E-tender System ID : 31011
CORRIGENDUM NO. 1
TENDER FOR
IMPLEMENTATION OF
ASSET INTEGRITY MANAGEMENT SYSTEM (AIMS)
AT BPCL GROUP REFINERIES
E-Tender System ID: 31011
E-tender System ID : 31011
1.0 SCOPE OF THIS CORRIGENDUM
1.1 This Corrigendum 1 is issued to clarify queries raised by bidders for the abovementioned
tender.
1.2 Except for details mentioned herein, all other details contained in the abovementioned tender enquiry, shall remain applicable and unchanged.
2.0 EXTENSION OF BID SUBMISSION DATE
2.1 The extended due date for submission of bids is 11:00 Hrs IST of 22.12.2017. 3.0 TECHNICAL QUERIES
3.1 BPCL response to the technical queries raised by bidders has been attached. 4.0 NON-TECHNICAL / COMMERCIAL / LEGAL QUERIES
4.1 BPCL response to the commercial queries raised by bidders has been attached. 4.2 With response to Non-Technical / Legal Queries, bidders are requested to abide by the BPCL tender terms and conditions. No additional or counter offer/condition/meaning is acceptable at this stage of tendering.
E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries
Bidder Sr
No
Tender
Page
No
Clause
No
Clause Clause details Bidder's Query BPCL response to bidder's queries
Wipro 1 35 6 ANNEXURE-1- SCOPE OF WORK FOR BPCL
MR & KR
Work shop
shall be held at BPCL MR and KR
Workshop will be required at both the
place? MR & KR.
Few FDS workshops shall be conducted at MR
and few at KR.
Wipro 3 42 12 Implementation agency shall help BPCL to
select and create 30 Policies to take
intelligent actions based on the IOW limits
of Health Indicator
Implementation agency shall help BPCL to select and create 30 Policies to take
intelligent actions based on the IOW limits of Health Indicator
This will be performed by BPCL user with
our SME Support?
Implemenattion agency shall create 30 nos.
policies with support from BPCL team.
Wipro 4 39 B UPGRADE OF EXISTIING AIMS APM
SOFTWARE INCLUDING INSTALLATION OF
NEW MODULES OF APM SOFTWARE
ALONG WITH DATABASE MERGING FOR
MR AND KR
APM Interface with other source Current Implemented APM have these
interface ? What type of Data exchange is
required? Automatic or schedule synch.?
Currently, APM has interface with SAP solution.
Some data to be synchronized automatic, some
periodic and some scheduled.
Wipro 5 43 4 APM HEALTH Handholding shall start only after software go-live at all sites. Software go live
shall take place after successful completion of configuration and testing.
Handholding shall be carried out for the following:
a) Implementation agency shall configure the software for handheld device and
configure the interface with handle held device with Meridium and is for 30
numbers of routes having 10 nos. equipment in each route with 15 tags per
equipment.
b) The implementation agency shall handhold BPCL to create 15 health
indicators each for MR, KR & pipelines (total 45 nos.).
Is vendor responsible for Data collection
using Handheld devices?
Implementation agency shall configure the hand
held devices in APM, configure interfaces,
customizations if any and hand hold. However,
BPCL will carry the hand held devices to plant and
take data for which implementation agency shall
guide initially.
Wipro 6 55 B ANNEXURE-2 IMPLEMENTATION OF ALL MODULES OF APM SOFTWARE
Implementation Agency shall carry out Software Installation on Server
Operating System Windows Server 2012 or later version (64 Bit) and SQL
Server 2014 or later version (64 Bit) on Physical Server Hardware and/or
Virtual Server (on VMware/Citrix platform) and/or public cloud.
Operating System, Database and APM Software and required hardware will be
provided by BORL.
Do we need to consider the cloud cost for
DR setup?
No.
Wipro 7 67 28 RBI reference drawing and Documents Implementation agency shall carry out Risked Based Analysis (RBI) for HGU
and HCU- DHDT complex.
Approximate quantity of static equipment, P & ID, PFD / MFD is given as below.
Is it paper based P&ID or CAD format? Available in PDF format.
