EGLINTON CROSSTOWNCedarvale-Forest Hill Construction Liaison CommitteeMay 31, 2017
2
Agenda
• Cedarvale Station Update
• Forest Hill Station Update
3
Cedarvale Station Updates
May 2017
• Monitoring instrument installations are complete
• Utilities relocation works are underway at Park Hill Rd and Eglinton Ave W
– Sanitary sewer & watermain works
• Invert tunnel concrete pour is ongoing at both the east and west side of Allen Rd
– Stage 1 (infill) is 100% complete
– Stage 2 (invert slab) is ongoing
• Shoring and construction for the east entrance (at Allen Rd North and Eglinton Ave) to start as early as June
• Shoring on the south side of Eglinton Ave to start as early as late June
4
Outdoor Bicycle Parking
Cedarvale Station Aerial Rendering
Accessible Entrance
Outdoor Bicycle Parking
Accessible Entrance
Outdoor Bicycle Parking
Eglinton West TTC Station
5
Construction Progress Picture
6
Construction Progress Picture
7
Construction Progress Picture
8
Construction Progress Picture
Forest Hill Station Construction Update
Complete
Demolition of 842, 874, 875 and 876 Eglinton Ave W
Installation of geotechnical monitoring equipment
Bell utilities relocation
Hydro utilities relocation
Installation of temporary traffic signals
Watermain servicing
Sanitary and storm sewer relocation
Piling the southwest side at the station box
Spring/Summer 2017
• Continue piling at the southeast side of the station box
• Continue shallow excavation at the southwest side of the station box
• Continue piling at the Secondary Entrance
• Piling at the Main Entrance
Forest Hill Station Concept Aerial View
Main Entrance
Secondary Entrance
*60% rendering
Forest Hill Station Construction Progress
11
Lowering rebar cage into pile
shaft Bell utility relocation
Forest Hill Station Construction Progress
12
Pile installation Shallow
excavation
Forest Hill Station Construction Progress
13