New North Atlanta High School Weekly Construction Report October 26, 2012 NNAHS Weekly Progress Report October 26, 2012 Page 1 THIS WEEK October 19, 2012 – October 26, 2012 Lakeside Building: Completion in July, 2013 Floating scaffolding nearing completion (top left). Drywall being hung with insulation on the 2 nd floor (top right). Third floor walls being framed around in wall plumbing rough in (bottom left). Third floors HVAC units set and connected to the overhead duct (bottom right).

Upload: others

Post on 21-Jun-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: New North Atlanta High School Weekly Construction Report ... · New North Atlanta High School Weekly Construction Report October 26, 2012 NNAHS Weekly Progress Report October 26,

New North Atlanta High School

Weekly Construction Report October 26, 2012

NNAHS Weekly Progress Report October 26, 2012 Page 1

THIS WEEK October 19, 2012 – October 26, 2012

Lakeside Building: Completion in July, 2013

Floating scaffolding nearing completion (top left). Drywall being hung with insulation on the 2nd floor (top right). Third floor walls being framed around in wall plumbing rough in (bottom left). Third floors HVAC units set and connected to the overhead duct (bottom right).

Page 2: New North Atlanta High School Weekly Construction Report ... · New North Atlanta High School Weekly Construction Report October 26, 2012 NNAHS Weekly Progress Report October 26,

New North Atlanta High School

Weekly Construction Report October 26, 2012

NNAHS Weekly Progress Report October 26, 2012 Page 2

Lakeside Building Cont’d: Completion in July, 2013 Existing CEP equipment being removed from the Lakeside Building by crane (top left). New window openings cut into the 4th floor exterior – west face of Lakeside (top right). Lakeside CMU shafts and existing duct being demolished (bottom left). SLC stair opening cut into the 11th floor (bottom right).

Page 3: New North Atlanta High School Weekly Construction Report ... · New North Atlanta High School Weekly Construction Report October 26, 2012 NNAHS Weekly Progress Report October 26,

New North Atlanta High School

Weekly Construction Report October 26, 2012

NNAHS Weekly Progress Report October 26, 2012 Page 3

Hillside Building: Completion in December, 2013 JE Dunn Construction sign hanging from the Hillside Building (top left). Explosives and connections wired to the Hillside columns (top right). Trailer with explosives staged in the Hillside Building (bottom left) Column wired with explosives (bottom right).

Page 4: New North Atlanta High School Weekly Construction Report ... · New North Atlanta High School Weekly Construction Report October 26, 2012 NNAHS Weekly Progress Report October 26,

New North Atlanta High School

Weekly Construction Report October 26, 2012

NNAHS Weekly Progress Report October 26, 2012 Page 4

Hillside Building Cont’d: Completion in December, 2013 Dynamite gel ready for cap and casing (top left). Dynamite being placed in casing (top right). Test blast performed on column (bottom).

Page 5: New North Atlanta High School Weekly Construction Report ... · New North Atlanta High School Weekly Construction Report October 26, 2012 NNAHS Weekly Progress Report October 26,

New North Atlanta High School

Weekly Construction Report October 26, 2012

NNAHS Weekly Progress Report October 26, 2012 Page 5

Lean Construction: Finish trades participating in JE Dunn’s second Lean Construction Boot Camp for NNAHS

(below).

Page 6: New North Atlanta High School Weekly Construction Report ... · New North Atlanta High School Weekly Construction Report October 26, 2012 NNAHS Weekly Progress Report October 26,

New North Atlanta High School

Weekly Construction Report October 26, 2012

NNAHS Weekly Progress Report October 26, 2012 Page 6

NEXT WEEK

October 22, 2012 – October 29, 2012

1st floor glazing will continue being installed.

2nd floor drywall will continue being hung.

Floating scaffolding will finish being erected and moved under the Lakeside Building.

Wall framing will continue on the 2nd and 3rd floors.

MEP in wall rough in will finish on the 2nd floor and begin on the 3rd floor.

MEP overhead rough in will continue on the 3rd and 4th floors.

Wall layout and MEP layout will continue on the 3rd, 4th, and 5th floors.

Window systems will continue being installed on the 2nd, 3rd, and 4th floors.

11th floor SLC stair cutout will be finished.

Asbestos abatement will begin on the 9th floor of the Lakeside Building.

Interior demolition will continue on the upper floors of Lakeside.

The Hillside Building remains (rubble and debris) will begin being hauled off site for

recycling and reuse.

Site-work layout for the new Hillside Building will begin.

KEY UPCOMING DATES Next OAC Meeting 10/31/12 @ 10:00 am at jobsite office

Hillside Building Implosion – 10/27/12

Page 7: New North Atlanta High School Weekly Construction Report ... · New North Atlanta High School Weekly Construction Report October 26, 2012 NNAHS Weekly Progress Report October 26,

New North Atlanta High School

Weekly Construction Report October 26, 2012

NNAHS Weekly Progress Report October 26, 2012 Page 7

IMPLOSION The much anticipated implosion of the old IBM building on the New North Atlanta High School project is

almost here! If you would like to join us this Saturday, October 27th, here are the specifics:

Everyone must arrive before 7:00am (6:30 is recommended). For safety reasons, the gates will be closed and locked at 7:00am sharp, no exceptions.

There will be personnel directing traffic onsite, but you can reference the below logistics plan for the parking and viewing area locations.

The actual implosion blast is planned for approximately 7:30am if the winds and weather cooperate. If the winds are not favorable, it will be delayed and nobody will be allowed to leave until the implosion has occurred.

The implosion will be loud. Bring ear plugs if you have them (if you forget, we have some extra onsite).

The implosion will produce a lot of dust, which may get pushed towards the viewing area.

For those of you who may not be able to attend the viewing, here is a link to our webcam which has live

video feed.

https://mds.multivista.com/index.cfm?fuseaction=webcampub.page&wcpp=c08b2d6f-e46a-4d9e-acd8-7225facb4c23