E. Rivers Elementary School Atlanta Public Schools Weekly Construction Progress Report WEEKLY CONSTRUCTION PROGRESS REPORT Project: E Rivers Elementary School Week Ending: February 1, 2014 THIS WEEK: Brent Scarbrough & Co. completed backfill of SMF 1 Scarbrough continued storm sewer installation, including storm line E. Ely Concrete placed concrete at building foundation wall from Col Line 1 to CL 15. Ely formed portion of radius at Wall A2.

Upload: ledien

Post on 12-Mar-2018

229 views

Category:

Documents


10 download

TRANSCRIPT

Page 1: WEEKLY CONSTRUCTION PROGRESS  · PDF fileE. Rivers Elementary School Atlanta Public Schools Weekly Construction Progress Report WEEKLY CONSTRUCTION PROGRESS REPORT

E. Rivers Elementary School Atlanta Public Schools

Weekly Construction Progress Report

WEEKLY CONSTRUCTION PROGRESS REPORT

Project: E Rivers Elementary School Week Ending: February 1, 2014 THIS WEEK:

Brent Scarbrough & Co. completed backfill of SMF 1 

Scarbrough continued storm sewer installation, including storm line E. 

Ely Concrete placed concrete at building foundation wall from Col Line 1 to CL 15. 

Ely formed portion of radius at Wall A2.    

 

   

 

   

  

Page 2: WEEKLY CONSTRUCTION PROGRESS  · PDF fileE. Rivers Elementary School Atlanta Public Schools Weekly Construction Progress Report WEEKLY CONSTRUCTION PROGRESS REPORT

E. Rivers Elementary School Atlanta Public Schools

Weekly Construction Progress Report

WEEKLY CONSTRUCTION PROGRESS REPORT

  

  

      

  

  

      

Page 3: WEEKLY CONSTRUCTION PROGRESS  · PDF fileE. Rivers Elementary School Atlanta Public Schools Weekly Construction Progress Report WEEKLY CONSTRUCTION PROGRESS REPORT

E. Rivers Elementary School Atlanta Public Schools

Weekly Construction Progress Report

WEEKLY CONSTRUCTION PROGRESS REPORT

NEXT WEEK – FEBRUARY 2-FEBRUARY 8: Place concrete at radius portion of wall A2. 

Begin wall forming at building foundation wall.  

Begin spread footing layout – lower level foundations. 

Continue underground utility installation, including san sewer line 2.    

SCHEDULED DATE OF SUBSTANTIAL COMPLETION

December 2014.    PREPARED BY: 

Paul Miley, Parrish Construction 

 COPIES TO: 

Danny Gutlay, APS 

Sandy Cooper, CCCA 

Brett Norton, CCCA 

Margarita Perez, CCCA  

Jim Fallon, Parrish Construction  

Art Cofelice, Parrish Construction 

Parrish Construction – Job File