Appendix K Needs Plan Project Costs, Purpose and Need

February 7, 2015

Page 2: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

This page is intentionally blank.

Page 3: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

Path Forward 2040 Long Range Transportation Plan

PURPOSE AND NEED STATEMENTS The Needs Plan included a six county area consisting of Baker, Clay, Duval, Nassau, Putnam and St. Johns counties. The Needs Plan is not a prioritized list of projects, nor is it constrained by financial resources.

The Needs Plan leveraged prior studies development by the Florida Department of Transportation, the North Florida Transportation Planning Organization and local governments. Maintaining the public consensus continuity of these efforts was essential to the credibility of the planning process.

Because of the level of visioning and planning that occurred within these studies, the known needs greatly exceeded the resources anticipated to be available. Building on the community consensus that was achieved, the development of the Needs Plan began with a review and confirmation of these studies. The following sources were used to define the needs.

2035 Envision Long Range Transportation Plan City of Jacksonville Mobility Plan Committed Development Projects Provided by Local Governments Coordination with local governments and stakeholders on additional needs FDOT’s Strategic Intermodal Systems Needs Plan and Cost Feasible Plan (includes 1st Five Year and 2nd Five

Year) FDOT’s Adopted Work Program First Coast Regional Greenways and Trails Plan Jacksonville Transportation Authority Blueprint 2020 Local Government Comprehensive Plans North Florida TPO Congestion Management Plan North Florida TPO Freight, Logistics and Intermodal Planning Framework Plan North Florida TPO ITS Master Plan North Florida TPO Regional Bicycle and Pedestrian Plan North Florida TPO Strategic Safety Plan North Florida TPO Transportation Improvement Program

As part of the planning process, these needs were confirmed through an analysis of the safety, congestion, mobility and emergency evacuation needs.

The following tables summarize the needs plan costs in present day dollars and provide a summary of the purpose and need for each project of the road and transit capacity projects.

1

Page 4: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

Path Forward 2040 Long Range Transportation Plan

Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost 

(millions)O&M Cost (millions)

Abaco Island Drive Extension Nassau 988 Abaco Island Drive Zion Court New 2 Lane Road $0.72 $0.00Alta Drive Duval 3 SR 105 Heckscher Drive I‐295 Widen to 4 Lanes $8.85 $0.21Alta Drive / Yellow Bluff Road Duval 2 I‐295 New Berlin Road (north ) Widen to 5 Lanes $14.50 $0.15Alta Drive Realignment Duval 1 SR 105 Zoo Parkway North of New Berlin Road (south) New 4 Lane Road $15.15 $0.10Amelia Island Parkway Nassau 704 South 14th Street CR 105A Buccaneer Trail Widen to 4 Lanes* $4.17 $0.10Argyle Forest Boulevard Duval 936 SR 23 First Coast Expressway Old Middleburg Road Widen to 6 Lanes $8.49 $0.48Arrigo‐Parliament Reconnection Nassau 980 Arrigo Boulevard Parliament Drive New 2 Lane Road $0.59 $0.00Barnwell‐0' Neil Scott Connector Nassau 1001 Barnwell Road O'Neil Scott Road New 2 Lane Road $2.89 $0.02Baxley Road Clay 900 CR 220 Doctors Inlet Road SR 21 Blanding Boulevard Widen to 4 Lanes $4.61 $0.05Blount Island Boulevard Extension Duval 1006 Spoil Island Jacksonville Port Authority New 2 Lane Bridge $80.21 $0.08Braddock Parkway Duval 939 SR 115 Lem Turner Road Pecan Park Road New 2 Lane Road $47.68 $0.24Brady Point‐Clements Connector Nassau 1002 Brady Point Road Clements Road New 2 Lane Road $2.89 $0.02Brinkhoff Road St. Johns 801 SR 207 Wildwood Drive New 2 Lane Road $4.32 $0.04Buffalo Road Putnam 503 Buffalo Road west Buffalo east New 2 Lane Bridge $34.71 $0.05Cahoon Road Duval 1016 Lenox Avenue US 90 Beaver Street Reconstruct 2 Lanes $10.20 $0.07Cardinal Street North Extension Nassau 976 Cardinal Avenue SR 200 SR AIA  Yulee Backage Roads New 2 Lane Road $1.44 $0.01Cardinal Street South Extension Nassau 975 Spring Meadow Avenue William Burgess Boulevard New 2 Lane Road $0.48 $0.00Cecil Field Connector Duval 972 Commerce Center SR 23 First Coast Expressway New 2 Lane Road $12.57 $0.07Chaffee Road Duval 971 SR 228 Normandy Boulevard Crystal Springs Road Widen to 5 Lanes $30.00 $0.39Cheswick Oak Avenue Extension Clay 13 Oakleaf Plantation Parkway Savannah Glen Boulevard New 4 Lane Road $23.08 $0.30Christian Way Extension Nassau 995 Christian Way Hampton Club Way New 2 Lane Road $6.49 $0.04Clark Road Extension Duval 1020 Broward Road Clark Road New 3 Lane Road $0.90 $0.04College Drive Clay 902 CR 220 Doctors Inlet Road SR 21 Blanding Boulevard Widen to 6 Lanes $16.29 $0.31College Drive Extension Clay 14 SR 21 Blanding Boulevard Challenger Drive (Branan Field Road) New 4 Lane Road $30.08 $0.23Collins Road Duval 930 Shindler Drive Rampart Road Widen to 4 Lanes $11.30 $0.22Collins Road Duval 932 Old Middleburg Road S Shindler Drive Widen to 4 Lanes $4.10 $0.15Collins Road Duval 15 SR 21 Blanding Boulevard Pine Verde Widen to 4 Lanes $4.30 $0.15Collins Road Duval 16 at US 17 Roosevelt Boulevard New Interchange $36.00 $0.19Collins Road Realignment Duval 16B Pine Verde US 17 Roosevelt Boulevard New 4 Lane Road, Two Overpass and New Interchange $104.84 $0.07

Comfort Road Putnam 505 Port Road US 17 Widen to 4 Lanes $5.86 $0.07Commodore Point Drive Extension Nassau 996 Commodore Point Drive Blackrock Road New 2 Lane Road $3.61 $0.02Concourse Loop Road Nassau 501 License Road Amelia Concourse New 2 Lane Road $3.17 $0.03Connector Road Putnam 502 US 17 Distribution Center New 2 Lane Road $0.95 $0.95CR 105A Buccaneer Trail Nassau 705 South Fletcher Avenue Canopy Drive Turn Lane Improvements* $1.41 $0.05CR 16A St. Johns 803 SR 16 Connector SR 13 Widen to 4 Lanes $24.85 $0.72CR 16A Extension St. Johns 802 CR 16A Leo Maguire Parkway New 2 Lane Road $1.41 $0.02CR 209 Russell Road Clay 905 CR 739 Henley Road US 17 Widen to 4 Lanes $71.88 $0.77CR 209 South Clay 906 Decoy Road US 17 Reconstruct 2 Lanes $68.15 $0.30CR 210 St. Johns 805 I‐95 near US 1 Widen to 6 Lanes $10.10 $0.44CR 210 St. Johns 807 Greenbriar Road Cimarrone Road Widen to 4 Lanes $19.90 $0.22CR 210 W St. Johns 849 Longleaf Pine Parkway Greenbriar Road Widen to 4 Lanes $10.08 $0.29CR 214 St. Johns 809 Holmes Boulevard US 1 Widen to 3 Lanes* $0.92 $0.13CR 218 Clay 1026 US 301 Cosmos Avenue Widen to 4 Lanes $90.98 $0.96CR 218 Clay 1027 Cosmos Avenue Pine Tree Lane Widen to 4 Lanes $7.50 $0.25CR 218 Clay 24 SR 21 Blanding Boulevard CR 739 Henley Road Widen to 4 Lanes $42.39 $0.45CR 218 Clay 909 SR 16 CR 739 Henley Road Widen to 4 Lanes $31.33 $0.33CR 218 Extension Clay 25 CR 739 Henley Road SR 23 First Coast Expressway New 4 Lane Road $33.40 $0.20CR 218 Extension Clay 26 SR 23 First Coast Expressway CR 315 New 4 Lane Road $26.00 $0.30CR 220 Doctors Inlet Road Clay 33 SR 21 Blanding Boulevard Knight Boxx Road Widen to 4 Lanes $36.86 $0.30CR 220 Doctors Inlet Road Clay 34 College Drive US 17 Widen to 6 Lanes $40.74 $0.77CR 2209 St. Johns 810 SR 23 First Coast Expressway CR 210 New 6 Lane Road $20.30 $0.52CR 2209 St. Johns 811 SR 16 Connector SR 23 First Coast Expressway New 6 Lane Road $17.75 $0.45CR 2209 St. Johns 812 International Golf Parkway SR 16 Connector New 6 Lane Road $11.50 $0.42CR 2209 St. Johns 813 CR 214 CR 208 New 4 Lane Road $27.13 $0.42CR 2209 St. Johns 814 SR 207/CR 305 CR 214 New 4 Lane Road $39.51 $0.61CR 2209 St. Johns 815 SR 16 International Golf Parkway New 4 Lane Road $11.50 $0.06CR 2209 St. Johns 816 CR 208 SR 16 New 4 Lane Road $26.22 $0.41CR 2209 St. Johns 843 at CR 210 New Interchange $35.23 $0.19CR 305 St. Johns 818 CR 204 SR 206 New 2 Lane Road $10.00 $0.16

Page 1 of 13

Page 5: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

Path Forward 2040 Long Range Transportation Plan

Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost 

(millions)O&M Cost (millions)

CR 305 St. Johns 850 SR 206 SR 207 Widen to 4 Lanes $13.39 $0.39CR 315 Clay 31 SR 16 CR 315B Widen to 4 Lanes $29.50 $0.30CR 315 Clay 32 CR 315B US 17 Widen to 4 Lanes $7.10 $0.10CR 739B Sandridge Road Clay 904 CR 739 Henley Road CR 209 Russell Road Widen to 4 Lanes $34.10 $0.36Crosby Avenue Extension Nassau 993 US 17 SR 5 Pinewood Drive New 2 Lane Road $0.72 $0.00Davis / 9B Parcel Duval 1036 SR 9B SR 152 Baymeadows Road Widen to 4 Lanes $3.15 $0.42Decoy Road Clay 907 US 17 CR 209 South Reconstruct 2 Lanes $3.37 $0.02Dixie Highway / Pellicer Lane St. Johns 1025 SR 207 CR 214 West of King Street Reconstruct 2 Lanes and Widen to add Sidewalks and Bike 

Lanes$2.27 $0.03

Dove Road Extension {west} Nassau 991 Harper Chapel Road Extension Mentoria Road New 2 Lane Road $2.78 $0.03Durbin Parkway St. Johns 819 9B Extension Nocatee Parkway New 4 Lane Road $52.52 $0.43Durbin Parkway St. Johns 844 at US 1/SR 5 Dixie Highway Modify Interchange $35.23 $0.19Duval Station Road Duval 942 US 17/SR 5 Main Street Starratt Road Widen to 4 Lanes $14.48 $0.13east Dove Road Extension Nassau 974 Harper Chapel Road William Burgess Boulevard New 2 Lane Road $0.30 $0.00East Nassau Connector Nassau 36 I‐95 Chester Road New 4 Lane Road $93.40 $0.82East Nassau Connector Nassau 969 at I‐95 New Interchange $35.23 $0.19Eastport Road Duval 37 SR 105 Heckscher Drive Pulaski Road Widen to 3 Lanes $11.80 $0.18Flora Parke‐Wal Mart Connector Nassau 986 Flora Parke Boulevard Walmart Supercenter New 2 Lane Road $1.44 $0.01Florida Boulevard Duval 1021 Penman Road SR 10 Atlantic Boulevard Widen to 3 Lanes $5.30 $0.14Future Corridor Initiative Baker/Clay/Duv

al721 Tampa Bay Northeast Florida Future Corridor $2,000.00 $5.10

Gator Bowl Boulevard Duval 43 Liberty Street Hart / Mathews Bridge Widen to 6 Lanes and Remove Ramps $40.50 $0.00

Gene Lasserre Boulevard Extension Nassau 985 Gene Lassere Boulevard SR 200A Pages Dairy Road New 2 Lane Road and Roundabout $1.44 $0.01Goodbread Road Reconstruction Nassau 977 US 17 SR 5 Hamilton Street New 2 Lane Road $1.98 $0.04Governors Park Road Clay 46 US 17 SR 16 New 4 Lane Road $71.80 $0.59Hamilton Street Extension Nassau 1000 Goodbread Circle New 2 Lane Road $2.37 $0.02Harlow Boulevard Duval 943 SR 134 103rd Street Lane Avenue Widen to 3 Lanes $1.89 $0.02Harper Chapel Extension Nassau 989 Harper Chapel Road Dove Road Extension New 2 Lane Road $0.49 $0.01Hart Expressway Ramps Duval 43B Liberty Street Hart / Mathews Bridge Remove Ramps $6.30 ‐$0.19Hartley Road Duval 49 SR 13 San Jose Boulevard Old St. Augustine Road Widen to 3 Lanes $8.40 $0.09Harts Road Duval 963 SR 104 Dunn Avenue I‐295 Widen to 4 Lanes $18.83 $0.22Holmes Boulevard St. Johns 821 CR 214 Four Mile Road Widen to 6 Lanes $5.08 $0.10I‐10 Duval 401 SR 23 First Coast Expressway I‐295 Add 4 Express Lanes $219.54 $7.00I‐10 Nassau 402* Baker/Nassau County Line Nassau/Duval County Line Add 4 Express Lanes $4.58 $0.71I‐10 Duval 403* Nassau/Duval County Line US 301 Add 4 Express Lanes $56.25 $3.28I‐10 Baker 404* W of CR 125 W of SR 121 Add 4 Express Lanes $50.57 $1.17I‐10 Baker 405* W of SR 121 Baker/Nassau County Line Add 4 Express Lanes $16.96 $3.28I‐10 Duval 406 US 301 SR 23 First Coast Expressway Add 4 Express Lanes $101.87 $6.32I‐10 Duval 432 I‐295 I‐95 Add 4 Express Lanes $372.32 $5.58I‐10 Baker 453 Baker/Columbia County Line CR 125 Add 4 Express Lanes $155.61 $18.49I‐10 Duval 454 at I‐295 Modify Interchange $131.63 $0.19I‐10/US 90 Parallel Reliever Baker 720 South Mac Clenny East Baldwin Future Corridor $144.00 $0.37I‐295 Duval/Clay 57 SR 13 San Jose Boulevard W of US 17 Roosevelt Boulevard Add 4 Express Lanes on Bridge $177.64 $5.20I‐295 Duval 119 SR 9B I‐295 Add 4 Express Lanes $12.30 $3.00I‐295 Duval 407 I‐95 North SR 105 Dames Point Bridge/Heckscher 

DriveAdd 4 Express Lanes $123.30 $6.08

I‐295 Duval 408 North of Trout River I‐95 Add 4 Express Lanes $87.38 $5.18I‐295 Duval 409 US 1 New Kings Road North of Trout River Add 4 Express Lanes $28.17 $1.16I‐295 Duval 410 SR 134 103rd Street I‐10 Add 4 Express Lanes $180.57 $6.22I‐295 Duval 411 I‐10 US 1 South of New Kings Road Add 4 Express Lanes $66.47 $5.47I‐295 Duval 431 US 17 Roosevelt Boulevard SR 134 103rd Street Add 4 Express Lanes $52.45 $6.31I‐295 Duval 964 at US 17 Roosevelt Boulevard Modify Interchange $34.10 $0.19I‐295 Duval 1022 I‐95 South SR 13 San Jose Boulevard Add 2 Express Lanes $0.85 $4.46I‐295 Duval 1023 SR 202 J. T. Butler Boulevard SR 9B Add 2 Express Lanes $0.85 $4.86I‐295 Duval 121 SR 113 Southside Connector SR 202 J. T. Butler Boulevard Add 4 Express Lanes $176.80 $8.39I‐95 Duval 68 at SR 102 Airport Road Modify Interchange $9.00 $0.19I‐95 St. Johns 138 at US 1/SR 5 Ponce De Leon Boulevard and at SR  Modify Interchange $13.18 $0.19I‐95 St. Johns 400 St. Johns/Flagler County Line SR 206 Add 4 Express Lanes $92.49 $8.00I‐95 Duval 413 SR 104 Dunn Avenue SR 102 Airport Road Add 4 Express Lanes $456.58 $3.62

Page 2 of 13

Page 6: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

Path Forward 2040 Long Range Transportation Plan

Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost 

(millions)O&M Cost (millions)

I‐95 Duval 414 North of Fuller Warren Bridge SR 104 Dunn Avenue Add 4 Express Lanes $2,167.51 $11.00I‐95 Duval 418A Duval/St. Johns County Line I‐295 Add 4 Express Lanes $67.16 $5.47I‐95 St. Johns 418B International Golf Parkway St. Johns/Duval County Line Add 4 Express Lanes $106.25 $8.64I‐95 Duval 419 at US 1/SR 15 MLK Modify Interchange $59.50 $0.19I‐95 St. Johns 420 SR 206 International Golf Parkway Add 4 Express Lanes $850.86 $18.00I‐95 Duval 433 SR 202 J. T. Butler Boulevard SR 10 Atlantic Boulevard Add 4 Express Lanes $301.38 $5.16I‐95 Duval 434 I‐295 SR 202 J. T. Butler Boulevard Add 4 Express Lanes $361.45 $6.21I‐95 St. Johns 846 at CR 210 Modify Interchange $36.00 $0.19I‐95 Duval 962 at SR 115 Southside Boulevard Modify Interchange $35.23 $0.19International Golf Parkway St. Johns 823 I‐95 Turn/Bend Widen to 4 Lanes* $0.43 $0.09Jones Road Duval 944 US 90 Beaver Street Pritchard Road Intersection Improvements $5.40 $0.18Kernan Boulevard Duval 73 SR 202 J. T. Butler Boulevard Glen Kernan Parkway Widen to 6 Lanes $4.50 $0.29Kernan Boulevard Duval 933 SR 10 Atlantic Boulevard SR 116 McCormick Road Widen to 6 Lanes $7.50 $0.55Knight Boxx Road Clay 901 CR 220 Doctors Inlet Road SR 21 Blanding Boulevard Widen to 6 Lanes $12.22 $0.23Lake Asbury East West 1 Clay 915 NS3 CR 209 Russell Road New 2 Lane Road $15.15 $0.08Lake Asbury North South Road 3 Clay 914 CR 739B Sandridge Road CR 209 Russell Road New 2 Lane Road $18.51 $0.10Lofton Creek Crossing Nassau 710 Hendricks Road Avant Road New 2 Lane Bridge $70.03 $0.12Long Bay Road Extension North Clay 911 Old Jennings Road Long Bay Road New 2 Lane Road $5.05 $0.03Macaw Avenue Extension Nassau 982 Cardinal Street US 17 SR 5 New 2 Lane Road $4.69 $0.03McDuff Avenue / 5th Street Duval 1019 Melson Avenue Huron Street Widen to 3 Lanes $25.09 $0.04Mentoria‐Wm Burgess Connector Nassau 990 William Burgess Boulevard Harper Chapel Road New 2 Lane Road $1.44 $0.01Merrill Road Duval 945 Hartsfield Road SR 113 Southside Connector Widen to 6 Lanes $5.03 $0.30Mickler Road St. Johns 825 Palm Valley Road SR A1A Widen to 4 Lanes $12.10 $0.13Monument Road Duval 946 Tredinick Parkway I‐295 Widen to 6 Lanes $6.15 $0.05Monument Road Duval 947 I‐295 Lee Road Widen to 6 Lanes $6.15 $0.25National Cemetery Road Duval 1033 Lannie Road Arnold Road New 2 Lane Road $25.00 $0.12New Berlin Road Duval 948 Pulaski Road Yellow Bluff Road Widen to 4 Lanes $42.67 $0.28New Berlin Road Duval 949 Yellow Bluff Road Cedar Point Road Widen to 4 Lanes $42.67 $0.10New World Avenue Duval 1034 SR 23 First Coast Expressway Chaffee Road New 2 Lane Road $4.30 $0.07New World Avenue Duval 1035 SR 23 First Coast Expressway Chaffee Road Widen to 4 Lanes $4.30 $0.17Norfolk Southern Railroad Overpass Duval 85 West 12th Street US 23 New Kings Road New 3 Lane Road / Bridge $24.90 $0.07Northern Cross Town Corridor Baker 500 CR 125 SR 121 New 2 Lane Road $6.65 $6.65Northern Outer Beltway Duval/Nassau 88 I‐10 I‐95 Future Corridor $787.90 $4.08Oakleaf Village Parkway Extension Clay 913 Oakleaf Plantation Parkway Oakleaf Village Parkway New 2 Lane Road $10.10 $0.05Old Kings Road Duval 951 SR 111 Edgewood Avenue Plummer Road Intersection Improvements $12.96 $0.30Old Middleburg Road Duval 1015 Argyle Forest Boulevard SR 134 103rd Street Widen to 4 Lanes $23.10 $0.39Old St. Augustine Road Duval 90 Bartram Park Boulevard US 1/SR 5 Phillips Highway Widen to 6 Lanes and Overpass $458.55 $0.36Old St. Augustine Road Duval 1010 at Greenland Road Intersection Improvements / Add 1 Lane $0.60 $0.05

Outer Loop Facility Baker/Duval 91 SR 228 Normandy Boulevard SR 228 Normandy Boulevard Future Corridor $1,600.00 $4.08Pages Dairy Road East Extension Nassau 987 Chester Road Blackrock Road New 2 Lane Road $7.22 $0.04Pages Dairy Road South Extension Nassau 983 SR 200 SR A1A Sowell Road New 2 Lane Road $1.70 $0.01Palm Valley Road St. Johns 826 Intracoastal Waterway Mickler Road Widen to 4 Lanes $11.43 $0.13Pecan Park Road Duval 952 Braddock Boulevard JIA North Access Road Widen to 4 Lanes $22.43 $0.09Pecan Park Road Duval 92 I‐95 US 17 Main Street Widen to 4 Lanes $5.40 $0.06Pulaski Road Duval 953*** Eastport Road I‐295 Widen to 4 Lanes $3.09 $0.03Pulaski Road / Starratt Road Duval 97 I‐295 Duval Station Road Widen to 4 Lanes $25.10 $0.28Race Track Road St. Johns 827 St. Johns Parkway Bartram Park Boulevard Widen to 4 Lanes $40.80 $0.17Race Track Road St. Johns 828 Bartram Park Boulevard Bartram Springs Widen to 4 Lanes $30.00 $0.15Race Track Road Connector St. Johns 851 Durbin Parkway / 9B Extension Race Track Road New 2 Lane Road $3.99 $0.03Ramona Boulevard Duval 935 Hammond Boulevard Cahoon Road South Widen to 5 Lanes $2.70 $0.07Rampart / Firestone Road Duval 98 Collins Road SR 134 103rd Street Widen to 4 Lanes $26.24 $0.30Ranch Road Duval 1038 Tradeport Road SR 102 North of Airport Road Widen to 4 Lanes $2.10 $0.03Ricker Road Duval 934 Morse Avenue Old Middleburg Road Widen to 3 Lanes $9.40 $0.21Salisbury Road Extension Duval 99 SR 152 Baymeadows Boulevard Belfort Road New 3 Lane Road $16.10 $0.13San Pablo Road Duval 1009 US 90 Beach Boulevard SR 10 Atlantic Boulevard Widen to 3 Lanes $35.19 $0.18Shindler Drive Duval 101 Collins Road SR 134 103rd Street Widen to 3 Lanes $11.40 $0.21SR 10 Atlantic Boulevard Duval 714 at Girvin Road Intersection Improvements $7.57 $0.05SR 10 Atlantic Boulevard Duval 715 at Hodges Boulevard Intersection Improvements $7.57 $0.05SR 10 Atlantic Boulevard Duval 716 at San Pablo Boulevard Intersection Improvements $7.57 $0.05

Page 3 of 13

Page 7: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

Path Forward 2040 Long Range Transportation Plan

Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost 

(millions)O&M Cost (millions)

