E-tender System ID : 31011

CORRIGENDUM NO. 1

TENDER FOR

IMPLEMENTATION OF

ASSET INTEGRITY MANAGEMENT SYSTEM (AIMS)

AT BPCL GROUP REFINERIES

E-Tender System ID: 31011

Page 2: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender System ID : 31011

1.0 SCOPE OF THIS CORRIGENDUM

1.1 This Corrigendum 1 is issued to clarify queries raised by bidders for the abovementioned

tender.

1.2 Except for details mentioned herein, all other details contained in the abovementioned tender enquiry, shall remain applicable and unchanged.

2.0 EXTENSION OF BID SUBMISSION DATE

2.1 The extended due date for submission of bids is 11:00 Hrs IST of 22.12.2017. 3.0 TECHNICAL QUERIES

3.1 BPCL response to the technical queries raised by bidders has been attached. 4.0 NON-TECHNICAL / COMMERCIAL / LEGAL QUERIES

4.1 BPCL response to the commercial queries raised by bidders has been attached. 4.2 With response to Non-Technical / Legal Queries, bidders are requested to abide by the BPCL tender terms and conditions. No additional or counter offer/condition/meaning is acceptable at this stage of tendering.

Page 3: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries

Bidder Sr

No

Tender

Page

No

Clause

No

Clause Clause details Bidder's Query BPCL response to bidder's queries

Wipro 1 35 6 ANNEXURE-1- SCOPE OF WORK FOR BPCL

MR & KR

Work shop

shall be held at BPCL MR and KR

Workshop will be required at both the

place? MR & KR.

Few FDS workshops shall be conducted at MR

and few at KR.

Wipro 3 42 12 Implementation agency shall help BPCL to

select and create 30 Policies to take

intelligent actions based on the IOW limits

of Health Indicator

Implementation agency shall help BPCL to select and create 30 Policies to take

intelligent actions based on the IOW limits of Health Indicator

This will be performed by BPCL user with

our SME Support?

Implemenattion agency shall create 30 nos.

policies with support from BPCL team.

Wipro 4 39 B UPGRADE OF EXISTIING AIMS APM

SOFTWARE INCLUDING INSTALLATION OF

NEW MODULES OF APM SOFTWARE

ALONG WITH DATABASE MERGING FOR

MR AND KR

APM Interface with other source Current Implemented APM have these

interface ? What type of Data exchange is

required? Automatic or schedule synch.?

Currently, APM has interface with SAP solution.

Some data to be synchronized automatic, some

periodic and some scheduled.

Wipro 5 43 4 APM HEALTH Handholding shall start only after software go-live at all sites. Software go live

shall take place after successful completion of configuration and testing.

Handholding shall be carried out for the following:

a) Implementation agency shall configure the software for handheld device and

configure the interface with handle held device with Meridium and is for 30

numbers of routes having 10 nos. equipment in each route with 15 tags per

equipment.

b) The implementation agency shall handhold BPCL to create 15 health

indicators each for MR, KR & pipelines (total 45 nos.).

Is vendor responsible for Data collection

using Handheld devices?

Implementation agency shall configure the hand

held devices in APM, configure interfaces,

customizations if any and hand hold. However,

BPCL will carry the hand held devices to plant and

take data for which implementation agency shall

guide initially.

Wipro 6 55 B ANNEXURE-2 IMPLEMENTATION OF ALL MODULES OF APM SOFTWARE

Implementation Agency shall carry out Software Installation on Server

Operating System Windows Server 2012 or later version (64 Bit) and SQL

Server 2014 or later version (64 Bit) on Physical Server Hardware and/or

Virtual Server (on VMware/Citrix platform) and/or public cloud.

Operating System, Database and APM Software and required hardware will be

provided by BORL.

Do we need to consider the cloud cost for

DR setup?

No.

Wipro 7 67 28 RBI reference drawing and Documents Implementation agency shall carry out Risked Based Analysis (RBI) for HGU

and HCU- DHDT complex.

Approximate quantity of static equipment, P & ID, PFD / MFD is given as below.

Is it paper based P&ID or CAD format? Available in PDF format.

Wipro 35 Annexur

e 1

Scope of work- As per RFP Request deletion of "including…but not limited to" as this makes the scope open ended No change in tender clause.

Wipro 51 J SPECIAL CONDITIONS: The work days shall be

Monday to Friday for all sites unless otherwise

specified. In case of exigencies, working will be

extended on closed days and holidays without

extra cost.

The work days shall be Monday to Friday for all sites unless otherwise specified. In case

of exigencies, working will be extended on closed days and holidays without extra cost.

mutually agreed terms and conditions

No change in tender clause.

Page 4: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries

Bidder Sr

No

Tender

Page

No

Clause

No

Clause Clause details Bidder's Query BPCL response to bidder's queries

Wipro 52 J SPECIAL CONDITIONS:No accommodation, travel

assistance, food, lodging and boarding will be

provided to Implementation agency.

Implementation agency will have to arrange all

travel, food, and accommodation,

lodging/boarding at their cost to their staff on

the work of this tender or any other work

related to this tender.The quoted rates shall be

inclusive of above.

No change in tender clause.

Wipro 53 J SPECIAL CONDITIONS: Any modification to the

software and processes to resolve any issues at

a site shall be replicated at other sites, if

applicable, without any extra cost.

SPECIAL CONDITIONS: Any modification to the software and processes to resolve any

issues at a site shall be replicated at other sites, if applicable, without any extra cost.

mutually agreed terms and conditions

No change in tender clause.

Wipro 53 J SPECIAL CONDITIONS: There may be incidences

of work getting affected due to site team

members not available for some time due to

exigencies, emergencies and plant shutdowns

for a maximum period of one month.

Implementation agency shall

plan the activities accordingly such that there is

no involvement of our site member during such

period.

SPECIAL CONDITIONS: There may be incidences of work getting affected due to site team

members not available for some time due to exigencies, emergencies and plant

shutdowns for a maximum period of one month. Implementation agency shall

plan the activities accordingly such that there is no involvement of our site member

during such period. In such any delay caused due to non availability of site member

should be excluded for calculating LD penalty and BPCL will pay for any idle time that

has been created due to non availability of site member

No change in tender clause.

Wipro 53 J SPECIAL CONDITIONS:In case the work gets

affected due to some interface/software issues

resulting in idling of the resources of

implementation agency and/or rescheduling of

the jobs, no extra compensation will be made.

SPECIAL CONDITIONS:In case the work gets affected due to some interface/software

issues resulting in idling of the resources of implementation agency and/or rescheduling

of the jobs, no extra cost will be paid as compensation will be made.

No change in tender clause.

Wipro 73 J SPECIAL CONDITIONS: The work days shall be

Monday to Friday for all sites unless otherwise

specified. In case of exigencies, working will be

extended on closed days and holidays without

extra cost.

The work days shall be Monday to Friday for all sites unless otherwise specified. In case

of exigencies, working will be extended on closed days and holidays without extra cost.

mutually agreed terms and conditions

No change in tender clause.

Wipro 74 J SPECIAL CONDITIONS:No accommodation, travel

assistance, food, lodging and boarding will be

provided to Implementation agency.

Implementation agency will have to arrange all

travel, food, and accommodation,

lodging/boarding at their cost to their staff on

the work of this tender or any other work

related to this tender.The quoted rates shall be

inclusive of above.

No change in tender clause.

Wipro 74 J SPECIAL CONDITIONS: Any modification to the

software and processes to resolve any issues at

a site shall be replicated at other sites, if

applicable, without any extra cost.

SPECIAL CONDITIONS: Any modification to the software and processes to resolve any

issues at a site shall be replicated at other sites, if applicable, without any extra cost.

mutually agreed terms and conditions

No change in tender clause.

Page 5: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries

Bidder Sr

No

Tender

Page

No

Clause

No

Clause Clause details Bidder's Query BPCL response to bidder's queries

Wipro 74 J SPECIAL CONDITIONS: There may be incidences

of work getting affected due to site team

members not available for some time due to

exigencies, emergencies and plant shutdowns

for a maximum period of one month.

Implementation agency shall

plan the activities accordingly such that there is

no involvement of our site member during such

period.

SPECIAL CONDITIONS: There may be incidences of work getting affected due to site team

members not available for some time due to exigencies, emergencies and plant

shutdowns for a maximum period of one month. Implementation agency shall

plan the activities accordingly such that there is no involvement of our site member

during such period. In such any delay caused due to non availability of site member

should be excluded for calculating LD penalty and BPCL will pay for any idle time that

has been created due to non availability of site member

No change in tender clause.

Wipro 74 J SPECIAL CONDITIONS:In case the work gets

affected due to some interface/software issues

resulting in idling of the resources of

implementation agency and/or rescheduling of

the jobs, no extra compensation will be made.

SPECIAL CONDITIONS:In case the work gets affected due to some interface/software

issues resulting in idling of the resources of implementation agency and/or rescheduling

of the jobs, no extra cost will be paid as compensation will be made.

No change in tender clause.

Wipro 77 Annexur

e 3

As per RFP Request deletion of "including…but not limited to" as this makes the scope open ended No change in tender clause.

Wipro 95 J SPECIAL CONDITIONS: The work days shall be

Monday to Friday for all sites unless otherwise

specified. In case of exigencies, working will be

extended on closed days and holidays without

extra cost.

The work days shall be Monday to Friday for all sites unless otherwise specified. In case

of exigencies, working will be extended on closed days and holidays without extra cost.

mutually agreed terms and conditions

No change in tender clause.

Wipro 95 J SPECIAL CONDITIONS:No accommodation, travel

assistance, food, lodging and boarding will be

provided to Implementation agency.

Implementation agency will have to arrange all

travel, food, and accommodation,

lodging/boarding at their cost to their staff on

the work of this tender or any other work

related to this tender.The quoted rates shall be

inclusive of above.

No change in tender clause.

Wipro 96 J SPECIAL CONDITIONS: Any modification to the

software and processes to resolve any issues at

a site shall be replicated at other sites, if

applicable, without any extra cost.

