Powerpoint template demo 18 July 2011 Yarra Valley Water Ltd 1 Yarra Valley Water Stormwater Harvesting Projects Asoka Jayaratne Water Quality Specialist 12 May 2011 Merrifield and Coburg Developments 400Ha industrial/commercial site zoned comprehensive development zone (CDZ2) being developed by MAB Corporation Potential recycled water users: > 3,655 apartments > 345 houses > 33 Ha of public open space Merrifield (Kalkallo) Stormwater Harvesting Project UGB – Northern Investigation Area Kalkallo Wallan Greenvale Craigieburn Epping North Mernda / Doreen Whittlesea Yan Yean Reservoir Greenvale Reservoir Western Water Yarra Valley Water Investigation Area Boundary Current Urban Growth Boundary Where is Merrifield Industrial Development? Merrifield Development (410Ha) Folkestone Development (320Ha) Kalkallo Township Relative Size Of The MCG (1/18 Of The Catchment) Wallan Melbourne What Does The Development Site Look Like Now? Photo taken prior to completion of Donnybrook Road overpass (now completed) Donnybrook Road N

Upload: others

Post on 03-Dec-2019

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Yarra Valley Water Stormwater Harvesting Projects · 18 July 2011 Yarra Valley Water Ltd 14 Coburg Principal Activity Centre Stormwater Harvesting And Reuse Project Issues Every developer

Powerpoint template demo

18 July 2011 Yarra Valley Water Ltd 1

Yarra Valley Water Stormwater Harvesting Projects

Asoka Jayaratne

Water Quality Specialist

12 May 2011

Merrifield and Coburg Developments

400Ha industrial/commercial site

zoned comprehensive development zone (CDZ2)

being developed by MAB Corporation

Potential recycled water users:

> 3,655 apartments

> 345 houses

> 33 Ha of public open space

Merrifield (Kalkallo) Stormwater Harvesting Project

UGB – Northern Investigation Area

Kalkallo

Wallan

Greenvale

Craigieburn

Epping North

Mernda / Doreen

Whittlesea

Yan Yean

Reservoir

Greenvale

Reservoir

Western Water

Yarra Valley Water

Investigation Area

Boundary

Current Urban

Growth Boundary

Where is Merrifield Industrial Development?

Merrifield Development

(410Ha)

Folkestone Development

(320Ha)

Kalkallo

Township

Relative Size Of The MCG

(1/18 Of The Catchment)

Wallan

Melbourne

What Does The Development Site Look Like Now?

Photo taken prior to completion of Donnybrook Road overpass

(now completed)

Donnybrook Road

N

Page 2: Yarra Valley Water Stormwater Harvesting Projects · 18 July 2011 Yarra Valley Water Ltd 14 Coburg Principal Activity Centre Stormwater Harvesting And Reuse Project Issues Every developer

Powerpoint template demo

18 July 2011 Yarra Valley Water Ltd 2

What Will It Look Like At Full Development?

The development will predominately include office, warehousing

and logistics, and light manufacturing industries

The wetland will be a key feature of the development

N

Where Will We Collect Stormwater From?

Merrifield Development

(410Ha)

Folkestone Development

(320Ha)

160Ha Catchment Area

We Will Collect

Stormwater From

Kalkallo

Township

Wallan

Melbourne

STEP 1

Street drains collect rainfall and

direct it to a series of treatment ponds and wetlands which

remove pollutants

STEP 2

The partially treated rainfall

enters a large wetland for further pollutant removal

STEP 3

The wetland overflows into a

large open storage dam

Main Wetland

Overflows To Creek

Storage Dam

STEP 4

Stormwater is pumped from the

storage dam into a state of the art treatment plant which is

capable of producing a drinking

water quality product

STEP 5

The treated water is stored in a

tank and tested to prove it has met the required treatment

standard

STEP 6

Once the quality is confirmed,

the water is released into supply

Release Into Supply

How Will It Work?

Stormwater

Tre

ated

Wat

er

Wetlands and

treatment ponds

Tanks where water

is stored and tested

prior to release

Dilution with

existing water

supply

Development

Storage dam

Lamella Plate

Separator

Advanced Oxidation

& Chlorination

Coagulation /

Ultra-filtration

Reverse Osmosis

Stormwater Treatment Plant

How Will We Manage The Risks Of Contaminating The Drinking Water Supply?