SR 100 Clay 450 Clay/Bradford County Line Clay/Putnam County Line Widen to 4 Lanes $20.59 $0.49SR 100 Putnam 451 Clay/Putnam County Line US 17 SR 5 Widen to 4 Lanes $96.87 $2.06SR 101 Mayport Road Duval 152B SR 116 Wonderwood Drive Mayport Main Gate Add 2 Northbound Lanes $0.49 $0.12SR 101 Mayport Road Duval 152 at SR 116 Wonderwood Drive Intersection Improvements $0.50 $0.05SR 102 Airport Road Duval 421 Airport Entrance I‐95 Widen to 6 Lanes $8.47 $0.39SR 104 Dunn Avenue Duval 940 US 1/SR 15 New Kings Road I‐295 Widen to 4 Lanes $25.71 $0.23SR 104 Dunn Avenue Duval 941 Old Kings Road US 23 New Kings Road Intersection Improvements $3.00 $0.05SR 115 Arlington Expressway Duval 100 SR 109 University Boulevard SR 10 Atlantic Boulevard Widen to 6 Lanes* $31.66 $0.64SR 115 Arlington Expressway * Duval 153 at SR 109 University Boulevard Modify Interchange $12.50 $0.19SR 115 Lem Turner Road Duval/Nassau 74 I‐295 US 1 / Callahan S Kings Road Widen to 4 Lanes $87.00 $1.56SR 115 Southside Boulevard Duval 102 US 1/SR 5 Philips Highway I‐95 Ramps Widen to 6 Lanes* $0.97 $0.37SR 115 Southside Boulevard Duval 103 SR 202 J. T. Butler Boulevard US 90 Beach Boulevard Widen to 6 Lanes* $8.50 $0.50SR 115 Southside Boulevard Duval 104 US 90 Beach Boulevard SR 10 Atlantic Boulevard Widen to 6 Lanes* $1.22 $0.47SR 115 Southside Boulevard Duval 960 Hogan Road Gate Parkway Intersection Improvements $25.50 $0.05SR 115 Southside Boulevard Duval 966 at SR 202 J. T. Butler Boulevard Modify Interchange $35.23 $0.19SR 115 Southside Boulevard Duval 967 at SR 152 Baymeadows Road Underpass $12.50 $0.19SR 115 Southside Boulevard Duval 968 at SR 10 Atlantic Boulevard Intersection Improvements $10.30 $0.05SR 152 Baymeadows Road Duval 937 I‐95 SR 115 Southside Boulevard Widen to 6 Lanes $10.52 $0.20SR 152 Baymeadows Road Duval 938 US 1 /SR 5 Philips Highway I‐95 Widen to 6 Lanes* $0.43 $0.16SR 16 Clay 106 CR 218 SR 15A Oakridge Avenue Widen to 4 Lanes $54.70 $0.69SR 16 St. Johns 110 I‐95 SR 313 Widen to 6 Lanes $20.25 $0.50SR 16 Clay 908 US 17 Shands Bridge Widen to 4 Lanes $37.78 $0.40SR 16 St. Johns 835 South Francis Road International Golf Parkway Widen to 4 Lanes $5.90 $0.17SR 16 St. Johns 836 CR 208 Outlet Mall South Francis Road Widen to 4 Lanes $15.59 $0.45SR 16 Connector St. Johns 829 SR 16/CR 16A CR 2209 New 4 Lane Road $26.00 $0.16SR 19 Connector Putnam 965 SR 19 Putnam County Boulevard New 4 lane road / bridge $198.93 $0.34SR 20 Putnam 422 Putnam/Alachua County Line SW 56th Avenue Widen to 4 Lanes $57.95 $0.72SR 20 Putnam 423 SW 56th Avenue CR 315 Interlachen Widen to 4 Lanes $44.68 $0.34SR 200  Overpass Nassau 1003 at US 17 SR 5 and Railroad Tracks Overpass $83.20 $0.19SR 200  William Burgess Connector Nassau 998 William Burgess Boulevard SR 200 SR A1A New 2 Lane Road $4.14 $0.03SR 200  Yulee Backage Roads Nassau 992 Cardinal Street North Extension Old Yulee Road New 2 Lane Road $4.26 $0.02SR 200 SR A1A Nassau 427 at US 17 Intersection Improvements $3.00 $0.05SR 200 SR A1A Nassau 703 Amelia Island Parkway Sadler Road Widen to 6 Lanes $3.79 $0.19SR 200A Pages Dairy Road Nassau 979 at Felmor Road Roundabout Projects $0.80 $0.02SR 207 St. Johns 113 I‐95 South Holmes Boulevard Widen to 6 Lanes $26.00 $0.65SR 207 St. Johns 830 Holmes Boulevard SR 312 Widen to 6 Lanes $26.00 $0.08SR 21 Blanding Boulevard Duval 9 I‐295 Wilson Boulevard Widen to 6 Lanes $75.18 $1.01SR 21 Blanding Boulevard Clay 114 SR 16 CR 215 Blanding Boulevard Widen to 4 Lanes $34.30 $0.39SR 21 Blanding Boulevard Duval 957A at Collins Road Intersection Improvements $5.80 $0.05SR 21 Blanding Boulevard Duval 957B at SR 134 103rd Street Intersection Improvements $5.80 $0.05SR 21 Blanding Boulevard Duval 957C at Cedar Hills Boulevard Intersection Improvements $5.80 $0.05SR 228 Hart Bridge Duval 47 SR 228  Hart Expressway ‐ Downtown SR 10 Atlantic Boulevard New 6 Lane Bridge $198.00 $0.23SR 228 Normandy Boulevard Duval 86 US 301 Bell Road (Equestrian Park ) Widen to 4 Lanes $54.70 $0.66SR 228 Normandy Boulevard Duval 87 SR 23 First Coast Expressway SR 111 Cassat Avenue Widen to 6 Lanes $69.30 $1.66SR 23 First Coast Expressway Clay 41 at CR 218 New Interchange $42.19 $42.19SR 23 First Coast Expressway Clay 8202 SR 21 Blanding Boulevard US 17 New 4 Lane Road $518.83 $518.83SR 23 First Coast Expressway Clay 1011 at SR 21 Blanding Boulevard New Interchange $35.43 $35.43SR 23 First Coast Expressway Clay 1012 at CR 739 New Interchange $35.43 $35.43SR 23 First Coast Expressway Clay 1013 at SR 16 New Interchange $35.43 $35.43SR 23 First Coast Expressway Clay/Duval 8201 I‐10 SR 21 Blanding Boulevard Widen to 6 Lanes $123.66 $123.66SR 23 First Coast Expressway Clay/St. Johns 8203 US 17 I‐95 New 6 Lane Road $706.26 $706.26SR 23 First Coast Expressway St. Johns 840 at I‐95 New Interchange $35.43 $35.43SR 23 First Coast Expressway St. Johns 841 at CR 16 A New Interchange $35.43 $35.43SR 23 First Coast Expressway St. Johns 847 at CR 2209 New Interchange $42.19 $42.19SR 243 JIA North Access Road Duval 701 SR 102 Airport Road Pecan Park Road Widen to 4 Lanes $32.40 $0.34SR 312 St. Johns 115 US 1/SR 5 Dixie Highway SR A1A Widen to 6 Lanes $22.80 $0.50SR 313 St. Johns 831 SR 207 SR 16 New 6 Lane Road $39.26 $0.82SR 313 St. Johns 832 SR 16 US 1 Dixie Highway New 4 Lane Road $34.35 $0.58SR 313 St. Johns 839 at US 1/SR 5 Dixie Highway New Interchange $35.23 $0.19SR 9B Duval 1024 US 1/SR 5 Philips Highway I‐295 Add 2 Auxiliary Lanes $0.85 $3.22

Page 4 of 13

Page 8: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

Path Forward 2040 Long Range Transportation Plan

Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost 

(millions)O&M Cost (millions)

SR 9B Duval 18 US 1/SR 5 Philips Highway I‐295 Widen to 6 Lanes $31.20 $1.06SR 9B Extension St. Johns 833 St. Johns Parkway Race Track Road Widen to 6 Lanes $23.87 $0.48SR 9B Extension St. Johns 842 at Durbin Parkway New Interchange $35.23 $0.19SR A1A St. Johns 128 Solana Road SR 202 J. T. Butler Boulevard Widen to 6 Lanes* $0.99 $0.38SR A1A Nassau 706 South Fletcher Avenue Amelia Island Parkway Turn Lane Improvements* $3.00 $0.06SR A1A St. Johns 1008 at Red Cox/Coquina Rd Intersection Improvements $3.00 $0.05SR A1A St. Johns 800 Mickler Road Palm Valley Road Widen to 4 Lanes $27.00 $0.27SR A1A Duval 151 SR 116 Wonderwood Drive Naval Station Mayport North Gate Widen to 4 Lanes* $3.00 $0.16SR A1A Anastasia Boulevard St. Johns 1031 Casanova Road Bridge of Lions CSS $2.10 $0.06SR A1A St Johns River Ferry Duval 2331 Ferry Slip Replacement $8.00St. Johns Parkway St. Johns 848 CR 2209 9B Extension Widen to 6 Lanes $11.12 $0.23Starratt Road Duval 954 Duval Station Road Yellow Bluff Road Widen to 4 Lanes $27.26 $0.25Touchton Road Duval 129 Belfort Road SR 115 Southside Boulevard Widen to 4 Lanes $7.00 $0.07Town Center Boulevard Clay 903 US 17 CR 220 Doctors Inlet Road Widen to 4 Lanes $34.10 $0.36Trout River Boulevard Duval 955 Old Kings Road US 23 New Kings Road Widen to 4 Lanes $6.60 $0.06Tynes Road Clay 912 Pipit Place Oakleaf Plantation Parkway New 2 Lane Road $11.78 $0.06US 1 SR 5 St. Johns 845 at CR 210 Modify Interchange $17.53 $0.19US 1/SR 15 New Kings Road Duval 82 Soutel Drive I‐295 Widen to 6 Lanes $24.50 $0.61US 1/SR 15 New Kings Road Duval 83 I‐295 Old Kings Road Widen to 6 Lanes $40.10 $1.05US 1/SR 15 New Kings Road Duval 950 SR 111 Edgewood Avenue Soutel Drive Intersection Improvements $1.08 $0.06US 1/SR 5 Dixie Highway St. Johns 130 SR 206 Lewis Point Road Widen to 6 Lanes $47.50 $1.27US 1/SR 5 Dixie Highway St. Johns 131 SR 313 International Golf Parkway Widen to 6 Lanes $22.20 $0.56US 1/SR 5 Dixie Highway St. Johns 132 International Golf Parkway Race Track Road Widen to 6 Lanes $60.90 $1.58US 1/SR 5 Philips Highway Duval 93 Nocatee Parkway / Race Track Road SR 9B Widen to 6 Lanes $19.90 $0.50US 1/SR 5 Philips Highway Duval 94 SR 9B I‐295 Widen to 6 Lanes* $6.56 $0.58US 1/SR 5 Philips Highway Duval 95 I‐95 at the Avenues SR 202 J. T. Butler Boulevard Widen to 6 Lanes* $7.00 $0.94US 1/SR 5 Philips Highway Duval 96 SR 202 J. T. Butler Boulevard SR 126 Emerson Street Widen to 6 Lanes $31.60 $0.70US 17 Clay 133 CR 315 Town Center Boulevard Widen to 6 Lanes $18.10 $0.39US 17 Nassau 707 Nassau/Duval County Line Harts Road Intersection Improvements $2.97 $0.09US 17 Nassau 709 SR 200 SR A1A Georgia State Line Widen to 4 Lanes $79.74 $0.91US 17 Clay 1037 Governor Street Haven Avenue Widen to 4 Lanes $7.15 $0.05US 17 Main Street Duval/Nassau 78 Pecan Park Road SR 200 / SR A1A Widen to 4 Lanes $69.80 $0.40US 17 Main Street Duval 1017 New Berlin Road Pecan Park Road Widen to 4 Lanes $78.50 $0.39US 17 Main Street Duval 959 at Eastport Road New Interchange $21.41 $0.19US 17 Pages Dairy Connector w/roundabout Nassau 984 US 17 SR 5 SR 200A Pages Dairy Road New 2 Lane Road and Roundabout $3.55 $0.03

US 17 Powerline Corridor Nassau 994 Vegas Boulevard Radio Avenue New 2 Lane Road $4.26 $0.06US 17 SR 15 Putnam 428 West of Dunn Creek Bridge Horse Landing Road Widen to 4 Lanes $50.70 $0.20US 17 SR 15 Putnam 429 CR 309 Satsuma West of Dunn Creek Bridge Widen to 4 Lanes $19.07 $0.28US 17 SR 15 Putnam 430 Putnam/Volusia County Line Pomona Park/Feagle Avenue Widen to 4 Lanes $66.47 $1.28US 17 SR 15 Putnam 452 Pomona Park/Feagle Avenue CR 309 Satsuma Widen to 4 Lanes $6.72 $0.46US 17 Yulee Backage Roads Nassau 999 US 17 SR 5 North of Koen Lane New 2 Lane Road $0.85 $0.00US 1B King Street St. Johns 1029 US 1 Ponce de Leon Boulevard Avenida Menendez Context Sensitive Solutions (CSS) $3.15 $0.04US 1B San Marco Avenue St. Johns 1030 Bridge of Lions SR 16 Context Sensitive Solutions (CSS) $7.15 $0.07US 301 SR 200 Duval 123 US 90 Duval/Nassau County Line Widen to 4 Lanes $146.09 $0.43US 301 SR 200 Clay 424 Clay/Bradford County Line Duval/Clay County Line Widen to 6 Lanes $28.05 $1.16US 301 SR 200 Nassau 708 US 1 at S Kings Road Intersection Improvements $7.16 $0.05US 301 SR 201 Duval 425 Duval/Clay County Line I‐10 Widen to 6 Lanes $25.08 $1.35US 90 / SR 115 Mathews Bridge Duval 79 Alt. US 1 MLK Jr. Parkway SR 109 University Boulevard New 6 Lane Bridge and Transit $1,175.00 $0.34US 90 Beaver Street Duval 6 SR 23 First Coast Expressway Cahoon Road Widen to 4 Lanes $60.71 $0.58US 90 Beaver Street Duval 7 Cahoon Road McDuff Avenue Widen to 4 Lanes $40.82 $0.46Various SR 200 Intersections Modifications Nassau 981 Intersection Improvements $8.00 $0.05

Veterans Parkway St. Johns 834 Greenbriar Road Longleaf Pine Parkway New 4 Lane Road $36.37 $0.30Wells Road Clay 910 Aquarius Concourse SR 21 Blanding Boulevard Reconstruct and New 2 Lane Road $0.31 $0.00Woodbridge Parkway Extension Nassau 997 Woodbrigde Parkway Clements Road New 2 Lane Road $1.44 $0.01Yellow Bluff Road Duval 956 Starratt Road New Berlin Road (north) Widen to 4 Lanes $33.06 $0.28* Candidates for context sensitive solutions

Page 5 of 13

Page 9: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

Path Forward 2040 Long Range Transportation Plan

Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost 

(millions)O&M Cost (millions)

Anastasia Island (Amphitheatre) St. Johns  2380     Park and Ride Lots $0.25 $0.00Area wide  Baker 2303     Local Bus Service  $1.00Area wide  Clay 2310     Local Bus Service  $1.00Area wide  Duval 2332     Local Bus Service  $69.00Area wide  Nassau 2370     Local Bus Service  $1.00Area wide  Putnam 2374     Local Bus Service $1.00Area wide  St. Johns  2378     Local Bus Service  $1.10Center Street Duval 2304 North of Drew Street (Baldwin)   Park and Ride Lots $0.25 $0.00CR 210 St. Johns  2381 east of US 1   Park and Ride Lots $0.25 $0.00CR 220  Doctors Inlet Road  Clay 2316 at Hollow Road   Park and Ride Lots $0.25 $0.00Cumberland Island Ferry Nassau 2369 Fernandina Cumberland Island Ferry Service $5.00 $1.00Downtown ‐ Sports Complex Duval 2349 Downtown Jacksonville (Bay Street & Main Street) Jacksonville Municipal Stadium Streetcar  $38.50 $0.41Downtown Facility Duval 2355     Transportation Center $60.00 $2.55Drew Street Duval 2305 at Center Street (Baldwin)   Park and Ride Lots $0.25 $0.00Duval Road Duval 2336 at I‐95   Park and Ride Lots $0.25 $0.00East First Coast Flyer Duval 2385 Downtown Jacksonville (Duval County) 3rd Street (Jacksonville Beach) BRT $28.00 $7.08Five Points/Core/Brooklyn Duval 2347 Central Station Brooklyn  Station  Skyway Extension  $26.60 $6.37Five Points/Core/Brooklyn Duval 2350 Five Points Downtown Jacksonville (Bay Street & Ma Streetcar  $85.00 $0.41I‐95 Duval 2326 Gateway Mall Jacksonville International Airport BRT   $12.20 $3.89I‐95 Duval 2330 Downtown Jacksonville (Duval County) Yulee (Nassau County) Express Bus Service $1.71La Villa/Core Duval 2351 Transportation Center Duval Street & Monroe Street to Ocean Streetcar  $31.50 $0.41Mayport Road Duval 2338 at SR A1A   Park and Ride Lots $0.25 $0.00North (CSX) Duval  2356 Downtown Jacksonville (Duval County) Yulee (Nassau County) Commuter Rail $271.69 $0.00North Extension (CSX) Nassau 2366 Yulee Fernandina Beach Commuter Rail $122.90 $4.49Northwest (CSX) Duval  2357 Downtown Jacksonville (Duval County) Callahan (Nassau County) Commuter Rail $179.60 $15.96Racetrack Road  St. Johns  2382 at US 1   Park and Ride Lots $0.25 $0.00Riverside/Avondale Duval 2352 Riverside (King Street) Five Points Streetcar  $26.25 $0.41South of Glen St. Mary Baker 2306     Park and Ride Lots $0.25 $0.00Southbank/San Marco Duval 2348 Kings Avenue Station Southwest  of Railroad Tracks (SouthbankSkyway Extension  $52.50 $4.24Southbank/San Marco Duval 2353 Kings Avenue Station Baptist Hospital / MOSH & Atlantic Boule Streetcar  $52.50 $0.41Southeast (FEC) Duval 2327 St. Augustine (St. Johns County) Downtown Jacksonville (Duval County) Commuter Rail $0.00 $0.00Southeast Extension (FEC) St. Johns  2377 Palm Coast (Flagler County) City of St. Augustine Commuter Rail $255.20 $14.97Southwest (CSX) Duval  2358 Green Cove Springs (Clay County) Downtown Jacksonville (Duval County) Commuter Rail $294.01 $0.00Southwest Extension (CSX) Clay  2319 Palatka (Putnam County) Green Cove Springs (Clay County) Commuter Rail $236.30 $14.97Southwest First Coast Flyer Duval 2386 Wells Road Downtown Jacksonville (Duval County) BRT $19.00 $4.96Springfield Duval 2354 FSCJ Station 8th Street/ Medical Complex Streetcar  $46.17 $0.41SR 115   Lem Turner Road  Duval 2337 at SR 104 Dunn Avenue   Park and Ride Lots $0.25 $0.00SR 115   Lem Turner Road  Duval  2361 at Soutel    Park and Ride Lots $0.25 $0.00SR 115   Lem Turner Road  Duval  2362 at I‐295   Park and Ride Lots $0.25 $0.00SR 115  Southside Boulevard  Duval 2325 Avenues Mall Regency Square Mall BRT  $18.00 $2.83SR 134  103rd Street  Duval 2321 SR 228  Normandy Boulevard   SR 21  Blanding Boulevard   BRT $38.35 $2.16SR 134  103rd Street  Duval 2334 at SR 228  Normandy Boulevard     Park and Ride Lots $0.25 $0.00SR 16*** St. Johns  2385     Park and Ride Lots $0.25 $0.00SR 200  SR A1A   Nassau 2371 at I‐95   Park and Ride Lots $0.25 $0.00SR 200  SR A1A   Nassau 2372 east of Yulee   Park and Ride Lots $0.25 $0.00SR 207*** St. Johns  2386     Park and Ride Lots $0.25 $0.00SR 21  Blanding Boulevard   Clay 2308 CR 218 Wells Road BRT $37.50 $3.01SR 21  Blanding Boulevard   Clay 2311 at Tanglewood   Park and Ride Lots $0.25 $0.00SR 21  Blanding Boulevard   Clay 2312 at Old Jennings Road   Park and Ride Lots $0.25 $0.00SR 21  Blanding Boulevard   Clay 2313 at Edson Drive   Park and Ride Lots $0.25 $0.00SR 21  Blanding Boulevard   Clay 2314 at Wells Road   Park and Ride Lots $0.25 $0.00SR 21  Blanding Boulevard   Clay 2315 at SR 224 Kingsley Avenue   Park and Ride Lots $0.25 $0.00SR 21  Blanding Boulevard   Clay 2318 North and South of Bolton Road   Park and Ride Lots $0.25 $0.00SR 21  Blanding Boulevard   Duval 2335 at Weconnett Boulevard   Park and Ride Lots $0.25 $0.00SR 21  Blanding Boulevard   Duval 2340 North and South of Wilson Boulevard   Park and Ride Lots $0.09 $0.00SR 21  Blanding Boulevard   Duval 2341 North and South of SR 134 103rd Street   Park and Ride Lots $0.25 $0.00SR 21  Blanding Boulevard   Duval  2360 at 105th Street   Park and Ride Lots $0.25 $0.00SR 21  Blanding Boulevard   Duval  2364 North of I‐295   Park and Ride Lots $0.25 $0.00SR 228  Normandy Boulevard   Duval 2322 SR 134 103rd Street Downtown Jacksonville (Duval County) BRT $97.45 $5.49

Transit Capacity Projects

Page 6 of 13

Page 10: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

Path Forward 2040 Long Range Transportation Plan

Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost 

(millions)O&M Cost (millions)

SR A1A Duval 2343 North and South of SR 202 J. T. Butler Boulevard   Park and Ride Lots $0.25 $0.00SR A1A St. Johns  2379 at Palm Valley Road   Park and Ride Lots $0.25 $0.00SR A1A  St Johns River Ferry  Duval 2329     Drydock /  Ferry Repairs $13.00 $13.00SR A1A  St Johns River Ferry  Duval 2331     Ferry Slip Replacement $8.00SR A1A  St Johns River Ferry  Duval 2333 Ft. George/Mayport   Long Term Site Improvements $8.00SR A1A  St Johns River Ferry  Duval 2344 JPA Property Mayport Terminal Relocation of Ferry offices $0.29SR A1A  St Johns River Ferry  Duval 2345 Mayport Ft. George Island Service & Capital Improvements $7.00 $0.80SR A1A  St Johns River Ferry  Duval 2346 Ft. George/Mayport   Site Improvements $0.89St. Augustine Airport St. Johns  2383     Park and Ride Lots $0.25 $0.00US 1 St. Johns  2384 at Lewis Speedway Road   Park and Ride Lots $0.25 $0.00US 1  Duval 2324 Lewis Speedway (St. Johns County) Avenues Mall (Duval County) BRT $132.03 $7.43US 1  St. Johns  2375 Lewis Speedway (St. Johns County) Avenues Mall (Duval County) BRTUS 1/SR 15  New Kings Road   Duval 2323 Downtown Jacksonville (Duval County) Edgewood Avenue BRT $29.55 $1.66US 1/SR 15  New Kings Road   Duval  2363 Timucuan DRI   Park and Ride Lots $0.25 $0.00US 17  Roosevelt Boulevard  Clay  2320 at Wells Road   Park and Ride Lots $0.25 $0.00US 17  Roosevelt Boulevard  Duval 2342 at SR 128 San Juan Avenue   Park and Ride Lots $0.25 $0.00US 90 Baker 2302 MacClenny (Baker County) Downtown Jacksonville (Duval County) Local Bus Service $2.14US 90  Beach Boulevard  Duval 2339 West and East of Kernan Boulevard   Park and Ride Lots $1.08 $0.00US 90  Beach Boulevard  Duval  2359 at San Pablo Road   Park and Ride Lots $0.25 $0.00West (CSX) Duval 2328 Baldwin (Duval County) Downtown Jacksonville (Duval County) Commuter Rail $170.10 $9.48West Extension (CSX) Baker 2301 MacClenny (Baker County) Baldwin (Duval County) Commuter Rail $85.10 $5.49Yellow Water Road Duval 2307 North of I‐10   Park and Ride Lots $0.25 $0.00Youngerman Circle Clay 2317 at Argyle Forest Boulevard   Park and Ride Lots $0.25 $0.00

SR 121 Rail Trail Corridor Baker 2000 Baker/Union County Line Baker/Nassau County Line Florida Greenway $3.08 $0.12Cecil Field Conservation Corridor Clay 2001 CR 218 Duval/Clay County Line Land Trail Opportunities $2.54 $0.10CR 218 Clay 2002 SR 16 SR 21 Florida Greenway $1.73 $0.07CR 220   Doctors Inlet Road  Clay 2004 College Drive  US 17 Multi‐Use Trail $0.93 $0.04CR 220   Doctors Inlet Road  Clay 2003 SR 21 College Drive  Florida Greenway $1.62 $0.06Long Bay Road Clay 2005 SR 21  Blanding Boulevard Old Jennings Road Multi‐Use Trail $1.28 $0.03Old Jennings Road Clay 2006 Long Bay Road SR 23  First Coast Expressway  Multi‐Use Trail $0.46 $0.02US 17 Clay 2007 at CR 220  (Fleming Island Area)   Accommodate Pedestrians and Bicyclist $0.34 $0.00US 17   Roosevelt Boulevard / Park Avenue  Clay 2009 Palatka Clay/Duval County Line Florida Greenway $18.14 $0.72US 17  Park Avenue  Clay 2008 at Kingsley Avenue (Orange Park)   Accommodate Pedestrians and Bicyclist $0.04 $0.00SR 16  Clay / St. Johns 2010 Kingsley Lake Drive SR 13  San Jose Boulevard  Florida Greenway ‐ Multi‐Use Trail $6.48 $0.265th Street Duval 2012 Lane Avenue  Melson Avenue Bike Lane $0.40 $0.02Arlington Road Duval 2013 Lone Star Road King Arthur Road Bike Lane $0.01 $0.00Arlington Road West Duval 2014 Cesery Road King Arthur Road Bike Lane $0.11 $0.00Bay Street Duval 2019 Myrtle Avenue Lee Street Bike Lane $0.09 $0.00Baymeadows Road Duval 2020 SR 115  at Southside Boulevard    Accommodate Pedestrians and Bicyclist $0.03 $0.00Beauclerc Road Duval 2023 I‐295 SR 13  San Jose Boulevard  Bi‐directional 12 ft. Shared Use Path $0.64 $0.03Boulevard Street Duval 2026 5th Street 12th Street Bike Lane $0.15 $0.01Bowden Road Duval 2028 Spring Park Road Southpoint Parkway Bike Lane $0.06 $0.00Bowden Road Duval 2027 US 1  Philips Highway  Spring Park Road Bike Lane $0.14 $0.01Broad Street Duval 2029 Water Street 5th Street Bike Lane $0.27 $0.01Cecil Field Conservation Corridor Duval 2031 Duval/Clay County Line US 90  Beaver Street  Florida Greenway $2.78 $0.11Clark Road Duval 2032 Broward Road US 17  Main Street  Bike Lane $0.19 $0.01Commonwealth Avenue Duval 2033 Imeson Road Lane Avenue Bike Lane $0.30 $0.01CSX Corridor North Duval 2034 US 17 Main Street  / S Rail Line US 17 Main Street / Trout River Drive Multi‐Use Path $0.71 $0.03Deerwood Area Duval 2035 Deerwood Park Boulevard Gate Parkway Multi‐Use Path $0.17 $0.01Downtown Jacksonville Duval 2036     Accommodate Pedestrians and Bicyclist $1.45 $0.02Downtown Neptune/Atlantic Beach Duval 2037 at Sherry Drive, 2nd Street, Ocean Street, Cherry Stre  Accommodate Pedestrians and Bicyclist $0.07 $0.00Duval Road Duval 2039 Airport Road Airport Center Drive Bike Lane $0.15 $0.01Duval Street Duval 2040 Lee Street Georgia Street Bike Lane $0.41 $0.02East Coast Greenway ‐ Duval County Corridor Duval 2041 St. Johns/ Duval County Line Nassau/Duval County Line Florida Greenway $11.30 $0.21Edgewood Avenue Duval 2043 St. Johns Avenue Post Street Bike Lane $0.32 $0.01Forest Street Duval 2045 Acosta Street Lime Street Bike Lane $0.13 $0.01Forsyth Street Duval 2046 Myrtle Avenue Lee Street Bike Lane $0.09 $0.00Gate Parkway East Duval 2047 Gate Parkway St. Johns Town Center Boulevard Multi‐Use Path $0.05 $0.00

