VENICE REFINERY LOGISTIC REBIRTH PROJECT

Temporary Business Association (“A.T.I.”)Set up by TECMA Srl (as Lead Contractor)

and by PIVER Srl and MARCATO SpA

Page 2: VENICE REFINERY LOGISTIC REBIRTH PROJECT - Tecma

Venice Refinery - Logis tic Rebirth Project

Page 3: VENICE REFINERY LOGISTIC REBIRTH PROJECT - Tecma

Venice Refinery - Logis tic Rebirth Project

Page 4: VENICE REFINERY LOGISTIC REBIRTH PROJECT - Tecma

Venice Refinery - Logis tic Rebirth Project

Scope of Work:Change of Service from Crude Oil to Refined Products

Sulphur content < 10 ppmSaybolt colour scale < 20 units difference

S. Leonardo Oil terminal 12” - 16” – 30”

Off-shore and on-shore pipeline 42” x 12 Km

Petroleum tank Island 20” - 24” – 30”

“Spaghetti” pipelines loop 16”

Page 5: VENICE REFINERY LOGISTIC REBIRTH PROJECT - Tecma

Venice Refinery - Logis tic Rebirth Project

Page 6: VENICE REFINERY LOGISTIC REBIRTH PROJECT - Tecma

S. Leonardo Oil Terminal

Pier / jetty

Load / unload arms

Load / unload arms

Page 7: VENICE REFINERY LOGISTIC REBIRTH PROJECT - Tecma

S. Leonardo Oil Terminal

Pier / jetty

Load / unload arms

Load / unload arms

•Pre - cleaned with hot water and special solvents•Flushed with refined products

Page 8: VENICE REFINERY LOGISTIC REBIRTH PROJECT - Tecma

S. Leonardo Oil te rmina l cleaning

The Tanker discharge took place alternatively from Mooring North

through each manifold loading arm;

Mooring North

Page 9: VENICE REFINERY LOGISTIC REBIRTH PROJECT - Tecma

S. Leonardo Oil te rmina l cleaning

The Tanker discharge took place alternatively from Mooring South

through each manifold loading arm;

Mooring South

Page 10: VENICE REFINERY LOGISTIC REBIRTH PROJECT - Tecma

S. Leonardo Oil te rmina l cleaning

30” Loop was cleaned by flushing hot water and finished products

30” loop

Page 11: VENICE REFINERY LOGISTIC REBIRTH PROJECT - Tecma

42” Sub-Lagoon Crude oil Pipeline preventive Inspection

from S. Leonardo Oil Terminal to the Petroleum Island (12 Km)

Courtesy of GE- PII

•Preventive MFL inspection•Corrosion Growth Assessment •Integrity assessment

Page 12: VENICE REFINERY LOGISTIC REBIRTH PROJECT - Tecma

42” Sub-Lagoon Crude oil Pipeline Cleaning & Change of Service

Product Batch Lenght 1,7 Km: Crude- Virgin Naptha- Diesel Fuel

Page 13: VENICE REFINERY LOGISTIC REBIRTH PROJECT - Tecma

Petroleum Tank Is land - Venice Refinery

Page 14: VENICE REFINERY LOGISTIC REBIRTH PROJECT - Tecma

Petroleum Tank Is land - Venice Refinery

Page 15: VENICE REFINERY LOGISTIC REBIRTH PROJECT - Tecma

Petroleum Tank Is land - Venice Refinery

Page 16: VENICE REFINERY LOGISTIC REBIRTH PROJECT - Tecma

Petroleum Tank Is land - Venice Refinery

Page 17: VENICE REFINERY LOGISTIC REBIRTH PROJECT - Tecma

•Preventive MFL inspection•Corrosion Growth study•Integrity assessment

16” Canal Crossing multi service “Spaghetti” pipelines

Courtesy of GE- PII

Page 18: VENICE REFINERY LOGISTIC REBIRTH PROJECT - Tecma

16” Canal Crossing multi service “Spaghetti” pipelines

• Cleaning• Change of Service

Page 19: VENICE REFINERY LOGISTIC REBIRTH PROJECT - Tecma

16” - 24”- 30” Pipeline Network on Petroleum Island

Installations & non piggable sections (expansion joints, jump over, drains, Pumps, Tees, etc.)

•Pre - cleaned with hot water and organic solvents•Flushed with refined products

Page 20: VENICE REFINERY LOGISTIC REBIRTH PROJECT - Tecma

16” - 24”- 30” Pipeline Network - Petroleum Island

Piggable sections

Cleaned with brush pigs pumped hot water and with refined products

Page 21: VENICE REFINERY LOGISTIC REBIRTH PROJECT - Tecma

Venice Refinery Logis tic Rebirth Project

Cleaning Pigs :- Flexible steel body pig, equipped with conical cups and tuft brushes- Heavy Duty special steel body Bi-di pig equipped with tuft brushes - Poly Pig medium density, reinforced with criss cross brushes

Page 22: VENICE REFINERY LOGISTIC REBIRTH PROJECT - Tecma

Venice Refinery Logis tic Rebirth Project

Procedure •Recover of residual crude oil •Water rinsing•Mechanical modifications•Hot water and solvent cleaning•Temporary trap installation•Cleaning by Pigging •Flushing with refined products (3,800 m3 Virgin Naphtha + 3,800 m3 Diesel)

General12”x 0,5 Km 16” x 1 Km20” x 1 Km 24” x 2 Km30” x 3 Km42” x 12 Km

Verified measured results: Sulphur content = 8 ppm

Saybolt colour scale = 5 units difference

Page 23: VENICE REFINERY LOGISTIC REBIRTH PROJECT - Tecma

VENICE REFINERY LOGISTIC REBIRTH PROJECT

Raffaele Zaffaroni