Wipro 35 Annexur
e 1
Scope of work- As per RFP Request deletion of "including…but not limited to" as this makes the scope open ended No change in tender clause.
Wipro 51 J SPECIAL CONDITIONS: The work days shall be
Monday to Friday for all sites unless otherwise
specified. In case of exigencies, working will be
extended on closed days and holidays without
extra cost.
The work days shall be Monday to Friday for all sites unless otherwise specified. In case
of exigencies, working will be extended on closed days and holidays without extra cost.
mutually agreed terms and conditions
No change in tender clause.
E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries
Bidder Sr
No
Tender
Page
No
Clause
No
Clause Clause details Bidder's Query BPCL response to bidder's queries
Wipro 52 J SPECIAL CONDITIONS:No accommodation, travel
assistance, food, lodging and boarding will be
provided to Implementation agency.
Implementation agency will have to arrange all
travel, food, and accommodation,
lodging/boarding at their cost to their staff on
the work of this tender or any other work
related to this tender.The quoted rates shall be
inclusive of above.
No change in tender clause.
Wipro 53 J SPECIAL CONDITIONS: Any modification to the
software and processes to resolve any issues at
a site shall be replicated at other sites, if
applicable, without any extra cost.
SPECIAL CONDITIONS: Any modification to the software and processes to resolve any
issues at a site shall be replicated at other sites, if applicable, without any extra cost.
mutually agreed terms and conditions
No change in tender clause.
Wipro 53 J SPECIAL CONDITIONS: There may be incidences
of work getting affected due to site team
members not available for some time due to
exigencies, emergencies and plant shutdowns
for a maximum period of one month.
Implementation agency shall
plan the activities accordingly such that there is
no involvement of our site member during such
period.
SPECIAL CONDITIONS: There may be incidences of work getting affected due to site team
members not available for some time due to exigencies, emergencies and plant
shutdowns for a maximum period of one month. Implementation agency shall
plan the activities accordingly such that there is no involvement of our site member
during such period. In such any delay caused due to non availability of site member
should be excluded for calculating LD penalty and BPCL will pay for any idle time that
has been created due to non availability of site member
No change in tender clause.
Wipro 53 J SPECIAL CONDITIONS:In case the work gets
affected due to some interface/software issues
resulting in idling of the resources of
implementation agency and/or rescheduling of
the jobs, no extra compensation will be made.
SPECIAL CONDITIONS:In case the work gets affected due to some interface/software
issues resulting in idling of the resources of implementation agency and/or rescheduling
of the jobs, no extra cost will be paid as compensation will be made.
No change in tender clause.
Wipro 73 J SPECIAL CONDITIONS: The work days shall be
Monday to Friday for all sites unless otherwise
specified. In case of exigencies, working will be
extended on closed days and holidays without
extra cost.
The work days shall be Monday to Friday for all sites unless otherwise specified. In case
of exigencies, working will be extended on closed days and holidays without extra cost.
mutually agreed terms and conditions
No change in tender clause.
Wipro 74 J SPECIAL CONDITIONS:No accommodation, travel
assistance, food, lodging and boarding will be
provided to Implementation agency.
Implementation agency will have to arrange all
travel, food, and accommodation,
lodging/boarding at their cost to their staff on
the work of this tender or any other work
related to this tender.The quoted rates shall be
inclusive of above.
No change in tender clause.
Wipro 74 J SPECIAL CONDITIONS: Any modification to the
software and processes to resolve any issues at
a site shall be replicated at other sites, if
applicable, without any extra cost.
SPECIAL CONDITIONS: Any modification to the software and processes to resolve any
issues at a site shall be replicated at other sites, if applicable, without any extra cost.
mutually agreed terms and conditions
No change in tender clause.
E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries
Bidder Sr
No
Tender
Page
No
Clause
No
Clause Clause details Bidder's Query BPCL response to bidder's queries
Wipro 74 J SPECIAL CONDITIONS: There may be incidences
of work getting affected due to site team
members not available for some time due to
exigencies, emergencies and plant shutdowns
for a maximum period of one month.
Implementation agency shall
plan the activities accordingly such that there is
no involvement of our site member during such
period.