Bicycle and Pedestrian Projects

Page 7 of 13

Page 11: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

Path Forward 2040 Long Range Transportation Plan

Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost 

(millions)O&M Cost (millions)

Gate Parkway South East Duval 2048 Deerwood Parkway St. Johns Town Center Boulevard Bike Lane $0.11 $0.00Hogan's Creek Greenway Duval 2052 Market Street North Riverbank Multi‐Use Path $0.23 $0.01Hubbard Street Duval 2053 Orange Street  14th Street Bike Lane $0.11 $0.01Imeson Road Duval 2054 Commonwealth Avenue Baldwin Rail Trail Bike Lane $0.08 $0.00Jacksonville Baldwin / East Coast Corridor Duval 2055 Bulls Bay Highway (Jacksonville Baldwin Corridor) St Johns River Ferry (East Coast GreenwayFlorida Greenway $17.47 $0.26Jacksonville Beach Area Duval 2056 at 3rd Avenue, Ocean Street, 2nd Avenue, South 10t   Accommodate Pedestrians and Bicyclist $0.23 $0.00Jefferson Street Duval 2057 Water Street 1st Street Bike Lane $0.21 $0.01Kernan Boulevard  Duval 2058 Baymeadows Road (SR 152) SR 116  Fort Caroline Road  Florida Greenway $3.05 $0.12Laura Street Duval 2059 8th Street S‐Line Pavement Markings and Signage $0.06 $0.00Laura Street Duval 2060 Bay Street 8th Street Pavement Markings and Signage $0.06 $0.00Lee Street Duval 2061 Water Street Duval Street Bike Lane $0.07 $0.00Lone Star Road Duval 2062 Mill Creek Road SR 113  Southside Connector  Bike Lane $0.11 $0.00Mandarin Road Duval 2065 San Jose Boulevard (SR 13) I‐295 Bi‐directional 12 ft. Shared Use Path $1.50 $0.06Mary Street Duval 2089 San Marco Boulevard  US 17  Main Street Bridge  Bike Lane $0.03 $0.00McCoys Creek Boulevard / Fitzgerald Street Duval 2067 Nixon Street Forest Street Multi‐Use Path $0.03 $0.00McCoys Creek Boulevard / Fitzgerald Street Duval 2066 McDuff Avenue Leland Street Bike Lane $0.10 $0.00Moncrief Road Duval 2068 13th Street Golfair Boulevard Bike Lane $0.30 $0.01Monument Road and  SR 10 Atlantic Boulevard  Duval 2069 SR 113  Southside Boulevard  N Regency Square Boulevard  Bike Lane $0.33 $0.01Myrtle Avenue Duval 2070 Forest Street Kings Road Bike Lane $0.29 $0.01Newnan Street Duval 2071 Bay Street Orange Street  Pavement Markings and Signage $0.07 $0.00Old Kings Road Duval 2073 S‐line Martha Street Bike Lane $0.05 $0.00Old Middleburg Road Duval 2074 Herlong Road Lenox Avenue Bike Lane $0.28 $0.01Old St Augustine Road Duval 2075 Losco Road SR 13  San Jose Boulevard  Bike Lane $0.05 $0.00Riverplace Boulevard Duval 2078 Prudential Drive US 1  Main Street  Bike Lane $0.08 $0.00Riverside/Five Point Area Duval 2080 at Stockton Street, Rossell Street, I‐95, St. Johns Rive   Accommodate Pedestrians and Bicyclist $0.67 $0.01Southpoint Parkway Duval 2090 Belfort Road Bowden Road Bike Lane $0.38 $0.02SR 10  Atlantic Boulevard  Duval 2017 Kings Road US 90  Beach Boulevard  Bike Lane $0.18 $0.01SR 10  Atlantic Boulevard  Duval 2016 US 90  Beach Boulevard  SR 228 Alt. US 1  Hart Expressway  Bike Lane $0.23 $0.01SR 10  Atlantic Boulevard  Duval 2018 SR 228  Hart Expressway  SR 109  University Boulevard  Bike Lane $0.29 $0.01SR 10  Atlantic Boulevard  Duval 2015 Hart Expressway (SR 228 Alt. US 1) SR A1A Bi‐directional 12 ft. Shared Use Path $3.16 $0.12SR 104  Dunn Avenue  Duval 2038 Biscayne Avenue US 17  Main Street  Bike Lane $0.37 $0.02SR 105  Zoo Parkway  Duval 2049 Busch Drive I‐295 Bike Lane $0.12 $0.01SR 105  Zoo Parkway  Duval 2050 US 17  Main Street  SR A1A Multi‐Use Path $0.14 $0.01SR 109  University Boulevard North  Duval 2102 SR 10  Atlantic Boulevard  Cesery Boulevard Bike Lane $0.11 $0.00SR 109  University Boulevard North  Duval 2103 University Boulevard / Cesery Boulevard Gable Lane Bike Lane $0.36 $0.01SR 111  Cassat Avenue  Duval 2030 SR 21  Blanding Boulevard   SR 111  Edgewood Avenue  Bike Lane $0.77 $0.03SR 111  Edgewood Avenue  Duval 2042 SR 111  Cassat Avenue  US 1/SR 15  New Kings Road   Bike Lane $0.77 $0.03SR 111  Tallulah Avenue  Duval 2099 US 17  Main Street  68th Street Bike Lane $0.22 $0.01SR 115  Southside Boulevard  Duval 2094 Gate Parkway Touchton Road Sidewalk Improvements $0.14 $0.00SR 115  Southside Boulevard  Duval 2095 US 1  Philips Highway  Belle Rive Boulevard Sidewalk Improvements $0.48 $0.00SR 115  Southside Boulevard  Duval 2093 Deerwood Park Boulevard US 90  Beach Boulevard  Sidewalk Improvements $0.72 $0.00SR 115  Southside Boulevard  Duval 2092 US 1  Philips Highway  Belle Rive Boulevard Multi‐Use Path $0.43 $0.02SR 115  Southside Boulevard  Duval 2091 Avenues Mall (US 1) SR 10 Atlantic Boulevard / Regency SquarBi‐directional 12 ft. Shared Use Path $2.30 $0.09SR 126  Emerson Street  Duval 2044 Hendricks Avenue US 1  Philips Highway  Bike Lane $0.25 $0.01SR 128  San Juan Avenue  Duval 2088 SR 21  Blanding Boulevard   SR 211  Herschel Street  Bike Lane $0.20 $0.01SR 13  Hendricks Avenue  Duval 2051 SR 13  San Jose Boulevard  San Marco Boulevard Bike Lane $0.50 $0.02SR 13  San Jose Boulevard  Duval 2086 Julington Creek Road Plummers Cove Road Bike Lane $0.07 $0.00SR 13  San Jose Boulevard  Duval 2085 Old St. Augustine Road SR 152  Baymeadows Road  Bike Lane $0.22 $0.01SR 13  San Jose Boulevard  Duval 2084 SR 152  Baymeadows Road  Hendricks Avenue Bike Lane $1.07 $0.04SR 13  San Jose Boulevard  Duval 2087 Loretto Road SR 152  Baymeadows Road  Accommodate Pedestrians and Bicyclist $3.18 $0.04SR 13  San Jose Boulevard  Duval 2083 Racetrack Road Downtown (Southbank) Bi‐directional 12 ft. Shared Use Path $3.10 $0.12SR 134  103rd Street  Duval 2011 Old Middleburg Road Old Middleburg Road North Bike Lane $0.19 $0.01SR 21  Blanding Boulevard   Duval 2024 Blackburn Road Appleton Avenue Bike Lane $0.09 $0.00SR 21  Blanding Boulevard   Duval 2025 Harlow Boulevard Wilson Boulevard  Bike Lane $0.15 $0.01SR 211  Riverside Avenue  Duval 2079 St. Johns Avenue Forest Street Bike Lane $0.36 $0.01SR 211  St. Johns Avenue  Duval 2098 Woodmere Street Talbot Avenue Bike Lane $0.22 $0.01SR 228  Normandy Boulevard  Duval 2072 SR 103  Lane Avenue  SR 111  Cassat Avenue  Bike Lane $0.30 $0.01SR A1A Duval 2096 SR 202  J. T. Butler Boulevard  SR 10  Atlantic Boulevard  Bi‐directional 12 ft. Shared Use Path $1.09 $0.04SR A1A  Duval 2097 St. Johns River Ferry Duval/Nassau County Line Bi‐directional 12 ft. Shared Use Path $2.27 $0.09UNF East Duval 2100 Kernan Boulevard UNF West Bike Lane $0.20 $0.01

Page 8 of 13

Page 12: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

Path Forward 2040 Long Range Transportation Plan

Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost 

(millions)O&M Cost (millions)

UNF West Duval 2101 I‐295 UNF East Bike Lane $0.43 $0.02US 1  Philips Highway  Duval 2077 Southside Boulevard (SR 115) Southbank Riverwalk Rails‐W‐Trails $2.46 $0.11US 1  Philips Highway  Duval 2076 Racetrack Road Downtown (Southbank) Bi‐directional 12 ft. Shared Use Path $4.39 $0.17US 17  Main Street  Duval 2064 Trout River Bridge New Berlin Road Rails‐W‐Trails $0.98 $0.04US 17  Main Street  Duval 2063 Eastport Road Pecan Park Road Bi‐directional 12 ft. Shared Use Path $2.30 $0.09US 17  Roosevelt Boulevard  Duval 2082 Duval/Clay County Line Forest Street Rails‐W‐Trails $2.28 $0.10US 17  Roosevelt Boulevard  Duval 2081 I‐295 Edison Avenue  Bi‐directional 12 ft. Shared Use Path $2.28 $0.09US 17  Roosevelt Boulevard  Duval 2104 Duval/Clay County Line Forest Street Florida Greenway $4.13 $0.16US 90  Beach Boulevard  Duval 2022 at Hodges Boulevard   Accommodate Pedestrians and Bicyclist $0.00 $0.00US 90  Beach Boulevard  Duval 2021 San Pablo Boulevard Downtown (Southbank) Bi‐directional 12 ft. Shared Use Path $1.97 $0.08Water Street Duval 2105 Lee Street Pearl Street Bike Lane $0.10 $0.00Jacksonville Baldwin Corridor Duval / Nassau 2106 West of Baldwin Bulls Bay Highway Florida Greenway $1.40 $0.158th Street Nassau 2107 at Sadler Road   Accommodate Pedestrians and Bicyclist $0.00 $0.00Amelia Island Parkway  Nassau 2108 at Amelia Road   Accommodate Pedestrians and Bicyclist $0.01 $0.00Amelia Island Parkway Path Segment 1 Nassau 2109 Bailey Road 8th Street/ SR A1A Multi‐Use Trail $0.63 $0.01Amelia Island Parkway Path Segment 2 Nassau 2110 14th Street Bailey Road Multi‐Use Trail $0.63 $0.01Amelia Island Parkway Path Segment 3 Nassau 2111 Via Del Rey 14th Steet Multi‐Use Trail $0.63 $0.01Amelia Island Parkway Path Segment 4 Nassau 2112 SR A1A Fletcher Avenue / Amelia Island Trail Via Del Rey Multi‐Use Trail $0.63 $0.01Amelia Island Trial ‐ Central (1st Ave) Nassau 2113.1 Bill Melton Matanzas Way Trail $0.16 $0.01Amelia Island Trial ‐ South (Buccaneer Trail) Nassau 2113 Fletcher Avenue Amelia Island Pkwy Trail $0.29 $0.01Amelia Island Trial‐ North ( Friendly/Clinch) Nassau 2113.2 Bailey Road Atlantic Avenue Trail $0.96 $0.04American Beach Loop  Nassau 2114 American Beach Loop Julia Street Segment American Beach Bike Lane $0.11 $0.00American Beach Loop  Nassau 2116 American Beach Loop Ocean Avenue Segment American Beach Multi‐Use Path $0.36 $0.00American Beach Loop  Nassau 2115 American Beach Loop Burney Road Segment American Beach Multi‐Use Path $0.60 $0.01Crandall Parkway Corridor Nassau 2117 East Coast Greenway (US 17) SR A1A  East Coast Greenway Corridor  Florida Greenway $1.75 $0.07East Coast Greenway ‐ Nassau County Corridor Nassau 2118 Nassau/Duval County Line Fernandina Beach Florida Greenway $2.02 $0.11ENCPA DSAP 1‐ Central (Old Yulee Vicinity) Nassau 2120.1 East Nassau Community Planning Area East Nassau Community Planning Area Multi‐Use Path $4.03 $0.16ENCPA DSAP 1‐ North (Owens Rd Vicinity) Nassau 2120.2 East Nassau Community Planning Area East Nassau Community Planning Area Multi‐Use Path $0.78 $0.03ENCPA DSAP 1‐ South (Harper Chapel Vicinity) Nassau 2120 East Nassau Community Planning Area East Nassau Community Planning Area Multi‐Use Path $0.66 $0.03Highland Broom Street  Nassau 2121 Proposed Highland Broom Street Multi‐use Trail Proposed Highland Broom Street  Multi‐Use Path $0.36 $0.01Maxine Street  Nassau 2123 Maxine Street Path Maxine Street Path Multi‐Use Path $0.13 $0.01Ocklawaha Trail Nassau 2124 Via Del Rey / Bill Melton Road Sadler Road Multi‐Use Trail $0.94 $0.03Orange Avenue Nassau 2125 Orange Avenue Path Orange Avenue Path Multi‐Use Path $0.25 $0.01Simmons Connector Nassau 2126 Simmons/AIP Connector Simmons/AIP Connector Multi‐Use Trail $1.72 $0.02SR 200  SR A1A  Nassau 2127 at SR 200 Bridge   Accommodate Pedestrians and Bicyclist $0.71 $0.01US 17 Nassau 2129 Nassau/Duval County Line SR 200  SR A1A  Bi‐directional 12 ft. Shared Use Path $3.13 $0.12US 17 / SR A1A  East Coast Greenway  Nassau 2119 Fernandina Beach Georgia State Line Florida Greenway $30.08 $0.19US 301/ SR 200  Trans Nassau Trail Corridor  Nassau 2128 CR 119 US 17 Main Street /  Yulee  Florida Greenway $6.58 $0.26William Burgess Boulevard  Nassau 2130 SR 200  SR A1A  US 17 Multi‐Use Trail $0.79 $0.03CR 121/CR 119  Jacksonville Baldwin Rail Trail Northern Extension CorridNassau / Duval 2122 Beaver Street (US 90) US 301/SR 200  Trans Nassau Trail Corrid Florida Greenway $3.09 $0.12CR 216 Putnam 2131 SR 100 US 17 Multi‐Use Path $0.58 $0.02Cross Florida Greenway Corridor Putnam 2132 Existing Cross Florida Greenway Trail Palatka Florida Greenway $6.05 $0.08SR 100 Putnam 2133 Clay/Putnam County  Line Palatka Florida Greenway $9.43 $0.23SR 20 Putnam 2134 Hawthorne Palatka Florida Greenway $15.23 $0.24US 17 Putnam 2135 Putnam/Volusia County Line Palatka Florida Greenway $38.54 $0.25US 17 Crescent City (parallel facilities) Putnam 2136 Prospect Street CR 308 Multi‐Use Path $0.58 $0.02SR 207 Putnam / St. Joh 2137 Palatka St. Augustine Florida Greenway $10.48 $0.23County Road 214 Corridor St. Johns 2138 SR 13  San Jose Boulevard  SR 207  Florida Greenway $2.74 $0.11CR 13  Spuds Palmo Trail Corridor  St. Johns 2149 Spuds (SR 207) SR 13  San Jose Boulevard  Florida Greenway $5.10 $0.20CR210 St. Johns 2139 at SR A1A    Accommodate Pedestrians and Bicyclist $0.02 $0.00Deep Creek to ECG Corridor St. Johns 2140 SR 207  SR A1A Florida Greenway $3.21 $0.13Downtown and Uptown St. Augustine St. Johns 2141 at US 1, Park Avenue, River, South Street, Riberia Str   Accommodate Pedestrians and Bicyclist $1.13 $0.01East Coast Greenway ‐ St. Johns County Corridor St. Johns 2142 St. Johns/Flagler County Line St. Johns/Duval County Line Florida Greenway $27.88 $0.41Nocatee Corridor St. Johns 2143 San Jose Boulevard (SR 13) SR A1A Florida Greenway $5.10 $0.20Race Track Road St. Johns 2147 San Jose Boulevard (SR 13) US 1  Philips Highway  Bi‐directional 12 ft. Shared Use Path $2.14 $0.08Racetrack Corridor St. Johns 2148 San Jose Boulevard (SR 13) Nocatee Corridor Florida Greenway $2.14 $0.09SR 13  San Jose Boulevard  St. Johns 2150 Roberts Road Julington Creek  Bi‐directional 12 ft. Shared Use Path $0.65 $0.03SR 13  William Bartram Trail Corridor  St. Johns 2155 CR 13 St. Johns/Duval County Line Florida Greenway $3.76 $0.15SR 16 St. Johns 2151 I‐95 Collins Avenue Bi‐directional 12 ft. Shared Use Path $0.77 $0.03SR A1A  St. Johns 2152 at SR 312    Accommodate Pedestrians and Bicyclist $0.03 $0.00

Page 9 of 13

Page 13: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

Path Forward 2040 Long Range Transportation Plan

Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost 

(millions)O&M Cost (millions)

St. Augustine Bike Plan St. Johns 2153 Areawide Areawide Bicycle accommodations $1.17 $0.00US 1  Dixie Highway  St. Johns 2146 at SR 312    Accommodate Pedestrians and Bicyclist $0.00 $0.00US 1  Dixie Highway  St. Johns 2145 Putnam/Flagler County Line SR 207 Bi‐directional 12 ft. Shared Use Path $3.77 $0.15US 1  Dixie Highway / Ponce De Leon Boulevard  St. Johns 2144 San Marco Avenue (US 1 B) (St. Augustine) Racetrack Road Bi‐directional 12 ft. Shared Use Path $3.88 $0.15US 1  St. Augustine to Nocatee Corridor  St. Johns 2154 St. Augustine Nocatee Corridor Florida Greenway $3.79 $0.15

CSX Transportation Clay 2200 at Wells Road Grade Separation $56.74 $0.10CSX Transportation Clay 2201 at SR 224 Kingsley Avenue Grade Separation $56.74 $0.10CSX Transportation Duval 2202 at SR 104  Busch Drive Grade Separation $90.78 $0.10CSX Transportation Nassau 2203 at SR A1A (SR 200) / Yulee Grade Separation $68.08 $0.10CSX Transportation Duval 2204 Beaver Street Interlocking Capacity Upgrade $6.00 $0.10CSX Transportation Duval 2205 North Rail Corridors Phase 1 Multi Modal Corridor $40.00 $0.10CSX Transportation Duval 2206 Westlake Cecil Commerce Connector Multi Modal Corridor $30.00 $0.10Florida East Coast Railway Duval 2207 at Bowden Intermodal Capacity Upgrade $14.36 $0.10Florida East Coast Railway Duval 2208 at Jacksonville Bridge Bridge $8.84 $0.10Jacksonville International Airport Duval 2209 Construction of Runway 7R/25L Construct Runway $53.50 $0.10Jacksonville International Airport Duval 2210 Air Cargo Ramp Improvements Expand Apron $2.82 $0.10Jacksonville International Airport Duval 2211 Air Cargo Surface Storage Expand Apron $0.54 $0.10Jacksonville International Airport Duval 2212 Design & Construct By‐Pass Taxiways Construct Taxiway $8.65 $0.10Jacksonville International Airport Duval 2213 Intermodal Terminal Facility Development Terminal Development $99.42 $0.10Norfolk Southern Duval 2214 at Norfolk Southern Railway (Near Simpson Yard) Grade Separation $14.75 $0.10Jacksonville Port Authority Duval 2215 Blount Island / Dames Point Marine Terminals Rail Internal Rail $32.42 $0.10Jacksonville Port Authority Duval 2216 Blount Island Marine Terminal Berth Upgrades Docks $32.42 $0.10Jacksonville Port Authority Duval 2217 Blount Island Marine Terminal Facility Upgrades Intermodal Transfer Improvement $97.26 $0.10Jacksonville Port Authority Duval 2218 Dames Point Marine Terminal Berth Upgrades Docks $54.04 $0.10Jacksonville Port Authority Duval 2219 Dames Point Marine Terminal Facility Upgrades Intermodal Transfer Improvement $97.26 $0.10Jacksonville Port Authority Duval 2220 New Cranes for Talleyrand and Blount Island Marine Terminals Intermodal Transfer Improvement $86.45 $0.10Jacksonville Port Authority Duval 2221 Talleyrand Marine Terminal Berth Upgrades Docks $43.23 $0.10Jacksonville Port Authority Duval 2222 Talleyrand Marine Terminal Facility Upgrades Intermodal Transfer Improvement $32.42 $0.10Jacksonville Port Authority Duval 2223 Talleyrand Marine Terminal Rail Internal Rail $21.62 $0.10Jacksonville Port Authority Duval 2224 Blount Island Marine Terminal Facility Upgrades Intermodal Transfer Improvement $81.05 $0.10Jacksonville Port Authority Duval 2225 Dames Point Marine Terminal Facility Upgrades Intermodal Transfer Improvement $37.82 $0.10Jacksonville Port Authority Duval 2226 New Cranes for Talleyrand and Blount Island Marine Terminals Intermodal Transfer Improvement $43.23 $0.10Jacksonville Port Authority Duval 2227 Talleyrand Marine Terminal Facility Upgrades Intermodal Transfer Improvement $21.62 $0.10Jacksonville Port Authority Duval 2228 Blount Island / Dames Point Terminals ‐ Rail and Bridge Internal Rail $270.18 $0.10Jacksonville Port Authority Duval 2229 Blount Island Marine Terminal Berth Upgrades Docks $43.23 $0.10Jacksonville Port Authority Duval 2230 Blount Island Marine Terminal Facility Upgrades Intermodal Transfer Improvement $81.50 $0.10Jacksonville Port Authority Duval 2231 Dames Point Marine Terminal Berth Upgrades Docks $32.42 $0.10Jacksonville Port Authority Duval 2232 Dames Point Marine Terminal Facility Upgrades Intermodal Transfer Improvement $32.42 $0.10Jacksonville Port Authority Duval 2233 Harbor Deepening Dredging Harbor $648.42 $0.10Jacksonville Port Authority Duval 2234 New Cranes for Talleyrand and Blount Island Marine Terminals Intermodal Transfer Improvement $32.42 $0.10Jacksonville Port Authority Duval 2235 Talleyrand Marine Terminal Berth Upgrades Docks $27.02 $0.10Jacksonville Port Authority Duval 2236 Talleyrand Marine Terminal Facility Upgrades Intermodal Transfer Improvement $21.61 $0.10Jacksonville Port Authority Duval 2237 Talleyrand Marine Terminal Rail Internal Rail $10.81 $0.10CSX Transportation Duval/Baker 2238 MacClenny  to Jacksonville Upgrade to Accommodate Freight and Passenger Service* $85.10CSX Transportation Duval/Clay 2239 Green Cove Springs to Jacksonville Upgrade to Accommodate Freight and Passenger Service $294.00CSX Transportation Duval/Nassau 2240 Jacksonville to Yulee Upgrade to Accommodate Freight and Passenger Service $271.69Florida East Coast Railway Duval/St. Johns 2241 St. Augustine to Jacksonville Upgrade to Accommodate Freight and Passenger Service $0.00CSX Transportation Duval 2242 at US 301 (SR 200) / Baldwin Grade Separation $53.33 $0.10CSX Transportation Nassau 2243 at US 301  / Crawford Diamond Grade Separation $32.42 $0.10Port of Fernandina Nassau 2244 Berth Improvements Docks $0.86 $0.10Port of Fernandina Nassau 2245 Cruise / Cargo Berth Docks $10.81 $0.10Port of Fernandina Nassau 2246 Rail Track Improvements Internal Rail $0.65 $0.10Port of Fernandina Nassau 2247 at Fernandina Port Access Improvements $5.00 $0.10City of Palatka Putnam 2248 SR 100 CR 309D Runway expansion $15.00 $0.10County Putnam 2249 Barge Port Operational and Capital Improvements $15.00 $0.10CSX Transportation Putnam 2250 at  SR 15 Reid Street Grade Separation $49.75 $0.10City of Saint Augustine St. Johns 2251 Historic Commercial Areas Mobility & Distribution Improvements $10.00 $0.10Florida East Coast Railway Statewide 2252 Amtrak Service Miami to Jacksonville New Passenger Service $162.16 $0.10

Multimodal Freight Projects

Page 10 of 13

Page 14: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

Path Forward 2040 Long Range Transportation Plan

Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost 

(millions)O&M Cost (millions)

Florida East Coast Railway Statewide 2253 Miami to Jacksonville Upgrade Bolt and Clip System Track Upgrade $21.67 $0.10Intercity Passenger Rail Statewide 2254 New Orleans to Jacksonville New Passenger Service TBD $0.10Intercity Passenger Rail Statewide 2255 Jacksonville to Savannah New Passenger Service TBD $0.10Intercity Passenger Rail Statewide 2256 Orlando to Jacksonville New Passenger Service TBD $0.10Norfolk Southern Duval 2257 Soutel Drive to Norfolk Southern Intermodal Yard New Connector $14.65 $0.10CSX Transportation Duval 2258 North Rail Corridors Phase 2 Multi Modal Corridor $5.00 $0.10Florida East Coast Railway Duval 2259 at Sunbeam Road  Grade Separation $52.82Downtown Transportation Center* Duval 2355 Downtown Facility Transportation Center $60.00Jacksonville Port Authority Duval 1006 Spoil Island Connector Bridge New 2 Lane Bridge $80.21Florida East Coast Railway Duval 2260 at Shad Road Grade Separation $40.00* Project costs are identified in the Transit Capacity Needs table.

