transport network reconstruction program safer roads surfaces disaster recovery panel session 16 may...

27
Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

Upload: erin-summers

Post on 02-Jan-2016

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

Transport Network Reconstruction Program

Safer Roads SurfacesDisaster recovery panel

session16 May 2011

Page 2: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

TNR Program vision

• Connecting Queensland – the Transport Network Reconstruction Program will restore our flood damaged transport network on time and in a safe and efficient manner.

Page 3: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

Setting the scene: 2010 – 2011 events

2010 events:• Cyclones Olga, Neville, Ului and Paul

Jan-Apr 2010• SW Queensland Flooding Sep 2010• SE Queensland Flooding Oct 2010

2011 events:• Queensland Flooding and TC Tasha Jan 2011• Severe TC Yasi Feb 2011• Queensland Monsoonal Flooding Mar 2011

Page 4: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

Damage across the State(at 30 April 2011)

• 28% (approx 9,170 km) of road network damaged by 2010 and 2011 weather events – road network suffered more damage than any other asset

• 29% of the rail network affected• 89 bridges and culverts damaged• 5% of TMR’s Brisbane cycle network and

5% of Cairns cycle network affected

Page 5: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

Types of damage

Cecil Plains East

Pavement damage – approx 85%

Page 6: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

Types of damage

Murphy’s Creek Road

Damage to bridges, culverts and floodways – approx 5%

Page 7: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

Types of damage

Damage due to slope instability – approx 10%

New England Highway, Mt Kynoch

Page 8: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

Types of damage

Esk Hampton Road

Page 9: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

$860M

$910M

$184M

$77M

$405M

$175M

$425M

$333M

$303M

$78M$468M

$142M

$4.36 billion statewide= $161 million per month

2011 events = $2.9 billion

Summary estimated damage (2011 dollars)

Page 10: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

Our historical and forecast expenditure (based on 2011 dollars)

Current NDRRA Program

TMR NDRRA Annual Expenditure

$18 $18 $28 $33 $25 $15 $12 $26 $18 $49 $50 $50

$227

$507

$2,221

$2,001

$0

$500

$1,000

$1,500

$2,000

$2,500

1997

-98

1998

-99

1999

-00

2000

-01

2001

-02

2002

-03

2003

-04

2004

-05

2005

-06

2006

-07

2007

-08

2008

-09

2009

-10

2010

-11

2011

-12

2012

-13

$ (M

illio

n)

Order of magnitude 100 times what’s been done before= $161 million per month

Page 11: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

NDRRA funding

Where does NDRRA funding come from?

• 75% of works reimbursed by Australian government

• 25% of works funded by State government • Emergency Management Australia (EMA)

administers NDRRA funding on behalf of the Australian government

• Queensland Reconstruction Authority (QldRA) and Emergency Management Queensland (EMQ) coordinate NDRRA funding in Queensland

Page 12: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

Australian Reconstruction Inspectorate

The Australian Reconstruction Inspectorate will:• scrutinise rebuilding contracts• directly inspect projects to ensure they are

meeting progress milestones• investigate complaints or issues raised by the

public• work directly with state reconstruction agencies to

develop contractual frameworks, tendering processes and project management systems

• scrutinise requests for reimbursement by local government for projects completed for the purpose of reconstruction

• examine high value of complex projects prior to execution

Page 13: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

State Government response

• Queensland Reconstruction Authority (QRA) established to reconnect, rebuild and improve Queensland communities and the economy.

• Six lines of reconstruction: Human and Social Economic Environment Building Road and Transport Communication and Engagement.

• QRA reports to the Premier. • Focus is on performance, quality, safety and

value for money.

Page 14: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

Governance

RoadtekRoadtek

Infrastructure Investment Committee

Infrastructure Investment Committee

TNRP Steering CommitteeTNRP Steering Committee

SPOSPO

RPOsRPOs

Contracting Community

Tier 1 / Other / Local Contractors

Contracting Community

Tier 1 / Other / Local ContractorsLocal GovernmentLocal Government

QRAQRA

The CommunityThe Community

Page 15: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

TMR Response

• Established Transport Network Reconstruction Program.

