weekly construction progress · pdf filee. rivers elementary school atlanta public schools...
TRANSCRIPT
E. Rivers Elementary School Atlanta Public Schools
Weekly Construction Progress Report
WEEKLY CONSTRUCTION PROGRESS REPORT
Project: E Rivers Elementary School Week Ending: February 1, 2014 THIS WEEK:
Brent Scarbrough & Co. completed backfill of SMF 1
Scarbrough continued storm sewer installation, including storm line E.
Ely Concrete placed concrete at building foundation wall from Col Line 1 to CL 15.
Ely formed portion of radius at Wall A2.
E. Rivers Elementary School Atlanta Public Schools
Weekly Construction Progress Report
WEEKLY CONSTRUCTION PROGRESS REPORT
E. Rivers Elementary School Atlanta Public Schools
Weekly Construction Progress Report
WEEKLY CONSTRUCTION PROGRESS REPORT
NEXT WEEK – FEBRUARY 2-FEBRUARY 8: Place concrete at radius portion of wall A2.
Begin wall forming at building foundation wall.
Begin spread footing layout – lower level foundations.
Continue underground utility installation, including san sewer line 2.
SCHEDULED DATE OF SUBSTANTIAL COMPLETION
December 2014. PREPARED BY:
Paul Miley, Parrish Construction
COPIES TO:
Danny Gutlay, APS
Sandy Cooper, CCCA
Brett Norton, CCCA
Margarita Perez, CCCA
Jim Fallon, Parrish Construction
Art Cofelice, Parrish Construction
Parrish Construction – Job File