SR 21  Blanding Boulevard   Clay 209 at Arora Boulevard    Safety Projects ‐ Intersections $1.50 $0.05

SR 21  Blanding Boulevard   Clay 212 at SR 16   Safety Projects ‐ Intersections $1.50 $0.05

SR 21  Blanding Boulevard   Clay 215 at Youngerman Circle   Safety Projects ‐ Intersections $1.50 $0.05

SR 21  Blanding Boulevard   Clay 219 at Argyle Forest Boulevard    Safety Projects ‐ Intersections $1.50 $0.05

SR 21  Blanding Boulevard   Clay 221 at Wells Road    Safety Projects ‐ Intersections $1.50 $0.05

SR 21  Blanding Boulevard   Clay 231 at CR 215   Safety Projects ‐ Intersections $1.50 $0.05

SR 21  Blanding Boulevard   Clay 605 Everett Avenue  Old Jennings Road  Safety Projects ‐ Corridors $7.05 $0.46

SR 21  Blanding Boulevard   Clay 606 Old Jennings Road  Argyle Forest Boulevard  Safety Projects ‐ Corridors $11.10 $0.73

SR 21  Blanding Boulevard  Clay 241 SR 16 CR 218 Safety Projects ‐ Corridors $11.85 $0.78

CR 215 Clay 202 SR 16 SR 21  Blanding Boulevard   Safety Projects ‐ Corridors $9.30 $0.61

CR 218 Clay 203 N Mimosa Avenue  CR 739  Henley Road   Safety Projects ‐ Corridors $9.90 $0.65

CR 220   Doctors Inlet Road  Clay 608 SR 21  Blanding Boulevard   CR 224  College Drive   Safety Projects ‐ Corridors $8.25 $0.54

CR 220A  Long Bay Road   Clay 204 CR 220  Doctors Inlet Road  Old Jennings Road  Safety Projects ‐ Corridors $2.85 $0.19

CR 209   Russell Road   Clay 201 Old Ferry Road  CR 220  Doctors Inlet Road   Safety Projects ‐ Corridors $2.85 $0.19

US 17 SR 15   Clay 327 CR 315 Kingsley Avenue  Arterial Management System $1.37 $0.08

SR 134  103rd Street  Duval 207 at New World Avenue    Safety Projects ‐ Intersections $1.50 $0.05

SR 134  103rd Street  Duval 218 at Firestone Road , I‐295 Interchanges   Safety Projects ‐ Intersections $1.50 $0.05

SR 134  103rd Street  Duval 222 at Harlow Boulevard    Safety Projects ‐ Intersections $1.50 $0.05

SR 134  103rd Street  Duval 225 at SR 21  Blanding Boulevard     Safety Projects ‐ Intersections $1.50 $0.05

SR 134  103rd Street  Duval 226 at Shindler Drive , Old Middleburg Road    Safety Projects ‐ Intersections $1.50 $0.05

SR 134  103rd Street  Duval 311 SR 228  Normandy Boulevard   I‐295 Arterial Management System $0.77 $0.04

SR 134  103rd Street  Duval 603 SR 228  Normandy Boulevard   Wesconnett Boulevard  Safety Projects ‐ Corridors $13.20 $0.87

SR 13  Acosta Bridge  Duval 310 I‐95  Broad Street Freeway Management System $0.28 $0.01

SR 115  Arlington Expressway   Duval 301 US 17 / US 17 SR 228  State Street  SR 10  Atlantic Boulevard   Freeway Management System $1.77 $0.06

SR 10  Atlantic Boulevard   Duval 650 Monument Road  Intracoastal Waterway Arterial Management System $1.04 $0.06

SR 10  Atlantic Boulevard   Duval 651 Hart Bridge Expressway  SR 109  University Boulevard  Arterial Management System $0.23 $0.01

US 90  Beach Boulevard   Duval 223 at Forest Boulevard    Safety Projects ‐ Intersections $1.50 $0.05

US 90  Beach Boulevard   Duval 652 Parental Home Road  San Pablo Road  Arterial Management System $1.16 $0.07

SR 21  Blanding Boulevard   Duval 230 at Collins Road    Safety Projects ‐ Intersections $1.50 $0.05

SR 21  Blanding Boulevard   Duval 232 at I‐295 NB Off Ramp   Safety Projects ‐ Intersections $1.50 $0.05

SR 21  Blanding Boulevard  Duval 242 Argyle Forest Boulevard  US 17  Roosevelt Boulevard  Safety Projects ‐ Corridors $9.00 $0.59

SR 21  Blanding Boulevard  Duval 317 Collins Road  US 17  Roosevelt Boulevard  Arterial Management System $1.07 $0.06

SR 109  Cesery Boulevard  Duval 653 SR 109  University Boulevard  SR 115  Arlington Expressway   Arterial Management System $0.27 $0.02

Collins Road  Duval 200 Shindler Drive  Rampart Road  Safety Projects ‐ Corridors $3.00 $0.20

SR 126  Emerson Street  Duval 304 I‐95 Bedford Road  Traffic Operations Improvements $2.42 $0.08

Firestone Road  Duval 205 Morse Avenue  SR 208  Wilson Boulevard   Safety Projects ‐ Corridors $4.65 $0.31

SR 23  First Coast Expressway  Duval 213 at US 90 , I‐10 Beaver Street    Safety Projects ‐ Intersections $1.50 $0.05

SR 116  Fort Caroline Road  Duval 654 Merrill Road  McCormick Road  Arterial Management System $0.15 $0.01

Harlow Boulevard  Duval 206 SR 134  103rd Street  SR 21  Blanding Boulevard   Safety Projects ‐ Corridors $2.70 $0.18

Alt US 1  Hart Bridge Expressway   Duval 300 Monroe Street US 90  Beach Boulevard   Freeway Management System $0.91 $0.03

I‐295 Duval 607 Old St Augustine Road  SR 228  Normandy Boulevard   Safety Projects ‐ Corridors $33.00 $2.16

Safety and Operations Improvements

Page 11 of 13

Page 15: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

Path Forward 2040 Long Range Transportation Plan

Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost 

(millions)O&M Cost (millions)

I‐295 Duval 610 SR 228  Normandy Boulevard   SR 115  Lem Turner Road   Safety Projects ‐ Corridors $18.30 $1.20

SR 202  J. T. Butler Boulevard  Duval 315 US 1/SR 5  Philips Highway  SR A1A Freeway Management System $65.06 $2.16

SR 202  J. T. Butler Boulevard  Duval 712 SR 115  Southside Boulevard  Hodges Boulevard  Safety Projects ‐ Corridors $7.65 $0.50

Jammes Road  Duval 233 Morse Avenue  San Juan Avenue   Safety Projects ‐ Corridors $5.85 $0.38

SR 115   Lem Turner Road  Duval 305 I‐95  I‐295 Arterial Management System $1.20 $0.07

US 17  Main Street  Duval 326 Bay Street I‐295 Arterial Management System $1.29 $0.07

US 1  Main Street Bridge  Duval 324 I‐95 Bay Street Arterial Management System $0.28 $0.01

SR 106  Merrill Road  Duval 663 SR 109  University Boulevard  SR 113  Southside Connector  Arterial Management System $0.37 $0.02

US 1  MLK Parkway   Duval 325 SR 115  Arlington Expressway   I‐95 Freeway Management System $18.69 $0.62

Monument Road  Duval 306 SR 10  Atlantic Boulevard   Fort Caroline Road  Arterial Management System $0.82 $0.05

Morse Avenue  Duval 234 Ricker Road  Jammes Road  Safety Projects ‐ Corridors $2.25 $0.15

Mt. Pleasant Road  Duval 657 McCormick Road  Girvin Road  Arterial Management System $0.14 $0.01

US 1/SR 15  New Kings Road   Duval 224 at Moncrief Road    Safety Projects ‐ Intersections $1.50 $0.05

US 1/SR 15  New Kings Road   Duval 307 I‐95  I‐295 Arterial Management System $2.07 $0.12

SR 228  Normandy Boulevard   Duval 208 at Fouraker Road    Safety Projects ‐ Intersections $1.50 $0.05

SR 228  Normandy Boulevard   Duval 220 at Blair Road  South   Safety Projects ‐ Intersections $1.50 $0.05

SR 228  Normandy Boulevard   Duval 318 SR 134  103rd Street  I‐295 Arterial Management System $0.79 $0.04

SR 228  Normandy Boulevard   Duval 609 I‐295 SR 111  Cassat Avenue   Safety Projects ‐ Corridors $3.90 $0.26

SR 228  Normandy Boulevard   Duval 611 SR 23  First Coast Expressway  I‐295 Safety Projects ‐ Corridors $12.90 $0.85

Old Middleburg Road  Duval 235 Argyle Forest Boulevard  SR 134  103rd Street  Safety Projects ‐ Corridors $7.20 $0.47

Old Middleburg Road  Duval 236 SR 134  103rd Street  Lenox Avenue Safety Projects ‐ Corridors $6.15 $0.40

Old St. Augustine Road  Duval 658 I‐95 US 1/ SR 5  Philips Highway   Arterial Management System $0.03 $0.00

US 1/SR 5  Philips Highway   Duval 229 at Bowden Road    Safety Projects ‐ Intersections $1.50 $0.05

Rampart Road  Duval 237 Argyle Forest Boulevard  Park City Drive  Safety Projects ‐ Corridors $1.50 $0.10

Ricker Road  Duval 238 Morse Avenue  SR 134  103rd Street  Safety Projects ‐ Corridors $1.50 $0.10

Ricker Road  Duval 239 SR 134  103rd Street  Old Middleburg Road  Safety Projects ‐ Corridors $2.10 $0.14

Shindler Drive  Duval 240 Collins Road  SR 134  103rd Street  Safety Projects ‐ Corridors $4.50 $0.30

US 17 / US 17 SR 228  State Street  Duval 322 I‐95  Liberty Street Arterial Management System $0.16 $0.01

SR 134  Timuquana Road  Duval 602 Wesconnett Boulevard  US 17  Roosevelt Boulevard   Safety Projects ‐ Corridors $3.90 $0.26

US 17 / US 17 SR 228  Union Street   Duval 323 I‐95 Liberty Street Arterial Management System $0.16 $0.01

SR 109  University Boulevard  Duval 659 St. Augustine Road  US 90  Beach Boulevard   Arterial Management System $0.28 $0.01

SR 109  University Boulevard  Duval 660 Arlington Road  Merrill Road  Arterial Management System $0.17 $0.01

SR 109  University Boulevard  Duval 661 SR 10  Atlantic Boulevard   SR 109  Cesery Boulevard  Arterial Management System $0.04 $0.00

US 301  SR 200   Duval 313 SR 228  Normandy Boulevard   US 90  Beaver Street  Rural ITS $0.36 $0.01

Wesconnett Boulevard  Duval 600 SR 21  Blanding Boulevard   SR 21  Blanding Boulevard   Safety Projects ‐ Corridors $2.85 $0.19

SR 208  Wilson Boulevard   Duval 601 Fouraker Road  SR 103  Lane Avenue   Safety Projects ‐ Corridors $2.25 $0.15

SR 116  Wonderwood Connector  Duval 655 Fort Caroline Road East Mt. Pleasant Road  Arterial Management System $0.32 $0.02

SR 116  Wonderwood Connector  Duval 656 SR 113  Southside Connector  Fort Caroline Road East Arterial Management System $0.07 $0.00

SR 116  Wonderwood Connector  Duval 662 Mt. Pleasant Road  SR 101  Mayport Road  Arterial Management System $0.40 $0.02

US 301  SR 200   Duval / Nassau314 US 90  Beaver Street  Mickler Street (Callahan) Rural ITS $0.97 $0.04

SR 9B Duval / St. Joh319 CR 2209 I‐295 Freeway Management System $1.13 $0.03

SR 200  SR A1A   Nassau 320 I‐95 Fernandina Beach Arterial Management System $0.82 $0.04

SR 200  SR A1A   Nassau 604 I‐95 Chester Road  Safety Projects ‐ Corridors $19.80 $1.30

US 1/SR 5  Dixie Highway   St. John's 210 at SR 312   Safety Projects ‐ Intersections $1.50 $0.05

US 1/SR 5  Dixie Highway   St. John's 214 at SR 206   Safety Projects ‐ Intersections $1.50 $0.05

US 1/SR 5  Dixie Highway/Ponce De Leon Boulevard   St. John's 328 SR 312 SR 16 Arterial Management System $0.34 $0.02

International Golf Parkway  St. John's 216 at SR 16   Safety Projects ‐ Intersections $1.50 $0.05

International Golf Parkway  St. John's 217 at US 1/SR 5  Dixie Highway    Safety Projects ‐ Intersections $1.50 $0.05

CR 214  King Street/Anastasia Boulevard  St. John's 303 I‐95  SR A1A Arterial Management System $0.69 $0.04

CR 210  Palm Valley Road  St. John's 302 SR 13 SR A1A Rural ITS $1.65 $0.08

US 1/SR 5  Ponce De Leon Boulevard  St. John's 329 SR 5A King Street  SR 16 Access Management Plan $0.19 $0.01

Race Track Road  St. John's 308 SR 13   San Jose Boulevard  US 1 Arterial Management System $0.83 $0.04

Page 12 of 13

Page 16: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

Path Forward 2040 Long Range Transportation Plan

Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost 

(millions)O&M Cost (millions)

SR 13 St. John's 309 Shands Bridge Julington Creek Road Arterial Management System $0.87 $0.04

SR 16 St. John's 312 CR 13  US 1 Arterial Management System $1.26 $0.07

SR 16/SR 13 St. John's 211 at CR 13   Safety Projects ‐ Intersections $1.50 $0.05

SR 207/SR 312 St. John's 316 I‐95  SR A1A Rural ITS $0.92 $0.05

SR A1A St. John's 321 SR 206 CR 214 Rural ITS $1.20 $0.06

US 1, A1A & SR 5A  St. John's 330     Transportation Management Plan $37.50 $1.23

Page 13 of 13

Page 17: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

1  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Road Capacity Projects 

Abaco Island Drive Extension  Nassau  988  Abaco Island Drive  Zion Court  New 2 Lane Road  Local government coordination 

The project's purpose is to construct a new two‐lane road called Abaco Island Drive Extension from Abaco Island Drive to Zion Court to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Alta Drive  Duval  3  SR 105 Heckscher Drive  I‐295  Widen to 4 Lanes  2035 Needs Plan 

The project's purpose is to widen Alta Drive to four lanes from SR 105 Heckscher Drive to I‐295 to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Alta Drive / Yellow Bluff Road  Duval  2  I‐295  New Berlin Road (north )  Widen to 5 Lanes  2035 Needs Plan 

The project's purpose is to widen to Alta Drive / Yellow Bluff Road to five lanes from I‐295 to New Berlin Road (north) to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Alta Drive Realignment  Duval  1  SR 105 Zoo Parkway  North of New Berlin Road (south)  New 4 Lane Road  2035 Needs Plan 

The project's purpose is to construct a new four‐lane road and realign Alta Drive from SR 105 Zoo Parkway to North of New Berlin Road (south) to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Amelia Island Parkway  Nassau  704  South 14th Street  CR 105A Buccaneer Trail  Widen to 4 Lanes*  Local government coordination 

The project's purpose is to widen Amelia Island Parkway to four lanes from South 14th Street to CR 105A Buccaneer Trail to address congestion needs and improve mobility. This project was also identified as candidate for context sensitive solutions. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Page 18: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

2  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Argyle Forest Boulevard  Duval  936  SR 23 First Coast Expressway  Old Middleburg Road  Widen to 6 Lanes  Argyle Traffic 

Circulation Study 

The project's purpose is to widen Argyle Forest Boulevard to six lanes from SR 23 First Coast Expressway to Old Middleburg Road to address congestion needs and improve mobility. 

The project need was established during a corridor planning study performed by the North Florida TPO to address congestion, mobility and safety needs. 

Arrigo‐Parliament Reconnection  Nassau  980  Arrigo Boulevard  Parliament Drive  New 2 Lane Road  Local government 

coordination 

The project's purpose is to construct a new two lane road called Arrigo‐Parliament Reconnection from Arrigo Boulevard to Parliament Drive to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Barnwell‐0' Neil Scott Connector  Nassau  1001  Barnwell Road  O'Neil Scott Road  New 2 Lane Road  Local government 

coordination 

The project's purpose is to construct a new two‐lane road called Barnwell‐0' Neil Scott Connector from Barnwell Road to O'Neil Scott Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Baxley Road  Clay  900  CR 220 Doctors Inlet Road  SR 21 Blanding Boulevard  Widen to 4 Lanes Other Local Government Priority 

The project's purpose is to widen Baxley Road to four lanes CR 220 Doctors Inlet Road to SR 21 Blanding Boulevard to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Blount Island Boulevard Extension  Duval  1006  Spoil Island  Jacksonville Port Authority  New 2 Lane Bridge 

Other Local Government Priority 

The project's purpose is to New two Lane Bridge along Blount Island Boulevard Extension from Spoil Island to Jacksonville Port Authority to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Page 19: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

3  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Braddock Parkway  Duval  939  SR 115 Lem Turner Road  Pecan Park Road  New 2 Lane Road  Local government coordination 

The project's purpose is to construct a new tow lane road called Braddock Parkway from SR 115 Lem Turner Road to Pecan Park Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Brady Point‐Clements Connector  Nassau  1002  Brady Point Road  Clements Road  New 2 Lane Road  Local government 

coordination 

The project's purpose is to construct a new two‐lane road called Brady Point‐Clements Connector from Brady Point Road to Clements Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Brinkhoff Road  St Johns  801  SR 207  Wildwood Drive  New 2 Lane Road Other Local Government Priority 

The project's purpose is to construct a new two‐lane road called Brinkhoff Road from SR 207 to Wildwood Drive to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Buffalo Road  Putnam  503  Buffalo Road west  Buffalo east  New 2 Lane Bridge Other Local Government Priority 

The project's purpose is to construct   new two‐lane bridge along Buffalo Road from Buffalo Road West to Buffalo East to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Cahoon Road  Duval  1016  Lenox Avenue  US 90 Beaver Street  Reconstruct 2 Lanes  Local Government CIP 

The project's purpose is to reconstruct two lanes of Cahoon Road from Lenox Avenue to US 90 Beaver Street to address congestion needs and improve mobility and provide bicycle and pedestrian accommodations. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

Page 20: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

4  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Cardinal Street North Extension  Nassau  976  Cardinal Avenue  SR 200 SR AIA  Yulee Backage 

Roads  New 2 Lane Road  Local government coordination 

The project's purpose is to construct a new two‐lane road called Cardinal Street North Extension from Cardinal Avenue to SR 200 SR AIA Yulee Backage Roads to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Cardinal Street South Extension  Nassau  975  Spring Meadow Avenue  William Burgess Boulevard  New 2 Lane Road  Local government 

coordination 

The project's purpose is to construct a new two‐lane road called Cardinal Street South Extension from Spring Meadow Avenue to William Burgess Boulevard to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Cecil Field Connector  Duval  972  Commerce Center  SR 23 First Coast Expressway  New 2 Lane Road  Local Government CIP 

The project's purpose is to construct a new two‐lane road called Cecil Field Connector from Commerce Center to SR 23 First Coast Expressway to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

Chaffee Road  Duval  971  SR 228 Normandy  Boulevard  Crystal Springs Road  Widen to 5 Lanes  Local 

Government CIP 

The project's purpose is to widen Chaffee Road to five lanes from SR 228 Normandy Boulevard to Crystal Springs Road to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

Cheswick Oak Avenue Extension  Clay  13  Oakleaf Plantation 

Parkway  Savannah Glen Boulevard  New 4 Lane Road  2035 Cost Feasible Plan 

The project's purpose is to construct a new four‐lane road called Cheswick Oak Avenue Extension from Oakleaf Plantation Parkway to Savannah Glen Boulevard to address congestion needs and improve mobility. 

The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process. 

Page 21: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

5  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Christian Way Extension  Nassau  995  Christian Way  Hampton Club Way  New 2 Lane Road  Local government coordination 

The project's purpose is to construct a new two‐lane road called Christian Way Extension from Christian Way to Hampton Club Way to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Clark Road Extension  Duval  1020  Broward Road  Clark Road  New 3 Lane Road  Local Government CIP 

The project's purposes to construct a new three‐lane road called Clark Road Extension from Broward Road to Clark Road to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

College Drive  Clay  902  CR 220 Doctors Inlet Road  SR 21 Blanding Boulevard  Widen to 6 Lanes  2035 Needs Plan 

The project's purpose is to widen College Drive to six lanes from CR 220 Doctors Inlet Road to SR 21 Blanding Boulevard to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

College Drive Extension  Clay  14  SR 21 Blanding Boulevard  Challenger Drive (Branan Field Road )  New 4 Lane Road  2035 Cost 

Feasible Plan 

The project's purpose is to construct a new four‐lane road called College Drive Extension from SR 21 Blanding Boulevard to Challenger Drive (Branan Field Road) to address congestion needs and improve mobility. 

The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process. 

Collins Road  Duval  930  Shindler Drive  Rampart Road  Widen to 4 Lanes  Local Government CIP 

The project's purpose is to widen Collins Road to four lanes from Shindler Drive to Rampart Road to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

Page 22: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

6  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Collins Road  Duval  932  Old Middleburg Road S  Shindler Drive  Widen to 4 Lanes  Local Government CIP 

The project's purpose is to widen Collins Road to four lanes from Old Middleburg Road S to Shindler Drive to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

Collins Road  Duval  15  SR 21 Blanding Boulevard  Pine Verde  Widen to 4 Lanes  2035 Needs Plan 

The project's purpose is to widen Collins Road to four lanes from SR 21 Blanding Boulevard to Pine Verde to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Collins Road  Duval  16  at US 17 Roosevelt Boulevard     New Interchange  2035 Needs Plan 

The project's purpose is to construct a new interchange along Collins Road at US 17 Roosevelt Boulevard to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Collins Road Realignment  Duval  16B  Pine Verde  US 17 Roosevelt Boulevard  New 4 Lane Road, Two Overpass and New Interchange 

Local government coordination and the project was part of the Better Jacksonville Plan 

The project's purpose is to construct a new four‐lane road, two overpasses and a new interchange along the Collins Road Realignment from Pine Verde to US 17 Roosevelt Boulevard to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Comfort Road  Putnam  505  Port Road  US 17  Widen to 4 Lanes Other Local Government Priority 

The project's purpose is to widen Comfort Road to four lanes from Port Road to US 17 to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Page 23: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

7  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Commodore Point Drive Extension  Nassau  996  Commodore Point Drive  Blackrock Road  New 2 Lane Road  Local government 

coordination 

The project's purpose is to construct a new two‐lane road called Commodore Point Drive Extension from Commodore Point Drive to Blackrock Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Concourse Loop Road  Nassau  501  License Road  Amelia Concourse  New 2 Lane Road Other Local Government Priority 

The project's purpose is to construct a new two‐lane road called Concourse Loop Road from License Road to Amelia Concourse to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Connector Road  Putnam  502  US 17  Distribution Center  New 2 Lane Road  SIS CFP 

The project's purpose is to construct a new two‐lane road called Connector Road from US 17 to Distribution Center to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

CR 105A Buccaneer Trail  Nassau  705  South Fletcher Avenue  Canopy Drive  Turn Lane Improvements*  Local government coordination 

The project's purpose is to construct turn lane improvements along CR 105A Buccaneer Trail from South Fletcher Avenue to Canopy Drive to address congestion needs and improve mobility.  This project was also identified as a candidate for context sensitive solutions. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

CR 16A  St Johns  803  SR 16 Connector  SR 13  Widen to 4 Lanes Other Local Government Priority 

The project's purpose is to widen CR 16A to four lanes from SR 16 Connector to SR 13 to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Page 24: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

8  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

CR 16A Extension  St Johns  802  CR 16A  Leo Maguire Parkway  New 2 Lane Road  Local government coordination 

The project's purpose is to construct a new two‐lane road called CR 16A Extension from CR 16A to Leo Maguire Parkway to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

CR 209 Russell Road  Clay  905  CR 739 Henley Road  US 17  Widen to 4 Lanes  2035 Needs Plan 

The project's purpose is to CR 209 Russell Road to four lanes from CR 739 Henley Road to US 17 to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

CR 209 South  Clay  906  Decoy Road  US 17  Reconstruct 2 Lanes Other Local Government Priority 

The project's purpose is to reconstruct two lanes along CR 209 South from Decoy Road to US 17 to address congestion needs and improve mobility and provide bicycle and pedestrian accommodations. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

CR 210  St Johns  805  I‐95  near US 1  Widen to 6 Lanes Other Local Government Priority 

The project's purpose is to widen CR 210 to six lanes from I‐95 to near US 1 to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

CR 210  St Johns  807  Greenbriar Road  Cimarrone Road  Widen to 4 Lanes  2035 Needs Plan 

The project's purpose is to widen CR 210 to four lanes from Greenbriar Road to Cimarrone Road to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Page 25: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

9  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

CR 210 West  St Johns  849  Longleaf Pine Parkway  Greenbriar Road  Widen to 4 Lanes Other Local Government Priority 

The project's purpose is to widen CR 210 West to four lanes from Longleaf Pine Parkway to Greenbriar Road to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

CR 214  St Johns  809  Holmes Boulevard  US 1  Widen to 3 Lanes* Other Local Government Priority 

The project's purpose is to widen CR 214 to three lanes from Holmes Boulevard to US 1 to address congestion needs and improve mobility.  This project was also identified as a candidate for context sensitive solutions in lieu of widening. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

CR 218  Clay  1026  US 301  Cosmos Avenue  Widen to 4 Lanes  Local Government CIP 

The project's purpose is to widen CR 218 to four lanes from US 301 to Cosmos Avenue to address congestion needs and improve mobility. 

