architecture contribution to risk & evidence …cae inc. 1135 innovation drive ottawa, ont., k2k...

169
ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE INFORMED DECISION MAKING WITHIN THE CANADIAN SAFETY AND SECURITY PROGRAM (CSSP) Geneviève Dubé CAE Inc. Prepared By: CAE Inc. Senior Capability Engineering and Architecture SME, Defence & Security 1135 Innovation Drive, Ottawa, ON K2K 3G7 Contractor's Document Number: 113129-004 Version 01 PWGSC Contract Number: W7714-135838 Technical Authority: Shaye K. Friesen, Risk Assessment Analyst Disclaimer: The scientific or technical validity of this Contract Report is entirely the responsibility of the Contractor and the contents do not necessarily have the approval or endorsement of the Department of National Defence of Canada. Contract Report DRDC-RDDC-2017-C085 March 2017

Upload: others

Post on 06-Mar-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE INFORMED DECISION MAKING WITHIN THE CANADIAN SAFETY AND SECURITY PROGRAM (CSSP) Geneviève Dubé CAE Inc. Prepared By: CAE Inc. Senior Capability Engineering and Architecture SME, Defence & Security 1135 Innovation Drive, Ottawa, ON K2K 3G7 Contractor's Document Number: 113129-004 Version 01 PWGSC Contract Number: W7714-135838 Technical Authority: Shaye K. Friesen, Risk Assessment Analyst Disclaimer: The scientific or technical validity of this Contract Report is entirely the responsibility of the Contractor and the contents do not necessarily have the approval or endorsement of the Department of National Defence of Canada.

Contract Report DRDC-RDDC-2017-C085 March 2017

Page 2: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Page 3: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CAE Inc.

1135 Innovation Drive

Ottawa, Ont., K2K 3G7 Canada

Tel: 613-247-0342

Fax: 613-271-0963

ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE

INFORMED DECISION MAKING WITHIN THE CANADIAN SAFETY AND SECURITY PROGRAM (CSSP)

CONTRACT #: W7714-135838

FOR

DEFENCE RESEARCH AND DEVELOPMENT CANADA – CENTRE FOR SECURITY SCIENCE

222 Nepean Street, Ottawa, Ontario, K1A 0K2

3 1 M a r c h 2 0 1 7

Document No. 113129-004 Version 01

Page 4: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CAE Inc.

1135 Innovation Drive

Ottawa, Ont., K2K 3G7 Canada

Tel: 613-247-0342

Fax: 613-271-0963

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la

Défense nationale, 2017

Page 5: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – iii – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

A P P R O V A L S H E E T

Document No. 113129-004 Version 01

Document Name: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE

INFORMED DECISION MAKING WITHIN THE CANADIAN SAFETY AND SECURITY PROGRAM (CSSP)

Primary Author

Name Dr. Geneviève Dubé

Position Intermediate Test and Evaluation SME, Defence & Security, CAE Canada

Reviewer

Name for Ian Bayne

Page 6: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – iv – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Position Senior Capability Engineering and Architecture SME, Defence & Security, CAE Canada

Approval

Name Damon Gamble

Position Project Manager, Defence & Security, CAE Canada

Page 7: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – v – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

R E V I S I O N H I S T O R Y

Revision Reason for Change Origin Date

Version 01 Initial document issued 31 March 2017

Page 8: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – vi – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

T A B L E O F C O N T E N T S

1 INTRODUCTION ........................................................................................................................1

1.1 Background ...................................................................................................................................... 1

1.2 Objective .......................................................................................................................................... 1

1.3 Scope ................................................................................................................................................ 2

1.4 This Document ................................................................................................................................. 2

2 ENTERPRISE ARCHITECTURE ......................................................................................................4

2.1 Framework ....................................................................................................................................... 5

2.2 QualiWare ........................................................................................................................................ 6

3 METHOD ...................................................................................................................................9

3.1 Phase 1 – Literature Review .......................................................................................................... 12

3.1.1 Data Collection Plan .................................................................................................................... 12

3.2 Phase 2 – High Level Structure Development ................................................................................ 13

3.3 Phase 3 – Architecture Development ............................................................................................ 15

3.3.1 Strategic Views ........................................................................................................................... 16

3.3.2 Functional Decomposition Diagrams (OV5a) ............................................................................. 18

3.3.3 RA Methodologies/ Process (OV-5b) .......................................................................................... 25

3.3.4 Taxonomy ................................................................................................................................... 26

3.4 Phase 4 – External Validation and Final Architecture .................................................................... 27

Page 9: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – vii – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

4 HTML REPORT ......................................................................................................................... 28

4.1 Strategic View and Functional Decomposition .............................................................................. 28

4.2 RA Methodologies .......................................................................................................................... 28

4.3 Taxonomy....................................................................................................................................... 28

5 RECOMMENDATIONS AND NEXT STEPS ................................................................................... 29

5.1 Strategic Level ................................................................................................................................ 29

5.2 Program Level ................................................................................................................................ 30

5.3 Focus Area – Seamless Borders ..................................................................................................... 30

5.4 Discussion ...................................................................................................................................... 31

6 CONCLUSIONS ........................................................................................................................ 32

6.1 Expected Benefits .......................................................................................................................... 32

6.2 Limitations ..................................................................................................................................... 32

7 REFERENCES ........................................................................................................................... 33

APPENDIX A DATA COLLECTION PLAN .................................................................................. A-1

A.1 Key References ......................................................................................................................... A-1

APPENDIX B ARCHITECTURE ................................................................................................ B-1

B.1 CSSP Planning Cycle ................................................................................................................... B-1

B.2 Call for Proposal ......................................................................................................................... B-2

B.3 Focus Area Narratives ................................................................................................................ B-4

B.4 SPG ........................................................................................................................................... B-10

Page 10: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – viii – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

B.5 S&T Challenges ........................................................................................................................ B-11

B.6 Evidence-Based Analysis .......................................................................................................... B-14

B.7 Performance Measurement .................................................................................................... B-17

B.8 Community Engagement ......................................................................................................... B-19

B.8.1 Biological Hazard Portfolio ................................................................................................... B-20

B.8.2 Border and transportation Security Portfolio ...................................................................... B-23

B.8.3 Critical Infrastructure ........................................................................................................... B-36

B.8.4 E-Security Portfolio ............................................................................................................... B-40

B.8.5 Emergency Management, Systems and Interoperability Portfolio ...................................... B-42

B.8.6 Explosives Portfolio .............................................................................................................. B-43

B.8.7 Fire Services Portfolio ........................................................................................................... B-52

B.8.8 Natural Hazard Portfolio ...................................................................................................... B-58

B.8.9 Paramedic Services Portfolio ................................................................................................ B-63

B.8.10 Radiological and Nuclear Portfolio ....................................................................................... B-72

B.8.11 Police Law Enforcement Portfolio ........................................................................................ B-76

B.8.12 Surveillance, Intelligence and Interdiction Portfolio ............................................................ B-85

B.8.13 Psycho-Social Portfolio ......................................................................................................... B-88

APPENDIX C RA METHODOLOGIES ....................................................................................... C-1

C.1 AHRA .......................................................................................................................................... C-1

C.2 National Risk Assessment .......................................................................................................... C-4

Page 11: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – ix – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

APPENDIX D TAXONOMY ..................................................................................................... D-1

L I S T O F F I G U R E S

Figure 2-1: DNDAF ......................................................................................................................................... 5

Figure 2-2: QualiWare System (from: Instruction slides for DNDAF Course 2016-05-01) ............................ 8

Figure 3-1: Overview of the Methodology .................................................................................................. 11

Figure 3-2: High-Level Structure Development Cycle ................................................................................. 13

Figure 3-3: Data Collection Approach (1) .................................................................................................... 14

Figure 3-4: Data Collection Approach (2) .................................................................................................... 15

Figure 3-5: Architecture Development Process .......................................................................................... 16

Figure 3-6: CSS Strategic View (1) ............................................................................................................... 17

Figure 3-7: Final Strategic View .................................................................................................................. 18

Figure 3-8: Example of a Functional Model Diagram .................................................................................. 19

Figure 3-9: Decomposition of a Business Function ..................................................................................... 20

Figure 3-10: Architecture Example Level 1 ................................................................................................. 21

Figure 3-11: Architecture Example Level 2 ................................................................................................. 22

Figure 3-12: Architecture Example Level 3 ................................................................................................. 22

Figure 3-13: Architecture Example Level 4 ................................................................................................. 23

Figure 3-14: Architecture Example Level 5 ................................................................................................. 23

Page 12: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – x – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure 3-15: Architecture Example Level 6 ................................................................................................. 23

Figure 3-16: Interrelations between Processes .......................................................................................... 24

Figure 3-17: RA Placeholders/Gaps............................................................................................................. 25

Figure 3-18:AHRA Methodology ................................................................................................................. 26

Figure 3-19: AHRA Risk Event Taxonomy [Public Security Technical Program Planning Scenario Final Report] ............................................................................................................................................... 27

Figure B-1: CSSP Planning Cycle ................................................................................................................. B-1

Figure B-2: Call for Proposal (CFP) ............................................................................................................. B-2

Figure B-3: CFP – CSSP Funding ................................................................................................................. B-2

Figure B-4: CFP – Process ........................................................................................................................... B-3

Figure B-5: CFP – Notice of Proposed Procurement .................................................................................. B-3

Figure B-6: CFP – Process Phase 1 ............................................................................................................. B-4

Figure B-7: Focus Area Narratives .............................................................................................................. B-4

Figure B-8: Seamless Borders (SB) Narrative ............................................................................................. B-5

Figure B-9: SB - Portfolio Activities ............................................................................................................ B-5

Figure B-10: SB – Gaps ............................................................................................................................... B-6

Figure B-11: SB – Priorities ......................................................................................................................... B-6

Figure B-12: SB – De-risk ............................................................................................................................ B-7

Figure B-13: SB – Risk-Informed Delivery Cycle ......................................................................................... B-7

Page 13: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – xi – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-14: SB – Establish Clients Priorities .............................................................................................. B-8

Figure B-15: SB – Formulate Program ........................................................................................................ B-8