SPECIAL CONDITIONS: There may be incidences of work getting affected due to site team
members not available for some time due to exigencies, emergencies and plant
shutdowns for a maximum period of one month. Implementation agency shall
plan the activities accordingly such that there is no involvement of our site member
during such period. In such any delay caused due to non availability of site member
should be excluded for calculating LD penalty and BPCL will pay for any idle time that
has been created due to non availability of site member
No change in tender clause.
Wipro 74 J SPECIAL CONDITIONS:In case the work gets
affected due to some interface/software issues
resulting in idling of the resources of
implementation agency and/or rescheduling of
the jobs, no extra compensation will be made.
SPECIAL CONDITIONS:In case the work gets affected due to some interface/software
issues resulting in idling of the resources of implementation agency and/or rescheduling
of the jobs, no extra cost will be paid as compensation will be made.
No change in tender clause.
Wipro 77 Annexur
e 3
As per RFP Request deletion of "including…but not limited to" as this makes the scope open ended No change in tender clause.
Wipro 95 J SPECIAL CONDITIONS: The work days shall be
Monday to Friday for all sites unless otherwise
specified. In case of exigencies, working will be
extended on closed days and holidays without
extra cost.
The work days shall be Monday to Friday for all sites unless otherwise specified. In case
of exigencies, working will be extended on closed days and holidays without extra cost.
mutually agreed terms and conditions
No change in tender clause.
Wipro 95 J SPECIAL CONDITIONS:No accommodation, travel
assistance, food, lodging and boarding will be
provided to Implementation agency.
Implementation agency will have to arrange all
travel, food, and accommodation,
lodging/boarding at their cost to their staff on
the work of this tender or any other work
related to this tender.The quoted rates shall be
inclusive of above.
No change in tender clause.
Wipro 96 J SPECIAL CONDITIONS: Any modification to the
software and processes to resolve any issues at
a site shall be replicated at other sites, if
applicable, without any extra cost.
SPECIAL CONDITIONS: Any modification to the software and processes to resolve any
issues at a site shall be replicated at other sites, if applicable, without any extra cost.
mutually agreed terms and conditions
No change in tender clause.
Wipro 96 J SPECIAL CONDITIONS: There may be incidences
of work getting affected due to site team
members not available for some time due to
exigencies, emergencies and plant shutdowns
for a maximum period of one month.
Implementation agency shall
plan the activities accordingly such that there is
no involvement of our site member during such
period.
SPECIAL CONDITIONS: There may be incidences of work getting affected due to site team
members not available for some time due to exigencies, emergencies and plant
shutdowns for a maximum period of one month. Implementation agency shall
plan the activities accordingly such that there is no involvement of our site member
during such period. In such any delay caused due to non availability of site member
should be excluded for calculating LD penalty and BPCL will pay for any idle time that
has been created due to non availability of site member
No change in tender clause.
E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries
Bidder Sr
No
Tender
Page
No
Clause
No
Clause Clause details Bidder's Query BPCL response to bidder's queries
Wipro 96 J SPECIAL CONDITIONS:In case the work gets
affected due to some interface/software issues
resulting in idling of the resources of
implementation agency and/or rescheduling of
the jobs, no extra compensation will be made.
SPECIAL CONDITIONS:In case the work gets affected due to some interface/software
issues resulting in idling of the resources of implementation agency and/or rescheduling
of the jobs, no extra cost will be paid as compensation will be made.
No change in tender clause.
Wipro Upgrade/Update/fixation of Patches Notwithstanding anything contrary elsewhere mentioned in the contract any
upgrade/update/fixation to the patches in software shall be at an additional cost to
BPCL
BPCL group refineries are procuring software
license along with maintenance and support.
APM Software down load will be provided by
BPCL. Bidder shall install the software. Any
patches, downloads of patches/bug fixes will be
provided by BPCL. However, implementation shall
be done by bidder during implementation work at
no extra cost.
Wipro 2. What is the length of MR & KR pipeline
section?
1) Mumbai Uran LPG pipeline section length
approximateley 28 km at MR.
2) Santacruz ATF pipeline length approximately 14
km at MR.