The project need was established in the Local Government CIP and confirmed as part of the planning process. 

CR 218  Clay  1027  Cosmos Avenue  Pine Tree Lane  Widen to 4 Lanes  2035 Needs Plan 

The project's purpose is to widen to CR 218 to four lanes from Cosmos Avenue to Pine Tree Lane to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

CR 218  Clay  24  SR 21 Blanding Boulevard  CR 739 Henley Road  Widen to 4 Lanes  Local Government CIP 

The project's purpose is to widen CR 218 to dour lanes from SR 21 Blanding Boulevard to CR 739 Henley Road to address congestion needs and improve mobility. 

The project need was established in the Local Government CIP and confirmed as part of the planning process. 

Page 26: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

10  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

CR 218  Clay  909  SR 16  CR 739 Henley Road  Widen to 4 Lanes  2035 Needs Plan 

The project's purpose is to widen CR 218 to four lanes from SR 16 to CR 739 Henley Road to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

CR 218 Extension  Clay  25  CR 739 Henley Road  SR 23 First Coast Expressway  New 4 Lane Road  2035 Needs Plan 

The project's purpose is to construct a new four‐lane road called CR 218 Extension from CR 739 Henley Road to SR 23 First Coast Expressway to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

CR 218 Extension  Clay  26  SR 23 First Coast Expressway  CR 315  New 4 Lane Road  2035 Needs Plan 

The project's purpose is to construct a new four‐lane road called CR 218 Extension from SR 23 First Coast Expressway to CR 315 to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

CR 220 Doctors Inlet Road  Clay  33  SR 21 Blanding Boulevard  Knight Boxx Road  Widen to 4 Lanes  2035 Needs Plan 

The project's purpose is to widen CR 220 Doctors Inlet Road to four lanes from SR 21 Blanding Boulevard to Knight Boxx Road to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

CR 220 Doctors Inlet Road  Clay  34  College Drive  US 17  Widen to 6 Lanes  2035 Needs Plan 

The project's purpose is CR 220 Doctors Inlet Road from College Drive to US 17 to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Page 27: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

11  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

CR 2209  St Johns  810  SR 23 First Coast Expressway  CR 210  New 6 Lane Road  2035 Cost 

Feasible Plan 

The project's purpose is to construct a new six‐lane road called CR 2209 from SR 23 First Coast Expressway to CR 210 to address congestion needs and improve mobility. 

The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process. 

CR 2209  St Johns  811  SR 16 Connector  SR 23 First Coast Expressway  New 6 Lane Road  2035 Cost Feasible Plan 

The project's purpose is to construct a new six‐lane road called CR 2209 from SR 16 Connector to SR 23 First Coast Expressway to address congestion needs and improve mobility. 

The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process. 

CR 2209  St Johns  812  International Golf Parkway  SR 16 Connector  New 6 Lane Road  2035 Cost 

Feasible Plan 

The project's purpose is to construct a new six‐lane road called CR 2209 from International Golf Parkway to SR 16 Connector to address congestion needs and improve mobility. 

The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process. 

CR 2209  St Johns  813  CR 214  CR 208  New 4 Lane Road  2035 Needs Plan 

The project's purpose is to construct a new four‐lane road called CR 2209 from CR 214 to CR 208 to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

CR 2209  St Johns  814  SR 207/CR 305  CR 214  New 4 Lane Road  2035 Needs Plan 

The project's purpose is to construct a new four‐lane road called CR 2209 from SR 207/CR 305 to CR 214 to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Page 28: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

12  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

CR 2209  St Johns  815  SR 16  International Golf Parkway  New 4 Lane Road  2035 Needs Plan 

The project's purpose is to construct a new four‐lane road called CR 2209 from SR 16 to International Golf Parkway to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

CR 2209  St Johns  816  CR 208  SR 16  New 4 Lane Road  2035 Needs Plan 

The project's purpose is to construct a new four‐lane road called CR 2209 from CR 208 to SR 16 to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

CR 2209  St Johns  843  at CR 210     New Interchange  2035 Needs Plan 

The project's purpose is to construct a new interchange along CR 2209 at CR 210 to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

CR 305  St Johns  818  CR 204  SR 206  New 2 Lane Road  2035 Needs Plan 

The project's purpose is to construct a new two‐lane road called CR 305 from CR 20four to SR 206 to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

CR 305  St Johns  850  SR 206  SR 207  Widen to 4 Lanes Other Local Government Priority 

The project's purpose is to widen CR 305 to four lanes from SR 206 to SR 207 to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Page 29: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

13  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

CR 315  Clay  31  SR 16  CR 315B  Widen to 4 Lanes  2035 Needs Plan 

The project's purpose is to widen CR 315 to four lanes from SR 16 to CR 315B to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

CR 315  Clay  32  CR 315B  US 17  Widen to 4 Lanes  2035 Needs Plan 

The project's purpose is to widen CR 315 to four lanes from CR 315B to US 17 to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

CR 739B Sandridge Road  Clay  904  CR 739 Henley Road  CR 209 Russell Road  Widen to 4 Lanes Other Local Government Priority 

The project's purpose is to widen CR 739B Sandridge Road to four lanes from CR 739 Henley Road to CR 209 Russell Road to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Crosby Avenue Extension  Nassau  993  US 17 SR 5  Pinewood Drive  New 2 Lane Road  Local government coordination 

The project's purpose is to construct a new two‐lane road called Crosby Avenue Extension from US 17 SR 5 to Pinewood Drive to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Davis / 9B Parcel  Duval  1036  SR 9B  SR 152 Baymeadows Road  Widen to 4 Lanes  Local government coordination 

The project's purpose is to widen Davis / 9B Parcel Road to four lanes from SR 9B to SR 152 Baymeadows Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Page 30: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

14  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Decoy Road  Clay  907  US 17  CR 209 South  Reconstruct 2 Lanes Other Local Government Priority 

The project's purpose is to reconstruct two lanes of Decoy Road from US 17 to CR 209 South to address congestion needs and improve mobility and provide bicycle and pedestrian accommodations. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Dixie Highway / Pellicer Lane  St Johns  1025  SR 207  CR 214 West of King Street Reconstruct 2 Lanes and Widen to add Sidewalks and Bike Lanes 

2035 Needs Plan 

The project's purpose is to reconstruct two lanes and widen Dixie Highway / Pellicer Lane to add sidewalks and bike lanes from SR 207 to CR 214 West of King Street to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Dove Road Extension {west}  Nassau  991  Harper Chapel Road Extension  Mentoria Road  New 2 Lane Road  Local government 

coordination 

The project's purpose is to construct a new two‐lane road called Dove Road Extension {west} from Harper Chapel Road Extension to Mentoria Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Durbin Parkway  St Johns  819  SR 9B Extension  Nocatee Parkway  New 4 Lane Road Other Local Government Priority 

The project's purpose is to construct a new four‐lane road called Durbin Parkway from the SR 9B Extension to Nocatee Parkway to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Durbin Parkway  St Johns  844  at US 1 SR 5 Dixie Highway     Modify Interchange 

Other Local Government Priority 

The project's purpose is to modify the interchange of Durbin Parkway at US 1 SR 5 Dixie Highway to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Page 31: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

15  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Duval Station Road  Duval  942  US 17 SR 5 Main Street  Starratt Road  Widen to 4 Lanes  Local government coordination 

The project's purpose is to widen Duval Station Road to four lanes from US 17 SR 5 Main Street to Starratt Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

East Dove Road Extension  Nassau  974  Harper Chapel Road  William Burgess Boulevard  New 2 Lane Road  Local government coordination 

The project's purpose is to construct a new two‐lane road called east Dove Road Extension from Harper Chapel Road to William Burgess Boulevard to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

East Nassau Connector  Nassau  36  I‐95  Chester Road  New 4 Lane Road  Local Government CIP 

The project's purpose is to construct a new four‐lane road called East Nassau Connector from I‐95 to Chester Road to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

East Nassau Connector  Nassau  969  at I‐95     New Interchange  Local government coordination 

The project's purpose is to construct a new interchange along East Nassau Connector at I‐95 to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Eastport Road  Duval  37  SR 105 Heckscher Drive  Pulaski Road  Widen to 3 Lanes  Local Government CIP 

The project's purpose is to widen Eastport Road to three lanes from SR 105 Heckscher Drive to Pulaski Road to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

Page 32: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

16  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Flora Parke‐Wal‐Mart Connector  Nassau  986  Flora Parke Boulevard  Walmart Supercenter  New 2 Lane Road  Local government 

coordination 

The project's purpose is to construct a new two‐lane road called Flora Parke‐Wal‐Mart Connector from Flora Parke Boulevard to Walmart Supercenter to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Florida Boulevard  Duval  1021  Penman Road  SR 10 Atlantic Boulevard  Widen to 3 Lanes  Local Government CIP 

The project's purpose is to widen Florida Boulevard to three lanes from Penman Road to SR 10 Atlantic Boulevard to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

Future Corridor Initiative  Baker/Clay/Duval  721  Tampa Bay  Northeast Florida  Future Corridor  SIS Unfunded Needs 

The project's purpose is to construct a new limited‐access roadway from Tampa Bay to Northeast Florida to address congestion needs and improve mobility. 

The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process. 

Gator Bowl Boulevard  Duval  43  Liberty Street  SR 228 Hart Bridge Expressway and SR 115 Mathews Bridge 

Widen to 6 Lanes and Remove Ramps  2035 Needs Plan 

The project's purpose is to widen Gator Bowl Boulevard to six lanes and remove ramps from Liberty Street to Hart SR 115 Mathews Bridge to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Gene Lassere Boulevard Extension  Nassau  985  Gene Lassere Boulevard  SR 200A Pages Dairy Road  New 2 Lane Road and 

Roundabout Local government coordination 

The project's purpose is to construct a new two lane road and roundabout called Gene Lassere Boulevard Extension from Gene Lassere Boulevard to SR 200A Pages Dairy Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Page 33: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

17  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Goodbread Road Reconstruction  Nassau  977  US 17 SR 5  Hamilton Street  New 2 Lane Road  Local government 

coordination 

The project's purpose is to construct a new two‐lane road called Goodbread Road Reconstruction from US 17 SR 5 to Hamilton Street to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Governors Park Road  Clay  46  US 17  SR 16  New 4 Lane Road  2035 Needs Plan 

The project's purpose is to construct a new four‐lane road called Governors Park Road from US 17 to SR 16 to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Hamilton Street Extension  Nassau  1000  Goodbread Circle     New 2 Lane Road  Local government coordination 

The project's purpose is to construct a new two‐lane road called Hamilton Street Extension from Goodbread Circle to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Harlow Boulevard  Duval  943  SR 134 103rd Street  Lane Avenue  Widen to 3 Lanes  Local government coordination 

The project's purpose is to widen Harlow Boulevard to three lanes from SR 134 103rd Street to Lane Avenue to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Harper Chapel Extension  Nassau  989  Harper Chapel Road  Dove Road Extension  New 2 Lane Road  Local government coordination 

The project's purpose is to construct a new two‐lane road called Harper Chapel Extension from Harper Chapel Road to Dove Road Extension to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Page 34: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

18  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Hart Expressway Ramps  Duval  43B  Liberty Street  SR 228 Hart Expressway and SR 115 Mathews Bridge  Remove Ramps  Phases in TIP or 

Work Program 

The project's purpose is to remove Ramps along SR 228 Hart Expressway ramps from Liberty Street to the SR 228 Hart Bridge and SR 115 Mathews Bridge to address congestion needs and improve mobility. 

The project need was established in the Phases in TIP or Work Program and confirmed as part of the planning process. 

Hartley Road  Duval  49  SR 13 San Jose Boulevard  Old St. Augustine Road  Widen to 3 Lanes  Local Government CIP 

The project's purpose is to widen Hartley Road to three lanes from SR 13 San Jose Boulevard to Old St. Augustine Road to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

Harts Road  Duval  963  SR 104 Dunn Avenue  I‐295  Widen to 4 Lanes Other Local Government Priority 

The project's purpose is to widen Harts Road to four lanes from SR 104 Dunn Avenue to I‐295 to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Holmes Boulevard  St Johns  821  CR 214  Four Mile Road  Widen to 6 Lanes Other Local Government Priority 

The project's purpose is to widen Holmes Boulevard to six lanes from CR 214 to Four Mile Road to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

I‐10  Duval  401  SR 23 First Coast Expressway  I‐295  Add 4 Express Lanes  SIS CFP 

The project's purpose is to add four express lanes along I‐10 from SR 23 First Coast Expressway to I‐295 to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

Page 35: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

19  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

I‐10  Nassau  402*  Baker/Nassau County Line  Nassau/Duval County Line  Add 4 Express Lanes  SIS CFP 

The project's purpose is to add four express lanes along I‐10 from Baker/Nassau County Line to Nassau/Duval County Line to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

I‐10  Duval  403*  Nassau/Duval County Line  US 301  Add 4 Express Lanes  SIS CFP 

The project's purpose is to add four express lanes along I‐10 from Nassau/Duval County Line to US 301 to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

I‐10  Baker  404*  W of CR 125  W of SR 121  Add 4 Express Lanes  SIS CFP 

The project's purpose is to add four express lanes along I‐10 from west of CR 125 to west of SR 121 to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

I‐10  Baker  405*  W of SR 121  Baker/Nassau County Line  Add 4 Express Lanes  SIS CFP 

The project's purpose is to add four express lanes along I‐10 from west of SR 121 to Baker/Nassau County Line to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

I‐10  Duval  406  US 301  SR 23 First Coast Expressway  Add 4 Express Lanes  Phases in TIP or Work Program 

The project's purpose is to add four express lanes along I‐10 from US 301 to SR 23 First Coast Expressway to address congestion needs and improve mobility. 

The project need was established in the Phases in TIP or Work Program and confirmed as part of the planning process. 

Page 36: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

20  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

I‐10  Duval  432  I‐295  I‐95  Add 4 Express Lanes  SIS CFP 

The project's purpose is to add four express lanes along I‐10 from I‐295 to I‐95 to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

I‐10  Baker  453  Baker/Columbia County Line  CR 125  Add 4 Express Lanes  SIS Unfunded 

Needs 

The project's purpose is to add four express lanes along I‐10 from Baker/Columbia County Line to CR 125 to address congestion needs and improve mobility. 

The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process. 

I‐10  Duval  454  at I‐295     Modify Interchange  SIS Unfunded Needs 

The project's purpose is to modify the interchange of I‐10 at I‐295 to address congestion needs and improve mobility. 

The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process. 

I‐10/US 90 Parallel Reliever  Baker  720  South MacClenny  East Baldwin  Future Corridor  2035 Needs Plan 

The project's purpose is to construct a new roadway called the I‐10 US 90 Parallel Reliever from South MacClenny to East Baldwin to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

I‐295  Duval/Clay  57  SR 13 San Jose Boulevard  W of US 17 Roosevelt Boulevard  Add 4 Express Lanes on Bridge  SIS CFP 

The project's purpose is to add four express lanes on the Buckman Bridge along I‐295 from SR 13 San Jose Boulevard to west of US 17 Roosevelt Boulevard to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

Page 37: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

21  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

I‐295  Duval  119  SR 9B  I‐295  Add 4 Express Lanes  SIS Unfunded Needs 

The project's purpose is to add four express lanes along I‐295 from SR 9B to   I‐295 to address congestion needs and improve mobility. 

The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process. 

I‐295  Duval  407  I‐95 North  SR 105 Dames Point Bridge/Heckscher Drive  Add 4 Express Lanes  Phases in TIP or 

Work Program 

The project's purpose is to add four express lanes along I‐295 from I‐95 North to SR 105 Dames Point Bridge/Heckscher Drive to address congestion needs and improve mobility. 

The project need was established in the Phases in TIP or Work Program and confirmed as part of the planning process. 

I‐295  Duval  408  North of Trout River  I‐95  Add 4 Express Lanes  SIS CFP 

The project's purpose is to add four express lanes along I‐295 from north of the Trout River to I‐95 to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

I‐295  Duval  409  US 1 New Kings Road  North of Trout River  Add 4 Express Lanes  SIS CFP 

The project's purpose is to add four express lanes along I‐295 from US 1 New Kings Road to north of Trout River to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

I‐295  Duval  410  SR 134 103rd Street  I‐10  Add 4 Express Lanes  SIS CFP 

The project's purpose is to add four express lanes along I‐295 from SR 134 103rd Street to I‐10 to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

Page 38: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

22  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

I‐295  Duval  411  I‐10  US 1 South of New Kings Road  Add 4 Express Lanes  SIS CFP 

The project's purpose is to add four express lanes along I‐295 from I‐10 to US 1 South of New Kings Road to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

I‐295  Duval  431  US 17 Roosevelt Boulevard  SR 134 103rd Street  Add 4 Express Lanes  SIS CFP 

The project's purpose is to add four express lanes along I‐295 from US 17 Roosevelt Boulevard to SR 134 103rd Street to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

I‐295  Duval  964  at US 17 Roosevelt Boulevard     Modify Interchange  Phases in TIP or 

Work Program 

The project's purpose is to modify the interchange of I‐295 at US 17 Roosevelt Boulevard to address congestion needs and improve mobility. 

The project need was established in the Phases in TIP or Work Program and confirmed as part of the planning process. 

I‐295  Duval  1022  I‐95 South  SR 13 San Jose Boulevard  Add 2 Express Lanes  SIS CFP 

The project's purpose is to add two express lanes along I‐295 from I‐95 South to SR 13 San Jose Boulevard to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

I‐295  Duval  1023  SR 202 J. T. Butler Boulevard  SR 9B  Add 2 Express Lanes  SIS CFP 

The project's purpose is to add two express lanes along I‐295 from SR 202 J. T. Butler Boulevard to SR 9B to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

Page 39: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

23  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

I‐295  Duval  121  SR 113 Southside Connector  SR 202 J. T. Butler Boulevard  Add 4 Express Lanes  SIS CFP 

The project's purpose is to add four express lanes along I‐295 from SR 113 Southside Connector to SR 202 J. T. Butler Boulevard to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

I‐95  Duval  68  at SR 102 Airport Road     Modify Interchange  2035 Cost Feasible Plan 

The project's purpose is to modify the interchange of I‐95 at SR 102 Airport Road to address congestion needs and improve mobility. 

The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process. 

I‐95  St Johns  138 at US 1/SR 5 Ponce De Leon Boulevard and at SR 206 

   Modify Interchange  SIS Unfunded Needs 

The project's purpose is to modify the interchange of I‐95 from US 1 SR 5 Ponce De Leon Boulevard to SR 206 to address congestion needs and improve mobility. 

The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process. 

I‐95  St Johns  400  St. Johns/Flagler County Line  SR 206  Add 4 Express Lanes  SIS Unfunded 

Needs 

The project's purpose is to add four express lanes along I‐95 from St. Johns/Flagler County Line to SR 206 to address congestion needs and improve mobility. 

The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process. 

I‐95  Duval  413  SR 104 Dunn Avenue  SR 102 Airport Road  Add 4 Express Lanes  SIS Unfunded Needs 

The project's purpose is to add four express lanes along I‐95 from SR 104 Dunn Avenue to SR 102 Airport Road to address congestion needs and improve mobility. 

The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process. 

Page 40: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

24  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

I‐95  Duval  414  North of Fuller Warren Bridge  SR 104 Dunn Avenue  Add 4 Express Lanes  SIS Unfunded 

Needs 

The project's purpose is to add four express lanes along I‐95 from North of Fuller Warren Bridge to SR 104 Dunn Avenue to address congestion needs and improve mobility. 

The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process. 

I‐95  Duval  418A  Duval/St. Johns County Line  I‐295  Add 4 Express Lanes  SIS CFP 

The project's purpose is to add four express lanes along I‐95 from Duval/St. Johns County Line to I‐295 to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

I‐95  St Johns  418B  International Golf Parkway  St. Johns/Duval County Line  Add 4 Express Lanes  SIS CFP 

The project's purpose is to add four express lanes along I‐95 from International Golf Parkway to St. Johns/Duval County Line to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

I‐95  Duval  419  at US 1/SR 15 MLK     Modify Interchange  SIS CFP 

The project's purpose is to modify the interchange of I‐95 at US 1/SR 15 MLK to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

I‐95  St Johns  420  SR 206  International Golf Parkway  Add 4 Express Lanes  SIS Unfunded Needs 

The project's purpose is to add four express lanes along I‐95 from SR 206 to International Golf Parkway to address congestion needs and improve mobility. 

The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process. 

Page 41: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

25  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

I‐95  Duval  433  SR 202 J. T. Butler Boulevard  SR 10 Atlantic Boulevard  Add 4 Express Lanes  SIS CFP 

The project's purpose is to add four express lanes along I‐95 from SR 202 J. T. Butler Boulevard to SR 10 Atlantic Boulevard to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

I‐95  Duval  434  I‐295  SR 202 J. T. Butler Boulevard  Add 4 Express Lanes  SIS Unfunded Needs 

The project's purpose is to add four express lanes along I‐95 from I‐295 to SR 202 J. T. Butler Boulevard to address congestion needs and improve mobility. 

The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process. 

I‐95  St Johns  846  at CR 210     Modify Interchange  2035 Needs Plan The project's purpose is to modify the interchange of I‐95 at CR 210 to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

I‐95  Duval  962  at SR 115 Southside Boulevard     Modify Interchange 

SR 115 Southside Boulevard Corridor Study 

The project's purpose is to modify the interchange of I‐95 at SR 115 Southside Boulevard to address congestion needs and improve mobility. 

The project need was established in the SR 115 Southside Boulevard Corridor Study and confirmed as part of the planning process. 

International Golf Parkway  St Johns  823  I‐95  Turn/Bend  Widen to 4 Lanes*  2035 Needs Plan 

The project's purpose is to widen International Golf Parkway to four from I‐95 to Turn/Bend to address congestion needs and improve mobility.  This corridor was also identified as a candidate for context sensitive solutions in lieu of widening. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Page 42: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

26  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Jones Road  Duval  944  US 90 Beaver Street  Pritchard Road  Intersection Improvements  Local government coordination 

The project's purpose is to construct intersection improvements along Jones Road from US 90 Beaver Street to Pritchard Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Kernan Boulevard  Duval  73  SR 202 J. T. Butler Boulevard  Glen Kernan Parkway  Widen to 6 Lanes  Local 

Government CIP 

The project's purpose is wide Kernan Boulevard to six lanes from SR 202 J. T. Butler Boulevard to Glen Kernan Parkway to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

Kernan Boulevard  Duval  933  SR 10 Atlantic Boulevard  SR 116 McCormick Road  Widen to 6 Lanes  Local Government CIP 

The project's purpose is to widen Kernan Boulevard to six lanes from SR 10 Atlantic Boulevard to SR 116 McCormick Road to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

Knight Boxx Road  Clay  901  CR 220 Doctors Inlet Road  SR 21 Blanding Boulevard  Widen to 6 Lanes Other Local Government Priority 

The project's purpose is to widen Knight Boxx Road to six lanes from CR 220 Doctors Inlet Road to SR 21 Blanding Boulevard to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Lake Asbury East West 1  Clay  915  NS3  CR 209 Russell Road  New 2 Lane Road  Local government coordination 

The project's purpose is to construct a new two‐lane road called Lake Asbury East West 1 from NS3 to CR 209 Russell Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Page 43: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

27  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Lake Asbury North South Road 3  Clay  914  CR 739B Sandridge Road  CR 209 Russell Road  New 2 Lane Road  Local government 

coordination 

The project's purpose is to construct a new two‐lane road called Lake Asbury North South Road 3 from CR 739B Sandridge Road to CR 209 Russell Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Lofton Creek Crossing  Nassau  710  Hendricks Road  Avant Road  New 2 Lane Bridge Other Local Government Priority 

The project's purpose is to construct a new two‐lane bridge called the Lofton Creek Crossing from Hendricks Road to Avant Road to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Long Bay Road Extension North  Clay  911  Old Jennings Road  Long Bay Road  New 2 Lane Road 

Other Local Government Priority 

The project's purpose is to construct a new two‐lane road called Long Bay Road Extension North from Old Jennings Road to Long Bay Road to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Macaw Avenue Extension  Nassau  982  Cardinal Street  US 17 SR 5  New 2 Lane Road  Local government coordination 

The project's purpose is to construct a new two‐lane road called Macaw Avenue Extension from Cardinal Street to US 17 SR 5 to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

McDuff Avenue / 5th Street  Duval  1019  Melson Avenue  Huron Street  Widen to 3 Lanes  Local Government CIP 

The project's purpose is to widen 5th Street to three lanes from Melson Avenue to Huron Street to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

Page 44: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

28  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Mentoria‐William Burgess Connector  Nassau  990  William Burgess 

Boulevard  Harper Chapel Road  New 2 Lane Road  Local government coordination 

The project's purpose is to construct a new two‐lane road called Mentoria‐William Burgess Connector from William Burgess Boulevard to Harper Chapel Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Merrill Road  Duval  945  Hartsfield Road  SR 113 Southside Connector  Widen to 6 Lanes  Local government coordination 

The project's purpose is to widen Merrill Road to six lanes from Hartsfield Road to SR 113 Southside Connector to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Mickler Road  St Johns  825  Palm Valley Road  SR A1A  Widen to 4 Lanes  2035 Needs Plan 

The project's purpose is to widen Mickler Road to four lanes from Palm Valley Road to SR A1A to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Monument Road  Duval  946  Tredinick Parkway  I‐295  Widen to 6 Lanes  Local government coordination 

The project's purpose is to widen Monument Road to six lanes from Tredinick Parkway to I‐295 to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Monument Road  Duval  947  I‐295  Lee Road  Widen to 6 Lanes  Local government coordination 

The project's purpose is to widen Monument Road to six lanes from I‐295 to Lee Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Page 45: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

29  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

National Cemetery Road  Duval  1033  Lannie Road  Arnold Road  New 2 Lane Road  2035 Cost Feasible Plan 

The project's purpose is to construct a new two‐lane road called National Cemetery Road from Lannie Road to Arnold Road to address congestion needs and improve mobility. 