Figure B-16: SB – Generate Evidence through Projects ............................................................................. B-9

Figure B-17: SB – Provide Advice ............................................................................................................... B-9

Figure B-18: SPG ....................................................................................................................................... B-10

Figure B-19: Focus Area Priorities ............................................................................................................ B-10

Figure B-20: S&T Challenges .................................................................................................................... B-11

Figure B-21: S&T – Use Action Research or Similar Methodology ........................................................... B-11

Figure B-22: S&T – Strengthen Capacity of Emergency Responders ....................................................... B-12

Figure B-23: S&T – Use Broadband Wireless Technologies to Provide Next-Generation Reliable Communications ............................................................................................................................. B-12

Figure B-24: S&T – Make Use of Nano and/or Synthetic Biological Technology ..................................... B-13

Figure B-25: S&T – Enhance Ability of Maritime Operators and Partners to Accomplish Public Safety and Security Objectives .......................................................................................................................... B-13

Figure B-26: S&T – Develop and Assess Options for Next-Generation Surveillance of Canada's Northern Waters and Approaches .................................................................................................................. B-14

Figure B-27: Evidence-Based Analysis (EBA) ............................................................................................ B-14

Figure B-28: EBA – Risk Assessment Framework ..................................................................................... B-15

Figure B-29: EBA – Enable and Inform CSSP Decision Making ................................................................. B-15

Figure B-30: EBA – Risk Assessment in Targeted Domains ...................................................................... B-16

Figure B-31: EBA – National Risk Assessment .......................................................................................... B-16

Page 14: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – xii – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-32: Performance Measurement (PM) ....................................................................................... B-17

Figure B-33: PM – CSSP Performance Measurement Strategy ................................................................ B-17

Figure B-34: PM – Strategy Principles ...................................................................................................... B-18

Figure B-35: PM – Key Performance Indicators ....................................................................................... B-18

Figure B-36: PM – Performance Evaluation ............................................................................................. B-19

Figure B-37: Community Engagement (CE) .............................................................................................. B-19

Figure B-38: CE – Portfolios/CoP Management ....................................................................................... B-20

Figure B-39: Biological Hazards (BH) Portfolio ......................................................................................... B-20

Figure B-40: BH – Program of Work ......................................................................................................... B-21

Figure B-41: BH – Rapid Diagnostics and Situational Awareness ............................................................ B-21

Figure B-42: BH – Containment and Decontamination ........................................................................... B-22

Figure B-43: BH – Medical Countermeasures .......................................................................................... B-22

Figure B-44: Border and Transportation Security (BTS) Portfolio ............................................................ B-23

Figure B-45: BTS – Policy/Operational Context ....................................................................................... B-23

Figure B-46: BTS – Partners ...................................................................................................................... B-24

Figure B-47: BTS – Program of Work ....................................................................................................... B-24

Figure B-48: BTS – Biometrics and Passenger Screening ......................................................................... B-25

Figure B-49: BTS – Biometrics – Existing Projects .................................................................................... B-25

Figure B-50: BTS – Biometrics – Activities for 2014/15 ........................................................................... B-26

Figure B-51: BTS – Biometrics – Remaining Challenges ........................................................................... B-26

Page 15: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – xiii – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-52: BST – Technologies to Increase Passenger Safety ............................................................... B-27

Figure B-53: BTS – Passenger Safety – Existing Projects .......................................................................... B-27

Figure B-54: BTS – Passenger Safety – Activities for 2014/2015 ............................................................. B-28

Figure B-55: BTS – Passenger Safety – Remaining Challenges ................................................................. B-28

Figure B-56: BTS – Technologies Supporting Fast Screening of Containers ............................................ B-29

Figure B-57: BTS – Technologies – Remaining Challenges ....................................................................... B-29

Figure B-58: BTS – Technologies – Pilots for Efficient Container Management ...................................... B-30

Figure B-59: BTS – Assessing Cyber Vulnerabilities ................................................................................. B-30

Figure B-60: BTS – Biometrics – Existing Projects .................................................................................... B-31

Figure B-61: BTS – Cyber Vulnerabilities – Activities for 2014/2015 ....................................................... B-31

Figure B-62: BTS – Cyber Vulnerabilities – Remaining Challenges .......................................................... B-32

Figure B-63: BTS – Arctic Security ............................................................................................................ B-32

Figure B-64: BTS – Arctic Security – Existing Projects .............................................................................. B-33

Figure B-65: BTS – Arctic Security – Activities for 2014/2015 ................................................................. B-33

Figure B-66: BTS – Arctic Security – Remaining Challenges ..................................................................... B-34

Figure B-67: BTS – Integration and Analysis ............................................................................................ B-34

Figure B-68: BTS – Integration and Analysis – Existing Projects .............................................................. B-35

Figure B-69: BTS – Integration and Analysis – Activities for 2014/2015 .................................................. B-35

Figure B-70: BTS – Integration and Analysis – Remaining Challenges ..................................................... B-36

Figure B-71: Critical Infrastructure (CI) Portfolio ..................................................................................... B-36

Page 16: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – xiv – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-72: CI – Focus ............................................................................................................................. B-37

Figure B-73: CI – Program of Work .......................................................................................................... B-37

Figure B-74: CI – Call for Proposals (CFP) Projects ................................................................................... B-38

Figure B-75: CI – Targeted Investments ................................................................................................... B-38

Figure B-76: CI – Technology Acquisition ................................................................................................. B-39

Figure B-77: CI – Community Development Workshops ......................................................................... B-39

Figure B-78: E-Security (E-S) Portfolio ..................................................................................................... B-40

Figure B-79: E-S – Operation Capabilities ................................................................................................ B-40

Figure B-80: E-S – Policy/Operational Context ........................................................................................ B-41

Figure B-81: E-S – Program of Work ........................................................................................................ B-41

Figure B-82: Emergency Management, Systems and Interoperability (EMSI) Portfolio.......................... B-42

Figure B-83: EMSI – Policy/Operational Context ..................................................................................... B-42

Figure B-84: EMSI – Program of Work ..................................................................................................... B-43

Figure B-85: Explosives (Exp) Portfolio .................................................................................................... B-43

Figure B-86: Exp – Specific S&T Areas ...................................................................................................... B-44

Figure B-87: Exp – Policy and Operational Context ................................................................................. B-44

Figure B-88: Exp – Metric Based on Resilience Four Pillars ..................................................................... B-45

Figure B-89: Exp – Program of Work ........................................................................................................ B-45

Figure B-90: Exp – Scenarios .................................................................................................................... B-46

Figure B-91: Exp – Analyze Scenarios....................................................................................................... B-46

Page 17: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – xv – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-92: Exp – Projects ...................................................................................................................... B-47

Figure B-93: Exp– Prevention ................................................................................................................... B-47

Figure B-94: Exp – Prevention – Existing Programs ................................................................................. B-48

Figure B-95: Exp – Prevention – Planned Activities ................................................................................. B-48

Figure B-96: Exp –Prevention – Remaining Challenges ........................................................................... B-49

Figure B-97: Exp – Preparedness ............................................................................................................. B-49

Figure B-98: Exp – Preparedness – Existing Projects ............................................................................... B-50

Figure B-99: Exp – Preparedness – Planned Activities ............................................................................. B-50

Figure B-100: Exp – Preparedness – Remaining Challenges .................................................................... B-51

Figure B-101: Exp – Preparedness- Existing Projects ............................................................................... B-51

Figure B-102: Fire Services (FS) Portfolio ................................................................................................. B-52

Figure B-103: FS – Primary Functions (PMS) ............................................................................................ B-52

Figure B-104: FS – Assess Impact of CSSP Output Upon Community ...................................................... B-53

Figure B-105: FS – Program of Work ........................................................................................................ B-53

Figure B-106: FS – Evidence-Based Decision Making ............................................................................... B-54

Figure B-107: FS – Evidence-Based Decision Making – Existing Work ..................................................... B-54

Figure B-108: FS – Evidence-Based Decision Making – Remaining Challenges ....................................... B-55

Figure B-109: FS – Dangerous Hazardous Goods ..................................................................................... B-55

Figure B-110: FS – Dangerous Hazardous Goods – Existing Work ........................................................... B-56

Figure B-111: FS – Dangerous Hazardous Goods – Remaining Challenges .............................................. B-56

Page 18: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – xvi – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-112: FS – Smart Firefighting ....................................................................................................... B-57

Figure B-113: FS – Smart Firefighting – Existing Work ............................................................................. B-57

Figure B-114: FS – Smart Firefighting – Remaining Challenges ............................................................... B-58

Figure B-115: Natural Hazard (NH) Portfolio ........................................................................................... B-58

Figure B-116: NH – Priorities .................................................................................................................... B-59

Figure B-117: NH – Policy/Operational Context ...................................................................................... B-59

Figure B-118: NH – Program of Work ...................................................................................................... B-60

Figure B-119: NH – Consolidated Priorities.............................................................................................. B-60

Figure B-120: NH – Priorities for Disaster Risk Reduction – Type of Work .............................................. B-61

Figure B-121: NH – Social Change ............................................................................................................ B-61

Figure B-122: NH – Social Change – Type of Work .................................................................................. B-62

Figure B-123: NH – Social Change – Planned Activities ........................................................................... B-62

Figure B-124: Paramedic Services (PMS) Portfolio .................................................................................. B-63

Figure B-125: PMS – Primary Functions ................................................................................................... B-63

Figure B-126: PMS – Assess the Impact of CSSP Outputs Upon Community........................................... B-64

Figure B-127: PMS – Policy/Operational Context .................................................................................... B-64

Figure B-128: PMS – Operational Context – Priority Domains ................................................................ B-65

Figure B-129: PMS – Program of work ..................................................................................................... B-65

Figure B-130: PMS – Mobilising Health Care ........................................................................................... B-66

Figure B-131: PMS – Mobilising Health Care – Existing Work ................................................................. B-66

Page 19: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – xvii – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-132: PMS – Mobilising Health Care – Remaining Challenges .................................................... B-67

Figure B-133: PMS – Evidence-Based Decision Making ........................................................................... B-67

