6.3 CPMU Recommendations
Nil.
Project Rehabilitation Report of Upper Mullamari Dam
29 | P a g e
7. PROCUREMENT OF WORKS
7.1 Package wise details
Work Package No.
Name of Works
Estimated
Cost
(INR in Lakhs)
Procurement
Method
Invitation for bids / NIT Issue
date
Pre-Bid Meeting
date
Bid Opening
date
Contract Agreement
No.
Contract Agreement
date
Contractor’s Name &
Address
Scheduled
Duration (Months)
Scheduled Completio
n date
Contract /
Award Value
(INR in Lakhs)
Completion Cost (INR in Lakhs)
Actual Date of
Completion
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
1
Dam Rehabilitation and Improvement Works to Upper Mullamari Dam
Under World Bank aided DRIP
program
277.00 NCB 04/07/16 02/08/16 08/08/16 27/ 2016-17 02/12/16
Sri B.N.Police Patil,
KPWD Class-I Contractor,
Rf o Budhihal, Tq. Shorapur, Dist. Yadagir
12 01/12/17 289.65 241.30 15/11/18
Project Rehabilitation Report of Upper Mullamari Dam
30 | P a g e
Longitudinal crack
7.2 Details of Bidding process
As per details in the above table.
7.3 Reason for Variation, if any
SPMU reported Rs. 48.66 lakhs savings due to omission of unnecessary items as
per site conditions. See completion certificate and savings report in Annexure C.
7.4 Litigation / Arbitration, If Any
No litigation.
8. THIRD PARTY CONSTRUCTION SUPERVISION VISITS BY
CPMU
8.1. Summary of Visits undertaken
Sl. No. Date of visit Transmittal details of CSV Report
a. 10-07-2017 5352/12-12-2017
b. 10-10-2017
c. 26-03-2018 5851/03-05-2018
d. 25-07-218 6392/28-09-2018
8.2. Summary of Third Party Material Testing
Third party quality control tests were performed on M20 concrete for dam top leadoff
drain, dam d/s slope chute and longitudinal drains using non-destructive Schmidt
hammer test (NDT). The tests gave satisfactory results. Detailed test report is
attached as Annexure D.
8.3. Summary of Major Recommendations
1st and 2nd Construction Site Visit Report
Observations & Recommendations:
During the visit on 11 July 2017, a longitudinal
crack was observed on dam d/s slope adjacent
to the curb between CH 0+390 and CH 0+420 m
(see photo on right side). The crack has since
been filled with soil and hand compacted. CPMU
notes that filling the crack with hand-compacted
soil is only a short-term solution to stop rain
water from percolating through the crack and
further weakening the slope. However, the long-
lasting solution will be to dig a trapezoidal trench
along the crack (up to the stable base of the
crack) and refill with suitable soil compacted by
hand held pneumatic tamper.
Project Rehabilitation Report of Upper Mullamari Dam
31 | P a g e
Noted construction compliance issues:
Sl. No
Observation / Deficiency Status Remarks
Observations during site visit on 11.07.2017
1 Non-availability of labour for work
Open Project authorities should insist contractor to mobilise the manpower.
2 Templates are damaged at many location
Open, Insufficient provision in the
estimate to complete the work
Action needs to be taken by project authorities to complete the work by approving variations if budget permits.
3 Crack formation between Ch. 390 & 420 m
Closed Filled the gap with soil and hand compacted to make it monolithic.
4
Depression at D/s of dam with pool of water, which was likely to impair on stability of dam due to saturation of foundation
Open
Filled with earth to avoid pooling of water. Repairs to RBC has to be carried out to arrest seepage to avoid flow of water in the vicinity of Toe of earthen dam..
5 Disturbance at U/s Revetment at Ch. 300 m to 330 m
Open To be rectified by resetting with filter below
6 Rain cuts/gullies formation at D/s face of earthen dam is observed
Open. No provision in the present
estimate to repair to designed slope
DSRT recommends for repair and providing protective cover of gross to avoid erosion damages.
Observations during site visit 10.10.2017
7 Shrubs in plenty have grown at the D/s slope of the earthen dam
Open
Action to be taken to uproot the shrubs as and when appears to avoid disturbing the embankment due to growth in the diameter of root & stem.
8
At many locations there is settlement in U/s revetment and also appears due to this there is settlement in dam top also.
Open
Recommended for survey and cross verification of actual sections with designed sections to find out whether there is any distortion and rectification if required.