Coagulant

Ultra-filtration

Reverse Osmosis

UV / Advanced

Oxidation

Chlorination

Alkali addition

Fluoridation

Batch Tank

Lamella Plate

Separator

B4, V4, P4

B3, V3, P0

Proposed treatment process:

• Bacteria = 10 log

• Viruses = 8 log

• Protozoa = 7 log

Normal Class A process:

• Viruses = 7 log

• Protozoa = 6 log

What Does the Planned Treatment Process Look Like?

CATCHMENT

SUPPLY

Wetlands and storage basin

(aerated storage)

B1, V1, P1

B2, V0, P2

Removes Algal Solids to Protect UF

Pre-validated to reduce virus & protozoa.With coagulation will remove colour, P, and Heavy metals to low concentrations.

Pre-validated to reduce virus & protozoa.Removes trace organics, taste, odour, color.Removes salt, heavy metals, N & P.

Pre-validated to reduce protozoa. Removes trace organics – pesticides & pharmaceuticals.

Pre-validated to reduce bacteria & virus.

Where do we get the LRV?Process

step

Critical limit value LRV Possible Virus LRV

(validated)

Protozoa

LRV

(validated)

Bacteria LRV

(validated)

Wetlands/

Storage dam

0.5 0 0 0

Coag-UF Pressure Test 4 or 3 (cost

both)

4 4

RO EC, TOC,

Fluorescence (new

tech), measure

concentrate

2 to 6 0 (but could be

better with new

tech)

UV-AOP

H2O2

Defined from

Chem assessment

2 to 4 (cost

options)

4 4

Cl2 4 0 4

Total 9 to 12 8 12

Required

Class A

3 3 3

Required

Potable

6 6 618 July 2011 12Yarra Valley Water Ltd

Page 3: Yarra Valley Water Stormwater Harvesting Projects · 18 July 2011 Yarra Valley Water Ltd 14 Coburg Principal Activity Centre Stormwater Harvesting And Reuse Project Issues Every developer

Powerpoint template demo

18 July 2011 Yarra Valley Water Ltd 3

Overview of Hazard Screening

� Tier 1 Screening – Hazard Identification through major

lit review ( ~ 3000)

� Tier 2 Screening. Filtering based on:

• Chemical attributes (~ 1500 )

• Presence in Australia (~700)

� Tertiary Screening: Additional filters based on likelihood

of presence and expert opinion

� Residual hazards to control and/or monitor (≈ 100 ?)

� > 55,000,000 substances registered to date

� >100,000 substances in industry

and commerce – Many potential

stormwater contaminants

Filtering Results

18 July 2011 14Yarra Valley Water Ltd

Coburg Principal Activity Centre

Stormwater Harvesting And Reuse Project

Issues

� Every developer wants to do something different:

• Small to large scale stormwater harvesting proposals

• Building scale black/grey water treatment plants

� YVW is best placed to deliver a whole of PAC solution:

• Economies of scale

• Water company experienced with management and operation of

similar schemes

• More likely to be able to source necessary funding

Coburg Stormwater Harvesting Project – Areas To Be Serviced

Potential recycled water users:

> 3,655 apartments

> 345 houses

> 33 Ha of public open space

Stormwater

Storm

water

Storm

water

Recycled Water

Underground

stormwater

storage tank

Ultra filtration

using

membranes

Rec

ycle

d W

ater

Tre

atm

ent

Pla

nt

Above ground

storage tank Development

(new and existing)

Merri Creek

Flow

diversion and

screening for fats,

greases, oils and

large solids

Existing

drainage

system

(pipes)

Stormwater

UV disinfection

Rec

ycle

d W

ater

ChlorinationScreens to

remove fine

solids

Schematic Of How Stormwater Will Be Harvested And Reused

Page 4: Yarra Valley Water Stormwater Harvesting Projects · 18 July 2011 Yarra Valley Water Ltd 14 Coburg Principal Activity Centre Stormwater Harvesting And Reuse Project Issues Every developer

Powerpoint template demo

18 July 2011 Yarra Valley Water Ltd 4

Impact On McDonald Reserve And Surrounds

Underground

Storage Tank

(18ML)

Diversion 1

Diversion 2

Proposed Underground Storage Tank Solution

Considering the use of the “Humes Stormtrap” product or equivalent

Reinforced concrete box culverts laid on top of each other

Provides incredibly strong structure with 100+ year lifespan