Figure B-134: PMS – Evidence-Based Decision Making – Existing Work ................................................. B-68

Figure B-135: PMS – Evidence-Based Decision Making – Remaining Challenges .................................... B-68

Figure B-136: PMS – Standards Development ......................................................................................... B-69

Figure B-137: PMS – Standards Development – Existing Work ............................................................... B-69

Figure B-138: PMS – Standards Development – Remaining Challenges .................................................. B-70

Figure B-139: PMS – Practitioner Well-Being .......................................................................................... B-70

Figure B-140: PMS – Practitioner Well-Being – Existing Work ................................................................ B-71

Figure B-141: PMS – Practitioner Well-Being – Remaining Challenges ................................................... B-71

Figure B-142: Radiological and Nuclear (RN) Portfolio ............................................................................ B-72

Figure B-143: RN – Vulnerabilities ........................................................................................................... B-72

Figure B-144: RN – Investment Strategy .................................................................................................. B-73

Figure B-145: RN – Policy/Operational Context ....................................................................................... B-73

Figure B-146: RN – Program of Work ....................................................................................................... B-74

Figure B-147: RN – Quantitative and Qualitative Threat Assessment ..................................................... B-74

Figure B-148: RN – Quantitative and Qualitative Threat Assessment – Run Scenarios .......................... B-75

Figure B-149: RN – Projects List ............................................................................................................... B-75

Figure B-150: Police Law Enforcement (PLE) Portfolio ............................................................................ B-76

Figure B-151: PLE – Policy/Operational Context ...................................................................................... B-76

Page 20: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – xviii – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-152: PLE - Program of Work ...................................................................................................... B-77

Figure B-153: PLE – Priorities Areas ......................................................................................................... B-77

Figure B-153: PLE – Priorities Areas – Improving Economics................................................................... B-78

Figure B-154: PLE – Priorities Areas – Improving Economics – Existing Work ......................................... B-78

Figure B-155: PLE – Priorities Areas – Improving Economics – Remaining Challenges ........................... B-79

Figure B-156: PLE – Priorities Areas – Employing Emerging Technology ................................................. B-79

Figure B-157: PLE – Priorities Areas – Employing Emerging Technology – Existing Work ....................... B-80

Figure B-158: PLE – Priorities Areas – Employing Emerging Technology – Remaining Challenges ......... B-80

Figure B-159: PLE – Priorities Areas – Reducing the Cost and Time of Investigation .............................. B-81

Figure B-160: PLE – Priorities Areas – Reducing the Cost and Time of Investigation – Existing Work .... B-81

Figure B-161: PLE – Priorities Areas – Evidence-Based Decision Making ................................................ B-82

Figure B-162: PLE – Priorities Areas – Evidence-Based Decision Making – Existing Work ...................... B-82

Figure B-163: PLE – Priorities Areas – Evidence-Based Decision Making – Remaining Challenges ......... B-83

Figure B-164: PLE – Priorities Areas – Employing Emerging Technology ................................................. B-83

Figure B-165: PLE – Priorities Areas – Employing Emerging Technology – Existing Work ....................... B-84

Figure B-166: PLE – Priorities Areas – Employing Emerging Technology – Remaining Challenges ......... B-84

Figure B-167: Surveillance, Intelligence and Interdiction (SII) Portfolio .................................................. B-85

Figure B-168: SII – Objectives .................................................................................................................. B-85

Figure B-169: SII – Policy/Operational Context ....................................................................................... B-86

Figure B-170: SII – Program of Work........................................................................................................ B-86

Page 21: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – xix – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-171: SII – Action Plan ................................................................................................................. B-87

Figure B-172: SII – Canada’s Counter-Terrorism Strategy ....................................................................... B-87

Figure B-173: SII – DSO Readiness Committee Priorities ......................................................................... B-88

Figure B-174: Psycho-Social (PS) Portfolio ............................................................................................... B-88

Figure B-175: PS – Capability Gaps .......................................................................................................... B-89

Figure B-176: PS – Partners ...................................................................................................................... B-89

Figure B-177: PS – Policy/Operational Context ....................................................................................... B-90

Figure B-178: PS – Emerging Issues ......................................................................................................... B-90

Figure B-179: PS – Program of Work ....................................................................................................... B-91

Figure B-180: PS – Counter-Violent Extremism ....................................................................................... B-91

Figure B-181: PS – Counter-Violent Extremism – Existing Work ............................................................. B-92

Figure B-182: PS – Counter-Violent Extremism – Remaining Challenges ................................................ B-92

Figure B-183: PS – Support to First Responders and Public ..................................................................... B-93

Figure B-184: PS – Support to First Responders and Public – Existing Work ........................................... B-93

Figure B-185: PS – Support to First Responders and Public – Remaining Challenges ............................. B-94

Figure B-186: PS – Community Resilience – Existing Work...................................................................... B-94

Figure B-187: PS – Community Resilience – Remaining Challenges ........................................................ B-95

Figure B-188: PS – Community Resilience – Better Understand Behavioural Implications of Effective Communications ............................................................................................................................. B-95

Figure B-189: PS – Develop Effective Whole-of-Community Approaches for Building Community Resilience......................................................................................................................................... B-96

Page 22: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – xx – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-190: PS – Cross-Cutting Challenge Areas ................................................................................... B-96

Figure C-1: Threat/Hazard Based Analysis ................................................................................................. C-1

Figure C-2: Step 1 – Setting the Context .................................................................................................... C-1

Figure C-3: Step 2 – Risk Identification ...................................................................................................... C-2

Figure C-4: Step 3 – Risk Analysis ............................................................................................................... C-2

Figure C-5: Step 4 – Risk Evaluation ........................................................................................................... C-3

Figure C-6: Step 5 – Risk Treatment ........................................................................................................... C-3

Figure C-7: National Risk Assessment ........................................................................................................ C-4

Figure D-1: Threat Taxonomy ................................................................................................................... D-1

Figure D-2: Capability Taxonomy .............................................................................................................. D-1

Figure D-3: Impact Category ..................................................................................................................... D-2

Figure D-4: Target Taxonomy .................................................................................................................... D-2

Figure D-5: DHS State Geographic State Analysis ..................................................................................... D-3

Figure D-6: Consequence Categories (DHS) .............................................................................................. D-4

L I S T O F T A B L E S

Table A-1: Preliminary Planning Tool ........................................................................................................ A-1

Page 23: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – xxi – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

L I S T O F A C R O N Y M S A N D D E F I N I T I O N S

AF ARCHITECTURE FRAMEWORK

AHRA ALL HAZARD RISK ASSESSMENT

BH BIOLOGICAL HAZARD

BTS BORDER AND TRANSPORTATION SECURITY

CAPV CAPABILITY VIEW

CBP CUSTOM BORDERS PROTECTION

CBRNE CHEMICAL, BIOLOGICAL, RADIOLOGICAL, NUCLEAR AND EXPLOSIVES

CBSA CANADA BORDER SERVICES AGENCY

CFP CALL FOR PROPOSALS

CE COMMUNITY ENGAGEMENT

CI CRITICAL INFRASTRUCTURE

COP COMMUNITY OF PRACTICE

CRA CONSOLIDATED RISK ASSESSMENT

CSS CENTER FOR SECURITY SCIENCE

CSSP CANADIAN SAFETY AND SECURITY PROGRAM

CV COMMON VIEW

Page 24: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – xxii – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

DEA DIRECTOR OF ENTERPRISE ARCHITECTURE

DHS DEPARTMENT OF HOMELAND SECURITY

DND DEPARTMENT OF NATIONAL DEFENSE

DNDAF DND ARCHITECTURE FRAMEWORK

DRR DISASTER RISK REDUCTION

EA ENTERPRISE ARCHITECTURE

EBA EVIDENCE-BASED ANALYSIS

EMSI EMERGENCY MANAGEMENT, SYSTEM AND INTEROPERABILITY

E-S E-SECURITY

EXP EXPLOSIVES

FS FIRE SERVICES

GC GOVERNMENT OF CANADA

HIRA HAZARD IDENTIFICATION RISK ASSESSMENT

HTRA HARMONIZED THREAT AND RISK ASSESSMENT

Page 25: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – xxiii – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

IV INFORMATION VIEW

NH NATURAL HAZARD

NRP NATIONAL RISK PROFILE

OV OPERATIONAL VIEW

PLE POLICE LAW ENFORCEMENT

PM PERFORMANCE MEASURE

PMS PARAMEDIC SERVICES

POW PROGRAM OF WORK

PS PSYCHO-SOCIAL

PS PUBLIC SAFETY

QW QUALIWARE

RA RISK ASSESSMENT

RN RADIOLOGICAL AND NUCLEAR

RRAP RESILIENCE ASSESSMENT PROGRAM

Page 26: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – xxiv – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

S&T SCIENCE AND TECHNOLOGY

SB SEAMLESS BORDER

SECV SECURITY VIEW

SII SURVEILLANCE, INTELLIGENCE AND INTERDICTION

SME SUBJECT MATTER EXPERT

SPG STRATEGIC PLANNING GUIDANCE

SRA SOCIETY FOR RISK ANALYSIS

STRATV STRATEGIC VIEW

SV SYSTEM VIEW

TA TASK AUTHORITY

TBA THEORY-BASED APPROACH

THIRA THREAT AND HAZARD IDENTIFICATION AND RISK ASSESSMENT

TV TECHNICAL VIEW

US UNITED STATES

Page 27: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – xxv – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

E X E C U T I V E S U M M A R Y

Defence Research and Development Canada’s (DRDC) Centre for Security Science (CSS) wants to demonstrate that their distribution of investments is based on evidence, and that it considers risks and other factors in a systematic manner. This project aims to support the development and/or improvement the internal risk assessment (RA) capabilities. The Architecture Framework (AF) is intended to support the CSS Annual Planning Process, and to improve communication and comparison of risk results across Focus Areas and Portfolios. The AF identifies where RA supports decision-making and Science and Technology (S&T) investment prioritization in each portfolio’s processes. The results serve as a template for adopting a more systematic and traceable approach to evidence-based assessments with risk being one decision factor. The concept is that improved visibility of risk information would contribute to increasing its value through more internal engagement and leveraging the experience of CSS staff, which would foster a culture of risk-informed decision making that is an integral part of CSS management processes.