3) Kochi ATF pipeline length approximately 34 km
at MR.
4) CCK pipeline section length approximately 40
km at KR.
Wipro 3. Does vendor we need to have separate
PM for different sites?
Separate project manager shall be deployed for
each site.
Wipro 4. Can vendor share Data and document
soft copy to offshore team?
Implementation agency can share
data/documents with off-shore team with
confidentiality agreement with BPCL/BORL/NRL.
TCS 1 35 Annexure-1, AFUNCTIONAL DESIGN SPECIFICATION Implementation Agency shall conduct a common workshop for FDS for all
modules / work processes listed in Annexure-A for BPCL MR & KR. Work shop
shall be held at BPCL MR and KR. Implementation Agency shall submit the FDS
to BPCL Team for approval.
As BPCL refered to common workshop for
FDS, we assume common workshop to be
held at either MR or KR. Please confirm.
Few FDS workshops shall be conducted at MR
and few at KR.
E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries
Bidder Sr
No
Tender
Page
No
Clause
No
Clause Clause details Bidder's Query BPCL response to bidder's queries
TCS 2 38 Annexure-1, B, 12, aAPM SAP Interfaces APM interfaces with SAP through PO or direct for the following to be done:
a. Equipment - Interfacing from SAP to APM
b. Functional Location - Interfacing from SAP to APM
c. Work History & work history detail - Interfacing from SAP to APM
d. Equipment Technical Characteristics - Interfacing from SAP to APM
e. Functional Location Technical Characteristics - Interfacing from SAP to APM
f. Work Management - Interfacing from SAP to APM
g. Notification Management - Interfacing from APM to SAP
h. Work Order Management - Interfacing from APM to SAP
i. ACA Adaptor - Direct Interfacing from APM to SAP
j. ASI Adaptor - Direct Interfacing from APM to SAP
This query has to be sent to software OEM
to confirm whether interfaces listed under
this clause are compatible with BPCL SAP
PO and ECC versions
TCS assumes the functionalities are built-
in and compatible with BPCL SAP software
and We will facilitate Deploy,
configure,Deploy ,Data transfer,Test and
Validate of existing interface in APM
software as required by BPCL, Please
confirm.
Yes all the adaptors are avilable as product
functionality. Configuration will have to be done
by respective implementation agency. This is
compatible with SAP ECC 6 EHP 5.0 and above.
TCS 3 38/39 Annexure-1, B, 12, bAPM Interfaces with other sources APM interfaces with following to be done:
a. ASPEN IP21,
b. LIMS,
c. STAR LIMNS,
d. BPMAI-XHQ,
e. EDMS-COSMOS,
f. EMERSON AMS SUITE,
g. SYSTEM-1.
This query has to be sent to software OEM
to confirm whether interfacing facility to
the listed softwares available by default in
Meridium APM software.
Whether BPCL has confirmation from
product vendor about the required
functionalities are avaialble in Standard
Product or not .Please confirm
TCS assumes the functionalities are built-
in the software and We will facilitate
Deploy, configure,Deploy ,Data
transfer,Test and Validate of existing
interface in APM software as required by
BPCL, Please confirm.
a. The following standard adaptors will be
available with APM.
1) ASPEN IP21.
2) EMERSON AMS SUITE.
3) SYSTEM-1.
APM Connect studio is being supplied for creating
custom interfaces. Implementation agency shall
build custom interfaces for the following during
implementation using APM connect studio based
on functional requirement analysis.
1) LIMS.
2) STAE LIMS.
3) BPMAI-XHQ.
4) EDMS-COMOS.
During FDS, implementation agency shall identify
the requirement and specification for all interface
adaptors on other third party software/systems.
Adaptors identified on third party system side
shall be made available by BPCL/BORL/NRL.
However, installation and required configuration
shall be done by implementation agency with no
additional cost.
E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries
Bidder Sr
No
Tender
Page
No
Clause
No
Clause Clause details Bidder's Query BPCL response to bidder's queries
TCS 4 39 Annexure-1, B, 13Bulk uploading Bulk uploading facility.
