Walden Athletic Complex Atlanta Public Schools Weekly Construction Progress Report WEEKLY CONSTRUCTION PROGRESS REPORT Project: Walden Athletic Complex Week Ending: January 10, 2018 THIS WEEK: Demolition of existing building completed Underground Plumbing finishing Underground Electrical finishing Installation of lighting/netting pole bases Backfill after demolition of existing building Storm Sewer continuing Floor trench drains being installed Backfill after demolition of existing building Underslab plumbing and electrical Lighting/Netting Pole bases installed

Upload: others

Post on 21-Jun-2020

64 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: WEEKLY CONSTRUCTION PROGRESS REPORT · Weekly Construction Progress Report WEEKLY CONSTRUCTION PROGRESS REPORT NEXT WEEK – Jan 11 thru Jan 18: Prepping field house slab Pouring

Walden Athletic Complex

Atlanta Public Schools Weekly Construction Progress Report

WEEKLY CONSTRUCTION PROGRESS REPORT

Project: Walden Athletic Complex Week Ending: January 10, 2018 THIS WEEK:

Demolition of existing building completed 

Underground Plumbing finishing 

Underground Electrical finishing 

Installation of lighting/netting pole bases 

Backfill after demolition of existing building 

Storm Sewer continuing   

 

Floor trench drains being installed 

 

 

 

 

 

 

 

 

 

 

 

Backfill after demolition of existing building 

 

 

 

 

 

 

 

 

 

 

 

 

 

Underslab plumbing and electrical  

 

 

 

 

 

 

 

 

 

 

 

Lighting/Netting Pole bases installed 

 

 

 

 

 

 

 

 

 

 

 

 

Page 2: WEEKLY CONSTRUCTION PROGRESS REPORT · Weekly Construction Progress Report WEEKLY CONSTRUCTION PROGRESS REPORT NEXT WEEK – Jan 11 thru Jan 18: Prepping field house slab Pouring

Walden Athletic Complex Atlanta Public Schools

Weekly Construction Progress Report

WEEKLY CONSTRUCTION PROGRESS REPORT

 

 

 

 

NEXT WEEK – Jan 11 thru Jan 18: Prepping field house slab 

Pouring field house slab 

Backfill continuing  

Storm and sewer work continuing 

Surveying for retaining wall base   Budget and Schedule Construction Budget:  $7,390,000.00 Progress Earned:  $0  Budget Status:    On Budget Completion Date:  August 8, 2018 (Substantial Completion) Schedule Status:  On Schedule  SCHEDULED DATE OF SUBSTANTIAL COMPLETION

August 8, 2018.  PREPARED BY: 

Chris Hubbard, Parrish Construction 

 COPIES TO: 

George Harkness, APS 

Michael Wright, Eberly & Associates 

Scott Griffin, Eberly & Associates 

John Rood, Parrish Construction 

Dave Yuhas, Parrish Construction  

Eric Wise, Parrish Construction 