SPECIAL CONDITIONS: Any modification to the software and processes to resolve any

issues at a site shall be replicated at other sites, if applicable, without any extra cost.

mutually agreed terms and conditions

No change in tender clause.

Wipro 96 J SPECIAL CONDITIONS: There may be incidences

of work getting affected due to site team

members not available for some time due to

exigencies, emergencies and plant shutdowns

for a maximum period of one month.

Implementation agency shall

plan the activities accordingly such that there is

no involvement of our site member during such

period.

SPECIAL CONDITIONS: There may be incidences of work getting affected due to site team

members not available for some time due to exigencies, emergencies and plant

shutdowns for a maximum period of one month. Implementation agency shall

plan the activities accordingly such that there is no involvement of our site member

during such period. In such any delay caused due to non availability of site member

should be excluded for calculating LD penalty and BPCL will pay for any idle time that

has been created due to non availability of site member

No change in tender clause.

Page 6: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries

Bidder Sr

No

Tender

Page

No

Clause

No

Clause Clause details Bidder's Query BPCL response to bidder's queries

Wipro 96 J SPECIAL CONDITIONS:In case the work gets

affected due to some interface/software issues

resulting in idling of the resources of

implementation agency and/or rescheduling of

the jobs, no extra compensation will be made.

SPECIAL CONDITIONS:In case the work gets affected due to some interface/software

issues resulting in idling of the resources of implementation agency and/or rescheduling

of the jobs, no extra cost will be paid as compensation will be made.

No change in tender clause.

Wipro Upgrade/Update/fixation of Patches Notwithstanding anything contrary elsewhere mentioned in the contract any

upgrade/update/fixation to the patches in software shall be at an additional cost to

BPCL

BPCL group refineries are procuring software

license along with maintenance and support.

APM Software down load will be provided by

BPCL. Bidder shall install the software. Any

patches, downloads of patches/bug fixes will be

provided by BPCL. However, implementation shall

be done by bidder during implementation work at

no extra cost.

Wipro 2. What is the length of MR & KR pipeline

section?

1) Mumbai Uran LPG pipeline section length

approximateley 28 km at MR.

2) Santacruz ATF pipeline length approximately 14

km at MR.

3) Kochi ATF pipeline length approximately 34 km

at MR.

4) CCK pipeline section length approximately 40

km at KR.

Wipro 3. Does vendor we need to have separate

PM for different sites?

Separate project manager shall be deployed for

each site.

Wipro 4. Can vendor share Data and document

soft copy to offshore team?

Implementation agency can share

data/documents with off-shore team with

confidentiality agreement with BPCL/BORL/NRL.

TCS 1 35 Annexure-1, AFUNCTIONAL DESIGN SPECIFICATION Implementation Agency shall conduct a common workshop for FDS for all

modules / work processes listed in Annexure-A for BPCL MR & KR. Work shop

shall be held at BPCL MR and KR. Implementation Agency shall submit the FDS

to BPCL Team for approval.

As BPCL refered to common workshop for

FDS, we assume common workshop to be

held at either MR or KR. Please confirm.

Few FDS workshops shall be conducted at MR

and few at KR.

Page 7: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries

Bidder Sr

No

Tender

Page

No

Clause

No

Clause Clause details Bidder's Query BPCL response to bidder's queries

TCS 2 38 Annexure-1, B, 12, aAPM SAP Interfaces APM interfaces with SAP through PO or direct for the following to be done:

a. Equipment - Interfacing from SAP to APM

b. Functional Location - Interfacing from SAP to APM

c. Work History & work history detail - Interfacing from SAP to APM

d. Equipment Technical Characteristics - Interfacing from SAP to APM

e. Functional Location Technical Characteristics - Interfacing from SAP to APM

f. Work Management - Interfacing from SAP to APM

g. Notification Management - Interfacing from APM to SAP

h. Work Order Management - Interfacing from APM to SAP

i. ACA Adaptor - Direct Interfacing from APM to SAP

j. ASI Adaptor - Direct Interfacing from APM to SAP

This query has to be sent to software OEM

to confirm whether interfaces listed under

this clause are compatible with BPCL SAP

PO and ECC versions

TCS assumes the functionalities are built-

in and compatible with BPCL SAP software

and We will facilitate Deploy,

configure,Deploy ,Data transfer,Test and

Validate of existing interface in APM

software as required by BPCL, Please

confirm.

Yes all the adaptors are avilable as product

functionality. Configuration will have to be done

by respective implementation agency. This is

compatible with SAP ECC 6 EHP 5.0 and above.

TCS 3 38/39 Annexure-1, B, 12, bAPM Interfaces with other sources APM interfaces with following to be done:

a. ASPEN IP21,

b. LIMS,

c. STAR LIMNS,

d. BPMAI-XHQ,

e. EDMS-COSMOS,

f. EMERSON AMS SUITE,

g. SYSTEM-1.

This query has to be sent to software OEM

to confirm whether interfacing facility to

the listed softwares available by default in

Meridium APM software.

Whether BPCL has confirmation from

product vendor about the required

functionalities are avaialble in Standard

Product or not .Please confirm

TCS assumes the functionalities are built-

in the software and We will facilitate

Deploy, configure,Deploy ,Data

transfer,Test and Validate of existing

interface in APM software as required by

BPCL, Please confirm.

a. The following standard adaptors will be

available with APM.

1) ASPEN IP21.

2) EMERSON AMS SUITE.

3) SYSTEM-1.

APM Connect studio is being supplied for creating

custom interfaces. Implementation agency shall

build custom interfaces for the following during

implementation using APM connect studio based

on functional requirement analysis.

1) LIMS.

2) STAE LIMS.

3) BPMAI-XHQ.

4) EDMS-COMOS.

During FDS, implementation agency shall identify

the requirement and specification for all interface

adaptors on other third party software/systems.

Adaptors identified on third party system side

shall be made available by BPCL/BORL/NRL.

However, installation and required configuration

shall be done by implementation agency with no

additional cost.

Page 8: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries

Bidder Sr

No

Tender

Page

No

Clause

No

Clause Clause details Bidder's Query BPCL response to bidder's queries

TCS 4 39 Annexure-1, B, 13Bulk uploading Bulk uploading facility.

The following bulk uploading using excel sheets shall be made available

a. TML bulk creation and upload.

b. Bulk up load of asset data.

c. TML measurement data.

d. Asset Criticality Analysis upload.

e. RBI component creation, analysis and re-analysis.

f. Task creation in bulk.

g. PV stress including addition, deletion or modification to look up table for

stress values for TM evaluation.

h. Template for inspection profiles and inspection methods.

i. Functional Aspects - building, modification and provide access control for

the following.

I. Query, Report, Graphs etc

II. Dash board, score card

III. Alerts

IV. Scheduling of task, data extraction scheduler

j. Mapping fields for interfacing the Meridium with third party software

k. Bulk upload of check list

l. Bulk upload of Vibration reading from vibration data collector

m. Asset Criticality Analysis data.

n. Measurement location and their IOW limits.

TCS assumption is all the required loaders

are available in software by default.Please

confirm.

Base line data loader will be available for TML

bulk creation and upload, Bulk up load of asset

data, TML measurement data, Asset Criticality

Analys upload, RBI component creation, analysis

and re-analysis, RBI Components and RBI analysis,

Task creation in bulk, PV stress including addition,

deletion or modification to look up table for

stress values for TM evaluation (Can be done

using APM Family loader, some configuration

expected), Template for inspection profiles and

inspection methods, Asset Criticality Analysis

data, Measurement location and their IOW limits

(Loader available for ML Limits), Bulk upload of

Vibration reading from vibration data collector

(can be uploaded as reading against

measurement location).

• Bulk upload of check list - No loader for

uploading checklists eixists. For existing checklists

we can use APM Family Loader, some

configuration expected. But, creating new

checklist is configuration and not possible

through a data loader.

Beyond these, there are generic data loaders

available for any other data to be loaded.

Data loaders are not applicable for the below:TCS 5 42 Annexure-1, C, 15, bACA Perform Asset Criticality Analysis for assets within one unit for KR and

one unit for MR and one pipe line as follows:

MR- NHT-CCR Plant

KR- NHT-CCR complex

Pipeline- Mumbai-Uran Pipeline

Need to clarify the counts of approximate

number of Assets for ACA for

MR- NHT-CCR Plant

KR- NHT-CCR complex

Pipeline- Mumbai-Uran Pipeline ..?

Please confirm.

BPCL Response:

KR: The asset count for NHT-CCR in BPCL KR is

400 which includes drivers & driven equipments.

MR: The asset count for NHT-CCR in BPCL MT is

350 which include drivers and driven equipment.

Mumbai-Uran pipeline: There are 4 nos. rotary

equipment in pipeline (2 main pums+2 booster

pumps). These also have drivers etc.

TCS 6 43 Annexure-1, C, 15, dRCM Carryout RCM of rotary equipments of Mumbai-Uran pipeline. Please provide number of approximate

rotary equipment of Mumbai-Uran

Pipeline

Mumbai-Uran pipeline: There are 4 nos. rotary

equipment in pipeline (2 main pums+2 booster

pumps). These also have drivers etc.

Page 9: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries

Bidder Sr

No

Tender

Page

No

Clause

No

Clause Clause details Bidder's Query BPCL response to bidder's queries

TCS 4 43 Annexure-1,D,4,aOperator Round Implementation agency shall configure the software for handheld device

and configure the interface with handle held device with Meridium and is

for 30 numbers of routes having 10 nos. equipment in each route with 15

tags per equipment.

1. What are make and model of the

handheld devices used by BPCL for

operator rounds.

2. Does Meridium software has capability

for custom configuration and interface

adaptor for BPCL procured handheld

devices? (Query to be sent to OEM).

3. Does BPCL wants implementing agenty

to develop Meridium interface adaptor for

handheld device?

1. Make and model of hande held devices will be

informed during FDS.

2. Meridium software will be compatible to

Android 6 and above with screen size 5.2 inches

and above.

3. No.

TCS 7 47 Annexure-1, G, 4Notification update in SAP and Meridium BPCL MR & KR wants to update the Notification history in SAP from Inspection

event document in Meridium as existing in MR. The Inspection event document

should be able to close the Notification both in Meridium and SAP, and update

the Inspection Task. Observation and failure codes etc. shall be populated to

SAP to the respective table.