The following bulk uploading using excel sheets shall be made available
a. TML bulk creation and upload.
b. Bulk up load of asset data.
c. TML measurement data.
d. Asset Criticality Analysis upload.
e. RBI component creation, analysis and re-analysis.
f. Task creation in bulk.
g. PV stress including addition, deletion or modification to look up table for
stress values for TM evaluation.
h. Template for inspection profiles and inspection methods.
i. Functional Aspects - building, modification and provide access control for
the following.
I. Query, Report, Graphs etc
II. Dash board, score card
III. Alerts
IV. Scheduling of task, data extraction scheduler
j. Mapping fields for interfacing the Meridium with third party software
k. Bulk upload of check list
l. Bulk upload of Vibration reading from vibration data collector
m. Asset Criticality Analysis data.
n. Measurement location and their IOW limits.
TCS assumption is all the required loaders
are available in software by default.Please
confirm.
Base line data loader will be available for TML
bulk creation and upload, Bulk up load of asset
data, TML measurement data, Asset Criticality
Analys upload, RBI component creation, analysis
and re-analysis, RBI Components and RBI analysis,
Task creation in bulk, PV stress including addition,
deletion or modification to look up table for
stress values for TM evaluation (Can be done
using APM Family loader, some configuration
expected), Template for inspection profiles and
inspection methods, Asset Criticality Analysis
data, Measurement location and their IOW limits
(Loader available for ML Limits), Bulk upload of
Vibration reading from vibration data collector
(can be uploaded as reading against
measurement location).
• Bulk upload of check list - No loader for
uploading checklists eixists. For existing checklists
we can use APM Family Loader, some
configuration expected. But, creating new
checklist is configuration and not possible
through a data loader.
Beyond these, there are generic data loaders
available for any other data to be loaded.
Data loaders are not applicable for the below:TCS 5 42 Annexure-1, C, 15, bACA Perform Asset Criticality Analysis for assets within one unit for KR and
one unit for MR and one pipe line as follows:
MR- NHT-CCR Plant
KR- NHT-CCR complex
Pipeline- Mumbai-Uran Pipeline
Need to clarify the counts of approximate
number of Assets for ACA for
MR- NHT-CCR Plant
KR- NHT-CCR complex
Pipeline- Mumbai-Uran Pipeline ..?
Please confirm.
BPCL Response:
KR: The asset count for NHT-CCR in BPCL KR is
400 which includes drivers & driven equipments.
MR: The asset count for NHT-CCR in BPCL MT is
350 which include drivers and driven equipment.
Mumbai-Uran pipeline: There are 4 nos. rotary
equipment in pipeline (2 main pums+2 booster
pumps). These also have drivers etc.
TCS 6 43 Annexure-1, C, 15, dRCM Carryout RCM of rotary equipments of Mumbai-Uran pipeline. Please provide number of approximate
rotary equipment of Mumbai-Uran
Pipeline
Mumbai-Uran pipeline: There are 4 nos. rotary
equipment in pipeline (2 main pums+2 booster
pumps). These also have drivers etc.
E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries
Bidder Sr
No
Tender
Page
No
Clause
No
Clause Clause details Bidder's Query BPCL response to bidder's queries
TCS 4 43 Annexure-1,D,4,aOperator Round Implementation agency shall configure the software for handheld device
and configure the interface with handle held device with Meridium and is
for 30 numbers of routes having 10 nos. equipment in each route with 15
tags per equipment.
1. What are make and model of the
handheld devices used by BPCL for
operator rounds.
2. Does Meridium software has capability
for custom configuration and interface
adaptor for BPCL procured handheld
devices? (Query to be sent to OEM).
3. Does BPCL wants implementing agenty
to develop Meridium interface adaptor for
handheld device?
1. Make and model of hande held devices will be
informed during FDS.
2. Meridium software will be compatible to
Android 6 and above with screen size 5.2 inches
and above.
3. No.
TCS 7 47 Annexure-1, G, 4Notification update in SAP and Meridium BPCL MR & KR wants to update the Notification history in SAP from Inspection
event document in Meridium as existing in MR. The Inspection event document
should be able to close the Notification both in Meridium and SAP, and update
the Inspection Task. Observation and failure codes etc. shall be populated to
SAP to the respective table.
