![Page 1: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/1.jpg)
Street Maintenance Program Managing Pavements
Richard E Martinez Assistant Director
Transportation and Public Works Department
October 9, 2019
![Page 2: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/2.jpg)
Pavement Management Overview
• Street System Inventory- 7,907 LM
• Street Condition Assessments (3 year cycle) • Prioritize Street Construction and Maintenance • Identify the Proper Pavement Treatments • Implement Proper Maintenance Cycles 2
![Page 3: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/3.jpg)
3
Service Areas
![Page 4: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/4.jpg)
Asset Management Pavement Infrastructure
4
![Page 5: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/5.jpg)
Pavement Management “The Good, The Bad and the Ugly”
• Maintenance Programs • Decision Making Process
– Data Collection – Asset Management System – Street Selection
• Right Street, Right Time, Right Application
• Barriers – Funding – Resources (Contractors, Materials)
5
![Page 6: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/6.jpg)
“The Good”
6
![Page 7: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/7.jpg)
“The Bad”
7
![Page 8: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/8.jpg)
“The Ugly”
8
![Page 9: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/9.jpg)
In-house
• Pothole Repair • Base and Pavement Repair • Concrete Repair • Chip Sealing • Crack Sealing • Asphalt Mill and Overlay • Bridge and Guardrail Repair
Contractual • Bridge Repair- Structural • Asphalt Mill and Overlay • Hot in Place Recycling • Micro-surfacing • Reclamation • Fog Sealing • Joint Sealing • Concrete Restoration
– Class B Repairs – Panel Replacement
9
Maintenance Programs
![Page 10: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/10.jpg)
Concrete Infrastructure Repair
10
$ 2.00 Linear Ft
Joint Seal - $21,000 Lane Mile
![Page 11: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/11.jpg)
Pavement Preservation
11
$ 2.10 Sq/Yd $ 0.13 Sq/Yd
Chip Seal - $16,000 Lane Mile Crack Seal -$1,000 Lane Mile
![Page 12: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/12.jpg)
Fog Sealing
12
![Page 13: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/13.jpg)
Seal Coating
13
![Page 14: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/14.jpg)
Street Reclamation
14
![Page 15: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/15.jpg)
15
Pothole Repair
High Priority Customer Satisfaction Indicator of Network Conditions
Sustainable Repairs Squared Tacked Compacted
Repaired Within 48 Hours 60% within 24 Hours
![Page 16: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/16.jpg)
Data Collection Assets Quantity Unit
Bridge/Culvert 422 EA
End of Road Barricade 1,100 EA
Guardrails 166 EA
Pavement 7,907 LM
Pavement Markings 8,591,487 LF
Pavement Symbols 8,775 EA
Railroad Signals 392 EA
ADA Ramps 32,529 EA
Sidewalk 3,638,823 LF
Signal Intersections 916 EA
Signs 127,902 EA
Street Lights 63,613 EA
Traffic Signal Heads 4,832 EA
• Infrastructure Condition Assessment • Customer Service and Work Orders • Advanced Modules
• Risk • Budgeting • Forecasting
![Page 17: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/17.jpg)
17
Network Conditions
![Page 18: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/18.jpg)
Street Selection
18
• Asset Condition - Pavements • Asset Segment – Work
Orders • Multimodal Aspects
• Bus Stops, Safe Routes and Proximity to Schools
• Population Density • Bus Stop Ridership –
Sidewalks, Bond Selection • Equity
– Condition
– Proactive Response
![Page 19: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/19.jpg)
Asset Management Advanced Modules
19
• Pavement Deterioration Curve
• Area of Ideal Maintenance • Area of Pavement
Preservation • Area of Recapitalization
![Page 20: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/20.jpg)
Reactive Maintenance
Time- 25 Years
Pave
men
t Con
ditio
n Preventive Maintenance
Pavement Life Extended
Optimized Maintenance- Asphalt
Rehabilitation / Reconstruction
Expensive Maintenance Zone
Effective Maintenance Zone
![Page 21: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/21.jpg)
Time- 40 Years
Pave
men
t Con
ditio
n Optimized Maintenance- Concrete
Pavement Life Extended
Reconstruction / Rehabilitation
![Page 22: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/22.jpg)
Decision Trees - Deduct Factors
22
![Page 23: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/23.jpg)
23
• System Runs Multiple Scenarios • Recommends Funding • Distribution
– Worst First vs Network Effectiveness
• Maintenance Distribution • Rehab Distribution
– Preservation vs Rehabiliation
• Recapitalization Distribution – Bond
Budget and Risk Modules
![Page 24: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/24.jpg)
Maintenance Cycles
24
New Pavement
Crack / Joint Seal
3 Years Flexible 8 Years Rigid
Full Sealant 8 Years Flexible
Rehabilitation
16 Years flexible
17 Years
Rigid
• 25 Year Street Life Cycle - Asphalt – Scheduled Maintenance, Sealants to
Rehabilitation – Recapitalization, Full Reconstruction
• 40 Year Street Life Cycle -
Concrete
– Joint Sealing to Panel Replacement – Recapitalization, Full Reconstruction
• Optimum Maintenance Cycle
– 16 Years- Asphalt – 25 Years- Concrete
• ROI - Minimal Maintenance
• Optimum-Short Cycle
– Deter Rehabilitation Costs
![Page 25: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/25.jpg)
25
$-
$5,000,000
$10,000,000
$15,000,000
$20,000,000
$25,000,000
$30,000,000
$35,000,000
$40,000,000
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
FY2026
FY2027
13.2M 13.3M 13.4M 13.4M 13.5M
13.6M 13.6M
13.7M 13.7M
13.7M 13.7M
Current Budget Funding Gap
Streets Funding Gap KPI – 70 Condition Rating
![Page 26: Managing Pavements - TML Conference...Pavement Management Overview • Street System Inventory - 7,907 LM • Street Condition Assessments (3 year cycle) • Prioritize Street Construction](https://reader034.vdocuments.site/reader034/viewer/2022042111/5e8c7273cc8e8a466b38b09f/html5/thumbnails/26.jpg)
Preservation or Potholes?