3rd Construction Site Visit Report
Observations and Quality Control issues:
The critical issue at this is a longitudinal crack observed on dam d/s slope adjacent
to the kerb between CH 0+390 and CH 0+420 m. The same was reported in
previous construction site visit. This section has now been excavated for
construction of dam top lead off drain. Other cracks were also observed on d/s side
of the dam crest. Rough measurements taken during this site visit show that the
observed cracks are 30-cm to 60-cm deep. Based on the observations made
during the inspection, the SPMU is recommended:
To identify and effectively repair all longitudinal cracks along the whole
length of the dam using best engineering practices by digging a trapezoidal
trench along the crack (up to the stable base of the crack) and refill layer
by layer with suitable soil compacted by hand held pneumatic tamper.
To construct the lead off (longitudinal) drain at the dam top after effective
repair of the longitudinal cracks (wherever observed crack intercepts the
longitudinal). This will help to ensure stability of the embankment.
For the V-notch weir currently under construction at the d/s toe of the dam,
CPMU recommends installation of a measuring staff gauge on the side
wall upstream of the V-notch at a distance ≥ 4×h (where h is maximum
depth of flow over the V-notch weir).
Project Rehabilitation Report of Upper Mullamari Dam
32 | P a g e
Noted construction compliance issues:
No. Deficiency / Observation Status Remarks
1.
Observed longitudinal crack adjacent to the d/s kerb between CH 0+390 and CH 0+420 m and other minor cracks on d/s side of dam crest
Open SPMU to identify and effectively repair all visible cracks along the whole dam length.
2.
Construction of the lead-off (longitudinal) drain at dam top (downstream side) before repair of cracks
Open
To ensure long-term stability of the structure, SPMU to effectively repair cracks before construction of lead off drain.
3. V-notch weir chamber full of water Open
Chamber needs to be effectively dewatered and properly graded for positive drainage before installation of V-notch weir.
4. No staff gauge for V-notch weir measurement
Open
To be provided upstream of the v-
notch at a distance ≥4×h (where h is maximum height of the V-notch weir).
5. Deep rain cuts on d/s slope of dam Open To be properly rectified.
6. Contract expired on 01/12/17 Open EOT to be approved.
4th Construction Site Visit Report Observations:
During this inspection, CPMU noted that the longitudinal crack was repaired by
excavating trapezoidal section as recommended in the previous visit. However,
compaction was not done using pneumatic equipment. Rather manual tampers
were used, which may not have attained the required degree of compaction. SPMU
is recommended to monitor any potential settlement of the lead-off drain
constructed over the repaired longitudinal crack.
Backfill behind the side walls of the dam top longitudinal drain needs to be
compacted well. At present, it is loose and can be eroded easily by rain water (see
photo 6). Also, excavated soil other than the part used for backfilling behind the
walls should not be disposed on the dam d/s slope. It should rather be disposed to
designated area.
Drying up of grasses (used for turfing) on d/s slope was reported as a Contractual
challenge at this site and other sites in KaWRD. SPMU was recommended to
consider the use of “Zoysia grass”, which is drought resistant.
Following this visit, CPMU carried out 3rd party NDT (Schmidt hammer rebound)
tests on M20 concrete for dam top leadoff drain, chute drain, and longitudinal drain
works. The tests gave satisfactory results but with some honeycombing present.
Noted construction compliance issues:
No. Deficiency / Observation Status Remarks
1.
Observed longitudinal crack adjacent to the d/s kerb between CH 0+390 and CH 0+420 m and other minor cracks on d/s side of dam crest
Closed Cracks repaired
2.
Construction of the lead-off (longitudinal) drain at dam top (downstream side) before repair of cracks
Open
Longitudinal crack was repaired but compaction was done by manual tampers not hand-held pneumatic compactor. SPMU recommended monitoring of any potential settlement of the dam top lead-off drain.
3. Defects such as honeycombing observed in M20 concrete of lead off
Open To be rectified.
Project Rehabilitation Report of Upper Mullamari Dam
33 | P a g e
drain
4. Loose soil around of lead off drain Open To be properly compacted.
5. V-notch weir chamber full of water Open
Chamber needs to be effectively dewatered and properly graded for positive drainage before installation of V-notch weir.
6. No staff gauge for V-notch weir measurement
Open
To be provided upstream of the v-notch
at a distance ≥4×h (where h is maximum height of the V-notch weir).
7. Deep rain cuts on d/s slope of dam Open To be properly rectified.
8. Contract expired on 01/12/17 Open EOT to be approved.
8.4. Summary of Compliance by SPMU
Compliance letter received from SPMU against the CPMU experts’ comments during
construction site visits is shown below on pages 34 to 36.
8.5. Summary of any Special Visits made by CWC/World Bank/Expert
Committee
Nil
8.6. Summary of Technical Assistance provided by CPMU
Review of PST. Review of design flood.
Provided technical guidance on maintaining quality of works as per design, contract agreement technical specification and best engineering practices.
Third party quality control tests.
9. ENVIRONMENTAL AND SOCIAL MANAGEMENT
FRAMEWORK (ESMF)
9.1 Basic Details
Sl. No.
