EGLINTON CROSSTOWNCedarvale-Forest Hill Construction Liaison CommitteeJuly 26, 2017

2

Agenda

• Cedarvale Station Update

• Forest Hill Station Update

3

Cedarvale Station Updates – July 2017

Complete

• Shoring for the east entrance (east of Allen Rd North, north of Eglinton Ave)

• Everden Road utilities relocation works (sanitary sewer & water main)

• First concrete pour in the launch shaft (east of the Allen)

• Traffic flip for Eglinton Road

• Invert tunnel concrete pour

Ongoing

• Excavation for the east entrance

• Waterproofing and formwork at the launch shaft

• Utilities relocation works (Sanitary sewer & water main) across the Toronto Police parking lot and Winnett Avenue

• Noise and vibration monitoring

Upcoming

• Shoring on the south side of Eglinton Ave

4

Construction Progress Picture

First concrete pour

Forest Hill Station Construction Update

Summer 2017

• Continue piling at the southeast side of the station box

• Continue shallow excavation at the southwest side of the station box

• Continue piling at the Secondary Entrance

• Piling at the Main Entrance

• Shift traffic on Bathurst Street to the east (tentative)

Forest Hill Station Concept Aerial View

Main Entrance

Secondary Entrance

*60% rendering

Forest Hill Station Construction Progress

7

GUIDEWALL CONSTRUCTUION

SOUTHWEST SHALLOW

EXCAVATION

Forest Hill Station Construction Progress

8June 2017 Flyover

Forest Hill Station Construction Progress

9June 2017 Flyover

Local Area Map