This feature should be available in
standard Meridium APM software. We
assume TCS to configure the feature
available in the software. Please confirm.
Update of notification history is supported as
standard. Additional fields may be configured
using avaialble free fields during implementation.
Closure of notification will be supported as
standard.
TCS 8 47 Annexure-1, G, 5Custom formulae and stress value Provision shall be made for addition of the custom formulae and stress values. This query has to be sent to software OEM
and please check software shall have
provison for addition of the custom
formulae and stress values.
Custom formulae to be created as defined during
FDS and to be configured by implementation
agency.
TCS 9 47 Annexure-1, G, 6T-min calculator for ASME Sec-VIII Div.2 In addition to existing T-min calculators, implementation agency shall add T- min
calculator for ASME Section VIII Division 2 and add relevant PV stress values for
all code years.
This query has to be sent to software OEM
to check for Tmin calculator for ASME
Section VIII Division 2 is available in
Meridium APM software.
We assume that BPCL shall provide
relevant PV stress values in excel format
for all code years. Please confirm.
Custom formulae to be created as defined during
FDS and to be configured by implementation
agency. BPCL will provide the PV stress values and
implementation agency shall upload the same
using data loaders.
TCS 10 47 Annexure-1, G, 7T-min calculator for Storage Tanks Implementation agency shall add T-min calculator for storage tanks and add
relevant PV stress values for the same.
This query has to be sent to software OEM
to check for T-min calculator for storage
tanks is available in Meridium APM
software.
We assume that BPCL shall provide
relevant PV stress values for the same in
excel format for all code years. Please
confirm.
Custom formulae to be created as defined during
FDS and to be configured by implementation
agency. BPCL will provide the PV stress values and
implementation agency shall upload the same
using data loaders.
E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries
Bidder Sr
No
Tender
Page
No
Clause
No
Clause Clause details Bidder's Query BPCL response to bidder's queries
TCS 11 47 Annexure-1, G, 9Risk ranking of each process unit Meridium to formulate a calculation of ranking of each process unit based on
each plant risk and place in Corporate Risk Matrix of respective site. The process
unit may contain few plants.
Meridium software has capability for risk
ranking process unit by default?
Implementing agency to carry out risk
ranking of each process unit in MR & KR?
As a standard, Risk analysis of each unit, system,
asset will have to be carried out in ACA, which
follows Corporate Risk Matrix (CRM). ACA allows
to drill down and roll up the risk ranking.
TCS 1 48 Annexure-1,G,22,bRBI study and CCD preparation Carry out RBI study of 2 nos. sections of a pipeline each for MR and KR.
Push RBI recommendation or inspection task analysis to ASM to
Inspection notification for the same with option of user intervention
BPCL to provide the counts for PFD and
P&ID for MR & KR pipeline.
Each pipeline generally have 1 to 2 PFD and 2 to 3
P&IDS for each sections at starting point station
and sectionalizing station, and pipe book for
pipeline. The exact number of PFDs & P&IDs can
not be exactly counted like done process plant.
TCS 12 52 Annexure-1, J, 14Update the risk ranks of existing records MR and KR handholding shall be considered as complete only when all the
existing analysis in RCM/FMEA/ASM/RBI are updated with new risk ranks in
accordance to the changes carried out in risk matrix.
Does implementing agency have to update
risk rank of all existing records as per new
CRM? So the existing records risk ranks
shall reflect the new ranks.
KR risk matrix for RCM will be made similar to MR
to standardize and push to CRM. For this, bidder
to run the analysis of RCM to bring it CRM.
TCS 13 54 Annexure-1, MTime of Completion The completion period for the entire scope of work for MR and KR shall be 15
months from the date of purchase order.
TCS request BPCL to revise the completion
period to 18 Months based on our
evaluaiton of total project scope.
The completion period for the entire scope of
work for MR and KR shall be 18
months from the date of purchase order. The
stabilization period of 6 months is in
addition to the completion period.