This feature should be available in

standard Meridium APM software. We

assume TCS to configure the feature

available in the software. Please confirm.

Update of notification history is supported as

standard. Additional fields may be configured

using avaialble free fields during implementation.

Closure of notification will be supported as

standard.

TCS 8 47 Annexure-1, G, 5Custom formulae and stress value Provision shall be made for addition of the custom formulae and stress values. This query has to be sent to software OEM

and please check software shall have

provison for addition of the custom

formulae and stress values.

Custom formulae to be created as defined during

FDS and to be configured by implementation

agency.

TCS 9 47 Annexure-1, G, 6T-min calculator for ASME Sec-VIII Div.2 In addition to existing T-min calculators, implementation agency shall add T- min

calculator for ASME Section VIII Division 2 and add relevant PV stress values for

all code years.

This query has to be sent to software OEM

to check for Tmin calculator for ASME

Section VIII Division 2 is available in

Meridium APM software.

We assume that BPCL shall provide

relevant PV stress values in excel format

for all code years. Please confirm.

Custom formulae to be created as defined during

FDS and to be configured by implementation

agency. BPCL will provide the PV stress values and

implementation agency shall upload the same

using data loaders.

TCS 10 47 Annexure-1, G, 7T-min calculator for Storage Tanks Implementation agency shall add T-min calculator for storage tanks and add

relevant PV stress values for the same.

This query has to be sent to software OEM

to check for T-min calculator for storage

tanks is available in Meridium APM

software.

We assume that BPCL shall provide

relevant PV stress values for the same in

excel format for all code years. Please

confirm.

Custom formulae to be created as defined during

FDS and to be configured by implementation

agency. BPCL will provide the PV stress values and

implementation agency shall upload the same

using data loaders.

Page 10: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries

Bidder Sr

No

Tender

Page

No

Clause

No

Clause Clause details Bidder's Query BPCL response to bidder's queries

TCS 11 47 Annexure-1, G, 9Risk ranking of each process unit Meridium to formulate a calculation of ranking of each process unit based on

each plant risk and place in Corporate Risk Matrix of respective site. The process

unit may contain few plants.

Meridium software has capability for risk

ranking process unit by default?

Implementing agency to carry out risk

ranking of each process unit in MR & KR?

As a standard, Risk analysis of each unit, system,

asset will have to be carried out in ACA, which

follows Corporate Risk Matrix (CRM). ACA allows

to drill down and roll up the risk ranking.

TCS 1 48 Annexure-1,G,22,bRBI study and CCD preparation Carry out RBI study of 2 nos. sections of a pipeline each for MR and KR.

Push RBI recommendation or inspection task analysis to ASM to

Inspection notification for the same with option of user intervention

BPCL to provide the counts for PFD and

P&ID for MR & KR pipeline.

Each pipeline generally have 1 to 2 PFD and 2 to 3

P&IDS for each sections at starting point station

and sectionalizing station, and pipe book for

pipeline. The exact number of PFDs & P&IDs can

not be exactly counted like done process plant.

TCS 12 52 Annexure-1, J, 14Update the risk ranks of existing records MR and KR handholding shall be considered as complete only when all the

existing analysis in RCM/FMEA/ASM/RBI are updated with new risk ranks in

accordance to the changes carried out in risk matrix.

Does implementing agency have to update

risk rank of all existing records as per new

CRM? So the existing records risk ranks

shall reflect the new ranks.

KR risk matrix for RCM will be made similar to MR

to standardize and push to CRM. For this, bidder

to run the analysis of RCM to bring it CRM.

TCS 13 54 Annexure-1, MTime of Completion The completion period for the entire scope of work for MR and KR shall be 15

months from the date of purchase order.

TCS request BPCL to revise the completion

period to 18 Months based on our

evaluaiton of total project scope.

The completion period for the entire scope of

work for MR and KR shall be 18

months from the date of purchase order. The

stabilization period of 6 months is in

addition to the completion period.

TCS 14 57 Annexure-2, B, 7(a)APM SAP Interfaces APM interfaces with SAP through RFC OR IDOC or direct for the following to be

done:

a. Equipment - Interfacing from SAP to APM

b. Functional Location - Interfacing from SAP to APM

c. Work History & work history detail - Interfacing from SAP to APM

d. Equipment Technical Characteristics - Interfacing from SAP to APM

e. Functional Location Technical Characteristics - Interfacing from SAP to APM

f. Work Management - Interfacing from SAP to APM

g. Notification Management - Interfacing from APM to SAP

h. Work Order Management - Interfacing from APM to SAP

i. ACA Adaptor - Direct Interfacing from APM to SAP

j. ASI Adaptor - Direct Interfacing from APM to SAP

This query has to be sent to software OEM

to confirm whether interfaces listed under

this clause are compatible with BORL SAP

ECC versions

TCS assumes the functionalities are built-

in and compatible with BORL SAP software

and We will facilitate Deploy,

configure,Deploy ,Data transfer,Test and

Validate of existing interface in APM

software as required by BPCL, Please

confirm.

Yes, all the adaptors are avilable as product

functionality. Configuration will have to be done

by implementation agency.

This is compatible with SAP ECC 6 EHP 5.0 and

above.

Page 11: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries

Bidder Sr

No

Tender

Page

No

Clause

No

Clause Clause details Bidder's Query BPCL response to bidder's queries

TCS 15 58 Annexure-2, B, 7(b)APM Interfaces APM interfaces with following to be done:-

a. Exaquantum PIMS – By Yokogawa,

b. Customized LIMS by Advika Software Solutions,

c. System ONE, Emerson AMS Suite,

d. ATOMS / AORA App and EDMS - Project Wise V8i (Select Series 3) to be done.

This query has to be sent to software OEM

to confirm whether interfacing facility to

the listed softwares available by default in

Meridium APM software. TCS assumes the

functionalities are built-in the software

and will facilitate configuration of existing

interface in APM software as required by

BPCL, Please confirm.

a. Exaquantum PIMS: - Custom interface will be

required, this has to be built during

implementation after functional requirement

analysis.

b. LIMS: - Custom interface will be required, this

has to be built during implementation after

functional requirement analysis.

C. EMERSON AMS SUITE, - standard adaptor is

available.

SYSTEM-1. - standard adaptor is available,

"Enterprise impact" software shall be needed

from System 1 side.

d. Custom interface will be required, this has to

be built during implementation after functional

requirement analysis.

APM Connect studio is being supplied for creating

custom interfaces.

TCS 16 58 Annexure-2, B, 8Bulk uploading Bulk uploading facility.

The following bulk uploading using excel sheets shall be made available

a. TML bulk creation and upload.

b. Bulk up load of asset data.

c. TML measurement data.

d. Asset Criticality Analysis upload.

e. RBI component creation, analysis and re-analysis.

f. Task creation in bulk.

g. PV stress including addition, deletion or modification to look up table for

stress values for TM evaluation.

h. Template for inspection profiles and inspection methods.

i. Functional Aspects - building, modification and provide access control for

the following.

I. Query, Report, Graphs etc

II. Dash board, score card

III. Alerts

IV. Scheduling of task, data extraction scheduler

j. Mapping fields for interfacing the Meridium with third party software

k. Bulk upload of check list

l. Bulk upload of Vibration reading from vibration data collector

m. Asset Criticality Analysis data.

n. Measurement location and their IOW limits.

Generally these data loaders given under

Bulk Uploading facility to be available in

Meridium APM software by defult .

If already available in software, TCS will

facilitate Bulk Upload of data as required

by BPCL.

If data loaders are not available additional

effort estimation is required by TCS.

Base line data loader will be available for TML

bulk creation and upload, Bulk up load of asset

data, TML measurement data, Asset Criticality

Analys upload, RBI component creation, analysis

and re-analysis, RBI Components and RBI analysis,

Task creation in bulk, PV stress including addition,

deletion or modification to look up table for

stress values for TM evaluation (Can be done

using APM Family loader, some configuration

expected), Template for inspection profiles and

inspection methods, Asset Criticality Analysis

data, Measurement location and their IOW limits

(Loader available for ML Limits), Bulk upload of

Vibration reading from vibration data collector

(can be uploaded as reading against

measurement location).

Bulk upload of check list - No loader for uploading

checklists eixists. For existing checklists APM

Family Loader can be used, some configuration

expected. But, creating new checklist is

configuration and not possible through a data

loader.

Beyond these, there are generic data loaders

available for any other data to be loaded.

Data loaders are not applicable for the below:

Page 12: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries

Bidder Sr

No

Tender

Page

No

Clause

No

Clause Clause details Bidder's Query BPCL response to bidder's queries

TCS 17 59 Annexure-2, C, 1, fKPI Apart from the standard KPIs, 30 nos. KPIs as defined by BPCL (Min. nos. for 5

each of the work processes) to be generated by the implementation agency.

Implementation agency to generate total

30 KPIs as defined by BPCL apart from the

KPI's already existing in Meridium APM.

Please confirm.

Yes. Confirmed.

TCS 18 60 Annexure-2, C, 3Email alerts Configuring the fields and email alerts as per ANNEXURE – C. This query has to be sent to software OEM

to check the feasiblity of Annexure-C

functionalities. TCS will configure the fields

and email alerts if the facilites are

available in Meridium APM software. If

not available, Please confirm.

It is possible to populate the text of multiple

required fields into the email alert body, will have

to be configured by implementation agency.

TCS 19 61 Annexure-2, C, 15, b/cAsset count forACA, RCM and FMEA Perform Asset Criticality Analysis for assets in HGU and HCU-DHDT complex at

BORL and Implementation agency shall carry out full RCM, FMEA on all the

assets as per Annexure-D

Need to clarify the counts for HGU and

HCU-DHDT complex for ACA..?

As per Annexure-D; the count is 45 system

( 97 rotary assets). Please confirm..?