The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process. 

New Berlin Road  Duval  948  Pulaski Road  Yellow Bluff Road  Widen to 4 Lanes  Local government coordination 

The project's purpose is to widen New Berlin Road to four lanes from Pulaski Road to Yellow Bluff Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

New Berlin Road  Duval  949  Yellow Bluff Road  Cedar Point Road  Widen to 4 Lanes  Local government coordination 

The project's purpose is to widen New Berlin Road to four lanes from Yellow Bluff Road to Cedar Point Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

New World Avenue  Duval  1034  SR 23 First Coast Expressway  Chaffee Road  New 2 Lane Road  Local 

Government CIP 

The project's purpose is to construct a new two‐lane road called New World Avenue from SR 23 First Coast Expressway to Chaffee Road to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

New World Avenue  Duval  1035  SR 23 First Coast Expressway  Chaffee Road  Widen to 4 Lanes  Local government 

coordination 

The project's purpose is to widen New World Avenue from SR 23 First Coast Expressway to Chaffee Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Page 46: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

30  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Norfolk Southern Railroad Overpass  Duval  85  West 12th Street  US 23 New Kings Road  New 3 Lane Road / Bridge  2035 Needs Plan 

The project's purpose is to construct a new three lane road and bridge called the Norfolk Southern Railroad Overpass from West 12th Street to US 23 New Kings Road to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Northern Cross Town Corridor  Baker  500  CR 125  SR 121  New 2 Lane Road Other Local Government Priority 

The project's purpose is to construct a new two‐lane road called Northern Cross Town Corridor from CR 125 to SR 121 to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Northern Outer Beltway  Duval/Nassau  88  I‐10  I‐95  Future Corridor  2035 Needs Plan 

The project's purpose is to construct a new limited‐access facility called the Northern Outer Beltway from I‐10 to I‐95 to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Oakleaf Village Parkway Extension  Clay  913  Oakleaf Plantation 

Parkway  Oakleaf Village Parkway  New 2 Lane Road Other Local Government Priority 

The project's purpose is to construct a new two‐lane road called Oakleaf Village Parkway Extension from Oakleaf Plantation Parkway to Oakleaf Village Parkway to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Old Kings Road  Duval  951  SR 111 Edgewood Avenue  Plummer Road  Intersection Improvements  Local government coordination 

The project's purpose is to construct intersection improvements along Old Kings Road from SR 111 Edgewood Avenue to Plummer Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Page 47: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

31  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Old Middleburg Road  Duval  1015  Argyle Forest Boulevard  SR 134 103rd Street  Widen to 4 Lanes  Local Government CIP 

The project's purpose is to widen Old Middleburg Road from Argyle Forest Boulevard to SR 134 103rd Street to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

Old St. Augustine Road  Duval  90  Bartram Park Boulevard  US 1/SR 5 Phillips Highway  Widen to 6 Lanes and Overpass  2035 Needs Plan 

The project's purpose is to widen Old St. Augustine Road to six lanes and construct an overpass of US 1 SR 5 Philips Highway from Bartram Park Boulevard to US 1 SR 5 Phillips Highway to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Old St. Augustine Road  Duval  1010  at Greenland Road     Intersection Improvements / Add 1 Lane 

Local Government CIP 

The project's purpose is to construct intersection improvements and add one lane along Old St. Augustine Road at Greenland Road to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

Outer Loop Facility  Baker/Duval  91  SR 228 Normandy  Boulevard  SR 228 Normandy  Boulevard  Future Corridor  2035 Needs Plan 

The project's purpose is to construct a new roadway called the Outer Loop Facility from SR 228 Normandy Boulevard to SR 228 Normandy Boulevard to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Pages Dairy Road East Extension  Nassau  987  Chester Road  Blackrock Road  New 2 Lane Road  Local government 

coordination 

The project's purpose is to construct a new two‐lane road called Pages Dairy Road East Extension from Chester Road to Blackrock Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Page 48: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

32  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Pages Dairy Road South Extension  Nassau  983  SR 200 SR A1A  Sowell Road  New 2 Lane Road  Local government 

coordination 

The project's purpose is to construct a new two‐lane road called Pages Dairy Road South Extension from SR 200 SR A1A to Sowell Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Palm Valley Road  St Johns  826  Intracoastal Waterway  Mickler Road  Widen to 4 Lanes Other Local Government Priority 

The project's purpose is to widen Palm Valley Road from Intracoastal Waterway to Mickler Road to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Pecan Park Road  Duval  952  Braddock Boulevard  JIA North Access Road  Widen to 4 Lanes  Local government coordination 

The project's purpose is to widen Pecan Park Road from Braddock Boulevard to JIA North Access Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Pecan Park Road  Duval  92  I‐95  US 17 Main Street  Widen to 4 Lanes  2035 Needs Plan 

The project's purpose is to widen Pecan Park Road from I‐95 to US 17 Main Street to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Pulaski Road  Duval  953***  Eastport Road  I‐295  Widen to 4 Lanes  Local government coordination 

The project's purpose is to widen Pulaski Road from Eastport Road to I‐295 to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Page 49: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

33  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Pulaski Road / Starratt Road  Duval  97  I‐295  Duval Station Road  Widen to 4 Lanes  2035 Needs Plan 

The project's purpose is to widen Pulaski Road / Starratt Road from I‐295 to Duval Station Road to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Race Track Road  St Johns  827  St. Johns Parkway  Bartram Park Boulevard  Widen to 4 Lanes  2035 Needs Plan 

The project's purpose is to widen Race Track Road from St. Johns Parkway to Bartram Park Boulevard to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Race Track Road  St Johns  828  Bartram Park Boulevard  Bartram Springs  Widen to 4 Lanes Other Local Government Priority 

The project's purpose is to widen Race Track Road from Bartram Park Boulevard to Bartram Springs to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Race Track Road Connector  St Johns  851  Durbin Parkway / 9B Extension  Race Track Road  New 2 Lane Road 

Other Local Government Priority 

The project's purpose is to construct a new two‐lane road called Race Track Road Connector from Durbin Parkway and 9B Extension to Race Track Road to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Ramona Boulevard  Duval  935  Hammond Boulevard  Cahoon Road South  Widen to 5 Lanes  Local Government CIP 

The project's purpose is to widen Ramona Boulevard to five lanes from Hammond Boulevard to Cahoon Road South to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

Page 50: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

34  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Rampart / Firestone Road  Duval  98  Collins Road  SR 134 103rd Street  Widen to 4 Lanes  2035 Needs Plan 

The project's purpose is to widen Rampart / Firestone Road to four lanes from Collins Road to SR 134 103rd Street to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Ranch Road  Duval  1038  Tradeport Road  SR 102 North of Airport Road  Widen to 4 Lanes  SIS Unfunded Needs 

The project's purpose is to widen Ranch Road to four lanes from Tradeport Road to SR 102 North of Airport Road to address congestion needs and improve mobility. 

The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process. 

Ricker Road  Duval  934  Morse Avenue  Old Middleburg Road  Widen to 3 Lanes  Local Government CIP 

The project's purpose is to widen Ricker Road to three lanes from Morse Avenue to Old Middleburg Road to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

Salisbury Road Extension  Duval  99  SR 152 Baymeadows Boulevard  Belfort Road  New 3 Lane Road  2035 Needs Plan 

The project's purpose is to construct a new three‐lane road called Salisbury Road Extension from SR 152 Baymeadows Boulevard to Belfort Road to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

San Pablo Road  Duval  1009  US 90 Beach Boulevard  SR 10 Atlantic Boulevard  Widen to 3 Lanes  Local Government CIP 

The project's purpose is to widen San Pablo Road to three lanes from US 90 Beach Boulevard to SR 10 Atlantic Boulevard to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

Page 51: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

35  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Shindler Drive  Duval  101  Collins Road  SR 134 103rd Street  Widen to 3 Lanes  Local Government CIP 

The project's purpose is to widen Shindler Drive to three lanes from Collins Road to SR 134 103rd Street to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

SR 10 Atlantic Boulevard  Duval  714  at Girvin Road     Intersection Improvements 

Phases are currently included in a local government capital improvement program. 

The project's purpose is to construct intersection improvements along SR 10 Atlantic Boulevard at Girvin Road to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

SR 10 Atlantic Boulevard  Duval  715  at Hodges Boulevard     Intersection Improvements  Local Government CIP 

The project's purpose is to construct intersection improvements along SR 10 Atlantic Boulevard at Hodges Boulevard to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

SR 10 Atlantic Boulevard  Duval  716  at San Pablo Boulevard     Intersection Improvements 

Phases are currently included in a local government capital improvement program. 

The project's purpose is to construct intersection improvements along SR 10 Atlantic Boulevard at San Pablo Boulevard to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

SR 100  Clay  450  Clay/Bradford County Line  Clay/Putnam County Line  Widen to 4 Lanes  SIS Unfunded Needs 

The project's purpose is to widen SR 100 to four lanes from Clay/Bradford County Line to Clay/Putnam County Line to address congestion needs and improve mobility. 

The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process. 

Page 52: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

36  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

SR 100  Putnam  451  Clay/Putnam County Line  US 17 SR 5  Widen to 4 Lanes  SIS Unfunded Needs 

The project's purpose is to widen SR 100 to four lanes from Clay/Putnam County Line to US 17 SR 5 to address congestion needs and improve mobility. 

The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process. 

SR 101 Mayport Road  Duval  152B  SR 116 Wonderwood Drive  Mayport Main Gate  Add 2 Northbound Lanes 

Through coordination with Mayport Naval Station  

The project's purpose is to add two northbound lanes along SR 101 Mayport Road from SR 116 Wonderwood Drive to Mayport Main Gate to address congestion needs and improve mobility. 

The project need was established in the through coordination with Mayport Naval Station and local government coordination.   

SR 101 Mayport Road  Duval  152  at SR 116 Wonderwood Drive     Intersection Improvements 

Through coordination with Mayport Naval Station 

The project's purpose is to construct intersection improvements along SR 101 Mayport Road at SR 116 Wonderwood Drive to address congestion needs and improve mobility. 

The project need was established in the through coordination with Mayport Naval Station and local government coordination.   

SR 102 Airport Road  Duval  421  Airport Entrance  I‐95  Widen to 6 Lanes  SIS Unfunded Needs 

The project's purpose is to widen SR102 Airport Road to 6 lanes from the Airport Entrance to I‐95 to address congestion needs and improve mobility. 

The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process. 

SR 104 Dunn Avenue  Duval  940  US 1/SR 15 New Kings Road  I‐295  Widen to 4 Lanes  2035 Needs Plan 

The project's purpose is to widen SR 104 Dunn Avenue to four lanes from US 1/SR 15 New Kings Road to I‐295 to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Page 53: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

37  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

SR 104 Dunn Avenue  Duval  941  Old Kings Road  US 23 New Kings Road  Intersection Improvements  2035 Needs Plan 

The project's purpose is to construct intersection improvements along SR 104 Dunn Avenue from Old Kings Road to US 23 New Kings Road to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

SR 115 Arlington Expressway  Duval  100  SR 109 University Boulevard  SR 10 Atlantic Boulevard  Widen to 6 Lanes* 

New need identified in the 2040 LRTP. 

The project's purpose is to widen SR 115 Arlington Expressway to six lanes from SR 109 University Boulevard to SR 10 Atlantic Boulevard to address congestion needs and improve mobility.  This project was also identified as a candidate for context sensitive solutions in lieu of widening. 

The project was identified as a candidate for context sensitive solutions through the planning process based on the lack of accessibility and mobility within the corridor.   

SR 115 Arlington Expressway   Duval  153  at SR 109 University Boulevard     Modify Interchange 

Established as part of the SR 115 Mathews Bridge Replacement PD&E Study and included in the Duval County LOGT program for PE. 

The project's purpose is to modify the interchange of SR 115 Arlington Expressway at SR 109 University Boulevard to address congestion needs and improve mobility. 

The project need was established as part of the SR 115 Mathews Bridge Replacement PD&E Study and included in the Duval County LOGT program for PE.  The need for this project was confirmed as part of the planning process. 

SR 115 Lem Turner Road  Duval/Nassau  74  I‐295  US 1 / Callahan S Kings Road  Widen to 4 Lanes  2035 Cost Feasible Plan 

The project's purpose is to widen SR 115 Lem Turner Road to four lanes from I‐295 to US 1 / Callahan S Kings Road to address congestion needs and improve mobility. 

The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process. 

SR 115 Southside Boulevard  Duval  102  US 1/SR 5 Philips Highway  I‐95 Ramps  Widen to 6 Lanes* 

SR115SouthsideBoulevardCorridorStudy

The project's purpose is to widen SR 115 Southside Boulevard to six lanes from US 1/SR 5 Philips Highway to the I‐95 Ramps to address congestion needs and improve mobility.  This project was also identified as a candidate for context sensitive solutions in lieu of widening. 

The project need was established in the 0 and confirmed as part of the planning process. 

Page 54: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

38  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

SR 115 Southside Boulevard  Duval  103  SR 202 J. T. Butler Boulevard  US 90 Beach Boulevard  Widen to 6 Lanes* 

SR115SouthsideBoulevardCorridorStudy

The project's purpose is to widen SR 115 Southside Boulevard to six lanes from SR 202 J. T. Butler Boulevard to US 90 Beach Boulevard to address congestion needs and improve mobility.  This project was also identified as a candidate for context sensitive solutions in lieu of widening. 

The project need was established in the 0 and confirmed as part of the planning process. 

SR 115 Southside Boulevard  Duval  104  US 90 Beach Boulevard  SR 10 Atlantic Boulevard  Widen to 6 Lanes*  2035 Needs Plan 

The project's purpose is to widen SR 115 Southside Boulevard to six lanes from US 90 Beach Boulevard to SR 10 Atlantic Boulevard to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

SR 115 Southside Boulevard  Duval  960  Hogan Road  Gate Parkway  Intersection Improvements  Local Government CIP 

The project's purpose is to construct intersection improvements along SR 115 Southside Boulevard from Hogan Road to Gate Parkway to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

SR 115 Southside Boulevard  Duval  966  at SR 202 J. T. Butler Boulevard     Modify Interchange 

SR115SouthsideBoulevardCorridorStudy

The project's purpose is to modify the interchange of SR 115 Southside Boulevard at SR 202 J. T. Butler Boulevard to address congestion needs and improve mobility. 

The project need was established in the 0 and confirmed as part of the planning process. 

SR 115 Southside Boulevard  Duval  967  at SR 152 Baymeadows Road     Underpass 

SR115SouthsideBoulevardCorridorStudy

The project's purpose is to construct an underpass where SR 152 Baymeadows Road would go under SR 115 Southside Boulevard to address congestion needs and improve mobility.   

The project need was established in the 0 and confirmed as part of the planning process. 

Page 55: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

39  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

SR 115 Southside Boulevard  Duval  968  at SR 10 Atlantic Boulevard     Intersection Improvements  Local 

Government CIP 

The project's purpose is to construct intersection improvements along SR 115 Southside Boulevard at SR 10 Atlantic Boulevard to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

SR 152 Baymeadows Road  Duval  937  I‐95  SR 115 Southside Boulevard  Widen to 6 Lanes  2035 Needs Plan 

The project's purpose is to widen SR 152 Baymeadows Road to 6 lanes from I‐95 to SR 115 Southside Boulevard to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

SR 152 Baymeadows Road  Duval  938  US 1 /SR 5 Philips Highway  I‐95  Widen to 6 Lanes*  2035 Needs Plan 

The project's purpose is to widen SR 152 Baymeadows Road to six lanes from US 1 SR 5 Philips Highway to I‐95 to address congestion needs and improve mobility. This project was also identified as a candidate for context sensitive solutions in lieu of widening. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

SR 16  Clay  106  CR 218  SR 15A Oakridge Avenue  Widen to 4 Lanes  2035 Needs Plan 

The project's purpose is to widen SR 16 to four lanes from CR two18 to SR 15A Oakridge Avenue to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

SR 16  St Johns  110  I‐95  SR 313  Widen to 6 Lanes  2035 Needs Plan 

The project's purpose is to widen SR 16 to six lanes from I‐95 to SR 313 to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Page 56: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

40  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

SR 16  Clay  908  US 17  Shands Bridge  Widen to 4 Lanes Other Local Government Priority 

The project's purpose is to widen SR 16 to four lanes from US 17 to Shands Bridge to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

SR 16  St Johns  835  South Francis Road  International Golf Parkway  Widen to 4 Lanes Other Local Government Priority 

The project's purpose is to widen SR 16 to four lanes from South Francis Road to International Golf Parkway to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

SR 16  St Johns  836  CR 208 Outlet Mall  South Francis Road  Widen to 4 Lanes Other Local Government Priority 

The project's purpose is to widen SR 16 to four lanes from CR 208 Outlet Mall to South Francis Road to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

SR 16 Connector  St Johns  829  SR 16/CR 16A  CR 2209  New 4 Lane Road  2035 Needs Plan 

The project's purpose is to construct a new four‐lane road called SR 16 Connector from SR 16/CR 16A to CR 2209 to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

SR 19 Connector  Putnam  965  SR 19  Putnam County Boulevard  New 4 lane road / bridge Other Local Government Priority 

The project's purpose is to construct a new four‐lane road / bridge called SR 19 Connector from SR 19 to Putnam County Boulevard to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Page 57: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

41  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

SR 20  Putnam  422  Putnam/Alachua County Line  SW 56th Avenue  Widen to 4 Lanes  Phases in TIP or 

Work Program 

The project's purpose is to widen SR 20 to four lanes from Putnam/Alachua County Line to SW 56th Avenue to address congestion needs and improve mobility. 

The project need was established in the Phases in TIP or Work Program and confirmed as part of the planning process. 

SR 20  Putnam  423  SW 56th Avenue  CR 315 Interlachen  Widen to 4 Lanes  Phases in TIP or Work Program 

The project's purpose is to widen SR20 to four lanes from SW 56th Avenue to CR 315 in Interlachen to address congestion needs and improve mobility. 

The project need was established in the Phases in TIP or Work Program and confirmed as part of the planning process. 

SR 200  Overpass  Nassau  1003  at US 17 SR 5 and Railroad Tracks     Overpass  2035 Needs Plan 

The project's purpose is to construct an overpass along SR 200 at US 17 SR 5 and the railroad tracks to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

SR 200  William Burgess Connector  Nassau  998  William Burgess 

Boulevard  SR 200 SR A1A  New 2 Lane Road  Local government coordination 

The project's purpose is to construct a new two‐lane Road called SR 200 William Burgess Connector from William Burgess Boulevard to SR 200 SR A1A to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

SR 200  Yulee Backage Roads  Nassau  992  Cardinal Street North Extension  Old Yulee Road  New 2 Lane Road  Local government 

coordination 

The project's purpose is to construct a new two‐lane road called SR 200 Yulee Backage Roads from the Cardinal Street North Extension to Old Yulee Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Page 58: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

42  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

SR 200 SR A1A  Nassau  427  at US 17     Intersection Improvements  SIS CFP 

The project's purpose is to construct intersection improvements along SR 200 SR A1A at US 17 to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

SR 200 SR A1A  Nassau  703  Amelia Island Parkway  Sadler Road  Widen to 6 Lanes  Local government coordination 

The project's purpose is to widen SR 200 SR A1A to six lanes from Amelia Island Parkway to Sadler Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

SR 200A Pages Dairy Road  Nassau  979  at Felmor Road     Roundabout Projects  Local government coordination 

The project's purpose is to construction a roundabout along SR 200A Pages Dairy Road at Felmor Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

SR 207  St Johns  113  I‐95  South Holmes Boulevard  Widen to 6 Lanes  2035 Needs Plan 

The project's purpose is to SR 207 widen to six lanes from I‐95 to South Holmes Boulevard to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

SR 207  St Johns  830  Holmes Boulevard  SR 312  Widen to 6 Lanes  2035 Needs Plan 

The project's purpose is to widen SR 207 to 6 lanes from Holmes Boulevard to SR 312 to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Page 59: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

43  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

SR 21 Blanding Boulevard  Duval  9  I‐295  Wilson Boulevard  Widen to 6 Lanes  2035 Needs Plan 

The project's purpose is to widen SR 21 Blanding Boulevard to six lanes from I‐295 to Wilson Boulevard to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

SR 21 Blanding Boulevard  Clay  114  SR 16  CR 215 Blanding Boulevard  Widen to 4 Lanes  2035 Needs Plan 

The project's purpose is to widen SR 21 Blanding Boulevard to four lanes from SR 16 to CR two15 Blanding Boulevard to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

SR 21 Blanding Boulevard  Duval  957A  at Collins Road     Intersection Improvements  Local Government CIP 

The project's purpose is to construct intersection improvements along SR 21 Blanding Boulevard at Collins Road to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

SR 21 Blanding Boulevard  Duval  957B  at SR 134 103rd Street     Intersection Improvements  Local Government CIP 

The project's purpose is to construct intersection improvements along SR 21 Blanding Boulevard at SR 134 103rd Street to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

SR 21 Blanding Boulevard  Duval  957C  at Cedar Hills Boulevard     Intersection Improvements  Local Government CIP 

The project's purpose is to construct intersection improvements along SR 21 Blanding Boulevard at Cedar Hills Boulevard to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

Page 60: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

44  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

SR 228 Hart Bridge  Duval  47  SR 228  Hart Expressway ‐ Downtown  SR 10 Atlantic Boulevard  New 6 Lane Bridge  2035 Needs Plan 

The project's purpose is to construct a replace the SR 228 Hart Bridge from SR 228 Hart Expressway ‐ Downtown to SR 10 Atlantic Boulevard to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

SR 228 Normandy  Boulevard  Duval  86  US 301  Bell Road (Equestrian Park )  Widen to 4 Lanes  2035 Needs Plan 

The project's purpose is to widen SR 228 Normandy Boulevard to four lanes from US 301 to Bell Road (Equestrian Park) to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

SR 228 Normandy  Boulevard  Duval  87  SR 23 First Coast Expressway  SR 111 Cassatt Avenue  Widen to 6 Lanes  2035 Needs Plan 

The project's purpose is to widen SR 228 Normandy Boulevard to six lanes from SR 23 First Coast Expressway to SR 111 Cassatt Avenue to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

SR 23 First Coast Expressway  Clay  41  at CR 218     New Interchange  SIS CFP 

The project's purpose is to construct a new interchange along SR 23 First Coast Expressway at CR two18 to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

SR 23 First Coast Expressway  Clay  8202  SR 21 Blanding Boulevard  US 17  New 4 Lane Road  SIS CFP 

The project's purpose is to construct a new four‐lane road called SR 23 First Coast Expressway from SR 21 Blanding Boulevard to US 17 to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

Page 61: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

45  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

SR 23 First Coast Expressway  Clay  1011  at SR 21 Blanding Boulevard     New Interchange  SIS CFP 

The project's purpose is to construct a new interchange along SR 23 First Coast Expressway at SR 21 Blanding Boulevard to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

SR 23 First Coast Expressway  Clay  1012  at CR 739     New Interchange  SIS CFP 

The project's purpose is to construct a new interchange along SR 23 First Coast Expressway at CR 739 to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

SR 23 First Coast Expressway  Clay  1013  at SR 16     New Interchange  SIS CFP 

The project's purpose is to construct a new interchange along SR 23 First Coast Expressway at SR 16 to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

SR 23 First Coast Expressway  Clay/Duval  8201  I‐10  SR 21 Blanding Boulevard  Widen to 6 Lanes  SIS CFP 

The project's purpose is to widen SR 23 First Coast Expressway from I‐10 to SR 21 Blanding Boulevard to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

SR 23 First Coast Expressway  Clay/St. Johns  8203  US 17  I‐95  New 6 Lane Road  SIS CFP 

The project's purpose is to construct a new six‐lane road called SR 23 First Coast Expressway from US 17 to I‐95 to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

Page 62: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

46  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

SR 23 First Coast Expressway  St Johns  840  at I‐95     New Interchange  SIS CFP 

The project's purpose is to construct a new interchange along SR 23 First Coast Expressway at I‐95 to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

SR 23 First Coast Expressway  St Johns  841  at CR 16 A     New Interchange  SIS CFP 

The project's purpose is to construct a new interchange along SR 23 First Coast Expressway at CR 16 A to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

SR 23 First Coast Expressway  St Johns  847  at CR 2209     New Interchange  SIS CFP 

The project's purpose is to construct a new interchange along SR 23 First Coast Expressway at CR 2209 to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