The architecture report presents the CSS strategic views and functions that were developed using a model-based method to visualize important factors for RA and risk-informed decision support. AF products are easy to maintain and update using the relatively intuitive user interface. The architecture helps diverse user groups to visualize the relations between functions, objectives, requirements and other objects, and to identify gaps and redundancies in the views. The architecture can also help to clarify the evidence base related to the S&T distribution of investments. The architecture may also guide data collection plans and analysis, and support requirements definition for future collaborative approaches to gap analysis, selection of program risk treatment strategies and investment distribution. It can support operational and risk scenario planning and management processes by developing the complementary architecture views. In addition, the architecture can provide a single window on operational and risk scenarios that o support the convergence of strategic planning, capability-based planning and risk assessments in support of CSSP, portfolios and Communities of Practice.

Page 28: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – xxvi – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Page 29: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 1 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

1 INTRODUCTION

This document is one deliverable for Project W7714-135838. The report describes the methodology used to develop a demonstration architecture as part of a Risk Assessment (RA) framework project. The architecture is intended to support further development of an RA framework and other tools to support decision making within the Canadian Safety and Security Program (CSSP). An html version is also provided.

1.1 Background

The Centre for Security Science (CSS) wants to demonstrate that their distribution of investments is based on evidence, and that it considers risk and other factors in a systematic manner.

This project aims at developing and improving CSS RA capabilities to support the Annual Planning Process, to enable the CSSP to consolidate RA products, and to improve communication of risk information across focus areas and Portfolios. An Architecture Framework (AF) was used to identify where RA is or should be integrated into strategic planning and decision making to prioritize Science and Technology (S&T) investments. The AF serves as a template for adopting a more systematic and sustainable approach to RA to support a culture of evidence-based and risk-informed decision making.

1.2 Objective

The objective of the architecture project is to provide a demonstration AF that models some of the relevant views of the CSSP analytic framework to show how risk information contributes to program alignment. The objective is not to rank specific risks, but to present information to decision makers in a way that supports an evidence-based approach, which includes evidence that partners and CSS manager have considered risk in the identification and prioritization of investments.

At a higher level, the goal of this work is to demonstrate the benefits of using AF support for the visualization and evaluation of evidence, and alignment of capability-based assessments to support decision making on multiple levels.

Page 30: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 2 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

1.3 Scope

To satisfactorily attain the objectives presented above, the following assumptions guided the development of the architecture technology demonstrator:

This project demonstrates the benefits of using AF for the visualization of RA information across the program. The Architecture Views are customized to satisfy the objective of the project. They do not represent traditional DNDAF architecture views.

The architecture focuses on RA within CSS processes, not on CSS processes themselves, which would be part of an Enterprise Architecture (EA).

The work focuses on the methodologies and processes. People and technology are not included.

It was anticipated that the architecture views would include specific information on risk, and threat scenarios including values and broader scope (e.g., national, regional and local views); however, this information was not identified during data collection.

The views developed in the architecture model are driven by CSS requirements. The Technical Authority (TA) requested specific hierarchical graphical views.

1.4 This Document

This document is organized into the following sections:

Section 1 – Introduction: Describes the background and objectives for this document;

Section 2 – Enterprise Architecture: Defines the EA and how it could be used and developed further;

Section 3 – Method: Outlines the methodology;

Section 4 – HTML Report: Presents links to the .html architecture views;

Section 5 – Recommendations and Next Steps: Presents recommendations for exploiting the AF to support visualization and evaluation of RA and the processes it supports;

Page 31: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 3 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Section 6 – Conclusions: Presents some benefits and limitations of the study that may influence the results or further work;

Section 7 – References: Identifies documents that guided the work; and

Appendices: Describe the architecture views and representative taxonomy.

Page 32: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 4 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

2 ENTERPRISE ARCHITECTURE

Enterprise architecture (EA) uses a holistic approach to conduct analysis of an enterprise’s related information. EA "applies architecture principles and practices to guide organizations through the business, information, process, and technology changes necessary to execute their strategies. These practices utilise the various aspects of an enterprise to identify, motivate, and achieve these changes" (Federation of Enterprise Architecture Professional Organisations, 2013).

EA can be used to describe an organisation as it currently is (“As-is”), using a predefined framework that organises the capabilities of an organisation in a logical manner. EA can also be used to present the future state of an organization (“To-be”), provided by pragmatic artifacts (e.g. requirements, specifications, guiding principles, and conceptual models). Then, EA follows a ‘system-of-systems’ perspective that helps to identify and fill gaps. Gaps between the “As-is” and the “To-be” state can be identified and a road map can be proposed to close those gaps and help the enterprise achieve its “To-be” state.

EA is particularly useful for:

finding flaws in a method;

linking documents and reports templates in the framework to facilitate access;

identifying tasks’ inputs and outputs;

standardising terminology and provide description;

identifying information and resources required to produce outputs;

standardising taxonomy; and

using a system of system perspective that helps identify and fill gaps.

For this specific project, the EA was used to find out what DRDC CSS’ processes, if any, involve RA. Once a review of how RA was conducted within DRDC CSS, the EA was used to identify the gaps (i.e., the need

Page 33: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 5 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

to include RA in certain processes) to eventually be able to close the gaps and show risks in an objective and comprehensive way that is consistent across portfolios.

2.1 Framework

A framework is the structure that supports the collection of processes, techniques, artifact descriptions, reference models and guidance for the development and organisation of a specific EA. The Department of National Defence (DND) has developed its own framework to provide a standard approach for all DND organizations; the DND Architecture Framework (DNDAF). DNDAF is an amalgamation of frameworks, from various public, private and defence sources and represents a unique DND/CF perspective (Department of National Defence and the Canadian Forces Architecture Framework (DNDAF) Volume 1, 2012). The DNDAF is comprised of eight views that are intertwined with one another, as depicted in Figure 2-1 (from Department of National Defence and the Canadian Forces Architecture Framework (DNDAF) Volume 2, 2012).

Figure 2-1: DNDAF

The eight views (Figure 2-1) are:

Page 34: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 6 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

1. the Common View (CV)

2. the Strategic View (StratV)

3. the Capability View (CapV)

4. the Operational View (OV)

5. the System View (SV)

6. the Technical View (TV)

7. the Information View (IV)

8. the Security View (SecV).

Each view can be decomposed into a set of sub-views that are interrelated within and across views. Architecture sub-views are those graphical, textual, and tabular items that are developed in the course of gathering architecture data, identifying their composition into related architecture components, and modelling the relationships among those components (Department of National Defence and the Canadian Forces Architecture Framework (DNDAF) Volume 2, 2012).

The DNDAF was used in this project as a framework for the development of the architecture, but was not used as prescribed by the Department of National Defence and the Canadian Forces Architecture Framework (DNDAF) Volume 2, (2012). This project is a ‘proof-of-concept’ study, where the architecture was used to demonstrate the benefits of using visualization of risk assessment for decision making. The StratV and OV5a of the DNDAF framework were customized to answer this need and to correspond to the requirements of DRDC CSS.

2.2 QualiWare

The architecture was developed using DND EA tool called QualiWare (QW), a global consulting services and business modeling software provider. QW is comprised of QLM diagram templates (i.e., process models, workflows, organization, strategy models, etc.) that are used to populate the DNDAF views. Each view has a pre-determined set of diagram templates (in QW) that can be used by the QW Lifecycle

Page 35: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 7 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Manager (the user). For each template, a set of objects and relations are offered to the user. The interactions between the objects of a template are regulated by a set of strict rules (e.g., an object can be related only to certain type of objects, by a predefined set of relations). This limits the flexibility of QW, but ensures a degree of stability in what can be expected in one particular view.

Each QW license connects to the repository, where all models and model objects created by a QW Lifecycle Manager are stored (see Figure 2-2). The repository is available to all users, so objects can be reused from one architecture to another for more consistency across models. In other words, the repository is a common corporate model to which all QW users contribute (see Figure 2-2). The repository is managed by the Repository Administrator, the Director of Enterprise Architecture (DEA). The DEA is responsible for implementing the DND EA Programme, and for integrating models and model objects developed by a QW Lifecycle Manager to the appropriate registry or repository. The usage of QW is restricted to DNDs employees or DND’s contractors. However, as shown in Figure 2-2, an EA model can be published on the intranet and made available to people who do not have access to the software.

Page 36: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 8 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure 2-2: QualiWare System (from: Instruction slides for DNDAF Course 2016-05-01)

Page 37: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 9 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

3 METHOD

This section describes the overall methodology used to develop DRDC CSS’ RA architecture. The methodology consists of four phases, including literature review, development of high-level structure, architecture development, and validation and verification. Figure 3-1 presents a ‘road map’ of the four main phases. Figure 3-1 aligns with the structure of this section, as follows:

Section 3.1 – Phase 1: Presents the rationale behind the selection of the literature and documentation that were reviewed and the data collection plan that served as the basis for the architecture development.

Section 3.2 – Phase 2: Describes the iterative cycle of the development of the high-level structure. Different versions of the Structure were developed based on the literature, input from Subject Matter Experts (SMEs) and comments and requirements from the TA. This high-level structure was used to provide the scope for the architecture development in the following Phase.

Section 3.3 – Phase 3: Presents the development of the architecture views based on the literature review, data collection and input from SMEs. Once populated, the architecture views were validated by the TA.

Section 3.4 – Phase 4: Presents the validation and verification of the architecture by stakeholders; update of the architecture based on their comments and requirements, and the final approval by the TA.