We have selected 45 critical equipment (assets)

from units HCU & HGU. It is further being clarified

that the number of sub-equipment e.g. in case of

feed pump the asset comprises of 1 pump, motor

and gearbox hence a total 3 sub-assets in 1

equipment tag. Likewise, all selected equipment

(assets) are divided into their sub-assets and the

total number is coming as 97. Please refer to the

list given in Annexure - D for details.

5 62 Annexure-2,D,3,fOperator Round Implementation agency shall configure the software for handheld device

and configure the interface with handle held device with Meridium and is

for 30 numbers of routes having 10 nos. equipment in each route with 15

tags per equipment.

1. What are make and model of the

handheld devices used by BPCL for

operator rounds.

2. Does Meridium software has capability

for custom configuration and interface

adaptor for BPCL procured handheld

devices? (Query to be sent to OEM).

3. Does BPCL wants implementing agenty

to develop Meridium interface adaptor for

handheld device?

1. Make and model of hande held devices will be

informed during FDS.

2. Meridium software will be compatible to

Android 6 and above with screen size 5.2 inches

and above.

3. No.

TCS 20 63 Annexure-2, E, 3Pipeline Strategies Strategies for pipeline facilities/systems to be included as a part of

implementation scope.

This query has to be sent to software OEM

to confirm standard pipeline strategies as

part of software package or not . Please

confirm.

Generic rotating equipment strategies shall be

available in Asset Strategy Library (ASL) and

pipeline strategies will be out come of RBI study.

TCS 21 64 Annexure-2, E, 8Pipeline system selection Subject matter experts from implementation agency shall help Pipeline team

to select one system for applying complete work process.

BPCL to provide exact number of

equipment on the selected pipeline for

carrying out the work process. Total

number of equipment required for exact

effort estimation.

SME to help for system selection during FDS. No

RBI and RCM to be considered under this clause.

However, however all the equipment related to

pipe line shall be uploaded in meridium for other

schedule generations like preventative

maintenance , notification etc. for all the static

and rotary equipment.

Page 13: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries

Bidder Sr

No

Tender

Page

No

Clause

No

Clause Clause details Bidder's Query BPCL response to bidder's queries

TCS 2 64 Annexu

re-2,E,8

&

Annexu

re - 2,

G

Mechanical Integrity process for Pipeline Subject matter experts from implementation agency shall help Pipeline team

to select one system for applying complete work process.

Does the complete work process include

Mechanical Integrity for Pipeline also, if so

please give count of PFDs and P&IDs for

BORL pipeline.

SME to help during FDS for system selection.

TCS 3 65 Annexure-2,F,5, aReliability Analytics Facilitators from the implementation agency shall facilitate BORL to

perform Root Cause Analysis - RCA / Reliability Analytics-RA for

equipment as per Annexure-D.

Please clarify which of Reliability Analysis

process(PA, SRA, SA, RDA, PDA, RGA) for

BORL 45 systems has to be followed.

SME to identify during hand holding and perform

one or multiple type of analysis as recommeded

by SME.

TCS 22 66 Annexure-2, G, 9Notification update in SAP and Meridium BORL wants to update the Notification history in SAP from Inspection event

document in Meridium as existing in MR. The Inspection event document

should be able to close the Notification both in Meridium and SAP, and update

the Inspection Task. Observation and failure codes etc. shall be populated to

SAP to the respective table.

This feature should be available in

standard Meridium APM software. We

assume TCS to configure the feature

available in the software. Please confirm.

Update of notification history is supported as

standard. Additional fields may be configured

using avaialble free fields during implementation.

Closure of notification will be supported as

standard.

TCS 23 66 Annexure-2, G, 11Custom formulae and stress value Provision shall be made for addition of the custom formulae and stress values. This query has to be sent to software OEM

and please check software shall have

provison for addition of the custom

formulae and stress values.

Custom formulae to be created as defined during

FDS and to be configured by implementation

agency.

TCS 24 66 Annexure-2, G, 12T-min calculator for ASME Sec-VIII Div.2 In addition to existing T-min calculators, implementation agency shall add T- min

calculator for ASME Section VIII Division 2 and add relevant PV stress values for

all code years.

This query has to be sent to software OEM

to check for Tmin calculator for ASME

Section VIII Division 2 is available in

Meridium APM software.

We assume that BPCL shall provide

relevant PV stress values in excel format

for all code years. Please confirm.

Custom formulae to be created as defined during

FDS and to be configured by implementation

agency. BORL will provide the PV stress values

and implementation agency shall upload the

same using data loaders.

TCS 25 66 Annexure-2, G, 15Risk ranking of each process unit Meridium to formulate a calculation of ranking of each process unit based on

each plant risk and place in Corporate Risk Matrix of respective site. The process

unit may contain few plants.

Meridium software has capability for risk

ranking process unit by default?

Implementing agency to carry out risk

ranking of each process unit in BORL?

As a standard, Risk analysis of each unit, system,

asset will have to be carried out in ACA, which

follows Corporate Risk Matrix (CRM). ACA allows

to drill down and roll up the risk ranking.

TCS 26 69 Annexure-2, G, 32, cCorrosion looping SME shall conduct the corrosion loop finalization work shop at BORL for 5 days

minimum and finalize the corrosion loops with BORL team. SME shall be

available at BORL Refinery site at the time of corrosion looping study.

Implementation agency shall identify, mark & verify corrosion loops and

damage mechanisms for both equipment & piping on P&ID based on existing

operating conditions, stream flows, corrosive fluids, fluid characteristics,

material specifications & damage mechanisms. Corrosion study is inclusive of

the scope.

Corrosion loops are identified at PFD level. Implementation agency shall mark corrosion

loops on both PFDs and P&IDs for all sites of BPCL

group refineries.

Page 14: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries

Bidder Sr

No

Tender

Page

No

Clause

No

Clause Clause details Bidder's Query BPCL response to bidder's queries

TCS 27 69 Annexu

re-2, G,

32, i

RBI Implementation All the process equipment (viz. columns, exchangers, pressure vessels, furnace

coils, piping, pressure relieving devices etc.) of HGU and HCU- DHDT shall be

covered in scope for RBI Implementation.

Generally PRVs are not part of corrosion

study.

Acceptable.

TCS 28 76 Annexure-2, MTime of Completion The completion period for the entire scope of work for MR and KR shall be 15

months from the date of purchase order.

TCS request BPCL to revise the completion

period to 18 Months based on our

evaluaiton of total project scope.

The completion period for the entire scope of

work for BORL shall be 18 months

from the date of purchase order. The stabilization

period of 6 months is in

addition to the completion period.

TCS 29 79 Annexu

re-3, B,

7(a)

APM SAP Interfaces APM interfaces with SAP through RFC or direct for the following to be done:

a. Equipment - Interfacing from SAP to APM

b. Functional Location - Interfacing from SAP to APM

c. Work History & work history detail - Interfacing from SAP to APM

d. Equipment Technical Characteristics - Interfacing from SAP to APM

e. Functional Location Technical Characteristics - Interfacing from SAP to APM

f. Work Management - Interfacing from SAP to APM

g. Notification Management - Interfacing from APM to SAP

h. Work Order Management - Interfacing from APM to SAP

i. ACA Adaptor - Direct Interfacing from APM to SAP

j. ASI Adaptor - Direct Interfacing from APM to SAP

This query has to be sent to software OEM

to confirm whether interfaces listed under

this clause are compatible with NRL SAP

ECC versions

TCS assumes the functionalities are built-

in and compatible with NRL SAP software

and We will facilitate Deploy,

configure,Deploy ,Data transfer,Test and

Validate of existing interface in APM

software as required by NRL, Please

confirm.

Yes all the adaptors are avilable as product

functionality. Configuration will have to be done

by implementation agency. This is compatible

with SAP ECC 6 EHP 5.0 and above. BPCL to

provide version compatibility

Page 15: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries

Bidder Sr

No

Tender

Page

No

Clause

No

Clause Clause details Bidder's Query BPCL response to bidder's queries

TCS 30 80 Annexu

re-3, B,

7(b)

APM Interfaces APM interfaces with the following to be done:-

a. Aspen IP21,

b. LIMS,

c. GE System 1,

d. DMS,

e. OLEMS

f. PROGNOST t

This query has to be sent to software OEM

to confirm whether interfacing facility to

the listed softwares available by default in

Meridium APM software. TCS assumes the

functionalities are built-in the software

and will facilitate configuration of existing

interface in APM software as required by

BPCL, Please confirm.

a. The following standard adaptors will be

available with APM.

1) ASPEN IP21.

2)SYSTEM-1. Enterprise impact shall be needed

from System1 side.

APM Connect studio is being supplied for creating

custom interfaces. Implementation agency shall

build custom interfaces for the following during

implementation using APM connect studio based

on functional requirement analysis.

1) LIMS.

2) DMS.

3) OLEMS.

4) PROGNOST.

During FDS, implementation agency shall identify

the requirement and specification for all interface

adaptors on other third party software/systems.

Adaptors identified on third party system side

shall be made available by BPCL/BORL/NRL.

However, installation and required configuration

shall be done by implementation agency with no

additional cost.

TCS 31 80 Annexu

re-3, B,

7, d

Additional data for Integration The additional data that is required to be integrated in Meridium is available in

different applications, as defined in this section.

Need details on system to be integrated. Together with GE System1, very recently NRL is

using Bently Nevda (GE) make vibration Analyzers

Scout, which uses Ascent 2015 Level2/R2

v15.1.65

(Windows 7, 64bit, SP1). Though this is to be

shortly integrated with System1, direct interfacing

of APM with Ascent 2015 Level2/R2 v15.1.65 may

also be required.

Page 16: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries

Bidder Sr

No

Tender

Page

No

Clause

No

Clause Clause details Bidder's Query BPCL response to bidder's queries

TCS 32 80 Annexu

re-3, B,

8

Bulk uploading Bulk uploading facility.

The following bulk uploading using excel sheets shall be made available

a. TML bulk creation and upload.

b. Bulk up load of asset data.

c. TML measurement data.

d. Asset Criticality Analysis upload.

e. RBI component creation, analysis and re-analysis.

f. Task creation in bulk.

g. PV stress including addition, deletion or modification to look up table for

stress values for TM evaluation.

h. Template for inspection profiles and inspection methods.

i. Functional Aspects - building, modification and provide access control for

the following.

