Agenda
• Cedarvale Station Update
• Forest Hill Station Update
3
Cedarvale Station Updates – September 2017
Complete
• Shoring for the east entrance (east of Allen Rd North, north of Eglinton Ave)
• Everden Road utilities relocation works (sanitary sewer & water main)
• 3/3 invert concrete pours in the launch shaft (east of the Allen)
• Invert tunnel concrete pour
• Utilities relocation works (Sanitary sewer & water main) across the Toronto Police parking lot
• Excavation for the east entrance
Ongoing
• Utilities relocation works on Winnett Avenue
• Waterproofing and formwork at the launch shaft
• Noise and vibration monitoring
• Shoring on the south side of Eglinton Ave
Upcoming
• South Allen Road Diversion
• Backfill of LS2 Crossover
• Shoring on the north side of Eglinton Ave
4
Construction Progress Picture
First pile at Cedarvale
Excavation at the East Entrance
5
Construction Progress Picture
Piling on the south side of Eglinton
6
Forest Hill Station Construction Update
Fall 2017
• Continue piling at the southeast side of the station box
• Continue shallow excavation at the southwest side of the station box
• Construct roof slab
• Continue piling at the Secondary Entrance
• Piling at the Main Entrance
• Shift traffic on Bathurst Street to the east (Completed in Mid-September)
• Utility Relocation
7
Forest Hill Station Concept Aerial View
Main Entrance
Secondary Entrance
*60% rendering
8
Forest Hill Station Construction Progress
8
SOUTHWEST ROOF SLAB POUR
SOUTHWEST REBAR
INSTALLED
SOUTHWEST OVERNIGHT ROOF SLAB
POUR
SOUTHWEST OVERNIGHT ROOF SLAB
POUR
9
Forest Hill Station Construction Progress
9June 2017 Flyover
10
Forest Hill Station Construction Progress
10June 2017 Flyover