Page 38: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 10 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

MethodMethod

Phase 1Literature Review

Section 3.1

Phase 1Literature Review

Section 3.1

Phase 2High Level Structure

DevelopmentSection 3.2

Phase 2High Level Structure

DevelopmentSection 3.2

Phase 3Architecture Development

Section 3.3

Phase 3Architecture Development

Section 3.3

Phase 4Validation and

VerificationSection 3.4

Phase 4Validation and

VerificationSection 3.4

ClientValidation

Revision

External Validation

Review Documents

ClientAcceptation

High Level Structure

Draft

Final Architecture

Documents provided by client

Validation with Client

Data Collection

PopulationInternal Validation

Page 39: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 11 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure 3-1: Overview of the Methodology

Page 40: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 12 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

3.1 Phase 1 – Literature Review

This section presents the method underlying the literature review and data collection that later informed the development of the High-Level Structure (refer to Section 3.2) and the development of the architecture views (refer to Section 3.3).

The documents relevant to this project were provided by DRDC CSS at the beginning and all along the progression of the project. As the amount of documentation provided was considerable, literature review was prioritized in collaboration with DRDC CSS. The priorities were established based on the relevance of the document for the development of the architecture views as follow:

narratives (Seamless Border);

strategic planning process including a Strategic Risk Assessment (SRA) methodology;

management framework;

Performance Measurement Strategy and performance indicators workbook;

environmental scan (process, criteria and most recent example);

Portfolio/Community of Practice (CoP);

terms of reference for Governance bodies; and

Defence & Security S&T Strategy.

The CAE team developed a data collection plan based on the initial reading of the documentation as described below (Section 3.1.1).

3.1.1 Data Collection Plan

To identify how risk fits within the overall management system, the data collection effort focused on three key areas – governance, decision making and objectives. Strategic outcomes (i.e., the CSSP Logic Model) were mapped to program, strategic planning, focus area, and portfolio and CoP objectives. Then,

Page 41: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 13 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

misalignment or opportunities to make risk more visible/useful were identified. To support this process, a list of key references was consulted, which raised some questions from the CAE team. A list of key references and related questions was developed and presented to DRDC CSS (refer to Appendix A). Answers were provided by SMEs and DRDC CSS during a subsequent meeting.

In addition to the identification of key references and questions, a data collection structure was developed. This structure was intended to provide guideline for the type of data that needs to be collected for the development of the architecture views. This table represents the main areas of concerns within CSS and the information resources that are used in those areas.

3.2 Phase 2 – High Level Structure Development

The creation of an integrated architecture requires information related to the processes, people, and technologies. Identifying these elements can prove challenging. Often, intermediate steps are required whereby architects and SMEs work together to talk-through situations and scenarios relevant to the problem space. In this context, the CAE team worked with DRDC CSS TA to come up with the high-level structure for data collection and architecture development that satisfy the projects’ objectives. This section describes the approach that was used to develop the high-level structure customized for this project (see Figure 3-2).

Figure 3-2: High-Level Structure Development Cycle

Page 42: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 14 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

As depicted in Figure 3-2, the development of the high-level structure for data collection and architecture development was an iterative process. Following the review of some key documents (previously identified with the help of the CSS TA, refer to Section 3.1), the CAE team developed a data collection approach based on their understanding of DRDCCSS processes. Figure 3-3 depicts the original framework built for this purpose.

Figure 3-3: Data Collection Approach (1)

After review and refinement with the CSS TA, it was decided to concentrate on the Strategic Level, and to include only Strategic Visions, Goals, Objectives and Business Functions in the architecture. The data collection approach was modified accordingly. Figure 3-4 depicts the resulting approach that was taken for this project. The area depicted by a purple circle represents the scope of this project.

Page 43: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 15 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure 3-4: Data Collection Approach (2)

3.3 Phase 3 – Architecture Development

This section describes the methodology used to develop the architecture views that supported DRDC CSS in mapping out how RA contributes decision making within the CSSP. The population of the architecture was an iterative process, as illustrated in Figure 3-5 (see also Phase 3 in Figure 3-1). A series of views were developed, based on the data collected from the literature. The views were validated by SMEs and changes were made according the recommendations. This cycle was repeated until a satisfactory version of the architecture was obtained and presented to DRDC CSS for review and approval. The following sections describe the development of StratV (Section 3.3.1), functional decomposition (Section 3.3.2), RA methodologies and processes (Section 3.3.3) and taxonomy (Section 3.3.4) in more details.

Page 44: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 16 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure 3-5: Architecture Development Process

3.3.1 Strategic Views

Once the scope of the architecture was established, StratVs were proposed to DRDC CSS. The first StratV proposed was developed based on CAE’s understanding of the Strategic Planning Guidance for 2017-18 (SPG) and is presented in Figure 3-6. After discussion with DRDC CSS TA, it was decided that this view did not fairly represent all the strategic functions of DRDC CSS. Further discussion led to the decision to use the DRDC CSS Planning Cycle illustrated in the SPG as a StratV. The DRDC CSS Planning Cycle was reproduced in QW and is presented in (Figure 3-7). The StratV was presented to DRDC CSS for approval, after which it was decomposed into a series of Functional Decomposition diagrams OV5a (refer to Section 3.3.2).

Page 45: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 17 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure 3-6: CSS Strategic View (1)

Page 46: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 18 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure 3-7: Final Strategic View

3.3.2 Functional Decomposition Diagrams (OV5a)

The architecture is composed of Business Process Networks (StratV; Architecture Level 1) and a series of Functional Model Diagrams (OV-5a’s; Architecture Level 2 and below). The OV-5a’s are decomposed using QW’s Functional Model Diagrams. Figure 3-8 presents an example of a Functional Model Diagram. Each function and sub-function in the OV5a is represented by a Business Function. Relations between functions and sub-functions are represented by links inside each function. The type of connections is mandatory in QW and could not be replaced by any other type of relation.

Page 47: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 19 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure 3-8: Example of a Functional Model Diagram

The architecture is comprised of up to seven levels of decomposition. To simplify the graphics, each graph is comprised of only two levels of decomposition. All subsequent levels of decomposition are illustrated in a separate graph. The link between a parent Business Function and its child Business Functions is represented in QW by a dark blue square icon at the bottom or beside the function. When one clicks on the icon beside the parent Business Function, QW automatically open the graph representing its decomposition, as illustrated in Figure 3-9.

Page 48: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 20 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure 3-9: Decomposition of a Business Function

The StratV described in the previous section (refer to Section 3.3.1) serves as the highest level of the architecture (Level 1) to which all the OV-5a’s are linked (see Figure 3-10). Each Business Function of the StratV represents a process of the ‘CSSP Planning Cycle’ and is decomposed into sub-processes, also represented by Business Functions (see Figure 3-11). The decomposition continues until no more sub-processes can be identified.

For example, the ‘Community Engagement’ process in Figure 3-10, Architecture Level 1, is decomposed into an Architecture Level 2 comprised of one sub-process, ‘Portfolio/CoP Management’ (Figure 3-11). The Level 2 ‘Portfolio/CoP Management’ can also be decomposed into an Architecture Level 3 that is comprised of a set of sub-functions (see Figure 3-12). All the sub-functions listed in Figure 3-12 are decomposed into an Architecture Level 4. Figure 3-13 shows the decomposition of Level 3 ‘Border and Transportation Security Portfolio’ into a Level 4 (see Figure 3-13). In this example, only three of the four sub-functions are decomposed into a fifth level of architecture (represented by a purple square icon).

Page 49: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 21 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure 3-14 illustrates the decomposition of Level 4 ‘Border and Transportation Security Policy/Operational Context’ into four Level 5 sub-functions. Here again, only two out of four sub-functions are decomposed into Level 6. Figure 3-15 shows the decomposition of Level 5 ‘Seamless Borders Gaps’ into two Level 6 sub-processes. As illustrated in Figure 3-15, the two sub-functions are not decomposed any further, which ends this branch of the architecture. The same function was used for each business function and sub-functions decomposition.

Figure 3-10: Architecture Example Level 1

Page 50: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 22 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure 3-11: Architecture Example Level 2

Figure 3-12: Architecture Example Level 3

Page 51: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 23 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure 3-13: Architecture Example Level 4

Figure 3-14: Architecture Example Level 5

Figure 3-15: Architecture Example Level 6

Page 52: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 24 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

To better represent the CSSP Planning Cycle, some functions and/or sub-functions were linked together to illustrate their relationship and interdependencies. Links between functions are represented in the architecture by an additional dark blue square icon, as illustrated in Figure 3-16. The difference between a functional decomposition and a link between functions is not readily available. One must open the related diagram and identify the first level functions. If the first level function is the same as the parent function that was just opened, it is a decomposition. If the first level function is not the same, then this is a link between two different functions. For example, in Figure 3-16, the functions ‘Seamless Border Gaps’ presents two icons. The left-handed icon opens the decomposition of ‘Seamless Border Gaps’ into two sub-functions. Therefore, the first level process of the child graphic is the same: ‘Seamless Border Gaps’. The right-handed icon opens a related graphic, therefore, the function at the first level of the child graphic is different, here, it represents a relation with the ‘S&T Challenges’ function.

Figure 3-16: Interrelations between Processes

Page 53: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 25 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

In this project, the AF was used to show risks in an objective and comprehensive way that is consistent across portfolios. However, in the literature that was reviewed, little mention is made regarding RA in the CSSP Annual Planning processes. To illustrate this gap and facilitate comparison across Portfolios, SMEs identified where, in the business functions, RA should be included. A placeholder was added to the diagrams to represent this gap. Missing RA processes are represented by a pink Business Functions, as depicted in Figure 3-17.

Figure 3-17: RA Placeholders/Gaps

3.3.3 RA Methodologies/ Process (OV-5b)

The CAE team used the architecture views to illustrate the RA methodologies that are used within DRDC CSS, the Portfolios and the CoPs. A Business Process Network was used to illustrate the relation between the RA processes and sub-processes. The objective of this phase was to document the RA’s steps, information requirements and sub-processes. The models developed here can be used as an instructional guideline to support the users following the RA’s steps properly and to ensure that all the requirements are satisfied. The models can also be used as a tool for analysis and comparison between different RA methodologies. Analysis could include the commonality, gaps, and overlaps. The models can also demonstrate what criteria were used to identify Risks in each RA methodology. Examples of these methodologies include but are not limited to:

Page 54: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 26 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Harmonized Threat and Risk Assessment (HTRA), Threat and Hazard Identification and Risk Assessment (THIRA), Hazard and Identification Risk Assessment (HIRA), Vulnerability assessment, resiliency assessment;

all Hazards Risk Assessment (AHRA), scenario and capability base planning; and

Chemical, Biological, Radiological/Nuclear and Explosive (CBRNE) Consolidated Risk Assessment (CRA).