I. Query, Report, Graphs etc

II. Dash board, score card

III. Alerts

IV. Scheduling of task, data extraction scheduler

j. Mapping fields for interfacing the Meridium with third party software

k. Bulk upload of check list

l. Bulk upload of Vibration reading from vibration data collector

m. Asset Criticality Analysis data.

n. Measurement location and their IOW limits.

Generally these data loaders given under

Bulk Uploading facility to be available in

Meridium APM software by defult .

If already available in software, TCS will

facilitate Bulk Upload of data as required

by BPCL.

If data loaders are not available additional

effort estimation is required by TCS.

Base line data loader will be available for TML

bulk creation and upload, Bulk up load of asset

data, TML measurement data, Asset Criticality

Analys upload, RBI component creation, analysis

and re-analysis, RBI Components and RBI analysis,

Task creation in bulk, PV stress including addition,

deletion or modification to look up table for

stress values for TM evaluation (Can be done

using APM Family loader, some configuration

expected), Template for inspection profiles and

inspection methods, Asset Criticality Analysis

data, Measurement location and their IOW limits

(Loader available for ML Limits), Bulk upload of

Vibration reading from vibration data collector

(can be uploaded as reading against

measurement location).

• Bulk upload of check list - No loader for

uploading checklists eixists. For existing checklists

we can use APM Family Loader, some

configuration expected. But, creating new

checklist is configuration and not possible

through a data loader.

Beyond these, there are generic data loaders

available for any other data to be loaded.

Data loaders are not applicable for the below:TCS 33 81 Annexu

re-3, C,

1, f

KPI Apart from the standard KPIs, 30 nos. KPIs as defined by NRL (Min. nos. for 5

each of the work processes) to be generated by the implementation agency.

Implementation agency to generate total

30 KPIs as defined by BPCL apart from the

KPI's already existing in Meridium APM.

Please confirm.

Yes. Confirmed.

TCS 34 82 Annexu

re-3, C,

3

Email alerts Configuring the fields and email alerts as per ANNEXURE – C. This query has to be sent to software OEM

to check the feasiblity of Annexure-C

functionalities. TCS will configure the fields

and email alerts if the facilites are

available in Meridium APM software. If

not available, Please confirm.

It is possible to populate the text of multiple

required fields into the email alert body, will have

to be configured by implementation agency.

TCS 35 83 Annexure-3, C, 15, b/cAsset count forACA, RCM and FMEA Perform Asset Criticality Analysis for assets Hydrocracker Unit (HCU) of

NRL.Implementation agency shall carry out the following for all the rotary

equipment at HCU of NRL (approx. 100 systems).

Need to clarify the counts for

Hydrocracker Unit (HCU) for ACA..?

Rotating Equipment Trains (Driver + Driven+

Intermediate Speed Variation Equipment, if any ):

120 Nos.

Page 17: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries

Bidder Sr

No

Tender

Page

No

Clause

No

Clause Clause details Bidder's Query BPCL response to bidder's queries

6 84 Annexure-3,D,4,aOperator Round Implementation agency shall configure the software for handheld device

and configure the interface with handle held device with Meridium and is

for 30 numbers of routes having 10 nos. equipment in each route with 15

tags per equipment.

1. What are make and model of the

handheld devices used by BPCL for

operator rounds.

2. Does Meridium software has capability

for custom configuration and interface

adaptor for BPCL procured handheld

devices? (Query to be sent to OEM).

3. Does BPCL wants implementing agenty

to develop Meridium interface adaptor for

handheld device?

1. Make and model of hande held devices will be

informed during FDS.

2. Meridium software will be compatible to

Android 6 and above with screen size 5.2 inches

and above.

3. No.

TCS 36 87 Annexu

re-3, G,

9

Notification update in SAP and Meridium NRL wants to update the Notification history in SAP from Inspection event

document in Meridium as existing in MR. The Inspection event document

should be able to close the Notification both in Meridium and SAP, and update

the Inspection Task. Observation and failure codes etc. shall be populated to

SAP to the respective table.

This feature should be available in

standard Meridium APM software. We

assume TCS to configure the feature

available in the software. Please confirm.

Update of notification history is supported as

standard. Additional fields may be configured

using avaialble free fields during implementation.

Closure of notification will be supported as

standard.

TCS 37 87 Annexu

re-3, G,

10

Custom formulae and stress value Provision shall be made for addition of the custom formulae and stress values. This query has to be sent to software OEM

and please check software shall have

provison for addition of the custom

formulae and stress values.

Custom formulae to be created as defined during

FDS and to be configured by implementation

agency.

TCS 38 87 Annexu

re-3, G,

11

T-min calculator for ASME Sec-VIII Div.2 In addition to existing T-min calculators, implementation agency shall add T- min

calculator for ASME Section VIII Division 2 and add relevant PV stress values for

all code years.

This query has to be sent to software OEM

to check for Tmin calculator for ASME

Section VIII Division 2 is available in

Meridium APM software.

We assume that BPCL shall provide

relevant PV stress values in excel format

for all code years. Please confirm.

NRL Response:

Custom formulae to be created as defined during

FDS and to be configured by implementation

agency. NRL will provide the PV stress values and

implementation agency shall upload the same

using data loaders.

TCS 39 88 Annexu

re-3, G,

12

T-min calculator for Storage Tanks Implementation agency shall add T-min calculator for storage tanks and add

relevant PV stress values for the same.

This query has to be sent to software OEM

to check for T-min calculator for storage

tanks is available in Meridium APM

software.

We assume that BPCL shall provide

relevant PV stress values for the same in

excel format for all code years. Please

confirm.

Custom formulae to be created as defined during

FDS and to be configured by implementation

agency. NRL will provide the PV stress values and

implementation agency shall upload the same

using data loaders.

Page 18: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries

Bidder Sr

No

Tender

Page

No

Clause

No

Clause Clause details Bidder's Query BPCL response to bidder's queries

TCS 40 88 Annexu

re-3, G,

14

Risk ranking of each process unit Meridium to formulate a calculation of ranking of each process unit based on

each plant risk and place in Corporate Risk Matrix of respective site. The process

unit may contain few plants.

Meridium software has capability for risk

ranking process unit by default?

Implementing agency to carry out risk

ranking of each process unit in NRL?

As a standard, Risk analysis of each unit, system,

asset will have to be carried out in ACA, which

follows Corporate Risk Matrix (CRM). ACA allows

to drill down and roll up the risk ranking.

TCS 41 88 Annexu

re-3, G,

23

RBI Analysis RBI analysis of PSVs of Hydro-cracker Unit. Please provide the number of total PSV's

for Hydro-cracket unit.

NRL Response:

There are 226 nos. of PSVs in Hydrocracker unit.

TCS 42 90 Annexure-3, G, 31, cCorrosion looping SME shall conduct the corrosion loop finalization work shop at NRL for 5 days

minimum and finalize the corrosion loops with NRL team. SME shall be available

at NRL Refinery site at the time of corrosion looping study. Implementation

agency shall identify, mark & verify corrosion loops and damage mechanisms

for both equipment & piping on P&ID based on existing operating conditions,

stream flows, corrosive fluids, fluid characteristics, material specifications &

damage mechanisms. Corrosion study is inclusive of the scope.

Corrosion loops are identified at PFD level Implementation agency shall mark corrosion

loops on both PFDs and P&IDs for all sites of BPCL

group refineries.

TCS 43 91 Annexu

re-3, G,

31, i

RBI Implementation All the process equipment (viz. columns, exchangers, pressure vessels, furnace

coils, piping, pressure relieving devices etc.) of HGU and HCU- DHDT shall be

covered in scope for RBI Implementation.

Generally PRVs are not part of corrosion

study. Whether BPCL is looking for doing

the RBI Analysis of all Pressure Relieving

devices of HGU and HCU- DHDT units. If

yes, please provide the count for the

same.

NRL Response:

RBI study also to be carried out for all 226 nos.

PSVs of HCU unit in NRL.

TCS 44 97 Annexure-3, MTime of Completion The completion period for the entire scope of work for MR and KR shall be 15

months from the date of purchase order.

TCS request BPCL to revise the completion

period to 18 Months based on our

evaluaiton of total project scope.

The completion period for the entire scope of

work for NRL shall be 18 months

from the date of purchase order. The stabilization

period of 6 months is in

addition to the completion period.

PwC General

query

Genera

l query

What is the amount of customisation in the existing implementation ? What are

the functionalities being currently used ?It can not be explicitely mentioned herein. You

may see existing system.

PwC General

query

Genera

l query

Would the training in KR & MR be conducted seprately in different locations or

would it be a common trainingTraining shall be conducted separately for MR

and KR.

PwC General

query

Genera

l query

Do you envisage any changes to the technical charecteristics maintained in SAP

system against functional location & equipment for any of the sites ?This can be known during FDS.

PwC General

query

Genera

l query

Please highlight any challenges and issues in previous implementation of

Meridium at MR & KR - change management, existing enterprise architecture,

integration issues, KPIs, workflows etc

This information can not be shared at this stage.

This is to be discussed during FDS.

PwC General

query

Genera

l query

How much of the customised features that are likely to be removed when you

upgrade to the new version. For instance a customization that’s done could be a

new feature in the latest version of meridium can be ignored. Can you please list

such functions.

This is to be studied by implementation agency

and to be discussed with site personel during FDS.

Page 19: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries

Bidder Sr

No

Tender

Page

No

Clause

No

Clause Clause details Bidder's Query BPCL response to bidder's queries

PwC General

query

Genera

l query

How much of customization documentation available currently for

implementation team to understand and migrate?Existing customization documents not available.

PwC General

query

Genera

l query

For the existing product, can we please look at the customisation data model and

new changes in the data models? You can visit and see existing Meridium system to

understand your requirement.

PwC General

query

Genera

l query

Regarding data migration, are there any existing scripts that can be used or the

implementation team has to prep up scripts from scratch.No scripts exist. Implementation agency to work

on this requirements.

