pmp exam flashcards presentation 2 of 5 ( pmbok - 5th edition - pmi ) download it in powerpoint

99
Discretio nary Dependenc y Cost of Quality (COQ) Summary Activity Baseline Activity Splitting Gantt Chart PMP EXAM FLASHCARDS By Jonathan Donado Over 500 dynamic Flashcards in PowerPoint PART 2 of 5

Upload: jonathan-donado

Post on 14-Feb-2017

130 views

Category:

Business


0 download

TRANSCRIPT

Page 1: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

DiscretionaryDependency

Cost ofQuality (COQ)

Summary Activity

Baseline

ActivitySplitting

Gantt Chart

PMP EXAM FLASHCARDS

By Jonathan Donado

Over 500 dynamic Flashcards in PowerPoint

PART 2 of

5

Page 2: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

52

About me

Linkedin.com/in/jonathandonado

www.branded.me/jonathandonado

Twitter.com/donadosays

Bilingual senior general management executive with expertise in international

business and Mergers & Acquisitions (M&A)

If you like the Flashcards, please give a ”Like” in SlideShare. It’s much appreciated !

o Education: - Senior Executive Fellow – Harvard University- MBA – IESE

o Certifications:- Six Sigma Black Belt (CSSBB) – ASQ Certified- Agile (ACP) – PMI Certified

Jonathan Donado

Page 3: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Data Date

A point in time when the status of the

project is recorded

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 4: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

DecisionTree Analysis

A diagramming and calculation technique for

evaluating the implications of a

chain of multiple options in the presence of

uncertainty

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 5: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Decomposition

A technique used for dividing and

subdividing the project scope and project deliverables into

smaller, more manageable parts

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 6: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Defect Repair

An intentional activity to modify a

nonconforming product or product component

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 7: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Dedicated Project Time

The amount of time that a resource is

available to the project taking into account the resource’s non-project

activities

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 8: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Define Scope

A process of developing a detailed

description of the project and the

product

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 9: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Define Estimate

An estimating technique usually made during the

planning phase that assigns a cost estimate range to

each work package in the WBS. This estimate typically falls between -5% and +10%

of the actual budget. Also known as bottom-up

estimating

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 10: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Deliverable

Any unique and verifiable product,

result, or capability to perform a service that is produced to complete a process,

phase, or project

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 11: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Deflection

The act of transferring all or part of a risk to another party, usually

by some form ofcontract

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 12: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Dependency

The relationship between project

activities

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 13: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Direct Costs

Costs incurred for the exclusive benefit of

the project

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 14: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

DiscreteEffort

An activity that can be planned and

measured and that yields a specific

output Note: Discrete effort is one of three earned value management (EVM)

types of activities used to measure work performance

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 15: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

DiscretionaryDependency

A preferred order of sequencing project

activities

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 16: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Dummy

An arrow in an AOA diagram that does not represent any actual work but is used to

show the relationship between two activities

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 17: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Duration

The total number of work periods required to complete an activity

or work breakdown structure component,

expressed in hours, days, or weeks

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 18: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Duration Compression

Shortening the project completion time

without changing the scope of the project

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 19: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Early FinishDate

In the critical path method, the earliest

possible point in time when the uncompleted portions of a schedule

activity can finish based on the schedule network logic, the data date, and any schedule constraints

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 20: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Early StartDate

In the critical path method, the earliest

possible point in time when the uncompleted portions of a schedule

activity can start based on the schedule network

logic, the data date, and any schedule constraints

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 21: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Earned Value(EV)

The measure of work performed expressed

in terms of the budget authorized

for that work

Explanation: Sum of costs estimates for activities completed during a given project

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 22: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Earned Value(EV) Analysis

The measurement of actual project status

versus expected project status as of the

measurement date

Explanation: Sum of costs estimates for activities completed during a given project

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 23: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Earned ValueManagement

A methodology that

combines scope, schedule, and resource

measurements to assess project performance and

progress

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 24: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Effort

The number of labor units required to

complete a schedule activity or work

breakdown structure component, often

expressed in hours, days, or weeks

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 25: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Effort Estimate

Calculation of the number of person hours

or days needed to complete an activity

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 26: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

EMV

A statistical technique that calculates the

average outcome when the future includes

scenarios that may or may not happen

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 27: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

End User

The person or group who will use the product

produced by the project

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 28: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

EnterpriseEnvironmental

Factor

Conditions, not under the immediate control of the

team, that influence, constrain, or direct the

project, program, or portfolio

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 29: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Estimate at Completion

(EAC)

The expected total cost of completing all work

expressed as the sum of the actual cost to date and the estimate to complete

EAC = AC + ETC

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 30: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Estimate to Complete