• Part of TMR QTRIP.• All modes

o roado railo portso maritime.

• Established statewide program office and regional project offices.

• TNR Program reports to the Queensland Reconstruction Authority.

Page 16: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

Statewide Program Office

• Key functions of the SPO include:o implementing consistent strategies,

systems and processes across the program

o statewide coordination of critical contractor and material resources

o statewide prioritisation of projectso liaison with key internal and external

stakeholders on program issueso program monitoring and reporting.

Page 17: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

Regional Project Offices

• The RPOs will work within existing TMR regional structure to deliver regional reconstruction programs, including:o design and specification of the workso obtain relevant approvals – environmental, cultural

heritageo develop, tender and award construction packageso undertake contract management including field

supervision, inspection and testingo project cost control, schedule control, progress

measurement and reporting at a regional level.

Page 18: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

Program delivery structureProgram Steering

Committee

Statewide Program Office

Program Director

South West

Regional Project Office

Northern

Regional Project Office

*Darling Downs &

Metro Regional Project Office

North West

Regional Project Office

Fitzroy Regional Project Office

Far North

Regional Project Office

South Coast

Regional Project Office

Central West

Regional Project Office

North Coast

Regional Project Office

Wide Bay/

Burnett Regional Project Office

Mackay / W’sday Regional Project Office

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

Construction

Contractor

* Represents 2 regions under 1 RPO

Page 19: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

Program timeframes

• Emergent works:• 60 days from declaration of NDRRA

Event• complete end April 2011.

• Reconstruction works:• all works to be completed by June 2014.

Page 20: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

Contracting philosophy

• Utilise local capability.• Ensure long term sustainability of local

industry.• Utilise major contractors to supplement

local industry.• Major contractors bring in staff, facilities

and equipment (self sustainable).• All contractors must be prequalified with

TMR.

Page 21: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

Three-pronged approach:• Roadtek and LGAs (average $20M and $5M respectively)

- sole invitation- benchmarked performance.

• Competitively tendered packages of values $5M to $50M to small to medium regionally based prequalified contractors

- rolling program 2nd and 3rd tranche- benchmarked performance.

• Competitively tendered large works packages of values $100M to $250M to large prequalified contractors

- rolling program 2nd tranche- benchmarked performance.

Contracting strategy

Page 22: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

Anticipated delivery by sector 2011-2014 (statewide)

Councils10%

RoadTek30%

Regional contractors20%

Major contractors40%

Page 23: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

Product Amount

Bitumen > 200,000 T

Granular Material > 10,500,000 T

Asphalt > 500,000 T

Cement > 225,000 T

Stabilisers > 70 (TBC)

Estimate of statewide Material and Plant requirements

Page 24: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

Materials strategy

• Leveraging existing TMR statewide supply agreements for bitumen and cement.

• Undertaking regional and statewide supply and demand analyses.

• Materials shortages potentially delivered under principal-supplied arrangements.

• Logistics solutions required.• Immediately pre-invest in and stockpile

non-perishable materials.

Page 25: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

Current status

• Regional Project Offices completed logging of damage• Submissions are being developed:

> $1.2B (2011)> $1.7B (2010)

• RPOs developing works packages and program.• 7 contractor information sessions held.• Emergent Works ≈ $287M completed.• Initial contracts have been awarded ≈ $423M.• Packages with market for tendering ≈ $318M.• Finalised second round of shortlisted contractors for

packages > $30M.• Finalise Statewide Program by end June 2011.• Finalising materials procurement strategy and commencing

negotiations with suppliers.

Page 26: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

Questions

Page 27: Transport Network Reconstruction Program Safer Roads Surfaces Disaster recovery panel session 16 May 2011

Current status

• 72% (approx 6627km) of damaged roads recovered• 93% of affected rail network reopened • 76% of navigational aids recovered• 72% of damaged bridges and culverts recovered• all ports open • all flood and cyclone-impacted school bus routes back

in service• all major freight routes reopened• all of TMR’s Brisbane and Cairns cycle network

recovered and operational