PwC General

query

Genera

l query

What is the size of the data to be migrated approximately ? MR Database Size - 19 GB including indexes

KR Database Size - 24 GB including indexes

PwC General

query

Genera

l query

Will there be any KT sessions provided on the customisation done in the product

so far ? We woud like to have some dedicated support from existing team for us

during the implementation phase. Can this be organised ?

During FDS, AS IS study to be done to arrive at TO

BE processes. Whatever available documents

available will be shared during FDS.

PwC General

query

Genera

l query

Are there any front end app level customisations done ? Like in the look and feel

of the app etc ? No.

PwC General

query

Genera

l query

Given the scale of the project, in order to enable us to complete our internl

formalities, we request you to please extend the bid submission date from 8th

December by 2 weeks

Kindly refer corrigendum.

PwC General

query

Genera

l query

Given the extensive handholding requirements, we also request you to please

extend the total timline for completion from the present 15 months to 22

months so as to enable proper training as well as handholding activities to be

performed

The completion period for the entire scope of

work for MR and KR, BORL and NRL shall be 18

months from the date of purchase order. The

stabilization period of 6 months is in addition to

the completion period.

BHGE 1 Page 35 F Identify the best option available in

solution offered based on the inputs given

by BPCL core team and identify those

processes, which have a “straight fit” in

solution offered. In case, there is no

straight fit in solution, offer ‘work around’

solution for such processes.

Requirements fit-gap For requirements that are not met

through a "straight fit", or through a

configurable work around and a

customization / development is required,

how is the additional

development/customization cost to be

handled?

As such additional development/cutomozation is

not envisaged.

BHGE 2 Page 36 A) I & J i) FAT to be carried out and approved by

BPCL before migrating all the

configurations/data to Quality

environment.

j) Pilot room testing shall be carried out

based on FDS and implementation agency

shall obtain approval from BPCL core team.

Any changes if required shall be

incorporated in the system

FAT and Pilot room testing What is Pilot Room testing, how is it

different from FATs ? How many rounds of

FAT and Pilot Room Testing is expected for

MR, KR, BORL, NRL, and Pipelines?

Pilot room testing is nothing but User Acceptance

Test (UAT) based on test cases identified.

Page 20: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries

Bidder Sr

No

Tender

Page

No

Clause

No

Clause Clause details Bidder's Query BPCL response to bidder's queries

BHGE 3 Page 42 12 Implementation agency shall help BPCL to

select and create 30 Policies to take

intelligent actions based on the IOW limits

of Health Indicators.

Create 30 policies Is it 30 policies for each site? 30 policies for each site.

BHGE 4 Page 42 14 Data for Mumbai, Pipeline and Kochi

refinery shall be filtered, the Data visibleto

a user shall only be restricted to that of his

site. Administrator should beable to

provide read only access to each other’s

data on internal approval.

Data Filtering Do we require Data Filtering between MR,

KR and Pipelines? To what extent do we

want data to be visible?

Data shall be visible to MR, KR and Pipeline.

However, edit option shall be restricted and with

administrator of respective site.

BHGE 5 Page 42 15c Implementation agency shall carry out the

following for 75 nos. rotary systems

consisting driver and driven equipment at

MR and 75 nos. rotary systems consisting

driver and driven equipment at KR

Perform RCM/FMEA for 75 systems at MR and 75 systems at KR Please provide breakdown of

High/Medium/Low critical assets.

This shall be based on ACA output.

BHGE 6 Page 42 15c Implementation agency shall carry out the

following for 75 nos. rotary systems

consisting driver and driven equipment at

MR and 75 nos. rotary systems consisting

driver and driven equipment at KR

Perform RCM/FMEA for 75 systems at MR and 75 systems at KR Please provide list of 75 assets for MR and

75 assets for KR.

The list of assets can be give during FDS.

BHGE 7 Page 43 D) 3 The Asset Health Management Module

shall be configured for both sites to add

health indicators based on strategic actions

for the asset.

ASPEN IP21 Is it possible for BPCL to setup a Dedicated

IP21 Server(s) or Matrikon GDA Servers

for Interfacing with APM? This will be

applicable for Interfacing with any Process

Historian.

BPCL Response:

Separate IP21 server exists for MR and KR at

respective sites. However, it will not be dedicated

for APM. OPC server will be provided by BPCL.

BHGE 8 Page 43 D.4.a Implementation agency shall configure the

software for handheld device and configure

the interface with handle held device with

Meridium and is for 30 numbers of routes

having 10 nos. equipment in each route

with 15 tags per equipment.

30 number of routes having 10 equipment Please confirm if it is 30 routes each for

MR and KR or consolidated 30 routes

30 routes having 10 equipment for each site.

BHGE 9 Page 44 4 Communicate the following information

that

was documented in previous steps of the

work process:

- The updated strategy profile.

- What changed from the original strategy?

- Why the updated strategy was selected.

- The return on investment value.

- The risk reduction numbers.

Strategies for Pipelines Is this for ASM Implementation only? This is part of ASM strategy.

Page 21: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries

Bidder Sr

No

Tender

Page

No

Clause

No

Clause Clause details Bidder's Query BPCL response to bidder's queries

BHGE 10 Page 46 5.a Facilitators from the implementation

agency shall facilitate BPCL to perform 10

(Ten) Root Cause Analysis (RCA) for

Mumbai Refinery, 10 (Ten) RCA analysis at

Kochi Refinery and 2 (two) RCA analysis for

Pipelines. These shall be suitably selected

from various disciplines like static, rotary,

electrical, instrumentation & process etc.

Perform RCA for MR/KR/Pipeline There are many dependencies on BPCL

internal team. While SME will facilitate

during the process, however successful

completion shall depend on data

collection by BPCL.

Noted.

BHGE 11 Page 48 18 Carry out RBI analysis of 10 (ten) PSVs at

each site

RBI for PSV's at each site` Does it also include Pipelines? PSVs of each site shall include some PSVs of

respective pipelines.

BHGE 12 Page 48 22d Implementation Agency shall help to bring

15 tags each from Process Historian and set

the IOW limits and also to add these as

health indicators for MR and KR refinery

pipelines.

Bring 15 tags from Process Historian AH is also suggesting 15 tags - is it same or

separate 15 tags?

These 15 nos. are separate for pipelines.

BHGE 13 Page 49 28c Meridium shall help BPCL to bring 15 tags

from Process Historian and set the IOW

limits and also to add these as health

indicators

Bring 15 tags from Process Historian AH is also suggesting 15 tags - is it same or

separate 15 tags?

These 15 nos. are for RBI.

BHGE 14 Page 53 25 There may be incidences of work getting

affected due to site team members not

available for some time due to exigencies,

emergencies and plant shutdowns for a

maximum period of one month.

Implementation agency shall plan the

activities accordingly such that there is no

involvement of our site member during

such period.

Unavailability of BPCL Delay in project due to unavailability of

BPCL Team shall not be accounted for LD.

No change in tender clause. You may plan job

accordingly.

BHGE 15 Page 61 14 Data for BORL Refinery, COT & VBPL shall

be filtered, the Data visible to a user shall

only be restricted to that of his site.

Administrator should be able to provide

read only access to each other’s data on

internal approval.

Site Filtering What is COT and VBPL? Is site filtering

required within BORL instance?

COT is Crude Oil Terminal and VBL is Vadinar Bina

Pipeline. No filtering is required.

BHGE 16 Page 64 7 15 equipment from each site i.e. BORL, COT

and VBPL shall be linked to ASM

ASM for 45 assets Is this different from the Assets defined in

Annexure D?

No. They are different.

BHGE 17 Page 65 5c Facilitators from the implementation

agency shall facilitate BORL to create 2

(Two) Reliability Distribution Analysis each

for HGU and HCUDHDT Complex

2 RA for HGU and HCU-DHDT Does that mean that these are 4 additional

RA's apart from the list of 45 RA's as

defined in Annexure-D?

No. They are different.

BHGE 18 Page 67 24 RBI analysis of 10 nos. PSVs each in HGU

and HCU-DHDT complex

RBI for PSV's at each site` Is this really applicable since point 28

contains the breakdown where RBI needs

to be performed?

RBI analysis of 10 PSVs to be done which is not

covered in point no. 28.

Page 22: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries

Bidder Sr

No

Tender

Page

No

Clause

No

Clause Clause details Bidder's Query BPCL response to bidder's queries

BHGE 19 Page 67 27 In combination with Metrics and

scorecards, BORL intends to create Key

Performance Indicators to be displayed on

the dashboards. Those KPIs shall be for the

entire work process. With the help of

implementation agency, BORL shall create

10 (Ten) KPIs that are to be monitored on a

scheduled basis at each site. The

implementation agency should suggest

best practice followed and suitable KPIs

suitable for BORL work processes.

10 KPI's for each Is this in addition to the 30 KPI's that we

have already defined in Metrics on Page

59?

These are separate in addition to 30 KPIs.

BHGE 20 Page 68 31 Hand holding shall include the following.

Handholding shall start only after software

go-live

Handholding Is this in scope in addition to Point 28? Or

this is in addition to RBI Scope defined?

Not connected to point no. 28.

BHGE 21 Page 70 M Site teams will provide the data initially in

Microsoft word/excel format. All required

conversions of provided data in to other

required formats/templates shall be carried

out by Implementation agency. BORL core

team will not carry out any conversion of

data in to other required formats.

Data in Excel Sheets If the data conversion is far complicated

compared to initially estimated, will BPCL

approve change requests for the same?

No changer request will be entertained.

BHGE 22 Page 80 7B APM Interface with other sources OLEMS Integration What is the use case to integrate to

OLEMS?

OLEM( On Line Energy Management) System

(Siemens SENTRON Power manager V3.1) will be

helpful to validate the health of equipment

through monitoring the power consumption at

feeder/equipment level.

BHGE 23 Page 83 14a The implementation agency shall create

one dashboard each for all the work

processes. The dashboard content shall be

discussed with NRL during the FDS

workshops. Role based Dash board or

home page is to be created for different

users of different departments

Role Based Dashboard For each work process, one dashboard is

required for one role only?

For each work process, one dash board is

required and content shall be given rolewise.

