Oconomowoc Area School DistrictFacility Construction Update

July 14, 2017

Page 2: Oconomowoc Area School District Facility Construction

IXONIA ELEMENTARY SCHOOL

CONSTRUCTION BEGAN

June 9, 2017

CONSTRUCTIONCONTINUES

August 2017-August 2018

SITE PREPARATION, RETENTION POND EXCAVATION, WELL INSTALLATION,

PLAYGROUND EXCAVATION, DEVELOPMENT OF BUS LOOP, AND RELOCATION OF UTILITIES BEGAN

June 2017

RETENTION POND CLAY LINER INSTALLATION BEGAN, CONTINUED DEVELOPMENT OF BUS

LOOP, RELOCATION OF UTILITIES CONTINUED, NEW WELL INSTALLED & TIED INTO INTERIOR

LINES, REMOVAL OF OLD WELL BEGANJuly 1-14, 2017

The Ixonia site has benefited from a few days of dry weather, though rain has delayed outside work slightly.

The new well is connected to the interior supply lines and water softening system and is operational.

Site work continues with dirt removal behind the building, for the new hard surface play area and bus loop. Grading continues on the West side of the building for the pad of the new building addition.

BEGIN WATER STORAGE TANK INSTALLATION FOR FIRE PROTECTION

SYSTEM, BEGIN REMOVAL OF EXTERIOR CANOPIES & CEILING SECTIONS,

CONTINUE EXTERIOR EXCAVATION July 17-31, 2017

Page 3: Oconomowoc Area School District Facility Construction

GREENLAND ELEMENTARY SCHOOL

CONSTRUCTION BEGAN

June 9, 2017

CONSTRUCTION COMPLETE

August 21, 2017

SITE DEMOLITION, BEGAN INSTALLATION OF SERVICE & FEEDER CONDUIT, BEGAN INSTALLATION OF PIPING, BEGAN

ROOF REMOVAL, BEGAN DUCT WORK INSTALLATIONJune 10-July 14, 2017

CONTINUE FIRE ALARM SYSTEM & EMERGENCY LIGHTING INSTALLATION, BEGIN CORRIDOR LIGHTING INSTALLATION,

CONTINUE DUCT WORK INSTALLATION, CONTINUE REMOVAL OF FURNACE/BOILER, CONTINUE ROOF REMOVAL AND REPLACEMENT

July 17-31, 2017

Main water lines at Greenland are nearly complete and pressure testing should begin within a week. Water lines continue to be run into classrooms from the main line. The exterior cuts have been made to install the new unit ventilators and roofing removal and installation continues. Installation of the new transformer unit is complete.

Page 4: Oconomowoc Area School District Facility Construction

PARK LAWN ELEMENTARY SCHOOL

.

CONSTRUCTION BEGAN

June 9, 2017

CONSTRUCTION COMPLETE

August 21, 2017

SITE DEMOLITION, CONDUIT RACK INSTALLATION, INSTALLATION OF PIPING, ROUGH-IN FOR UNIT VENTILATORS, FIRE

ALARM SYSTEM INSTALLATION, DUCT WORK INSTALLATIONJune 10-July 14, 2017

CONTINUE INSTALLATION OF PIPPING, CONTINUE DUCT WORK INSTALLATION,

COMPLETE FIRE ALARM SYSTEM INSTALLATION, BEGIN NEW ELECTRICAL

PANELS IN BOILER ROOMJuly 17-31, 2017

Main water lines at Park Lawn are also near completion and pressure testing should being within a week. Water

lines continue to be run into classrooms from the main line. A

prototype installation mock-up of a unit ventilator has been prepared at

Park Lawn, in advance of the ventilator installation phase, to ensure

accuracy. Once roof replacement is complete at Greenland, Park Lawn

roof work will begin.

Page 5: Oconomowoc Area School District Facility Construction

MEADOW VIEW ELEMENTARY

The archeologist’s report from the Commonwealth Heritage Group has been submitted to, and accepted by, the Wisconsin Historical Society. The Commonwealth Heritage Group has also forwarded this approval to the DNR, and the NE Corridor project received its Notice of Intent permit from the DNR this week. The City of Oconomowoc is hoping to begin work at the site within the next two weeks with initial paving completion in early November, 2017.

SCHEMATIC DESIGNS PRESENTED TO OASD

SCHOOL BOARDJune 20, 2017

DESIGN DEVELOPMENT & CONSTRUCTION

DOCUMENTSJuly 2017-March 2018

CONSTRUCTION BEGINS

April 2018

GROUND BREAKING

CEREMONYMay 2018

BIDDING OPENMarch 2018

CONSTRUCTION COMPLETE

August 2019

CELEBRATION OF COMPLETIONAugust 2019

The OASD School Board approved initial schematic designs for the new Meadow View Elementary School at their June 20, 2017, meeting. The design and development phases will continue through the spring of 2018 before public bidding and construction begin.

Page 6: Oconomowoc Area School District Facility Construction

OHS: MAIN & EAST CAMPUS

Visioning for improvements and renovations to OHS Main Campus and East Campus (known formerly as the Wilkinson building) has begun. This visionary team is comprised of teachers, administration, and staff from EUA working together to create instructional space for a variety of innovative programs such as science, STEM, bio-medical, business, engineering, design, digital arts, communications, government and public administration.

The project will include:• Renovation of existing OHS manufacturing and building trades

classrooms• Renovation of existing OHS space for an automotive classroom• Creation of a permanent, lighted walking path with video

surveillance, connecting OHS Main Campus and East Campus• Renovation of the East Campus building to create instructional

capacity for approximately 300 OHS students• Relocation of the district administrative offices currently housed

at Meadow View Elementary.

OHS MAIN CAMPUS & OHS EAST CAMPUS INSTRUCTIONAL SPACE

PROJECT VISIONING BEGAN

April 2017

DESIGN PHASEMay-November 2017

CONSTRUCTION BEGINS

December 2017/January 2018

CELEBRATION OF COMPLETION

September 2018

PUBLIC BIDDING PHASEDecember 2017

CONSTRUCTION COMPLETE

August 2018