weekly construction progress report crawford long … · 7/29/2016  · weekly construction...

4
WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 29th, 2016 Page 1 of 4 Prepared For: Atlanta Public Schools Prepared By: Austin Nichols Aerial View Aerial View Aerial View Auditorium Terrazzo

Upload: others

Post on 15-Oct-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long … · 7/29/2016  · WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 29th, 2016 Page 4 of 4 o Finish punch

WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 29th, 2016

Page 1 of 4

Prepared For: Atlanta Public Schools

Prepared By: Austin Nichols

Aerial View Aerial View

Aerial View Auditorium Terrazzo

Page 2: WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long … · 7/29/2016  · WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 29th, 2016 Page 4 of 4 o Finish punch

WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 29th, 2016

Page 2 of 4

Admin Entrance Canopy Lighting

LED Sign Auditorium Sidewalk

Last Week’s Activities:

• Classroom Addition

o Finished installing tack boards and whiteboards

o Continued punch

• Auditorium

o Continued installing terrazzo

• Administration Addition

o Finished Installing terrazzo

o Finished painting

o Finished installing carpet

o Finished installing casework

Page 3: WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long … · 7/29/2016  · WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 29th, 2016 Page 4 of 4 o Finish punch

WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 29th, 2016

Page 3 of 4

• Administration Renovation

o Finished painting

o finished installing VCT

o Finished installing carpet

o Finished installing casework

• Gym Renovation

o Continued installing waste and vent

o Continued MEP overhead rough in new classrooms

o Began installing new doors in lower level

This Week’s Activities:

• Classroom Addition

o Completed punch

• Auditorium

o Finished installing terrazzo

• Administration Addition

o Began punch

o Installed tack boards

o Installed corner guard

• Administration Renovation

o Began punch

o Installed corner guard

o Waxed VCT

• Gym Renovation

o Finished painting lower level

o Finished hanging doors in lower level

Next Week’s Activities:

• Classroom Addition

o Final coats of wax

• Auditorium

o Finish installing coiling door

o Finish installing lights

• Administration Addition

o Finish punch

o Finish installing security system

o Finish pouring sidewalk

• Administration Renovation

Page 4: WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long … · 7/29/2016  · WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 29th, 2016 Page 4 of 4 o Finish punch

WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 29th, 2016

Page 4 of 4

o Finish punch

• Gym Renovation

o Wax lower level

o Continue MEP rough in

Schedule:

• Status: Weather dependent

• Substantial Completion Dates:

o Classroom Addition: July 15, 2016

o Renovations: July 20, 2016

o Administration Addition: August 1, 2016

o Track and Field: September 1, 2016

o Auditorium Addition: September 7, 2016

o Gym Renovation: October 7, 2016

• Final Completion: December 31, 2016

Budget:

• Construction Budget: $15,920,000

• Budget Status: On Budget

• Gross Billed To Date: $10,118,024