Cedarvale Station Updates – July 2017
Complete
• Shoring for the east entrance (east of Allen Rd North, north of Eglinton Ave)
• Everden Road utilities relocation works (sanitary sewer & water main)
• First concrete pour in the launch shaft (east of the Allen)
• Traffic flip for Eglinton Road
• Invert tunnel concrete pour
Ongoing
• Excavation for the east entrance
• Waterproofing and formwork at the launch shaft
• Utilities relocation works (Sanitary sewer & water main) across the Toronto Police parking lot and Winnett Avenue
• Noise and vibration monitoring
Upcoming
• Shoring on the south side of Eglinton Ave
Forest Hill Station Construction Update
Summer 2017
• Continue piling at the southeast side of the station box
• Continue shallow excavation at the southwest side of the station box
• Continue piling at the Secondary Entrance
• Piling at the Main Entrance
• Shift traffic on Bathurst Street to the east (tentative)