Item Yes / No Remarks
a. ESMF Issue Identified in PST Yes
b. Mitigation Measures Proposed Yes
c. Any Rehabilitation and Resettlement involved No
d. Site Visit Date of CPMU E&S Specialists -
e. Site Visit Report of CPMU E&S Specialists -
9.2 Summary of Observations
ESMF management during implementation was generally satisfactory but PPE was
hardly during construction. ESMF OK Card is attached in Annexure E.
9.3 Details of ESMF/EIA study (if any)
Nil.
Project Rehabilitation Report of Upper Mullamari Dam
34 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
35 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
36 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
37 | P a g e
10. OTHER NON-STRUCTURAL INTERVENTIONS
10.1 Basic Details
Sl. No.
Item Yes / No Remarks
a
Emergency Action Plan (EAP)
(i) EAP Available at Site
(ii) EAP Prepared under DRIP
(iii) EAP Published
(iv) Stake holder consultations
No
Yes
No
No
DBA, inundation maps and EAP are currently being undertaken by SPMU
b. O&M Manual availability Yes It is to be revised as per guidelines issued by Central Water Commission (CWC) in January 2018
c. Inflow Forecasting No
d. DHARMA Implementation Yes In progress
e. Siren No Needs to be installed
10.2 Summary of Observations
Nil
11. PENDING REHABILITATION WORKS
11.1 Details of pending works
i. Complete flood routing study & determine MWL for the revised design flood.
Check adequacy of available freeboard.
ii. Carryout DBA and prepare inundation maps and EAP.
iii. Preparation of O&M Manual as per guideline published by DRIP.
iv. Completion of data entry in DHARMA.
11.2 Further course of action
All pending actions stated above should be completed before December 2019.
12. REFERENCES
i. PST
ii. DSRP report
iii. Construction site visit report.
iv. Information received from SPMU from time to time
v. Completion Certificate.
vi. World Bank approval
vii. Third party testing.
viii. Compliance letters from SPMU.
ix. ESMF OK Card
Project Rehabilitation Report of Upper Mullamari Dam
38 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Upper Mullamari Dam
39 | P a g e
Annex A: PST Approval Letter
Project Rehabilitation Report of Upper Mullamari Dam
40 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
41 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
42 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Upper Mullamari Dam
43 | P a g e
Annex B: Drawings issued for
Rehabilitation measures
Project Rehabilitation Report of Upper Mullamari Dam
44 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Upper Mullamari Dam
45 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
46 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
47 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
48 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Upper Mullamari Dam
49 | P a g e
Annex C: Completion Certificate
Project Rehabilitation Report of Upper Mullamari Dam
50 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Upper Mullamari Dam
51 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
52 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
53 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
54 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
55 | P a g e
Annex D: Third Party QC Tests
Project Rehabilitation Report of Upper Mullamari Dam
56 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Upper Mullamari Dam
57 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
58 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Upper Mullamari Dam
59 | P a g e
Annex E: ESMF OK Card
Project Rehabilitation Report of Upper Mullamari Dam
60 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Upper Mullamari Dam
61 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
62 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
63 | P a g e
Annex F: Photographs Before and
After Rehabilitation Works
Project Rehabilitation Report of Upper Mullamari Dam
64 | P a g e
THIS PAGE IS LEFT BLANK INTENTIONALLY
Project Rehabilitation Report of Upper Mullamari Dam
65 | P a g e
Approach Road - Before
Approach Road – During Construction
Project Rehabilitation Report of Upper Mullamari Dam
66 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
67 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
68 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
69 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
70 | P a g e
Approach Road – After
Embankment Dam Downstream Slope – Before
Project Rehabilitation Report of Upper Mullamari Dam
71 | P a g e
Project Rehabilitation Report of Upper Mullamari Dam
72 | P a g e
Embankment Dam Top & D/s Slope Drains – During Construction
Project Rehabilitation Report of Upper Mullamari Dam
73 | P a g e
Embankment Dam Top & D/s Slope Drains – After
Project Rehabilitation Report of Upper Mullamari Dam
74 | P a g e
Upstream Slope Riprap – Before
Upstream Slope Riprap – During Construction
Project Rehabilitation Report of Upper Mullamari Dam
75 | P a g e
Upstream Slope Riparap – After
Project Rehabilitation Report of Upper Mullamari Dam
76 | P a g e
Dam Top Lead-off Drain – During Construction
Dam Top Lead-off Drain – After (Also showing 3rd Party NDT tesing by CPMU)
Project Rehabilitation Report of Upper Mullamari Dam
77 | P a g e
V-notch Weir Chamber – During Construction
Project Rehabilitation Report of Upper Mullamari Dam
78 | P a g e
V-notch Weir Chamber – After
V-notch Weir - After