(ETC)

The expected cost to finish all the remaining

project work

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 31: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Ethics

In the conduct of their operations, state organizations and their

employees will employ information technology in a legal

and ethical manner consistent with government statutes, rules,

and regulations. Information technology will not be used for

purposes that are unrelated to the state organization’s mission or

violates state or federal law

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 32: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Execution Process Group

Those processes performed to complete

with work define in project management

plan to satisfy the project specifications

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 33: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Expectancy

Theory that proposes that employees’ effort will lead to effective performance and the

employees will be rewarded for

accomplishments

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 34: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Expected Monetary Value

The product of an event's probability of occurrence and

the gain or loss that will result. For example, if there is a 60 percent probability that

it will rain, and rain will result in a $100 loss, the expected monetary value of the rain

event is $60 (.6 x $100)

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 35: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Expert Judgement

Using subject matter experts to assist in

decision making

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 36: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

External Dependency

A relationship between a project activity and a

factor outside the scope of the project that

influences the completion of that activity

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 37: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Fast Tracking

A schedule compression technique, in which activities or phases normally done in

sequence are performed in parallel or overlapping for at least a portion of

their duration

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 38: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Feasibility Study

A study undertaken to determine whether a

project is viable

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 39: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Financial Audit

A thorough examination of a project by an evaluation team

which includes a detailed overview of the project’s

financial procedures, budgets, records, etc. It may deal with

a project as a whole or the separate individual parts of a

project

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 40: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Financial Closure

The process of completing and terminating the financial and budgetary aspects of the project being performed. It

includes both (external) contract closure and(internal)

project account closure

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 41: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Finish-to-Finish

A logical relationship in which a successor activity cannot finish until a predecessor

activity has finished

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 42: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Finish-to-FinishDependency

When the completion of an activity is

dependent on the completion of the preceding activity

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 43: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Finish-to-Start

A logical relationship in which a successor activity cannot start until a predecessor

activity has finished

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 44: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Finish-to-StartDependency

When the start of an activity is dependent on the completion of the previous activity

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 45: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Firm Fixed Price

Contract where buyer pays the seller a set

amount, regardless of the seller’s cost

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 46: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Fishbone Diagram

A graphical diagram that shows how causes or

potential causes relate to create potential

problems. Also known as Ishikawa diagram

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 47: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Fixed Cost

A cost that remains constant regardless of a

change in production

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 48: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Fixed FormulaMethod

A method of estimating Earned Value in which a

specified percentage of the budget value of a work

package is assigned to the start milestone and the remaining percentage is assigned when the work

package is complete

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 49: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Fixed Price Contract

(FPC)

A contract where work is performed or a product

is provided for a predetermined price

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 50: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Fixed Price Incentive (FPI) Fee Contract

A fixed price contract that contains incentives

for meeting or exceeding predetermined specifications

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 51: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Fixed Resources An amount of a

resource (human, equipment, material)

that cannot be changed

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 52: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Float

Another term for Slack. The amount of time a task can be delayed

without delaying the project’s completion

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 53: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Flowchart A diagram showing the

steps in a process or system from beginning

to end

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 54: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Forecast A prediction of future project status

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 55: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Forward

Pass

A critical path method technique for calculating the early start and early finish dates by working

forward through the schedule model from the

project start date or a given point in time

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 56: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Formal Acceptance

When the authorized stakeholder provides

sign-off, indicating the product has been

received and is acceptable

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 57: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Free Float

The amount of time that a schedule activity can be delayed without delaying the early start date of any

successor or violating a schedule constraint

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 58: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Functional

Organization

An organizational structure in which staff is

grouped by areas of specialization and the project manager has

limited authority to assign work and apply resources

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 59: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

FunctionalManager

The person responsible for the activities of a

specific functional department

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 60: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Functional

Requirements

Conditions that the product must meet to

support how the end users will interact with the

product

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 61: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Gantt Chart

A bar chart of schedule information where

activities are listed on the vertical axis, dates are

shown on the horizontal axis, and activity durations

are shown as horizontal bars placed according to

start and finish dates

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 62: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Grade

A category or rank used to distinguish items having the same functional use (e.g.,"hammer"), but do

not share the same requirements for quality (e.g., different hammers may need to withstand

different amounts of force)

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 63: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

GERT

Network analysis technique that allows

for loops or conditional branches

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 64: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Governance

The overall structure of the roles, responsibilities

and relationships between the project decision

makers and the organization’s long-term

operational decision makers

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 65: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Guideline

Used to define a collection of steps that are recommendations to be followed to meet

a stated policy(s)

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 66: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Hammock

