EGLINTON CROSSTOWN CONSTRUCTION UPDATE

CENTRAL WEST OPEN HOUSE | MARCH 03, 2020

Welcome

Our Central West Open House will feature the following stations:

• Fairbank

• Oakwood

• Cedarvale

• Forest Hill

• Chaplin

• Avenue

• and Eglinton

2

Agenda

3

• Welcome from Beth Tzedec

• Introduction

• Behind the Scenes Construction Progress Video

• Construction Update

– Milestones in 2019

– Remaining Work in 2020

Eglinton Crosstown LRT Project

• A 19-kilometre route separated from regular traffic • 10-kilometres underground; 9-kilometres at surface in east • 15 underground stations and 10 surface stops • A maintenance and storage facility • Transit communications system • Links to 54 bus routes, 3 subway stations, GO Transit, UP Express station

4

2019 Project Highlights

5

6

First Light Rail Vehicle on Mainline

Fairbank Station Renderings

MAIN ENTRANCE SECONDARY ENTRANCE

SERVICE BUILDING EXTERIOR PLAZA

Fairbank Station: What to Expect

Year What to Expect

Milestone

• Start of structural steel installation

Remaining work for

2020

• Completion of deep excavation and concrete works

• Structural steel and panels installed at entrances

• Reduced road occupancy during utilities reinstatement work

• Begin road restoration and landscaping

Fairbank Station Progress Photo

Fairbank Station Progress Photos

DEEP EXCAVATION MAIN ENTRANCE CONCRETE AND

STRUCTURAL STEEL

Oakwood Station Renderings

MAIN ENTRANCE

CONCOURSE

SECONDARY ENTERANCE

PLATFORM

Oakwood Station: What to Expect

Year What to Expect

Milestone

• Mining completed in 2019

Remaining Work for

2020

• Completion of final lining works, including installation

waterproofing, rebar and formwork

• Completion of concrete works

• Installation of structural steel and panels at entrances

Oakwood Station Progress Photo

13

Oakwood Station Progress Photos

FORMWORK INSTALLATION WATERPROOFING

Cedarvale Station Renderings

MAIN ENTRANCE

SECONDARY ENTRANCE

EXTERIOR PLAZA

TERTIARY ENTERANCE

Cedarvale Station: What to Expect

Year What to Expect

2019

Milestone

• Underpinning complete

Remaining

Work for 2020

• Completion of deep excavation

• Closure of Eglinton West Station bus loop to construct the Cedarvale Station concourse roof

• Traffic configuration changes

17

TTC Station Underpinning

January 2020 Underpinned subway tunnel

Cedarvale Station Progress Photos

TTC UNDERPINNING DEEP EXCAVATION

Eglinton West Bus Loop Reroute –

Effective end of March

20

Forest Hill Station Renderings

MAIN ENTRANCE SECONDARY ENTRANCE

PLATFORM LOBBY

Forest Hill Station: What to Expect

Year What to Expect

Remaining

Work for 2020

• Deep excavation and concrete works

• Completion of utility works

• Traffic bridge removal

• Traffic configuration changes and reinstatement of some turns at Bathurst St and Eglinton Ave

• Installation of structural steel and panels at entrances

• Completion of the Secondary Entrance

Forest Hill Station Progress Photo

23

Forest Hill Station Progress Photos

SECONDARY ENTRANCE CONSTRUCTION

DEEP EXCAVATION BENEATH STATION ROOF

Chaplin Station Renderings

MAIN ENTRANCE SECONDARY ENTRANCE

PLATFORM TERTIARY ENTRANCE

Chaplin Station: What to Expect

Year What to Expect

Milestone

• All station roof pours complete

Remaining Work for 2020

• Deep excavation and concrete works

• Intersection closure for traffic bridge removal

• Traffic configuration changes

• Installation of structural steel and panels at entrances

Chaplin Station Progress Photo

27

Chaplin Station Progress Photos

MAIN ENTRANCE/DEEP EXCAVATION

DEEP EXCAVATION BENEATH THE STATION ROOF

Avenue Station Renderings

Station Features Accessible main entrance

Covered & uncovered bicycle parking

Retail space in main entrance??

SECONDARY ENTRANCE

MAIN ENTRANCE

MAIN ENTRANCE INTERIOR

AERIAL VIEW

Avenue Station Mining Progress

Avenue Station: What to Expect

Year What to Expect

Milestone

• Completion of mining excavation in summer 2020

Remaining Work

for 2020

• Completion of concrete works at entrances

• Completion of final lining works, including installation waterproofing, rebar and formwork

• Begin installation of structural steel and panels at entrances

• Begin implementation of Eglinton Connects

Avenue Station Progress Photo

32

Avenue Station Progress Photos

FINAL LINING WORKS FINAL LINING WORKS

Eglinton Station Renderings

Station Features Accessible main entrance

Covered & uncovered bicycle parking

Retail space in main entrance??

LOBBY

PLATFORM

TTC SERVICE BUILDING (BERWICK AVE)

MAIN ENTRANCE

Eglinton Station: What to Expect

Year What to Expect

Milestone

• All pedestrian crosswalks open at intersection

• Start of underpinning work

Remaining Work for 2020

• Deep excavation

• Removal of tunnel boring machines

• TTC station underpinning

• Construction of the south ventilation building at Berwick Ave

• Construction of the north tunnel ventilation shaft

Eglinton Station Progress Photo

36

Eglinton Station Progress Photos

MAIN ENTRANCE DEEP EXCAVATION

38

QUESTIONS & ANSWERS