Figure 3-18 depicts the high-level steps that are taken in the AHRA.

Figure 3-18:AHRA Methodology

3.3.4 Taxonomy

AF provides a standard way to organize the information related to RA. Using the AF tool, the risks’ taxonomy can be translated into an IV diagram (IV-1). Using the Taxonomy, risks can be linked to capabilities, which are decomposed into people, processes and technologies. These capabilities can be illustrated as factors that can reduce the likelihood and impact of the risks. Figure 3-19 is an example of Risk Event Taxonomy for AHRA:

Page 55: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 27 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure 3-19: AHRA Risk Event Taxonomy [Public Security Technical Program Planning Scenario Final Report]

3.4 Phase 4 – External Validation and Final Architecture

Once the architecture was populated and validated by SMEs and DRDC CSS, it was presented to stakeholders for further comments and validation. The architecture was presented and explained, starting from the StratV and going down to the lowest level of decomposition. Due to time contraints, part of the architecture could not be validated by the stakeholders.

During the validation session, the stakeholders provided comments and additional information regarding DRDC CSS’ RA processes. The comments were noted and modifications were made to the architecture to better reflect the CSS’ RA processes. Finally, final approval from DRDC CSS was obtained.

Page 56: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 28 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

4 HTML REPORT

This section provides the links to architecture views.

4.1 Strategic View and Functional Decomposition

Combined together, the Strategic View and the Functional Decomposition form the chore of the architecture. They can be accessed using the following html link: Architecture

Screenshots from the architecture are presented in Appendix B. The .qrp file will be provided separately.

4.2 RA Methodologies

The graphics illustrating the RA Methodologies can be accessed using the following html link: RA Methodologies

Screenshots from the RA Methodologies are presented in Appendix C. The .qrp file will be provided separately.

4.3 Taxonomy

Screenshots from the Taxonomy are presented in Appendix D. The .qrp file will be provided separately.

Page 57: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 29 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

5 RECOMMENDATIONS AND NEXT STEPS

This section presents the recommendations and outlines a potential way forward. The recommendations that are made here are based on the architecture work and inputs from the Seamless Borders SRA literature scan.

5.1 Strategic Level

At the strategic level, CAE recommends to link the Seamless Borders prototype to the program level. This involves incorporating the three Focus Area Narratives that were not included in this study (i.e., Critical Infrastructure Resilience, Operator Capabilities and Resilient Communities) and linking them to key enablers. Once a complete architecture is available, the product should be used to establish a common risk lexicon and a list of acronyms to be included in the existing Taxonomy (refer to Appendix B). The architecture product should then be used to review options for consolidating portfolio resources.

CAE also recommends linking the Focus Area Narratives to:

The Performance Measurement Strategic Plan (i.e., CSSP indicators).

CSSP dashboards or trend analysis (risk exposure; investment history; case studies; typologies, etc.).

CSSP governance.

DRDC S&T Strategic objectives.

Public Safety (PS) strategies and action plans (e.g., critical infrastructure, cybersecurity).

The architecture views demonstrated that little mention is made regarding RA in the CSSP Annual Planning processes. With the help of SMEs, placeholders were included in the architecture views to identify where, in the processes, RA should be involved. CAE recommends that DRDC CSS uses the architecture views to identified the gaps and modify the existing processes to include RA where applicable. Ideally, RA processes would be related to the RA methodologies presented in Section 3.3.3.

Page 58: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 30 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

5.2 Program Level

At the program level, CAE recommends extending the Seamless Borders prototype (decomposition of the Seamless Border Focus Area as a whole) included in the existing architecture product to the other Focus Areas (Critical Infrastructure Resilience, Operator Capability and Resilient Community). As for the Focus Area Narratives mentioned above (refer to Section 5.1), links between the Focus Areas and enablers should be identified. In addition, Threat and Hazard Mitigation should be expanded and linked to the evidence-based assessments component of the CSSP Annual Planning Process. Finally, key partners should be identified for each Focus Area. Then, a partners’ dependency matrix should be developed.

5.3 Focus Area – Seamless Borders

Depending on what CSS decides to do with EA (and QW); there are several opportunities to build on the Seamless Borders AF work including:

Incorporate an inventory of the different types of high-level risk scenarios and supporting threat and hazard-specific scenarios and vignettes to evaluate the architecture as a scenario management tool.

Incorporate stakeholders’ RA practices and the most current RA outputs to provide evidence that partners considered risk in their identification of gaps and investment priorities, and use the AF to complement portfolios and CoP managers’ understanding of the operational risk environment.

Incorporate an inventory of partners’ impact categories and assessment approaches, and support investigation of a unifying framework to support comparison of assessments across Seamless Borders risk domains.

Include process flow diagrams to illustrate general and specific RA processes (i.e., risk; threat / hazard, vulnerability; criticality; resilience; etc.) and link them to RA placeholders included in the architecture views. This would support the use of standardised RA methodologies; and contribute to data collection, evidence gathering, and performance measurement; and facilitate knowledge management within CSS.

Page 59: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 31 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

5.4 Discussion

In the light of the results and recommendations (Sections 5.1 to 5.4) proposed above, some issues and line of thoughts arise which will have an influence on the way forward for CSS.

The first issue that arises is in relation with the continuity of the architecture. It is not clear whether DRDC CSS wants to implement the EA (e.g., using QW) at the enterprise or program level. Some limiting factors include having personnel dedicated in maintaining the EA on a regular basis. If it is the case, then the recommendations proposed at the strategic and program levels remain relevant. If DRDC CSS decides to go forward with keeping the architecture alive, a set of scoping questions need to be answered:

Is DRDC implementing QW (and/or other tools)?

If so, are there interoperability requirements?

What partners are using the same or similar approaches)?

What is the DRDC CSS total cost of ownership and resource commitment?

Another issue raised by the results and recommendations concerns the capability assessment: does DRDC CSS want to link capability-based assessment to risk assessment as primary inputs to decision making? If so, then the recommendations proposed at the Focus Area level are essential to streamline and test the concept. If DRDC CSS considers this option, then the following information need to be gathered:

Status of Canada and US Core Capabilities Lists; criteria, history; trends; and how is risk used on assessment process.

Performance measurement (indicators).

Page 60: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 32 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

6 CONCLUSIONS

This section presents the expected benefits of the architecture product and the limitations of this project.

6.1 Expected Benefits

The architecture developed for this project may be beneficial for CSS. The RA architecture presents the DRDC CSS strategic views and functions using a mode-based method to visualize all the important factors for RA. Architecture products are intuitive and easy to maintain and update the interface. The architecture visualises the relations between all the required functions and requirements and makes it easy to identify gaps and redundancy in the processes. The architecture can also help to clarify the evidence base in relation to the Portfolios and S&T Challenges.

The architecture developed in this project may also guide data collection plan and analysis and support requirements definition for future collaboration environment. It can support operational and risk scenario planning and management processes by developing the related architecture views. Finally, the architecture may be used to get an inventory of strategic and complex risk scenarios and existing specific threat and hazard scenarios (i.e., All Hazards Risk Assessment (AHRA), Consolidated Risk Assessment (CRA), and the National Risk Profile (NRP) for Canada).

6.2 Limitations

Some factors have limited the scope of this study and influenced the results. First, there was no interview performed to support data collection; the technical content of the architecture was validated by SMEs (the TA and another SME), and two stakeholders from the DRDC CSS Policy and Planning team. Therefore, the gaps identified in the architecture represent only the opinion of the SMEs consulted.

In addition, the architecture presented in Appendix A is limited to the documentation provided by DRDC CSS. In addition, due to time and budget constraints, not all the documentation could be included in the architecture at this point. The list of references that constitute the architecture is provided in Section 7. It is also important to note that the only Focus Area Narrative considered in this study is the Seamless Border Narrative; the other three narratives were not available.

Page 61: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 33 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

7 REFERENCES

Bayne, I. (2016). Comprehensive scan for CSSP risk assessment framework: Establishing a method and process for assessing the distribution of CSSP investments. Document No. 5843-011 Version 06.

Bayne, I., Duncan, J., Mills, B., Friesen, S., & Goudreau, A. (2013). The Federal All Hazards Risk Assessment Framework Body of Knowledge Volume1: Establishing an Information Baseline and Way Forward.

Call for Proposals under the Canadian Safety and Security Program Bidder’s Guidebook for 2016. (2016).

Canadian Safety and Security Program Environmental Scan. (2013).

Department of National Defence and the Canadian Forces Architecture Framework (DNDAF) Volume 1: Overview and Definitions. (2012). Version 1.8.1

Federation of EA Professional Organizations. (2013). Common Perspectives on Enterprise Architecture. Architecture and Governance Magazine, 9(4)

Gobeil, R. & Godsoe, M. (2015). Canadian Safety and Security Program Environmental Scan.

https://www.qualiware.com/

Hubbard, P. (2014). Border and Transportation Security (BTS). CSSP-2014-BTSCOP-Z27

Management Framework Review of the Canadian Safety and Security Program. (2015).

New CSSP Logic Model. (April 2015).

Performance Measurement Strategy. (January, 2016).

Performance Measurement Strategy – Implementation Guide. (May, 2016).

Policy on Governement Security – Glossary. (2015). Treasury Board.

Risk Taxonomy (O-RT) Version 2.0. (2013). The Open Group.

Page 62: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – 34 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Seamless Border Focus Area Narrative

Strategic Planning Guidance for 2017-18. (2016)

Theory-Based Approaches to Evaluation: Concepts and Practices. (2012). ISBN 978-1-100-20593-9

Page 63: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – A-1 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

APPENDIX A DATA COLLECTION PLAN

A.1 Key References

Table A-1 is a preliminary planning tool. It identifies questions, potential data sources and reference material to support the architecture work. The team did not maintain or update the tool during the project. The tool does not include GC partners’ or DHS S&T Directorate references, in the SRA and other projects identified.