An aggregate or summary activity (a group of related activities is shown as one

and reported at a summary level). A

hammock may or may not have an internal sequence

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 67: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Hanger

An unintended break in a network path. Hangers are usually caused by missing activities or missing logical

relationships

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 68: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Historical Information

Records of past projects that are used to assist in planning

future projects

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 69: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Human ResourcesManagement

Plan

A component of the project or program

management plan that describes the roles and

responsibilities, reporting relationships, and staff management

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 70: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Human ResourcesPlanning

The process of planning and hiring the project team, outlining roles, responsibilities and

reporting structure and defining team development

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 71: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Identify Risk

The process of determining which risks may affect the project and documenting their

characteristics

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 72: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Impact Statement

A cause and effect report generated at the manager level to show the impact

that new projects will have on current schedules

and resources as they enter the work stream

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 73: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Implementation

Occurs when products

have completed testing are moved into production

or into their working environment

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 74: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Independent Project Oversight

A process that employs a variety of quality control,

inspection, testing measurement, and other observation processes to

ensure that planned project objectives are achieved in

accordance with an approved plan

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 75: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Information Distribution

Enacting the communications plan

and providing stakeholders with

needed information in a timely manner

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 76: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Initiation

Formal definition and authorization of a new project or continuation of an ongoing project

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 77: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Inputs

Information that is required for a process

to begin

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 78: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Inspection

A quality control method to examine and

measure work results against baseline

specifications and requirements

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 79: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Indirect Costs

Overhead costs allocated to the project by the organization, as a cost of doing business

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 80: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Integration Change Control

Coordinating and managing change across the entire

project scope, schedule and budget

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 81: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Integration Planning

The planning process to establish how all

elements of the project will be coordinated and

how changes will be managed throughout

the project

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 82: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Integration Management

Plan

A plan that documents how elements of the

project will be integrated and outlines

how changes will be managed across the

project

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 83: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Invitation to Bid

Another term for Request For Proposal

(RFP)

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 84: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Ishikawa Diagram

Another term for the Fishbone Diagram or

the Cause-Effect Diagram

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 85: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Issue

An identified element or event that may have

a negative impact on the project and needs

to be avoided or resolved

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 86: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Issue Log

A document that outlines each project issue, along with the

person responsible for resolving it, status and

expected resolution date

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 87: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Iterating

Updating project plans to reflect changes that

occur during the planning phase and

throughout the project

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 88: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Kick-off Meeting

A meeting held at the end of major planning activities for

all stakeholders to provide an overview of the project and

outline expectations, ensure a common understanding of the

project and to build consensus and excitement

about the project

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 89: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Lag

The amount of time whereby a successor

activity will be delayed with respect

to a predecessor activity

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 90: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Late FinishDate (LF)

In the critical path method, the latest possible point in

time when the uncompleted portions of a schedule

activity can finish based on the schedule network logic, the project completion date,

and any schedule constraints

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 91: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Late StartDate (LS)

In the critical path method, the latest possible point in

time when the uncompleted portions of a schedule

activity can start based on the schedule network logic, the project completion date,

and any schedule constraints

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 92: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Lead

The amount of time whereby a successor

activity can be advanced with respect

to a predecessor activity

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 93: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Lessons Learned

The knowledge gained during a project which

shows how project events were addressed or should be addressed

in the future for the purpose of improving future performance

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 94: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Level of Effort

An activity that does not produce definitive

end products and is measured by the passage of time

Note: Level of effort is one of three earned value management (EVM) types of activities used to measure work performance

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 95: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Lessons Learned

The learning that takes place

during the project and is documented to provide

information on what went well and which aspects could have been improved. Lessons learned serve as references

for future projects

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 96: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Life Cycle Costing

Estimation of acquisition, operating

and disposal costs related to a product; not just project costs

to develop the product

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 97: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

LogicalRelationship

A dependency between two activities or

between an activity and a milestone

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 98: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Loop

A network path that passes the same node twice. Loops cannot be

analyzed using traditional network analysis

techniques such as CPM and PERT. Loops are

allowed in GERT

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 99: PMP Exam Flashcards   presentation 2 of 5   ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

52

Connect with me

Linkedin.com/in/jonathandonado

www.branded.me/jonathandonado

Twitter.com/donadosays

Bilingual senior general management executive with expertise in international

business and Mergers & Acquisitions (M&A)

If you like the Flashcards, please give a ”Like” in SlideShare. It’s much appreciated !

o Education: - Senior Executive Fellow – Harvard University- MBA – IESE

o Certifications:- Six Sigma Black Belt (CSSBB) – ASQ Certified- Agile (ACP) – PMI Certified

Jonathan Donado

> Check my other Project Management presentations on SlideShare <

THANK YOU