TCS 14 57 Annexure-2, B, 7(a)APM SAP Interfaces APM interfaces with SAP through RFC OR IDOC or direct for the following to be
done:
a. Equipment - Interfacing from SAP to APM
b. Functional Location - Interfacing from SAP to APM
c. Work History & work history detail - Interfacing from SAP to APM
d. Equipment Technical Characteristics - Interfacing from SAP to APM
e. Functional Location Technical Characteristics - Interfacing from SAP to APM
f. Work Management - Interfacing from SAP to APM
g. Notification Management - Interfacing from APM to SAP
h. Work Order Management - Interfacing from APM to SAP
i. ACA Adaptor - Direct Interfacing from APM to SAP
j. ASI Adaptor - Direct Interfacing from APM to SAP
This query has to be sent to software OEM
to confirm whether interfaces listed under
this clause are compatible with BORL SAP
ECC versions
TCS assumes the functionalities are built-
in and compatible with BORL SAP software
and We will facilitate Deploy,
configure,Deploy ,Data transfer,Test and
Validate of existing interface in APM
software as required by BPCL, Please
confirm.
Yes, all the adaptors are avilable as product
functionality. Configuration will have to be done
by implementation agency.
This is compatible with SAP ECC 6 EHP 5.0 and
above.
E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries
Bidder Sr
No
Tender
Page
No
Clause
No
Clause Clause details Bidder's Query BPCL response to bidder's queries
TCS 15 58 Annexure-2, B, 7(b)APM Interfaces APM interfaces with following to be done:-
a. Exaquantum PIMS – By Yokogawa,
b. Customized LIMS by Advika Software Solutions,
c. System ONE, Emerson AMS Suite,
d. ATOMS / AORA App and EDMS - Project Wise V8i (Select Series 3) to be done.
This query has to be sent to software OEM
to confirm whether interfacing facility to
the listed softwares available by default in
Meridium APM software. TCS assumes the
functionalities are built-in the software
and will facilitate configuration of existing
interface in APM software as required by
BPCL, Please confirm.
a. Exaquantum PIMS: - Custom interface will be
required, this has to be built during
implementation after functional requirement
analysis.
b. LIMS: - Custom interface will be required, this
has to be built during implementation after
functional requirement analysis.
C. EMERSON AMS SUITE, - standard adaptor is
available.
SYSTEM-1. - standard adaptor is available,
"Enterprise impact" software shall be needed
from System 1 side.
d. Custom interface will be required, this has to
be built during implementation after functional
requirement analysis.
APM Connect studio is being supplied for creating
custom interfaces.
TCS 16 58 Annexure-2, B, 8Bulk uploading Bulk uploading facility.
The following bulk uploading using excel sheets shall be made available
a. TML bulk creation and upload.
b. Bulk up load of asset data.
c. TML measurement data.
d. Asset Criticality Analysis upload.
e. RBI component creation, analysis and re-analysis.
f. Task creation in bulk.
g. PV stress including addition, deletion or modification to look up table for
stress values for TM evaluation.
h. Template for inspection profiles and inspection methods.
i. Functional Aspects - building, modification and provide access control for
the following.
I. Query, Report, Graphs etc
II. Dash board, score card
III. Alerts
IV. Scheduling of task, data extraction scheduler
j. Mapping fields for interfacing the Meridium with third party software
k. Bulk upload of check list
l. Bulk upload of Vibration reading from vibration data collector
m. Asset Criticality Analysis data.
n. Measurement location and their IOW limits.
Generally these data loaders given under
Bulk Uploading facility to be available in
Meridium APM software by defult .
If already available in software, TCS will
facilitate Bulk Upload of data as required
by BPCL.
If data loaders are not available additional
effort estimation is required by TCS.
Base line data loader will be available for TML
bulk creation and upload, Bulk up load of asset
data, TML measurement data, Asset Criticality
Analys upload, RBI component creation, analysis
and re-analysis, RBI Components and RBI analysis,
Task creation in bulk, PV stress including addition,
deletion or modification to look up table for
stress values for TM evaluation (Can be done
using APM Family loader, some configuration
expected), Template for inspection profiles and
inspection methods, Asset Criticality Analysis
data, Measurement location and their IOW limits
(Loader available for ML Limits), Bulk upload of
Vibration reading from vibration data collector
(can be uploaded as reading against
measurement location).
