    Development with a corner wall instead of the column

    Plans of the Aum House of New Delhi Plans of the Aum House of Narangarh, Orissa

  • 7/28/2019 5 Aum House En

    3/6

    Plans of the Aum House of Khavda, Gujarat Plans of the Aum House of Mundra, Gujarat

    Aum hou se at New Delhi

    Loading the lorry at Auroville Aum house built at New Delhi in 66 hours House at New Delhi, view on the kitchen side

  • 7/28/2019 5 Aum House En

    4/6

    House at New Delhi, view on the toilet side

    House at New Delhi, view on toilet and shower

    House at New Delhi, view on the living room

    Construction steps of the Aum house at Khavda, Gujarat

    6 hours Digging the foundations 11 hours Stabilised Rammed earth foundation completed 13 hours Building the first course of the plinth

  • 7/28/2019 5 Aum House En

    5/6

    14 hours Building the second course of the plinth 16 hours Plinth beam completed 17 hours Filling the basement and starting the walls

    25 hours Sill ring beam completed 30 hours Building the sills and visitors from the village 35 hours- Lintel ring beam completed

    43 hours Roof ring beam completed 46 hours Laying ferrocement channels 48 hours Laying ferrocement channels completed and starting thefinishes

  • 7/28/2019 5 Aum House En

    6/6

    Aum house completed in 62 hours by a 20-man team Visitors visiting the house after completion Villagers visiting the house

    Modification for the new design of the Aum house