Table A-1: Preliminary Planning Tool

References Questions / Discussion Points

GC and DND priorities (and strategic outcomes) especially related to S&T / R&D

Sources? How are these priorities evaluated and included in the planning process?

TB oversight instruments (do not need to review, but they are an input, and they drive the level of effort to administer the program)

“Delivery agent” priorities; are risk assessment techniques; risk assessments visible in partners’ prioritization processes? No standard for capability gap analysis?

PS priorities (strategies, programs, policies, action plans, MOUs)

PS performance measurement approach PS role – “policy advice to CSSP”? (PM Strategic Plan,

1.6 Governance)

Program Alignment Architecture

(sub-sub program 2.2.6 of DND PAA

3 outcomes (1.3, PM Strategy)

PAA process (part of SPG development) How is PAA used (logic model, performance

measurement)

Performance Measurement (PM) Strategic Plan, Oct 15 (Draft)

Strategic risks and external factors (2.5)

Annual Performance Report Management Guide (SOP for strategic risk assessment) What documentation is there for capability gap analysis

(and prioritization)? Performance indicator workbook - status? (Draft, Oct 15 -

to be implemented in FY16/17) Management action plan (process?)

Page 64: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – A-2 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

References Questions / Discussion Points

DRDC Performance Management Strategy, Mar 14

Logic Model (program is evidence-based, interconnected and resilient”; PM Strategy, 2.4)

Immediate outcomes Intermediate outcomes Ultimate outcomes

Criteria for success; measures of effectiveness; feedback loops to capture evidence?

“implications for program design and/or operations” (Performance Measurement Strategic Plan, 2.3, bullet 3)

Management Framework Review, WindReach, Apr 15

4. Governance

1.4 Risk factors (“complexity = inherent risk”)

“Of greatest concern are the risks that may lead to an unclear or inconsistent set of federal priorities for the program and, downstream of this, a misalignment of scarce federal resources to the pre-defined priorities. In other words, for programs such as these, there is a high degree of inherent risk that priorities will not be clearly defined, will diverge from the federal mandate or will be inappropriately funded”

2.0, “net risk facing the program”

A Framework for Public Safety and Security S&T 2012/13, DRDC, June 2012 (current version?)

Program review process? Criteria? Ranking system? Governance – terms of reference; standard agenda; risk

register / action items? o Steering Committee (SC) o Program Management Board (PMB) o Advisory Board (AB)

Issue – “key player in PS is EM & Programs Branch”? – focus is not on security

Policy decision – budget allocation; procurement method breakdown? Internal capability #/%. Malicious vs non-malicious?

Ration of budget spent on management overhead compared to delivery? Small budget for scope. Frequency of strategic planning cycle – currently annual – too frequent? Too much time spend on reporting and program administration – too many controls for size of program – risk areas (not identified)

Strategic Planning Guidance

Risk section

Procurement mechanisms

Environmental scan – methodology, process, recent example?

Foresight and futures studies – are these inputs? How doe scan deal with safety and security S&T

Value of program? Vision statement? Risk appetite / tolerance statement?

Page 65: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – A-3 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

References Questions / Discussion Points

Technology Acquisition Targeted Investment Community Development Calls for Innovation

Planning process – documented, timing, validation; risk and issue identification?

Performance indicators / metrics for procurement? o Budget allocation & trends for procurement

“modalities”. Effort per vehicle (ROI/benefit, risks) Canada’s S&T Strategy, Seizing Canada’s moment:

Moving Forward in Science, Technology & Innovation, 2014

Defence & Security S&T Strategy, 2013

Narratives (Focus Areas)

Seamless Borders Critical Infrastructure Resilience Threat & Hazards Mitigation Safer Communities

Provided Seamless Borders only (due to sensitivity of the information at the time)

What is meant by threats & hazards mitigation (protection of responders / “security practitioners”) – partners / delivery agents’ responsibility (ROI) – who defines protection levels? Risk input? Capability gap analysis process?

Status of portfolio / CoP narratives (last ones 2014/15 – See Risk Scan)

Performance reports from portfolios / CoPs? Theory-Based Approaches to Evaluation: Concepts &

Practices, TB, 2012 Does T/H Mitigation scan international practices (e.g.,

NRAs, EM lessons)

Portfolios / CoPs, networks

Performance reports

Performance indicators

Risk indicators

Capability gap analysis reports

Narratives? Capability gap analysis standard / SOP How do communities scan lessons from real events,

exercises, intelligence reports, open source intelligence? How are network scans amalgamated and rolled up? What guides and tools exist for threat, hazard,

vulnerability, criticality, impact and risk assessments for domains (security and CIP; Health, safety and environment; natural hazards and resilience)

Page 66: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-1 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

APPENDIX B ARCHITECTURE

B.1 CSSP Planning Cycle

Figure B-1: CSSP Planning Cycle

Page 67: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-2 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

B.2 Call for Proposal

Figure B-2: Call for Proposal (CFP)

Figure B-3: CFP – CSSP Funding

Page 68: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-3 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-4: CFP – Process

Figure B-5: CFP – Notice of Proposed Procurement

Page 69: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-4 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-6: CFP – Process Phase 1

B.3 Focus Area Narratives

Figure B-7: Focus Area Narratives

Page 70: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-5 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-8: Seamless Borders (SB) Narrative

Figure B-9: SB - Portfolio Activities

Page 71: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-6 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-10: SB – Gaps

Figure B-11: SB – Priorities

Page 72: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-7 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-12: SB – De-risk

Figure B-13: SB – Risk-Informed Delivery Cycle

Page 73: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-8 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-14: SB – Establish Clients Priorities

Figure B-15: SB – Formulate Program

Page 74: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-9 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-16: SB – Generate Evidence through Projects

Figure B-17: SB – Provide Advice

Page 75: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-10 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

B.4 SPG

Figure B-18: SPG

Figure B-19: Focus Area Priorities

Page 76: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-11 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

B.5 S&T Challenges

Figure B-20: S&T Challenges

Figure B-21: S&T – Use Action Research or Similar Methodology

Page 77: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-12 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-22: S&T – Strengthen Capacity of Emergency Responders

Figure B-23: S&T – Use Broadband Wireless Technologies to Provide Next-Generation Reliable Communications

Page 78: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-13 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-24: S&T – Make Use of Nano and/or Synthetic Biological Technology

Figure B-25: S&T – Enhance Ability of Maritime Operators and Partners to Accomplish Public Safety and Security Objectives

Page 79: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-14 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-26: S&T – Develop and Assess Options for Next-Generation Surveillance of Canada's Northern Waters and Approaches

B.6 Evidence-Based Analysis

Figure B-27: Evidence-Based Analysis (EBA)

Page 80: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-15 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-28: EBA – Risk Assessment Framework

Figure B-29: EBA – Enable and Inform CSSP Decision Making

Page 81: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-16 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-30: EBA – Risk Assessment in Targeted Domains

Figure B-31: EBA – National Risk Assessment

Page 82: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-17 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

B.7 Performance Measurement

Figure B-32: Performance Measurement (PM)

Figure B-33: PM – CSSP Performance Measurement Strategy

Page 83: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-18 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-34: PM – Strategy Principles

Figure B-35: PM – Key Performance Indicators

Page 84: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-19 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-36: PM – Performance Evaluation

B.8 Community Engagement

Figure B-37: Community Engagement (CE)

Page 85: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-20 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-38: CE – Portfolios/CoP Management

B.8.1 Biological Hazard Portfolio

Figure B-39: Biological Hazards (BH) Portfolio

Page 86: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-21 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-40: BH – Program of Work

Figure B-41: BH – Rapid Diagnostics and Situational Awareness

Page 87: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-22 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-42: BH – Containment and Decontamination

Figure B-43: BH – Medical Countermeasures

Page 88: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-23 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

B.8.2 Border and transportation Security Portfolio

Figure B-44: Border and Transportation Security (BTS) Portfolio

Figure B-45: BTS – Policy/Operational Context

Page 89: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-24 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-46: BTS – Partners

Figure B-47: BTS – Program of Work

Page 90: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-25 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-48: BTS – Biometrics and Passenger Screening

Figure B-49: BTS – Biometrics – Existing Projects

Page 91: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-26 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-50: BTS – Biometrics – Activities for 2014/15

Figure B-51: BTS – Biometrics – Remaining Challenges

Page 92: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-27 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-52: BST – Technologies to Increase Passenger Safety

Figure B-53: BTS – Passenger Safety – Existing Projects

Page 93: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-28 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-54: BTS – Passenger Safety – Activities for 2014/2015

Figure B-55: BTS – Passenger Safety – Remaining Challenges

Page 94: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-29 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-56: BTS – Technologies Supporting Fast Screening of Containers

Figure B-57: BTS – Technologies – Remaining Challenges

Page 95: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-30 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-58: BTS – Technologies – Pilots for Efficient Container Management

Figure B-59: BTS – Assessing Cyber Vulnerabilities

Page 96: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-31 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-60: BTS – Biometrics – Existing Projects

Figure B-61: BTS – Cyber Vulnerabilities – Activities for 2014/2015

Page 97: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-32 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-62: BTS – Cyber Vulnerabilities – Remaining Challenges

Figure B-63: BTS – Arctic Security

Page 98: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-33 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-64: BTS – Arctic Security – Existing Projects

Figure B-65: BTS – Arctic Security – Activities for 2014/2015

Page 99: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-34 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-66: BTS – Arctic Security – Remaining Challenges

Figure B-67: BTS – Integration and Analysis

Page 100: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-35 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-68: BTS – Integration and Analysis – Existing Projects

Figure B-69: BTS – Integration and Analysis – Activities for 2014/2015

Page 101: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-36 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-70: BTS – Integration and Analysis – Remaining Challenges

B.8.3 Critical Infrastructure

Figure B-71: Critical Infrastructure (CI) Portfolio

Page 102: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-37 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-72: CI – Focus

Figure B-73: CI – Program of Work

Page 103: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-38 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-74: CI – Call for Proposals (CFP) Projects

Figure B-75: CI – Targeted Investments

Page 104: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-39 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-76: CI – Technology Acquisition