SR 243 JIA North Access Road  Duval  701  SR 102 Airport Road  Pecan Park Road  Widen to 4 Lanes  2035 Needs Plan 

The project's purpose is to widen SR 243 JIA North Access Road to four lanes from SR 102 Airport Road to Pecan Park Road to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

SR 312  St Johns  115  US 1/SR 5 Dixie Highway  SR A1A  Widen to 6 Lanes  2035 Needs Plan 

The project's purpose is to widen SR 312 to six lanes from US 1/SR 5 Dixie Highway to SR A1A to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Page 63: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

47  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

SR 313  St Johns  831  SR 207  SR 16  New 6 Lane Road  2035 Needs Plan 

The project's purpose is to construct a new six lane road called SR 313 from SR 207 to SR 16 to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

SR 313  St Johns  832  SR 16  US 1 Dixie Highway  New 4 Lane Road  2035 Needs Plan 

The project's purpose is to construct a new four‐lane road called SR 313 from SR 16 to US 1 Dixie Highway to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

SR 313  St Johns  839  at US 1/SR 5 Dixie Highway     New Interchange 

Other Local Government Priority 

The project's purpose is to construct a new interchange along SR 313 at US 1 SR 5 Dixie Highway to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

SR 9B  Duval  1024  US 1/SR 5 Philips Highway  I‐295  Add 2 Auxiliary Lanes  SIS CFP 

The project's purpose is to add two auxiliary lanes along SR 9B from US 1/SR 5 Philips Highway to I‐295 to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

SR 9B  Duval  18  US 1/SR 5 Philips Highway  I‐295  Widen to 6 Lanes  SIS CFP 

The project's purpose is to widen SR 9B to six lanes from US 1 SR 5 Philips Highway to I‐295 to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

Page 64: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

48  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

SR 9B Extension  St Johns  833  St. Johns Parkway  Race Track Road  Widen to 6 Lanes Other Local Government Priority 

The project's purpose is to widen the SR 9B Extension to six lanes from St. Johns Parkway to Race Track Road to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

SR 9B Extension  St Johns  842  at Durbin Parkway     New Interchange  2035 Needs Plan 

The project's purpose is to construct a new interchange along the SR 9B Extension at Durbin Parkway to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

SR A1A  St Johns  128  Solana Road  SR 202 J. T. Butler Boulevard  Widen to 6 Lanes*  2035 Needs Plan 

The project's purpose is to widen SR A1A to six lanes from Solana Road to SR 202 J. T. Butler Boulevard to address congestion needs and improve mobility.  This project was also identified as a candidate for context sensitive solutions in lieu of widening. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

SR A1A  Nassau  706  South Fletcher Avenue  Amelia Island Parkway  Turn Lane Improvements*  Local government coordination 

The project's purpose is to construct turn lane improvements along SR A1A from South Fletcher Avenue to Amelia Island Parkway to address congestion needs and improve mobility.  This project was also identified as a candidate for context solutions. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

SR A1A  St Johns  1008  at Red Cox/Coquina Road     Intersection Improvements Other Local Government Priority 

The project's purpose is to construct intersection improvements along SR A1A at Red Cox/Coquina Road to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Page 65: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

49  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

SR A1A  St Johns  800  Mickler Road  Palm Valley Road  Widen to 4 Lanes  2035 Needs Plan 

The project's purpose is to widen SR A1A to four lanes from Mickler Road to Palm Valley Road to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

SR A1A  Duval  151  SR 116 Wonderwood Drive  Naval Station Mayport North Gate  Widen to 4 Lanes*  2035 Needs Plan 

The project's purpose is to widen SR A1A to four lanes from SR 116 Wonderwood Drive to Naval Station Mayport North Gate to address congestion needs and improve mobility.  This project was also identified as a candidate for context sensitive solutions in lieu of widening. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

SR A1A Anastasia Boulevard  St Johns  1031  Casanova Road  Bridge of Lions  CSS  St. Augustine Mobility Institute 

The project's purpose is to construct context sensitive solutions along SR A1A Anastasia Boulevard from Casanova Road to Bridge of Lions to address congestion needs and improve mobility. 

The project need was established in the St. Augustine Mobility Institute and confirmed as part of the planning process. 

SR A1A St Johns River Ferry  Duval  2331        Ferry Slip Replacement  2035 Cost Feasible Plan 

The project's purpose is to replace the St. Johns River ferry slip to maintain service, address congestion needs and improve mobility. 

The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process. 

St. Johns Parkway  St Johns  848  CR 2209  9B Extension  Widen to 6 Lanes Other Local Government Priority 

The project's purpose is to widen the St. Johns Parkway to six lanes from CR 2209 to 9B Extension to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Page 66: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

50  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Starratt Road  Duval  954  Duval Station Road  Yellow Bluff Road  Widen to 4 Lanes  Local government coordination 

The project's purpose is to widen Starratt Road to four lanes from Duval Station Road to Yellow Bluff Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Touchton Road  Duval  129  Belfort Road  SR 115 Southside Boulevard  Widen to 4 Lanes  2035 Needs Plan 

The project's purpose is to widen Touchton Road to four lanes from Belfort Road to SR 115 Southside Boulevard to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Town Center Boulevard  Clay  903  US 17  CR 220 Doctors Inlet Road  Widen to 4 Lanes Other Local Government Priority 

The project's purpose is to widen Town Center Boulevard to four lanes from US 17 to CR 220 Doctors Inlet Road to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Trout River Boulevard  Duval  955  Old Kings Road  US 23 New Kings Road  Widen to 4 Lanes  Local government coordination 

The project's purpose is to widen Trout River Boulevard to four lanes from Old Kings Road to US two3 New Kings Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Tynes Road  Clay  912  Pipit Place  Oakleaf Plantation Parkway  New 2 Lane Road Other Local Government Priority 

The project's purpose is to construct a new two‐lane road called Tynes Road from Pipit Place to Oakleaf Plantation Parkway to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Page 67: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

51  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

US 1 SR 15 New Kings Road  Duval  82  Soutel Drive  I‐295  Widen to 6 Lanes  2035 Needs Plan 

The project's purpose is to widen US 1 SR 15 New Kings Road to six lanes from Soutel Drive to I‐295 to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

US 1 SR 15 New Kings Road  Duval  83  I‐295  Old Kings Road  Widen to 6 Lanes  2035 Needs Plan 

The project's purpose is to widen US 1 SR 15 New Kings Road to six lanes from I‐295 to Old Kings Road to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

US 1 SR 15 New Kings Road  Duval  950  SR 111 Edgewood Avenue  Soutel Drive  Intersection Improvements  Local government coordination 

The project's purpose is to construct intersection improvements along US 1 SR 15 New Kings Road at SR 111 Edgewood Avenue to Soutel Drive to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

US 1 SR 5  St Johns  845  at CR 210     Modify Interchange  Phases in TIP or Work Program 

The project's purpose is to modify the interchange of US 1 SR 5 at CR 210 to address congestion needs and improve mobility. 

The project need was established in the Phases in TIP or Work Program and confirmed as part of the planning process. 

US 1 SR 5 Dixie Highway  St Johns  130  SR 206  Lewis Point Road  Widen to 6 Lanes  2035 Needs Plan 

The project's purpose is to widen US 1 SR 5 Dixie Highway to six lanes from SR 206 to Lewis Point Road to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Page 68: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

52  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

US 1 SR 5 Dixie Highway  St Johns  131  SR 313  International Golf Parkway  Widen to 6 Lanes  2035 Needs Plan 

The project's purpose is to widen US 1 SR 5 Dixie Highway to six lanes from SR 313 to International Golf Parkway to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

US 1 SR 5 Dixie Highway  St Johns  132  International Golf Parkway  Race Track Road  Widen to 6 Lanes  2035 Needs Plan 

The project's purpose is to widen US 1 SR 5 Dixie Highway to six lanes from International Golf Parkway to Race Track Road to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

US 1 SR 5 Philips Highway  Duval  93  Nocatee Parkway / Race Track Road  SR 9B  Widen to 6 Lanes  2035 Needs Plan 

The project's purpose is to widen US 1 SR 5 Philips Highway to six lanes from Nocatee Parkway / Race Track Road to SR 9B to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

US 1/SR 5 Philips Highway  Duval  94  SR 9B  I‐295  Widen to 6 Lanes*  2035 Needs Plan 

The project's purpose is to widen US 1 SR 5 Philips Highway to six lanes from SR 9B to I‐295 to address congestion needs and improve mobility.  This project was also identified as a candidate for context sensitive solutions in lieu of widening. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

US 1/SR 5 Philips Highway  Duval  95  I‐95 at the Avenues  SR 202 J. T. Butler Boulevard  Widen to 6 Lanes*  2035 Needs Plan 

The project's purpose is to widen to US 1 SR 5 Philips Highway to six lanes from I‐95 at the Avenues to SR 202 J. T. Butler Boulevard to address congestion needs and improve mobility.  This project was also identified as a candidate for context sensitive solutions in lieu of widening. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Page 69: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

53  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

US 1/SR 5 Philips Highway  Duval  96  SR 202 J. T. Butler Boulevard  SR 126 Emerson Street  Widen to 6 Lanes  2035 Needs Plan 

The project's purpose is to widen to US 1 SR 5 Philips Highway to six lanes from SR 202 J. T. Butler Boulevard to SR 1two6 Emerson Street to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

US 17  Clay  133  CR 315  Town Center Boulevard  Widen to 6 Lanes  2035 Needs Plan 

The project's purpose is to widen US 17 to six lanes from CR 315 to Town Center Boulevard to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

US 17  Nassau  707  Nassau/Duval County Line  Harts Road  Intersection Improvements  Local government coordination 

The project's purpose is to construct intersection improvements along US 17 from Nassau/Duval County Line to Harts Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

US 17  Nassau  709  SR 200 SR A1A  Georgia State Line  Widen to 4 Lanes  I‐95 Parallel Corridor Study 

The project's purpose is to widen US 17 to four lanes from SR 200 SR A1A to Georgia State Line to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

US 17  Clay  1037  Governor Street  Haven Avenue  Widen to 4 Lanes  2035 Cost Feasible Plan 

The project's purpose is to widen US 17 to four lanes from Governor Street to Haven Avenue to address congestion needs and improve mobility. 

The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process. 

Page 70: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

54  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

US 17 Main Street  Duval/Nassau  78  Pecan Park Road  SR 200 / SR A1A  Widen to 4 Lanes  2035 Needs Plan 

The project's purpose is to widen US 17 Main Street to four lanes from Pecan Park Road to SR 200 / SR A1A to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

US 17 Main Street  Duval  1017  New Berlin Road  Pecan Park Road  Widen to 4 Lanes  2035 Cost Feasible Plan 

The project's purpose is to widen US 17 to four lanes from New Berlin Road to Pecan Park Road to address congestion needs and improve mobility. 

The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process. 

US 17 Main Street  Duval  959  at Eastport Road     New Interchange  Local Government CIP 

The project's purpose is to construct a new interchange along US 17 Main Street at Eastport Road to address congestion needs and improve mobility. 

The project need was established based on project phases being programmed in a local government capital improvement program.  The project needs were confirmed as part of the planning process. 

US 17 Pages Dairy Connector w/roundabout  Nassau  984  US 17 SR 5  SR 200A Pages Dairy Road  New 2 Lane Road and 

Roundabout Local government coordination 

The project's purpose is to construct a new road called US 17 Pages Dairy Connector from US 17 SR 5 to SR 200A Pages Dairy Road and roundabout at SR 200A Paiges Dairy Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

US 17 Powerline Corridor  Nassau  994  Vegas Boulevard  Radio Avenue  New 2 Lane Road  Local government coordination 

The project's purpose is to construct a new two‐lane road called US 17 Powerline Corridor from Vegas Boulevard to Radio Avenue to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Page 71: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

55  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

US 17 SR 15  Putnam  428  West of Dunn Creek Bridge  Horse Landing Road  Widen to 4 Lanes  SIS Unfunded 

Needs 

The project's purpose is to widen US 17 SR 15 to four lanes from West of Dunn Creek Bridge to Horse Landing Road to address congestion needs and improve mobility. 

The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process. 

US 17 SR 15  Putnam  429  CR 309 Satsuma  West of Dunn Creek Bridge  Widen to 4 Lanes  SIS Unfunded Needs 

The project's purpose is to widen US 17 SR 15 from CR 309 Satsuma to West of Dunn Creek Bridge to address congestion needs and improve mobility. 

The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process. 

US 17 SR 15  Putnam  430  Putnam/Volusia County Line  Pomona Park/Feagle Avenue  Widen to 4 Lanes  SIS Unfunded 

Needs 

The project's purpose is to widen to US 17 SR 15 to four lanes from the Putnam/Volusia County Line to Pomona Park/Feagle Avenue to address congestion needs and improve mobility. 

The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process. 

US 17 SR 15  Putnam  452  Pomona Park/Feagle Avenue  CR 309 Satsuma  Widen to 4 Lanes  SIS CFP 

The project's purpose is to widen US 17 SR 15 to four lanes from Pomona Park/Feagle Avenue to CR 309 Satsuma to address congestion needs and improve mobility. 

The project need was established in the SIS CFP and confirmed as part of the planning process. 

US 17 Yulee Backage Roads  Nassau  999  US 17 SR 5  North of Koen Lane  New 2 Lane Road  Local government coordination 

The project's purpose is to construct a new two‐lane road called the US 17 Yulee Backage Roads from US 17 SR 5 to North of Koen Lane to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Page 72: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

56  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

US 1B King Street  St Johns  1029  US 1 Ponce de Leon Boulevard  Avenida Menendez  Context Sensitive Solutions  St. Augustine 

Mobility Institute 

The project's purpose is to construct context sensitive solutions along US 1B King Street from US 1 Ponce de Leon Boulevard to Avenida Menendez to address congestion needs and improve mobility. 

The project need was established in the St. Augustine Mobility Institute and confirmed as part of the planning process. 

US 1B San Marco Avenue  St Johns  1030  Bridge of Lions  SR 16  Context Sensitive Solutions   St. Augustine Mobility Institute 

The project's purpose is to construct context sensitive solutions along US 1B San Marco Avenue from Bridge of Lions to SR 16 to address congestion needs and improve mobility. 

The project need was established in the St. Augustine Mobility Institute and confirmed as part of the planning process. 

US 301 SR 200  Duval  123  US 90  Duval/Nassau County Line  Widen to 4 Lanes  2035 Needs Plan 

The project's purpose is to widen US 301 SR 200 to four lanes from US 90 to Duval/Nassau County Line to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

US 301 SR 200  Clay  424  Clay/Bradford County Line  Duval/Clay County Line  Widen to 6 Lanes  SIS Unfunded Needs 

The project's purpose is to widen US 301 SR 200 to six lanes from the Clay/Bradford County Line to Duval/Clay County Line to address congestion needs and improve mobility. 

The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process. 

US 301 SR 200  Nassau  708  US 1 at S Kings Road     Intersection Improvements  Local government coordination 

The project's purpose is to construct intersection improvements along US 301 SR 200 from US 1 at South Kings Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Page 73: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

57  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

US 301 SR 200  Duval  425  Duval/Clay County Line  I‐10  Widen to 6 Lanes  SIS Unfunded Needs 

The project's purpose is to widen US 301 SR 200 to six lanes from Duval/Clay County Line to I‐10 to address congestion needs and improve mobility. 

The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process. 

US 90 / SR 115 Mathews Bridge  Duval  79  Alt. US 1 MLK Jr. Parkway  SR 109 University Boulevard  New 6 Lane Bridge and Transit  2035 Needs Plan 

The project's purpose is to reconstruct the US 90 / SR 115 Mathews Bridge as a six lane bridge and provide transit accommodations from Alt. US 1 MLK Jr. Parkway to SR 109 University Boulevard to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

US 90 Beaver Street  Duval  6  SR 23 First Coast Expressway  Cahoon Road  Widen to 4 Lanes  2035 Needs Plan 

The project's purpose is to widen US 90 Beaver Street to four lanes from SR 23 First Coast Expressway to Cahoon Road to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

US 90 Beaver Street  Duval  7  Cahoon Road  McDuff Avenue  Widen to 4 Lanes  2035 Needs Plan 

The project's purpose is to widen US 90 Beaver Street to four lanes from Cahoon Road to McDuff Avenue to address congestion needs and improve mobility. 

The project need was established in the 2035 Needs Plan and confirmed as part of the planning process. 

Various SR 200 Intersections Modifications  Nassau  981        Intersection Improvements  Local government 

coordination 

The project's purpose is to construct intersection improvements along SR 200 at various locations to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Page 74: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

58  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Veterans Parkway  St Johns  834  Greenbriar Road  Longleaf Pine Parkway  New 4 Lane Road Other Local Government Priority 

The project's purpose is to construct a new four‐lane road called Veterans Parkway from Greenbriar Road to Longleaf Pine Parkway to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Wells Road  Clay  910  Aquarius Concourse  SR 21 Blanding Boulevard  Reconstruct and New 2 Lane Road 

Other Local Government Priority 

The project's purpose is to reconstruct Wells Road and construct new two‐lane road extension of Wells Road from Aquarius Concourse to SR 21 Blanding Boulevard to address congestion needs and improve mobility. 

The project need was established in the Other Local Government Priority and confirmed as part of the planning process. 

Woodbridge Parkway Extension  Nassau  997  Woodbrigde Parkway  Clements Road  New 2 Lane Road  Local government 

coordination 

The project's purpose is to construct a new two‐lane road called Woodbridge Parkway Extension from Woodbrigde Parkway to Clements Road to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Yellow Bluff Road  Duval  956  Starratt Road  New Berlin Road (north)  Widen to 4 Lanes  Local government coordination 

The project's purpose is to widen Yellow Bluff Road from Starratt Road to New Berlin Road (north) to address congestion needs and improve mobility. 

The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process. 

Transit Capacity Projects 

East First Coast Flyer  Duval  2385  Downtown Jacksonville (Duval County)  3rd Street (Jacksonville Beach)  BRT  Blueprint 2020 

and 2035 LRTP 

This project's purpose is to provide higher quality bus services throughout the region. 

The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process. 

Page 75: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

59  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Southwest First Coast Flyer  Duval  2386  Wells Road  Downtown Jacksonville (Duval County)  BRT  Blueprint 2020 

and 2035 LRTP 

This project's purpose is to provide higher quality bus services throughout the region. 

The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process. 

SR 134  103rd Street   Duval  2321  SR 228  Normandy Boulevard    SR 21  Blanding Boulevard    BRT  Blueprint 2020 

and 2035 LRTP 

This project's purpose is to provide higher quality bus services throughout the region. 

The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process. 

SR 21  Blanding Boulevard    Clay  2308  CR 218  Wells Road  BRT  Blueprint 2020 and 2035 LRTP 

This project's purpose is to provide higher quality bus services throughout the region. 

The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process. 

SR 228  Normandy Boulevard    Duval  2322  SR 134 103rd Street  Downtown Jacksonville (Duval County)  BRT  Blueprint 2020 

and 2035 LRTP 

This project's purpose is to provide higher quality bus services throughout the region. 

The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process. 

US 1   Duval  2324  Lewis Speedway (St. John's County)  Avenues Mall (Duval County)  BRT  Blueprint 2020 

and 2035 LRTP 

This project's purpose is to provide higher quality bus services throughout the region. 

The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process. 

Page 76: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

60  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

US 1   St. John's   2375  Lewis Speedway (St. John's County)  Avenues Mall (Duval County)  BRT  Blueprint 2020 

and 2035 LRTP 

This project's purpose is to provide higher quality bus services throughout the region. 

The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process. 

US 1/SR 15  New Kings Road    Duval  2323  Downtown Jacksonville (Duval County)  Edgewood Avenue  BRT  Blueprint 2020 

and 2035 LRTP 

This project's purpose is to provide higher quality bus services throughout the region. 

The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process. 

SR 115  Southside Boulevard   Duval  2325  Avenues Mall  Regency Square Mall  BRT   Blueprint 2020 and 2035 LRTP 

This project's purpose is to provide higher quality bus services throughout the region. 

The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process. 

I‐95  Duval  2326  Gateway Mall  Jacksonville International Airport  BRT    Blueprint 2020 and 2035 LRTP 

This project's purpose is to provide higher quality bus services throughout the region. 

The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process. 

North (CSX)  Duval   2356  Downtown Jacksonville (Duval County)  Yulee (Nassau County)  Commuter Rail  Blueprint 2020 

and 2035 LRTP 

The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region. 

The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process. 

Page 77: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

61  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

North Extension (CSX)  Nassau  2366  Yulee  Fernandina Beach  Commuter Rail  Blueprint 2020 and 2035 LRTP 

The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region. 

The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process. 

Northwest (CSX)  Duval   2357  Downtown Jacksonville (Duval County)  Callahan (Nassau County)  Commuter Rail  Blueprint 2020 

and 2035 LRTP 

The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region. 

The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process. 

Southeast (FEC)  Duval  2327  St. Augustine (St. John's County) 

Downtown Jacksonville (Duval County)  Commuter Rail  Blueprint 2020 

and 2035 LRTP 

The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region. 

The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process. 

Southeast Extension (FEC)  St. John's   2377  Palm Coast (Flagler County)  City of St. Augustine  Commuter Rail  Blueprint 2020 

and 2035 LRTP 

The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region. 

The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process. 

Southwest (CSX)  Duval   2358  Green Cove Springs (Clay County) 

Downtown Jacksonville (Duval County)  Commuter Rail  Blueprint 2020 

and 2035 LRTP 

The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region. 

The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process. 

Page 78: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

62  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Southwest Extension (CSX)  Clay   2319  Palatka (Putnam County)  Green Cove Springs (Clay County)  Commuter Rail  Blueprint 2020 and 2035 LRTP 

The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region. 

The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process. 

West (CSX)  Duval  2328  Baldwin (Duval County)  Downtown Jacksonville (Duval County)  Commuter Rail  Blueprint 2020 

and 2035 LRTP 

The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region. 

The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process. 

West Extension (CSX)  Baker  2301  MacClenny (Baker County)  Baldwin (Duval County)  Commuter Rail  Blueprint 2020 

and 2035 LRTP 

The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region. 

The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process. 

I‐95  Duval  2330  Downtown Jacksonville (Duval County)  Yulee (Nassau County)  Express Bus Service  Blueprint 2020  

The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region. 

The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process. 

Cumberland Island Ferry  Nassau  2369  Fernandina  Cumberland Island  Ferry Service  Nassau County 

The project's purpose is to provide direct access to Cumberland Island from Florida allowing travelers to avoid crossing the St. Mary's River to access this National Park. 

The need for this project was identified based on the Florida East Coast Greenway study and confirmed as part of the planning process. 

Page 79: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

63  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

SR A1A  St Johns River Ferry   Duval  2331        Ferry Slip Replacement  St. Johns River Ferry Commission 

This project's purpose is to provide safer and more efficient operations of the St. Johns River Ferry.  The project will replace the ferry slips. 

The need for this project was identified through coordination with the St. Johns River Ferry Commission and confirmed as part of the planning process. 

SR A1A  St Johns River Ferry   Duval  2329        Drydock /  Ferry Repairs  St. Johns River Ferry Commission 

This project's purpose is to provide safer and more efficient operations of the St. Johns River Ferry. 

The need for this project was identified through coordination with the St. Johns River Ferry Commission and confirmed as part of the planning process. 

SR A1A  St Johns River Ferry   Duval  2333  Ft. George/Mayport     Long Term Site Improvements  St. Johns River Ferry Commission 

This project's purpose is to provide safer and more efficient operations of the St. Johns River Ferry by improving the vehicular access and storage. 

The need for this project was identified through coordination with the St. Johns River Ferry Commission and confirmed as part of the planning process. 

SR A1A  St Johns River Ferry   Duval  2344  JPA Property  Mayport Terminal  Relocation of Ferry offices  St. Johns River Ferry Commission 

This project's purpose is to provide safer and more efficient operations of the St. Johns River Ferry by improving the vehicular access and storage. 

The need for this project was identified through coordination with the St. Johns River Ferry Commission and confirmed as part of the planning process. 

SR A1A  St Johns River Ferry   Duval  2345  Mayport  Ft. George Island  Service & Capital Improvements 

St. Johns River Ferry Commission 

This project's purpose is to provide safer and more efficient operations of the St. Johns River Ferry by improving the vehicular access and storage and long‐term service. 

The need for this project was identified through coordination with the St. Johns River Ferry Commission and confirmed as part of the planning process. 

Page 80: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

64  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

SR A1A  St Johns River Ferry   Duval  2346  Ft. George/Mayport     Site Improvements  St. Johns River Ferry Commission 

This project's purpose is to provide safer and more efficient operations of the St. Johns River Ferry by improving the vehicular access and storage with short‐term enhancements. 

The need for this project was identified through coordination with the St. Johns River Ferry Commission and confirmed as part of the planning process. 

Area wide ****  Putnam  2374        Local Bus Service  Blueprint 2020  

This project's purpose is to provide local bus service throughout the region to enhance accessibility and mobility choices. 

The need for this project was identified through coordination with local governments and confirmed as part of the planning process. 

US 90  Baker  2302  MacClenny (Baker County) 

Downtown Jacksonville (Duval County)  Local Bus Service  Blueprint 2020  

This project's purpose is to provide local bus service throughout the region to enhance accessibility and mobility choices. 

The need for this project was identified through coordination with local governments and confirmed as part of the planning process. 

Area wide ****  Baker  2303        Local Bus Service   Blueprint 2020  

This project's purpose is to provide local bus service throughout the region to enhance accessibility and mobility choices. 

The need for this project was identified through coordination with local governments and confirmed as part of the planning process. 

Area wide ****  Clay  2310        Local Bus Service   Blueprint 2020  

This project's purpose is to provide local bus service throughout the region to enhance accessibility and mobility choices. 

The need for this project was identified through coordination with local governments and confirmed as part of the planning process. 