BHGE 24 Page 84 3d Handheld devices for rounds for identified

parameters. (Presently NRL plans to

develop the functionality for this

requirement. Actualimplementation shall

be done at later stage.)

Handheld Devices Which handheld to be interfaced and it

should be compatible to Meridium.

This can be discussed during FDS.

BHGE 25 Page 85 E6 Subject matter experts from

implementation agency shall help NRL

team for applying complete work process

for HCU unit.

Complete Work Process for HCU Unit Repetition of Pg83 14c. Both should be done together.

Page 23: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries

Bidder Sr

No

Tender

Page

No

Clause

No

Clause Clause details Bidder's Query BPCL response to bidder's queries

BHGE 26 Page 88 23 RBI analysis of PSVs of Hydro-cracker Unit PSV of HCU Repetition of Point 27 in Page 89 RBI analysis of 10 PSVs to be done which is not

covered in point no. 27.

BHGE 27 Page 88 26 In combination with Metrics and

scorecards NRL intends to create Key

Performance Indicators to be displayed on

the dashboards. Those KPIs shall be for the

entire work process. With the help of

implementation agency, NRL shall create 10

(Ten) KPIs that are to be monitored on a

scheduled basis at

each site. The implementation agency

should suggest best practice followed

and suitable KPIs suitable for NRL work

processes

Create 10 KPI's Considering Repitition - Already covered in

Page 81 C1f

These are separate in addition to 30 KPIs.

Page 24: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 : Corrigendum 1 - Reply to Bidder Queries

Bidder Technical/

non-technical

Sr No Tender

Page No

Clause

No

Clause Query BPCL Response

Wipro Non-technical 7 6 OFFER VALIDITY- The Offers shall be

valid for a period of 180 days from Tender

Due Date / Extended

Tender Due Date for placement of order.

The Offers shall be valid for a period of 180

days from Tender Due Date / Extended

Tender Due Date for placement of order.

BPCL Tender condition prevails.

Wipro Non-technical 24 Section 5 (1) The Bidder declares that no previous

transgression occurred in the last 3 years

with any other Company in any country

conforming to the TI approach or with any

other

Public Sector Enterprise in India that could

justify his exclusion from the tender

process.

The Bidder declares that no previous

transgression occurred in the last 3 years with

any other Government Company in any country

India conforming to the TI approach or with

any other

Public Sector Enterprise in India that could

justify his exclusion from the tender process.

BPCL Tender condition prevails.

Wipro Non-technical 54 N The scope of services shall be completed as

per the time schedule and to the full

satisfaction of site teams and in case the

Implementation agency fail to complete the

whole work within the stipulated period

from the date of purchase order, they shall

be liable to pay Liquidated Damages (LD)

of 0.5% of the lump sum fee per week or

part thereof of delay subject to a maximum

of 5% of the lump sum fee or part thereof.

The scope of services shall be completed as per

the time schedule and to the full satisfaction of

site teams and in case the Implementation

agency fail to complete the whole work within

the stipulated period from the date of purchase

order, they shall be liable to pay Liquidated

Damages (LD) of 0.5% of the lump sum fee of

the undelivered portion per week or part

thereof of delay subject to a maximum of 5% of

the lump sum fee or part thereof.

BPCL Tender condition prevails.

Wipro Non-technical 76 N The scope of services shall be completed as

per the time schedule and to the full

satisfaction of site teams and in case the

Implementation agency fail to complete the

whole work within the stipulated period

from the date of purchase order, they shall

be liable to pay Liquidated Damages (LD)

of 0.5% of the lump sum fee per week or

part thereof of delay subject to a maximum

of 5% of the lump sum fee or part thereof.

The scope of services shall be completed as per

the time schedule and to the full satisfaction of

site teams and in case the Implementation

agency fail to complete the whole work within

the stipulated period from the date of purchase

order, they shall be liable to pay Liquidated

Damages (LD) of 0.5% of the lump sum fee for

the undelivered portion per week or part

thereof of delay subject to a maximum of 5% of

the lump sum fee or part thereof. Attributable

to MR and MK implementation value

BPCL Tender condition prevails.

Page 25: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 : Corrigendum 1 - Reply to Bidder Queries

Bidder Technical/

non-technical

Sr No Tender

Page No

Clause

No

Clause Query BPCL Response

Wipro Non-technical 76 N The scope of services shall be completed as

per the time schedule and to the full

satisfaction of site teams and in case the

Implementation agency fail to complete the

whole work within the stipulated period

from the date of purchase order, they shall

be liable to pay Liquidated Damages (LD)

of 0.5% of the lump sum fee per week or

part thereof of delay subject to a maximum

of 5% of the lump sum fee or part thereof.

The scope of services shall be completed as per

the time schedule and to the full satisfaction of

site teams and in case the Implementation

agency fail to complete the whole work within

the stipulated period from the date of purchase

order, they shall be liable to pay Liquidated

Damages (LD) of 0.5% of the lump sum fee for

the undelivered portion per week or part

thereof of delay subject to a maximum of 5% of

the lump sum fee or part thereof. Attributable

to BORL implementation value

BPCL Tender condition prevails.

Wipro Non-technical 97 N The scope of services shall be completed as

per the time schedule and to the full

satisfaction of site teams and in case the

Implementation agency fail to complete the

whole work within the stipulated period

from the date of purchase order, they shall

be liable to pay Liquidated Damages (LD)

of 0.5% of the lump sum fee per week or

part thereof of delay subject to a maximum

of 5% of the lump sum fee or part thereof.

The scope of services shall be completed as per

the time schedule and to the full satisfaction of

site teams and in case the Implementation

agency fail to complete the whole work within

the stipulated period from the date of purchase

order, they shall be liable to pay Liquidated

Damages (LD) of 0.5% of the lump sum fee for

the undelivered portion per week or part

thereof of delay subject to a maximum of 5% of

the lump sum fee or part thereof. Attributable

to NRL implementation value

BPCL Tender condition prevails.

Page 26: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 : Corrigendum 1 - Reply to Bidder Queries

Bidder Technical/

non-technical

Sr No Tender

Page No

Clause

No

Clause Query BPCL Response

Wipro Non-technical 116 13 To ensure performance of the contract and

due discharge of the contractual

obligations, the successful contractor will

have to provide security deposit of 10% of

the contract

value within 30 days of receipt by him of

the notifications of acceptance of tender.

This Security deposit may be furnished in

the form of an Account payee Demand

Draft payable to BPCL or Bank Guarantee

in the prescribed format. The contractor

shall have

the option to adjust any Earnest Money

Deposit (EMD), if paid in forms other than

Bank Guarantee, towards security deposit if

he so desires.

In the case of security deposit submitted in

the form of Bank guarantee, the Bank

Guarantee shall be valid and remain in

force till the completion of contractual

completion

period, defect liability period of 12 months

plus a claim period of 3 months. The Bank

Guarantee shall be in the form prescribed.

The security deposit will be retained till the

successful completion of the work and

thereafter till the expiry of the defect

To ensure performance of the contract and due

discharge of the contractual obligations, the

successful contractor will have to provide

security deposit of 10% of the contract

value within 30 days of execution of Contract

receipt by him of the notifications of acceptance

of tender.

This Security deposit may be furnished in the

form of an Account payee Demand Draft

payable to BPCL or Bank Guarantee in the

prescribed format. The contractor shall have

the option to adjust any Earnest Money Deposit

(EMD), if paid in forms other than Bank

Guarantee, towards security deposit if he so

desires.

In the case of security deposit submitted in the

form of Bank guarantee, the Bank Guarantee

shall be valid and remain in force till the

completion of contractual completion

period, defect liability period of 12 months plus

a claim period of 3 months. The Bank Guarantee

shall be in the form prescribed.

The security deposit will be retained till the

successful completion of the work and thereafter

till the expiry of the defect liability period, if

applicable. This retention

money/Bank guarantee held shall be released

BPCL Tender condition prevails.

Wipro Non-technical 117 14 Forfeiture of Security Deposit Whenever any claim against the Consultant for

the payment of a sum of money arises out of or

under the contract, the BPCL shall be entitled to

recover such sum from the amount due to the

consultant and if still there is any amount over

and above the the sume due, same has to be

intimated to the consultant if consultant haven't

responded with in 30 days of notice same can be

forfeited from security deposit.

BPCL Tender condition prevails.

Wipro Non-technical 1. Can BPCL provide accommodation for

Project team member at NRL township

guesthouse?

NRL Response : No accomodation shall

be provided by NRL.

Page 27: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 : Corrigendum 1 - Reply to Bidder Queries

Bidder Technical/

non-technical

Sr No Tender

Page No

Clause

No

Clause Query BPCL Response

TCS Non-technical 45 4/148 5.1 The interest-free Earnest Money Deposit

(EMD) of Rs 1.00,000/- (Rupees One

Lakh Only) to be submitted by way of

crossed account payee Demand Draft

drawn

on any nationalized / scheduled bank in

favour of "BHARAT PETROLEUM

CORPORATION LTD" payable at

Mumbai. The EMD shall be arranged prior

to

the due date & time of opening of the "Pre-

qualification Bid".

Kindly reduce the EMD amount to Rs 50,000. BPCL Tender condition prevails.

TCS Non-technical 46 7/148 6.0 The Offers shall be valid for a period of

180 days from Tender Due Date / Extended

Tender Due Date for placement of order

Kindly reduce the validity to 90 days. BPCL Tender condition prevails.

TCS Non-technical 47 54/148 L) a) PAYMENT TERMS FOR MR & KR Kindly provide 15% advance at the time of

project kick off & 100% by Go Live.

BPCL Tender condition prevails.

TCS Non-technical 48 75/148 L)A) PAYMENT TERMS FOR BORL Kindly provide 15% advance at the time of

project kick off & 100% by Go Live.

BPCL Tender condition prevails.

TCS Non-technical 49 97/148 L)A) PAYMENT TERMS FOR NRL Kindly provide 15% advance at the time of

project kick off & 100% by Go Live.

BPCL Tender condition prevails.

