introduction of ertms in the uk - a view after our first 12 months

13
Introduction of ERTMS in the UK - a view after our first 12 months Peter Leppard Peter Leppard Arriva UK Trains

Upload: duongdang

Post on 12-Feb-2017

217 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Introduction of ERTMS in the UK - a view after our first 12 months

Introduction of ERTMS in the UK - a view after our first 12 months

Peter LeppardPeter LeppardArriva UK Trains

Page 2: Introduction of ERTMS in the UK - a view after our first 12 months

The Cambrian line• UK’s pilot site for

ERTMS Level 2:Sh b Ab t th− Shrewsbury-Aberystwyth (‘Cambrian main line’ – part of the Trans European Network), and

− Machynlleth-Pwllheli (‘Cambrian Coast’)

− Both are single lines with passing loopsloops

− Previously Radio Token Block, with no train detection and ‘sprung’ points

• Trains: 24 x ATW 2 car class 158 based− 24 x ATW 2-car class 158, based at Machynlleth

− 3 x NR class 97 for engineering or special trains, based ator special trains, based at Shrewsbury

Page 3: Introduction of ERTMS in the UK - a view after our first 12 months

Cambrian ERTMS projectCambrian ERTMS project

• Authorised by UK government 2003Authorised by UK government 2003• 218 route-km• Contract awarded to Ansaldo-STS 2006Contract awarded to Ansaldo STS 2006• Joint project team Network Rail/Ansaldo/Arriva Trains

WalesWales• Harlech-Pwllheli commissioned into public use in

October 2010, the remainder in March 2011• Train performance quite poor at first – ERTMS issues

meant we were achieving weekly punctuality of c.60% • Several ‘SPADs’ in the early weeks • But, 12 months on, we are almost back to normal

punctuality!

Page 4: Introduction of ERTMS in the UK - a view after our first 12 months

International context

• Previous ERTMS projects worldwide had new lines and/or rolling stock - with considerable trial & test

i i bli i trunning in a non-public environment • Retro-fit of both rolling stock and infrastructure on

Cambrian was much more difficult to manage!Ca b a as uc o e d cu t to a age• Easing ourselves in slowly was essential:

− Level 0 (Level STM) running before Level 2 − Harlech-Pwllheli before full-CambrianHarlech Pwllheli before full Cambrian

• We have the 1st passenger terminus and 1st train-maintenance depot in the world on an ERTMS Level 2 railway2 railway

• Transition from traditional semaphore signals to ERTMS Level 2 (near Shrewsbury) is also a first

Page 5: Introduction of ERTMS in the UK - a view after our first 12 months

ERTMS on-board equipment, on class 158q p ,

Eurocabinet, EVC, GSM-R

GSM-R Voice antenna

fans, GSM-R rack & Juridical Recorder

Unit (JRU)

Data antenna& GPS

DMI & GSM-R radio

Balise Transmission Module (BTM)( )

Train & x-feed jumpers &

ASIG unit (57

Balise antenna

Odometry sensor

Doppler radar

ASIG unit (57 car)

Page 6: Introduction of ERTMS in the UK - a view after our first 12 months

Driver-machine interface (DMI)Driver-machine interface (DMI)

Page 7: Introduction of ERTMS in the UK - a view after our first 12 months

Wh t h b th bl ?What have been the problems? -(i) Trains• Making alterations to 20-year-old trains causes faults!

− Driver-Machine Interface (DMI) screen going blankB li T i i M d l (BTM) f il− Balise Transmission Module (BTM) failures

− Odometry faults− Non-ETCS faults

DMI ‘ h d t’ b li ht ( ll b ) b t t• DMI ‘washed out’ by sunlight (very small cabs), but too bright at night. (Also GSM-R radio screen brightness)

• Displayed ‘release speed’ can confuse• Displayed release speed can confuse • Some icons on the DMI are too small/too similar• ERTMS has a more cautious braking curve than humansERTMS has a more cautious braking curve than humans• Cab boot-up times• Upto 12 months to achieve software upgrades• Upto 12 months to achieve software upgrades

Page 8: Introduction of ERTMS in the UK - a view after our first 12 months

What have been the problems? -p(ii) Infrastructure• Reduced capacity when crossing at loops• Reduced capacity when crossing at loops• Permanent speed restrictions are applied too restrictively• Axle counter data over FTN (Fixed Telecomms Network)• Axle-counter data over FTN (Fixed Telecomms Network)• Radio Block Centre (RBC) becoming ‘confused’, by

− 2 trains in the same platform both seeking Movement Authorities2 trains in the same platform both seeking Movement Authorities− Crossing trains at loops ‘too quickly’− Trains shunting from the running line into the depot

Mi t f il /h d k /h• Mixture of mile/hr and km/hr• Lack of incorporation of automatic level crossings into

ERTMS (only the CCTV level crossings are included)ERTMS (only the CCTV level crossings are included) • 2 different certifications – Interoperable/non-TEN

Page 9: Introduction of ERTMS in the UK - a view after our first 12 months

Safety and risk

• The system does always act correctly safety-wisey y y y• No system fault in traffic has been a wrong-side

safety fault (but train performance does suffer!)All ‘SPAD’ h d i hi h S L• All ‘SPAD’ events have stopped within the SvL

• Do we need a new SPAD category? – RSSB is consideringconsidering

• ERTMS requires a different approach to driving – HF issues maybe not yet fully understoody y y

Page 10: Introduction of ERTMS in the UK - a view after our first 12 months

Lessons learned for futureLessons learned for future schemes - 1

• ERTMS is still somewhat immature - an ongoing R&D g gproject for Europe! Don’t expect perfection on Day 1.

• Accept that derogations to TSIs etc. will be necessary • Integrating state-of-the-art kit onto existing infrastructure

& rolling-stock needs lots of care! • Do not underestimate the scale of change in the way the

railway operates, including operating Rules impact • Training and competence management of all staff needs

review

1

Page 11: Introduction of ERTMS in the UK - a view after our first 12 months

Lessons learned for futureLessons learned for future schemes - 2

• You cannot overdo the amount of testing – as reliability takes time to build (Hertford test-track now to be created)

• Do more Operations-scenario testing - in (better) simulators• But, however much you test, the unexpected will crop up,

once into day-to-day operation • Keep the project team together, after commissioning until

well into day-to-day operation• Include automatic odometry calculation at the outset• Use the need for a JRU to replace existing black-box

(OTMR) to create one data source

1

Page 12: Introduction of ERTMS in the UK - a view after our first 12 months

Have there been benefits from ERTMS on the Cambrian?

For the UK• Learning how ERTMS can work in a UK context (and that• Learning how ERTMS can work in a UK context (and that

ERTMS is not as well-developed technically as we’d hoped!)• Excellent experience of the problems of trying to convert an

i i ilexisting railway

Although for Arriva on the Cambrian lineAlthough, for Arriva on the Cambrian line…• …our very simple railway has been converted to something

much more complex!

Page 13: Introduction of ERTMS in the UK - a view after our first 12 months

We are determined to make Cambrian SERTMS a success – and it nearly is….!