Page 81: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

65  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Area wide ****  Duval  2332        Local Bus Service   Blueprint 2020  

This project's purpose is to provide local bus service throughout the region to enhance accessibility and mobility choices. 

The need for this project was identified through coordination with local governments and confirmed as part of the planning process. 

Area wide ****  Nassau  2370        Local Bus Service   Blueprint 2020  

This project's purpose is to provide local bus service throughout the region to enhance accessibility and mobility choices. 

The need for this project was identified through coordination with local governments and confirmed as part of the planning process. 

Area wide ****  St. John's   2378        Local Bus Service   Blueprint 2020  

This project's purpose is to provide local bus service throughout the region to enhance accessibility and mobility choices. 

The need for this project was identified through coordination with local governments and confirmed as part of the planning process. 

Anastasia Island (Amphitheatre)  St. John's   2380        Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide off‐site parking for the Amphitheatre to provide additional transit access. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

Center Street  Duval  2304  North of Drew Street (Baldwin)     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

Page 82: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

66  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

CR 210  St. John's   2381  east of US 1     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

CR 220  Doctors Inlet Road   Clay  2316  at Hollow Road     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

Drew Street  Duval  2305  at Center Street (Baldwin)     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

Duval Road  Duval  2336  at I‐95     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

Mayport Road  Duval  2338  at SR A1A     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

Page 83: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

67  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Racetrack Road   St. John's   2382  at US 1     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

South of Glen St. Mary  Baker  2306        Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

SR 115   Lem Turner Road   Duval  2337  at SR 104 Dunn Avenue     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

SR 115   Lem Turner Road   Duval   2361  at Soutel      Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

SR 115   Lem Turner Road   Duval   2362  at I‐295     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

Page 84: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

68  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

SR 134  103rd Street   Duval  2334  at SR 228  Normandy Boulevard       Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

SR 16***  St. John's   2385        Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

SR 200  SR A1A    Nassau  2371  at I‐95     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

SR 200  SR A1A    Nassau  2372  east of Yulee     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

SR 207***  St. John's   2386        Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

Page 85: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

69  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

SR 21  Blanding Boulevard    Clay  2311  at Tanglewood     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

SR 21  Blanding Boulevard    Clay  2312  at Old Jennings Road     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

SR 21  Blanding Boulevard    Clay  2313  at Edson Drive     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

SR 21  Blanding Boulevard    Clay  2314  at Wells Road     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

SR 21  Blanding Boulevard    Clay  2315  at SR 224 Kingsley Avenue     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

Page 86: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

70  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

SR 21  Blanding Boulevard    Clay  2318  North and South of Bolton Road     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

SR 21  Blanding Boulevard    Duval  2335  at Weconnett Boulevard     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

SR 21  Blanding Boulevard    Duval  2340  North and South of Wilson Boulevard     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

SR 21  Blanding Boulevard    Duval  2341  North and South of SR 134 103rd Street     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

SR 21  Blanding Boulevard    Duval   2360  at 105th Street     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

Page 87: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

71  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

SR 21  Blanding Boulevard    Duval   2364  North of I‐295     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

SR A1A  Duval  2343  North and South of SR 202 J. T. Butler Boulevard     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

SR A1A  St. John's   2379  at Palm Valley Road     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

St. Augustine Airport  St. John's   2383        Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

US 1  St. John's   2384  at Lewis Speedway Road     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

Page 88: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

72  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

US 1/SR 15  New Kings Road    Duval   2363  Timucuan DRI     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

US 17  Roosevelt Boulevard   Clay   2320  at Wells Road     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

US 17  Roosevelt Boulevard   Duval  2342  at SR 128 San Juan Avenue     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

US 90  Beach Boulevard   Duval  2339  West and East of Kernan Boulevard     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

US 90  Beach Boulevard   Duval   2359  at San Pablo Road     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

Page 89: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

73  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Yellow Water Road  Duval  2307  North of I‐10     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

Youngerman Circle  Clay  2317  at Argyle Forest Boulevard     Park and Ride Lots  Blueprint 2020  

The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT. 

The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process. 

Five Points/Core/Brooklyn  Duval  2347  Central Station  Brooklyn  Station   Skyway Extension **  Blueprint 2020 and 2035 LRTP 

The project's purpose is to provide an extension of the Automated Skyway Express to the Five Points and Brooklyn neighborhoods from the urban core. 

The need for enhanced transit service to these areas was confirmed through the planning process.  ** The specific technology that will be the efficient and cost effective to provide this service will be determined in subsequent Alternatives Analysis phases. 

Southbank/San Marco  Duval  2348  Kings Avenue Station  Southwest  of Railroad Tracks (Southbank)  Skyway Extension **  Blueprint 2020 

and 2035 LRTP 

The project's purpose is to provide an extension of the Automated Skyway Express to the Southbank and San Marco neighborhoods from the urban core. 

The need for enhanced transit service to these areas was confirmed through the planning process.  ** The specific technology that will be the efficient and cost effective to provide this service will be determined in subsequent Alternatives Analysis phases. 

Downtown ‐ Sports Complex  Duval  2349  Downtown Jacksonville (Bay Street & Main Street)  Jacksonville Municipal Stadium  Streetcar **  Blueprint 2020 

and 2035 LRTP 

The project's purpose is to provide a streetcar or other fixed‐guideway transit service to the Downtown Sports Complex neighborhoods from the urban core. 

The need for enhanced transit service to these areas was confirmed through the planning process.  ** The specific technology that will be the efficient and cost effective to provide this service will be determined in subsequent Alternatives Analysis phases. 

Page 90: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

74  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Five Points/Core/Brooklyn  Duval  2350  Five Points  Downtown Jacksonville (Bay Street & Main Street)  Streetcar **  Mobility 2030 

Plan 

The project's purpose is to provide a new streetcar service to the Five Points and Brooklyn neighborhoods from the urban core. 

The need for enhanced transit service to these areas was confirmed through the planning process.  ** The specific technology that will be the efficient and cost effective to provide this service will be determined in subsequent Alternatives Analysis phases. 

La Villa/Core  Duval  2351  Transportation Center  Duval Street & Monroe Street to Ocean  Streetcar **  Mobility 2030 

Plan 

The project's purpose is to provide a new streetcar service to the La Villa neighborhood from the urban core. 

The need for enhanced transit service to these areas was confirmed through the planning process.  ** The specific technology that will be the efficient and cost effective to provide this service will be determined in subsequent Alternatives Analysis phases. 

Riverside/Avondale  Duval  2352  Riverside (King Street)  Five Points  Streetcar **  Mobility 2030 Plan 

The project's purpose is to provide a new streetcar service to the Riverside and Avondale neighborhoods from the urban core. 

The need for enhanced transit service to these areas was confirmed through the planning process.  ** The specific technology that will be the efficient and cost effective to provide this service will be determined in subsequent Alternatives Analysis phases. 

Southbank/San Marco  Duval  2353  Kings Avenue Station  Baptist Hospital / MOSH & Atlantic Boulevard  Streetcar **  Mobility 2030 

Plan 

The project's purpose is to provide a new streetcar service to the Southbank and San Marco neighborhoods from the urban core. 

The need for enhanced transit service to these areas was confirmed through the planning process.  ** The specific technology that will be the efficient and cost effective to provide this service will be determined in subsequent Alternatives Analysis phases. 

Springfield  Duval  2354  FSCJ Station  8th Street/ Medical Complex  Streetcar **  Mobility 2030 Plan 

The project's purpose is to provide a new streetcar service to the Springfield neighborhood from the urban core. 

The need for enhanced transit service to these areas was confirmed through the planning process.  ** The specific technology that will be the efficient and cost effective to provide this service will be determined in subsequent Alternatives Analysis phases. 

Page 91: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

75  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Downtown Facility  Duval  2355        Transportation Center  Blueprint 2020 and 2035 LRTP 

This project's purpose is to construct a new Downtown Transit hub to integrate services between all modes. 

The need for the construction of a new Downtown transit hub was confirmed during the planning process. 

Transit Capacity Projects 

CSX Transportation  Clay  2200  at Wells Road     Grade Separation  SIS Multimodal Needs Plan 

This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow. 

The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion.  The need was confirmed as part of this planning process. 

CSX Transportation  Clay  2201  at SR 224 Kingsley Avenue     Grade Separation  SIS Multimodal Needs Plan 

This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow. 

The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion.  The need was confirmed as part of this planning process. 

CSX Transportation  Duval  2202  at SR 104  Busch Drive     Grade Separation  SIS Multimodal Needs Plan 

This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow. 

The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion. 

CSX Transportation  Nassau  2203  at SR A1A (SR 200) / Yulee     Grade Separation  SIS Multimodal Needs Plan 

This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow. 

The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion.  The need was confirmed as part of this planning process. 

Page 92: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

76  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

CSX Transportation  Duval  2204  Beaver Street Interlocking     Capacity Upgrade  SIS Multimodal Needs Plan 

This project's purpose is to improve capacity at the Beaver Street interlock to enhance service reliability. 

The need for this project was identified based on coordination with railroads during the development of the SIS Multimodal Plan. The need was confirmed as part of this planning process. 

CSX Transportation  Duval  2205  North Rail Corridors Phase 1  Multi Modal Corridor North Rail Corridor Feasibility Study 

This project's purpose is the construct a new rail connector to reduce rail traffic through downtown which will improve safety.  The project will also enhance rail access to the Dames Point and Blount Island terminals. 

The need for this project was identified based on coordination with railroads during the development of the SIS Multimodal Plan. The need was confirmed as part of this planning process. 

CSX Transportation  Duval  2206  Westlake Cecil Commerce Connector  Multi Modal Corridor  SIS Multimodal Needs Plan 

This project's purpose is the enhance access to the Westlake and Cecil Commerce center to support economic development. 

The need for this project was identified based on coordination with railroads during the development of the SIS Multimodal Plan. The need was confirmed as part of this planning process. 

Florida East Coast Railway  Duval  2207  at Bowden Intermodal     Capacity Upgrade  SIS Multimodal Needs Plan 

This project's purpose is to improve track capacity near the Bowden Intermodal Yard to reduce rail crossing blockings and enhance service quality. 

The need for this project was identified based on coordination with railroads during the development of the SIS Multimodal Plan. The need was confirmed as part of this planning process. 

Florida East Coast Railway  Duval  2208  at Jacksonville Bridge     Bridge  SIS Multimodal Needs Plan 

The project will provide repairs and train control technologies on the St. Johns River bridge. 

The need for this project was identified based on coordination with railroads during the development of the SIS Multimodal Plan. The need was confirmed as part of this planning process. 

Page 93: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

77  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Jacksonville International Airport  Duval  2209  Construction of Runway 7R/25L  Construct Runway  SIS Multimodal 

Needs Plan This project will construct a new parallel runway to meet future demand. 

The project need was identified as part of the Jacksonville International Airport's planning process. The need was confirmed as part of this planning process. 

Jacksonville International Airport  Duval  2210  Air Cargo Ramp Improvements  Expand Apron  SIS Multimodal 

Needs Plan This project will construct additional air cargo capacity to meet future demand. 

The project need was identified as part of the Jacksonville International Airport's planning process. The need was confirmed as part of this planning process. 

Jacksonville International Airport  Duval  2211  Air Cargo Surface Storage     Expand Apron  SIS Multimodal 

Needs Plan This project will construct additional air cargo capacity to meet future demand. 

The project need was identified as part of the Jacksonville International Airport's planning process. The need was confirmed as part of this planning process. 

Jacksonville International Airport  Duval  2212  Design & Construct By‐Pass Taxiways  Construct Taxiway  SIS Multimodal 

Needs Plan 

This project will construct by‐pass taxiways to improve the operational efficiencies. 

The project need was identified as part of the Jacksonville International Airport's planning process. The need was confirmed as part of this planning process. 

Jacksonville International Airport  Duval  2213  Intermodal Terminal Facility Development  Terminal Development  SIS Multimodal 

Needs Plan This project will construct additional air cargo capacity to meet future demand. 

The project need was identified as part of the Jacksonville International Airport's planning process. The need was confirmed as part of this planning process. 

Page 94: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

78  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Norfolk Southern  Duval  2214  at Norfolk Southern Railway (Near Simpson Yard)  Grade Separation NS CSX SIS Intermodal Connector PD&E 

This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow. 

The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion. The need was confirmed as part of this planning process. 

Jacksonville Port Authority  Duval  2215  Blount Island / Dames Point Marine Terminals Rail  Internal Rail  JAXPORT Master Plan 

This project will provide additional on‐dick rail capacity to meet future demand. 

The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process. 

Jacksonville Port Authority  Duval  2216  Blount Island Marine Terminal Berth Upgrades  Docks  JAXPORT Master Plan 

This project will provide additional capacity at berths in the Blount Island marine terminal to improve efficiencies and meet future demand. 

The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process. 

Jacksonville Port Authority  Duval  2217  Blount Island Marine Terminal Facility Upgrades  Intermodal Transfer Improvement 

JAXPORT Master Plan 

This project will provide on‐dock rail capacity at berths in the Blount Island marine terminal to improve efficiencies and meet future demand. 

The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process. 

Jacksonville Port Authority  Duval  2218  Dames Point Marine Terminal Berth Upgrades  Docks  JAXPORT Master Plan 

This project will provide additional capacity at berths in the Blount Island marine terminal to improve efficiencies and meet future demand. 

The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process. 

Page 95: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

79  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Jacksonville Port Authority  Duval  2219  Dames Point Marine Terminal Facility Upgrades  Intermodal Transfer Improvement 

JAXPORT Master Plan 

This project will provide gates and other facilities within the marine terminal to improve efficiencies and meet future demand. 

The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process. 

Jacksonville Port Authority  Duval  2220  New Cranes for Talleyrand and Blount Island Marine Terminals  Intermodal Transfer Improvement 

JAXPORT Master Plan 

This project will provide new cranes to meet future demand at the port. 

The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process. 

Jacksonville Port Authority  Duval  2221  Talleyrand Marine Terminal Berth Upgrades  Docks  JAXPORT Master Plan 

This project will provide additional capacity at berths in the Talleyrand marine terminal to improve efficiencies and meet future demand. 

The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process. 

Jacksonville Port Authority  Duval  2222  Talleyrand Marine Terminal Facility Upgrades  Intermodal Transfer Improvement 

JAXPORT Master Plan 

This project will provide gates and other facilities within the marine terminal to improve efficiencies and meet future demand. 

The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process. 

Jacksonville Port Authority  Duval  2223  Talleyrand Marine Terminal Rail  Internal Rail  JAXPORT Master Plan 

This project will provide on‐dock rail capacity at berths in the Blount Island marine terminal to improve efficiencies and meet future demand. 

The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process. 

Page 96: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

80  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Jacksonville Port Authority  Duval  2224  Blount Island Marine Terminal Facility Upgrades  Intermodal Transfer Improvement 

JAXPORT Master Plan 

This project will provide gates and other facilities within the marine terminal to improve efficiencies and meet future demand. 

The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process. 

Jacksonville Port Authority  Duval  2225  Dames Point Marine Terminal Facility Upgrades  Intermodal Transfer Improvement 

JAXPORT Master Plan 

This project will provide gates and other facilities within the marine terminal to improve efficiencies and meet future demand. 

The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process. 

Jacksonville Port Authority  Duval  2226  New Cranes for Talleyrand and Blount Island Marine Terminals  Intermodal Transfer Improvement 

JAXPORT Master Plan 

This project will provide new cranes to meet future demand at the port. 

The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process. 

Jacksonville Port Authority  Duval  2227  Talleyrand Marine Terminal Facility Upgrades  Intermodal Transfer Improvement 

JAXPORT Master Plan 

This project will provide gates and other facilities within the marine terminal to improve efficiencies and meet future demand. 

The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process. 

Jacksonville Port Authority  Duval  2228  Blount Island / Dames Point Terminals ‐ Rail and Bridge  Internal Rail  JAXPORT Master Plan 

This project will provide on‐dock rail capacity at berths in the Blount Island marine terminal to improve efficiencies and meet future demand. 

The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process. 

Page 97: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

81  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Jacksonville Port Authority  Duval  2229  Blount Island Marine Terminal Berth Upgrades  Docks  JAXPORT Master Plan 

This project will provide additional capacity at berths in the marine terminal to improve efficiencies and meet future demand. 

The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process. 

Jacksonville Port Authority  Duval  2230  Blount Island Marine Terminal Facility Upgrades  Intermodal Transfer Improvement 

JAXPORT Master Plan 

This project will provide gates and other facilities within the marine terminal to improve efficiencies and meet future demand. 

The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process. 

Jacksonville Port Authority  Duval  2231  Dames Point Marine Terminal Berth Upgrades  Docks  JAXPORT Master Plan 

This project will provide additional capacity at berths in the marine terminal to improve efficiencies and meet future demand. 

The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process. 

Jacksonville Port Authority  Duval  2232  Dames Point Marine Terminal Facility Upgrades  Intermodal Transfer Improvement 

JAXPORT Master Plan 

This project will provide gates and other facilities within the marine terminal to improve efficiencies and meet future demand. 

The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process. 

Jacksonville Port Authority  Duval  2233  Harbor Deepening     Dredging Harbor  JAXPORT Master Plan 

This project will deepen the St. Johns River main channel to 48‐ft to meet demand for post‐Panamax ships. 

The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process. 

Page 98: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

82  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Jacksonville Port Authority  Duval  2234  New Cranes for Talleyrand and Blount Island Marine Terminals  Intermodal Transfer Improvement 

JAXPORT Master Plan 

This project will provide new cranes to meet future demand at the port. 

The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process. 

Jacksonville Port Authority  Duval  2235  Talleyrand Marine Terminal Berth Upgrades  Docks  JAXPORT Master Plan 

This project will provide additional capacity at berths in the marine terminal to improve efficiencies and meet future demand. 

The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process. 

Jacksonville Port Authority  Duval  2236  Talleyrand Marine Terminal Facility Upgrades  Intermodal Transfer Improvement 

JAXPORT Master Plan 

This project will provide gates and other facilities within the marine terminal to improve efficiencies and meet future demand. 

The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process. 

Jacksonville Port Authority  Duval  2237  Talleyrand Marine Terminal Rail  Internal Rail  JAXPORT Master Plan 

This project will provide on‐dock rail capacity at berths in the Blount Island marine terminal to improve efficiencies and meet future demand. 

The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process. 

CSX Transportation  Duval/Baker  2238  MacClenny  to Jacksonville     Upgrade to Accommodate 

Freight and Passenger Service*  Blueprint 2020 This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs. 

The need for additional track capacity to accommodate freight and transit operations was identified in the SIS Multimodal Needs Plan and confirmed through the Blueprint 2020 and Commuter Rail feasibility studies. 

Page 99: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

83  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

CSX Transportation  Duval/Clay  2239  Green Cove Springs to Jacksonville  Upgrade to Accommodate Freight and Passenger Service  Blueprint 2020 

This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs. 

The need for additional track capacity to accommodate freight and transit operations was identified in the SIS Multimodal Needs Plan and confirmed through the Blueprint 2020 and Commuter Rail feasibility studies. 

CSX Transportation  Duval/Nassau  2240  Jacksonville to Yulee     Upgrade to Accommodate Freight and Passenger Service  Blueprint 2020 

This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs. 

The need for additional track capacity to accommodate freight and transit operations was identified in the SIS Multimodal Needs Plan and confirmed through the Blueprint 2020 and Commuter Rail feasibility studies. 

Florida East Coast Railway  Duval/St. Johns  2241  St. Augustine to Jacksonville  Upgrade to Accommodate Freight and Passenger Service  Blueprint 2020 

This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs. 

The need for additional track capacity to accommodate freight and transit operations was identified in the SIS Multimodal Needs Plan and confirmed through the Blueprint 2020 and Commuter Rail feasibility studies. 

CSX Transportation  Duval  2242  at US 301 SR 200  Baldwin     Grade Separation    This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow. 

The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion. 

CSX Transportation  Nassau  2243  at US 301  Crawford Diamond  Grade Separation    This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow. 

The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion. The need was confirmed as part of this planning process. 

Page 100: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

84  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Port of Fernandina  Nassau  2244  Berth Improvements     Docks  Port Master Plan 

This project will provide additional capacity at berths in the marine terminal to improve efficiencies and meet future demand. 

The need for the project was defined during the development of the OHPA Master Plan. The need was confirmed as part of this planning process. 

Port of Fernandina  Nassau  2245  Cruise / Cargo Berth     Docks  Port Master Plan The project will construct new berths needed to accommodate cruise and larger cargo ships. 

The need for the project was defined during the development of the OHPA Master Plan. The need was confirmed as part of this planning process. 

Port of Fernandina  Nassau  2246  Rail Track Improvements     Internal Rail  Port Master Plan  This project will enhance near‐dock and on‐dock rail services. 

The need for the project was defined during the development of the OHPA Master Plan. The need was confirmed as part of this planning process. 

Port of Fernandina  Nassau  2247  at Fernandina Port     Access Improvements  Port Master Plan 

This project's purpose is to improve truck access to the port within the context of the historic district in Fernandina. 

The need for the project was defined during the development of the OHPA Master Plan. The need was confirmed as part of this planning process. 

City of Palatka  Putnam  2248  SR 100 CR 309D     Runway expansion  SIS Multimodal Needs Plan 

This project's purpose is to expand the runway. 

The need for the project was defined during the development of airport master plan. The need was confirmed as part of this planning process. 

Page 101: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

85  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Nassau County  Putnam  2249  Barge Port     Operational and Capital Improvements 

SIS Multimodal Needs Plan 

This project's purpose is to construct capital improvements to improve the operations at the port. 

The need for the project was defined during the development of airport master plan. The need was confirmed as part of this planning process. 

CSX Transportation  Putnam  2250  at  SR 15 Reid Street     Grade Separation  SIS Multimodal Needs Plan 

This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow. 

The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion. 

City of Saint Augustine  St. Johns  2251  Historic Commercial Areas     Mobility & Distribution Improvements 

SIS Multimodal Needs Plan 

This project's purpose is to develop strategies to improve parking management within the historic district of St. Augustine. 

The need was identified by the City of St. Augustine. The need was confirmed as part of this planning process. 

Florida East Coast Railway  Statewide  2252  Amtrak Service Miami to Jacksonville  New Passenger Service  SIS Multimodal Needs Plan 

This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs. 

The need was identified through the SIS Multimodal Needs Plan. The need was confirmed as part of this planning process. 

Florida East Coast Railway  Statewide  2253  Miami to Jacksonville Upgrade Bolt and Clip System  Track Upgrade  SIS Multimodal Needs Plan 

This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs. 

The need was identified through the SIS Multimodal Needs Plan. The need was confirmed as part of this planning process. 

Page 102: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

86  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Intercity Passenger Rail  Statewide  2254  New Orleans to Jacksonville  New Passenger Service  SIS Multimodal Needs Plan 

This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs. 

The need was identified through the SIS Multimodal Needs Plan. The need was confirmed as part of this planning process. 

Intercity Passenger Rail  Statewide  2255  Jacksonville to Savannah     New Passenger Service  SIS Multimodal Needs Plan 

This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs. 

The need was identified through the SIS Multimodal Needs Plan. The need was confirmed as part of this planning process. 

Intercity Passenger Rail  Statewide  2256  Orlando to Jacksonville     New Passenger Service  SIS Multimodal Needs Plan 

This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs. 

The need was identified through the SIS Multimodal Needs Plan. The need was confirmed as part of this planning process. 

Norfolk Southern  Duval  2257  Soutel Drive to Norfolk Southern Intermodal Yard  New Connector  SIS Multimodal Needs Plan 

This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs. 

The need was identified through the NS CSX SIS Connector study performed by FDOT to improve access and operations of the Norfolk Southern intermodal yard.  

CSX Transportation  Duval  2258  North Rail Corridors Phase 2  Multi Modal Corridor North Rail Corridor Feasibility Study 

The purpose of this project is to consider extensions of the North Rail corridor and to construct a two‐lane roadway within the corridor right of way. 

This need was identified through the freight capacity analysis performed in the LRTP to address future rail and truck access needs. The need was confirmed as part of this planning process. 

Page 103: 2040 LRTP Appendix K: Needs Plan Project Costs Purpose and Need

87  

Table 2. Project Purpose and Need Statements for Major Capacity Projects 

Facility  County  Map ID  From  To  Improvement Type  Source  Purpose  Need 

Florida East Coast Railway  Duval  2259  at Sunbeam Road      Grade Separation  SIS Multimodal Needs Plan 

This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow. 

The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion. The need was confirmed as part of this planning process. 

Downtown Transportation Center  Duval  2355  Downtown Facility     Transportation Center  SIS Multimodal 

Needs Plan 

This project's purpose is to construct a downtown intermodal facility where multiple transit modes can be connected. 

This project's need was identified in the 2035 LRTP and confirmed as part of the Blueprint 2020 plan to provide greater systems integration of the transit modes. The need was confirmed as part of this planning process. 

Jacksonville Port Authority  Duval  1006  Spoil Island Connector Bridge  New 2 Lane Bridge 

New need identified in the 2040 LRTP by JAXPORT. 

This project's purpose is to construct a new bridge for the management and distribution of spoil material associated with dredging the St. Johns River. 

The need for this project was identified by JAXPORT as an opportunity to better manage spoil and reduce environmental impacts.  

Florida East Coast Railway  Duval  2260  at Shad Road     Grade Separation New need identified in the 2040 LRTP. 

This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow. 

The need for this project was identified through a process which included an analysis of the safety record and crossroad congestion.  

Intermodal Logistics Center        Intermodal Logistics Center     New capacity 

New need identified in the 2040 LRTP. 

This project's purpose is to construct an intermodal logistics center in North Florida to improve rail efficiencies and the interchange of intermodal traffic between railroads and over the road trucking. 

The need for this project was identified as part of the rail system capacity analysis performed during the planning process.  

 