Figure B-77: CI – Community Development Workshops

Page 105: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-40 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

B.8.4 E-Security Portfolio

Figure B-78: E-Security (E-S) Portfolio

Figure B-79: E-S – Operation Capabilities

Page 106: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-41 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-80: E-S – Policy/Operational Context

Figure B-81: E-S – Program of Work

Page 107: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-42 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

B.8.5 Emergency Management, Systems and Interoperability Portfolio

Figure B-82: Emergency Management, Systems and Interoperability (EMSI) Portfolio

Figure B-83: EMSI – Policy/Operational Context

Page 108: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-43 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-84: EMSI – Program of Work

B.8.6 Explosives Portfolio

Figure B-85: Explosives (Exp) Portfolio

Page 109: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-44 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-86: Exp – Specific S&T Areas

Figure B-87: Exp – Policy and Operational Context

Page 110: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-45 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-88: Exp – Metric Based on Resilience Four Pillars

Figure B-89: Exp – Program of Work

Page 111: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-46 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-90: Exp – Scenarios

Figure B-91: Exp – Analyze Scenarios

Page 112: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-47 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-92: Exp – Projects

Figure B-93: Exp– Prevention

Page 113: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-48 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-94: Exp – Prevention – Existing Programs

Figure B-95: Exp – Prevention – Planned Activities

Page 114: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-49 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-96: Exp –Prevention – Remaining Challenges

Figure B-97: Exp – Preparedness

Page 115: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-50 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-98: Exp – Preparedness – Existing Projects

Figure B-99: Exp – Preparedness – Planned Activities

Page 116: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-51 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-100: Exp – Preparedness – Remaining Challenges

Figure B-101: Exp – Preparedness- Existing Projects

Page 117: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-52 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

B.8.7 Fire Services Portfolio

Figure B-102: Fire Services (FS) Portfolio

Figure B-103: FS – Primary Functions (PMS)

Page 118: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-53 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-104: FS – Assess Impact of CSSP Output Upon Community

Figure B-105: FS – Program of Work

Page 119: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-54 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-106: FS – Evidence-Based Decision Making

Figure B-107: FS – Evidence-Based Decision Making – Existing Work

Page 120: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-55 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-108: FS – Evidence-Based Decision Making – Remaining Challenges

Figure B-109: FS – Dangerous Hazardous Goods

Page 121: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-56 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-110: FS – Dangerous Hazardous Goods – Existing Work

Figure B-111: FS – Dangerous Hazardous Goods – Remaining Challenges

Page 122: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-57 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-112: FS – Smart Firefighting

Figure B-113: FS – Smart Firefighting – Existing Work

Page 123: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-58 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-114: FS – Smart Firefighting – Remaining Challenges

B.8.8 Natural Hazard Portfolio

Figure B-115: Natural Hazard (NH) Portfolio

Page 124: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-59 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-116: NH – Priorities

Figure B-117: NH – Policy/Operational Context

Page 125: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-60 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-118: NH – Program of Work

Figure B-119: NH – Consolidated Priorities

Page 126: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-61 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-120: NH – Priorities for Disaster Risk Reduction – Type of Work

Figure B-121: NH – Social Change

Page 127: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-62 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-122: NH – Social Change – Type of Work

Figure B-123: NH – Social Change – Planned Activities

Page 128: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-63 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

B.8.9 Paramedic Services Portfolio

Figure B-124: Paramedic Services (PMS) Portfolio

Figure B-125: PMS – Primary Functions

Page 129: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-64 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-126: PMS – Assess the Impact of CSSP Outputs Upon Community

Figure B-127: PMS – Policy/Operational Context

Page 130: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-65 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-128: PMS – Operational Context – Priority Domains

Figure B-129: PMS – Program of work

Page 131: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-66 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-130: PMS – Mobilising Health Care

Figure B-131: PMS – Mobilising Health Care – Existing Work

Page 132: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-67 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-132: PMS – Mobilising Health Care – Remaining Challenges

Figure B-133: PMS – Evidence-Based Decision Making

Page 133: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-68 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-134: PMS – Evidence-Based Decision Making – Existing Work

Figure B-135: PMS – Evidence-Based Decision Making – Remaining Challenges

Page 134: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-69 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-136: PMS – Standards Development

Figure B-137: PMS – Standards Development – Existing Work

Page 135: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-70 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-138: PMS – Standards Development – Remaining Challenges

Figure B-139: PMS – Practitioner Well-Being

Page 136: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-71 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-140: PMS – Practitioner Well-Being – Existing Work

Figure B-141: PMS – Practitioner Well-Being – Remaining Challenges

Page 137: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-72 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

B.8.10 Radiological and Nuclear Portfolio

Figure B-142: Radiological and Nuclear (RN) Portfolio

Figure B-143: RN – Vulnerabilities

Page 138: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-73 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-144: RN – Investment Strategy

Figure B-145: RN – Policy/Operational Context

Page 139: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-74 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-146: RN – Program of Work

Figure B-147: RN – Quantitative and Qualitative Threat Assessment

Page 140: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-75 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-148: RN – Quantitative and Qualitative Threat Assessment – Run Scenarios

Figure B-149: RN – Projects List

Page 141: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-76 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

B.8.11 Police Law Enforcement Portfolio

Figure B-150: Police Law Enforcement (PLE) Portfolio

Figure B-151: PLE – Policy/Operational Context

Page 142: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-77 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-152: PLE - Program of Work

Figure B-153: PLE – Priorities Areas

Page 143: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-78 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-154: PLE – Priorities Areas – Improving Economics

Figure B-155: PLE – Priorities Areas – Improving Economics – Existing Work

Page 144: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-79 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-156: PLE – Priorities Areas – Improving Economics – Remaining Challenges

Figure B-157: PLE – Priorities Areas – Employing Emerging Technology

Page 145: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-80 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-158: PLE – Priorities Areas – Employing Emerging Technology – Existing Work

Figure B-159: PLE – Priorities Areas – Employing Emerging Technology – Remaining Challenges

Page 146: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-81 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-160: PLE – Priorities Areas – Reducing the Cost and Time of Investigation

Figure B-161: PLE – Priorities Areas – Reducing the Cost and Time of Investigation – Existing Work

Page 147: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-82 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-162: PLE – Priorities Areas – Evidence-Based Decision Making

Figure B-163: PLE – Priorities Areas – Evidence-Based Decision Making – Existing Work

Page 148: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-83 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-164: PLE – Priorities Areas – Evidence-Based Decision Making – Remaining Challenges

Figure B-165: PLE – Priorities Areas – Employing Emerging Technology

Page 149: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-84 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-166: PLE – Priorities Areas – Employing Emerging Technology – Existing Work

Figure B-167: PLE – Priorities Areas – Employing Emerging Technology – Remaining Challenges

Page 150: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-85 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

B.8.12 Surveillance, Intelligence and Interdiction Portfolio

Figure B-168: Surveillance, Intelligence and Interdiction (SII) Portfolio

Figure B-169: SII – Objectives

Page 151: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-86 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-170: SII – Policy/Operational Context

Figure B-171: SII – Program of Work

Page 152: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-87 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-172: SII – Action Plan

Figure B-173: SII – Canada’s Counter-Terrorism Strategy

Page 153: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-88 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-174: SII – DSO Readiness Committee Priorities

B.8.13 Psycho-Social Portfolio

Figure B-175: Psycho-Social (PS) Portfolio

Page 154: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-89 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-176: PS – Capability Gaps

Figure B-177: PS – Partners

Page 155: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-90 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-178: PS – Policy/Operational Context

Figure B-179: PS – Emerging Issues

Page 156: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-91 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-180: PS – Program of Work

Figure B-181: PS – Counter-Violent Extremism

Page 157: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-92 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-182: PS – Counter-Violent Extremism – Existing Work

Figure B-183: PS – Counter-Violent Extremism – Remaining Challenges

Page 158: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-93 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-184: PS – Support to First Responders and Public

Figure B-185: PS – Support to First Responders and Public – Existing Work

Page 159: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-94 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-186: PS – Support to First Responders and Public – Remaining Challenges

Figure B-187: PS – Community Resilience – Existing Work

Page 160: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-95 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-188: PS – Community Resilience – Remaining Challenges

Figure B-189: PS – Community Resilience – Better Understand Behavioural Implications of Effective Communications

Page 161: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – B-96 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure B-190: PS – Develop Effective Whole-of-Community Approaches for Building Community Resilience

Figure B-191: PS – Cross-Cutting Challenge Areas

Page 162: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – C-1 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

APPENDIX C RA METHODOLOGIES

C.1 AHRA

Figure C-1: Threat/Hazard Based Analysis

Figure C-2: Step 1 – Setting the Context

Page 163: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – C-2 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure C-3: Step 2 – Risk Identification

Figure C-4: Step 3 – Risk Analysis

Page 164: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – C-3 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure C-5: Step 4 – Risk Evaluation

Figure C-6: Step 5 – Risk Treatment

Page 165: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – C-4 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

C.2 National Risk Assessment

Figure C-7: National Risk Assessment

Page 166: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – D-1 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

APPENDIX D TAXONOMY

Figure D-1: Threat Taxonomy

Figure D-2: Capability Taxonomy

Page 167: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – D-2 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure D-3: Impact Category

Figure D-4: Target Taxonomy

Page 168: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – D-3 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure D-5: DHS State Geographic State Analysis

Page 169: ARCHITECTURE CONTRIBUTION TO RISK & EVIDENCE …CAE Inc. 1135 Innovation Drive Ottawa, Ont., K2K 3G7 Canada Tel: 613-247-0342 Fax: 613-271-0963 ARCHITECTURE CONTRIBUTION TO RISK &

CSSP Task 28

Architecture Contribution to Evidence-Based

and Risk-Informed Decision Making

31 March 2017 – D-4 – 113129-004 Version 01

© Her Majesty the Queen in Right of Canada, as represented by the Minister of National Defence, 2017

© Sa Majesté la Reine (en droit du Canada), telle que représentée par le ministre de la Défense nationale, 2017

Figure D-6: Consequence Categories (DHS)