TCS Non-technical 50 116/148 13 In the case of security deposit submitted in

the form of Bank guarantee, the Bank

Guarantee shall be valid and remain in

force till the completion of contractual

completion

period, defect liability period of 12 months

plus a claim period of 3 months. The Bank

Guarantee shall be in the form prescribed.

Kindly accept a validity till contract completion

+ 3 months claim period.

BPCL Tender condition prevails.

TCS Non-technical 51 116/148 13 To ensure performance of the contract and

due discharge of the contractual

obligations,

the successful contractor will have to

provide security deposit of 10% of the

contract

value within 30 days of receipt by him of

the notifications of acceptance of tender

Kindly reduce the security deposit to 5% of

contract value

BPCL Tender condition prevails.

Page 28: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 : Corrigendum 1 - Reply to Bidder Queries

Bidder Technical/

non-technical

Sr No Tender

Page No

Clause

No

Clause Query BPCL Response

TCS Non-technical 5.7 EMD of other unsuccessful bidders shall be

released after declaration of the successful

bidder issuance of FOA/LOA/contract Order

against this tender. However, in case of

successful bidder the EMD shall be released on

receipt of performance bank guarantee.

Noted.

TCS Non-technical 5.9 The Earnest Money deposited by successful

tenderer shall be forfeited if the successful

tenderer fails to sign the mutually agreed

contract. honour the offer terms prior to ordering

and Contractual terms after issuance of

FOA/LOA/contract Order.

BPCL Tender condition prevails.

TCS Non-technical 53 13 15.12 Firm Prices Subject to the cost escalation provision agreed

by the parties, tThe Contract Price shall remain

firm and fixed till the completion of Work in all

respects and no escalation in prices on any

account shall be admissible to the BIDDER /

CONTRACTOR

BPCL Tender condition prevails.

TCS Non-technical All invoices and bills will be raised by Bidder as

per the Payment Terms and will become due for

payment within thirty (30) days of presentation.

All payments due for more than thirty (30) days

will attract an interest at the rate of 2 percent

per month on the invoice amount calculated

from the date the payment became due until the

recovery is made in full with interest. Without

prejudice to the other rights available, Bidder

also reserves the right to withhold the provision

of Services till such time all the payments due to

it under this Agreement have been made by

Bank and any such withholding by the Bidder

shall not be treated as breach by it of the

provisions of this Agreement.

TCS Non-technical

TCS Non-technical The scope of services shall be completed as per

the time schedule and to the full

TCS Non-technical satisfaction of site teams and in case the

Implementation agency fail to complete

52 7-Apr 5 Earnest Money Deposit (EMD)

57 54/76/97 Annexure-

1/Annexure-

2/Annexure-3

N: Liquidated Damages

BPCL Tender condition prevails.

BPCL Tender condition prevails.

Page 29: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 : Corrigendum 1 - Reply to Bidder Queries

Bidder Technical/

non-technical

Sr No Tender

Page No

Clause

No

Clause Query BPCL Response

TCS Non-technical the whole work within the stipulated period

from the date of purchase order, they

TCS Non-technical shall be liable to pay Liquidated Damages (LD)

of 0.5% of value of goods/equipment or the

particular phase/part of the contract in relation

to which delay has occurred the lump sum fee

per

TCS Non-technical week or part thereof of delay subject to a

maximum of 5% of the value of

goods/equipment or the particular phase/part of

the contract in relation to which delay has

occurred lump sum fee or

TCS Non-technical part thereof.

TCS Non-technical

TCS Non-technical The Liquidated Damages will be applicable

provided the delay is due to the reasons solely

and directly attributable to the Bidder and not

due to BPCL or its vendors/customers and Force

Majeure conditions.

PwC Non-technical 1 112 Sec 2 of GCC Proprietary information and data: The

standard exclusion to confidentiality have

not been documented.

Survival – There is no outer boundary for

survival of confidentiality obligations

This restriction shall be applicable for a period

of six (6) months from the termination or expiry

of the contract. The confidentiality obligations

under the contract will not apply to information

already in the public domain or available to us

independently of this contract

Further, it is clarified that ownership of any Pre-

exisitng work by Bidder shall vest in Bidder.

Bidder shall transfer the ownership of the

deliverables and reports upon receiving the

payments thereof.

BPCL Tender condition prevails.

PwC Non-technical 2 113 Sec 3 of GCC IPR infringement indemnity The references to indemnity should be deleted,

the reason being in the event of a dispute the

aggrieved party will have adequate recourse to

court/arbitration.

BPCL Tender condition prevails.

Page 30: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 : Corrigendum 1 - Reply to Bidder Queries

Bidder Technical/

non-technical

Sr No Tender

Page No

Clause

No

Clause Query BPCL Response

PwC Non-technical 3 118/119 Sec 16 & 19

of GCC

Time is of essence of the contract. LDs -

In case the contractor fails to complete the

whole work within the stipulated period, he

shall be liable to pay liquidated damages of

0.5% of the value of contract per week and

or part thereof of the delay subject to a

maximum of

5% of the value of the contract.

It is clarified that delivery of goods & serives

shall be as per mutually agreed delivery

schedule. LDs shall be applicable only for

delays solely attributable to PwC. Further, LD

shall be the sole remedy for Client in case of

delay in delivery.

BPCL Tender condition prevails.

PwC Non-technical 4 120 Sec 24 & 25

of GCC

BPCL has the right to employ a 3rd party to

have the work done at the cost & risk of

Bidder

It is clarified that PwC does not assume a

liability for any part of our scope of work which

is performed by anyone else, or for the payment

obligations to such person/ entity.

BPCL Tender condition prevails.

PwC Non-technical 5 121 Sec 26 Liabilities: Unlimited liabilities for

following:

(a) In the event of breach of any Applicable

Law;

(b) In the event of fraud, willful misconduct

or illegal or unlawful acts, or gross

negligence of the Contractor or any person

acting on behalf of the Contractor; or

(c) In the event of acts or omissions of the

Contractor which are contrary to the most

elementary rules of diligence which a

conscientious Contractor would have

followed in similar circumstances; or

(d) In the event of any claim or loss or

damage arising out of infringement of

Intellectual Property; or

(e) For any damage to any third party,

including death or injury of any third party

caused by the Contractor or any person or

firm acting on behalf of the Contractor in

executing the Works.

Our overall liability shall not exceed the amount

of fees paid to us under the engagement without

any exceptions. We will not be liable for

indirect/consequential losses.

BPCL Tender condition prevails.

Page 31: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 : Corrigendum 1 - Reply to Bidder Queries

Bidder Technical/

non-technical

Sr No Tender

Page No

Clause

No

Clause Query BPCL Response

PwC Non-technical 6 121 Sec 28 Industrial & Intellectual property:

Indemnity obligations and ownership rights

fo BPCL for all documents, reports,

information, data collected and prepared by

Consultant in connection with the scope of

work submitted to BPCL

As clarified above, references to indemnity

should be deleted, the reason being in the event

of a dispute the aggrieved party will have

adequate recourse to court/arbitration.

Further, ownership of any Pre-exisitng work by

Bidder shall vest in Bidder. Bidder shall transfer

the ownership of the deliverables and reports

upon receiving the payments thereof.

BPCL Tender condition prevails.

PwC Non-technical 7 122 Sec 29 Liens: If, at any time, there should be

evidence or any lien or claim for which

BPCL might have become liable and which

is chargeable to the Consultant, BPCL shall

have the right to retain out of any payment

then due or thereafter to become due an

amount sufficient to completely indemnify

BPCL against such lien or claim and if such

lien or claim be valid, BPCL may pay and

discharge the same and deduct the amount

so paid from any money which may be or

may become due and payable to the

Consultant.

It is clarified that lien on any amounts payable to

PwC is not acceptable.

BPCL Tender condition prevails.

PwC Non-technical 8 126 Sec 35 Risk Purchase clause It is clarified that Risk Purchase is not

acceptable as PwC does not assume a liability

for any part of our scope of work which is

performed by anyone else, or for the payment

obligations to such person/ entity.

BPCL Tender condition prevails.

PwC Non-technical 9 Right to Audit We will retain our records as per our record

retention policies. Upon reasonable notice we

will allow client to inspect our invoicing records

under this engagement; such inspection shall be

done in a pre agreed manner and during normal

business hours. For avoidance of doubt, such

inspection should not cause us to be in breach of

our organisational confidentiality requirements

BPCL Tender condition prevails.

Page 32: TENDER FOR IMPLEMENTATION OF ASSET INTEGRITY …

E-tender : 31011 : Corrigendum 1 - Reply to Bidder Queries

Bidder Technical/

non-technical

Sr No Tender

Page No

Clause

No

Clause Query BPCL Response

PwC Non-technical 10 Conflict Nothing in this engagement shall affect our or

other PwC firms’ ability to perform services for

our other clients so long as we do not use or

disclose your confidential information

BPCL Tender condition prevails.

PwC Non-technical 11 Subcontracting We may take assistance from our contractors or

other PwC firms (each of which is a separate

and independent) legal entity and may share

confidential information with them in

connection with this engagement. However we

remain solely liable to client for their acts;

claims (if any) in relation to this engagement

will be routed solely through client and us

BPCL Tender condition prevails.

BHGE Non-technical 28 Page 122 30 The Consultant shall not sub-let or assign the

work or any part thereof to another party

without the written consent of BPCL and no

such sub-letting or assignment shall relieve

the Consultant from full and entire

responsibility of his obligation under the

Agreement.

As part of our proposal, OEM would like to sublet to

other agencies to give the best and most optimum

proposal to BPCL. We will clearly state in the

proposal which external parties we are subletting

the work to. If BPCL finds external agencies in

Holiday Listing, BPCL has the right to cancel our bid.

While we will be sub-letting the work to other

partner agencies, we will own the entire delivery of

the project and BPCL shall hold us liable for

execution of this project.For execution ease &

utililize our internal best resources effectively and

to offer our best & optimal proposal, we will

subcontract this order to its affiliate group entity as

clearly stipulated in our proposal. Hence

consulatant will have right to sub-contract/ sublet

this order to any of their affiliate group entity

without BPCL approval..

BPCL Tender condition prevails.