Bulk upload of check list - No loader for uploading
checklists eixists. For existing checklists APM
Family Loader can be used, some configuration
expected. But, creating new checklist is
configuration and not possible through a data
loader.
Beyond these, there are generic data loaders
available for any other data to be loaded.
Data loaders are not applicable for the below:
E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries
Bidder Sr
No
Tender
Page
No
Clause
No
Clause Clause details Bidder's Query BPCL response to bidder's queries
TCS 17 59 Annexure-2, C, 1, fKPI Apart from the standard KPIs, 30 nos. KPIs as defined by BPCL (Min. nos. for 5
each of the work processes) to be generated by the implementation agency.
Implementation agency to generate total
30 KPIs as defined by BPCL apart from the
KPI's already existing in Meridium APM.
Please confirm.
Yes. Confirmed.
TCS 18 60 Annexure-2, C, 3Email alerts Configuring the fields and email alerts as per ANNEXURE – C. This query has to be sent to software OEM
to check the feasiblity of Annexure-C
functionalities. TCS will configure the fields
and email alerts if the facilites are
available in Meridium APM software. If
not available, Please confirm.
It is possible to populate the text of multiple
required fields into the email alert body, will have
to be configured by implementation agency.
TCS 19 61 Annexure-2, C, 15, b/cAsset count forACA, RCM and FMEA Perform Asset Criticality Analysis for assets in HGU and HCU-DHDT complex at
BORL and Implementation agency shall carry out full RCM, FMEA on all the
assets as per Annexure-D
Need to clarify the counts for HGU and
HCU-DHDT complex for ACA..?
As per Annexure-D; the count is 45 system
( 97 rotary assets). Please confirm..?
We have selected 45 critical equipment (assets)
from units HCU & HGU. It is further being clarified
that the number of sub-equipment e.g. in case of
feed pump the asset comprises of 1 pump, motor
and gearbox hence a total 3 sub-assets in 1
equipment tag. Likewise, all selected equipment
(assets) are divided into their sub-assets and the
total number is coming as 97. Please refer to the
list given in Annexure - D for details.
5 62 Annexure-2,D,3,fOperator Round Implementation agency shall configure the software for handheld device
and configure the interface with handle held device with Meridium and is
for 30 numbers of routes having 10 nos. equipment in each route with 15
tags per equipment.
1. What are make and model of the
handheld devices used by BPCL for
operator rounds.
2. Does Meridium software has capability
for custom configuration and interface
adaptor for BPCL procured handheld
devices? (Query to be sent to OEM).
3. Does BPCL wants implementing agenty
to develop Meridium interface adaptor for
handheld device?
1. Make and model of hande held devices will be
informed during FDS.
2. Meridium software will be compatible to
Android 6 and above with screen size 5.2 inches
and above.
3. No.
TCS 20 63 Annexure-2, E, 3Pipeline Strategies Strategies for pipeline facilities/systems to be included as a part of
implementation scope.
This query has to be sent to software OEM
to confirm standard pipeline strategies as
part of software package or not . Please
confirm.
Generic rotating equipment strategies shall be
available in Asset Strategy Library (ASL) and
pipeline strategies will be out come of RBI study.
TCS 21 64 Annexure-2, E, 8Pipeline system selection Subject matter experts from implementation agency shall help Pipeline team
to select one system for applying complete work process.
BPCL to provide exact number of
equipment on the selected pipeline for
carrying out the work process. Total
number of equipment required for exact
effort estimation.
SME to help for system selection during FDS. No
RBI and RCM to be considered under this clause.
However, however all the equipment related to
pipe line shall be uploaded in meridium for other
schedule generations like preventative
maintenance , notification etc. for all the static
and rotary equipment.
E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries
Bidder Sr
No
Tender
Page
No
Clause
No
Clause Clause details Bidder's Query BPCL response to bidder's queries
TCS 2 64 Annexu
re-2,E,8
&
Annexu
re - 2,
G
Mechanical Integrity process for Pipeline Subject matter experts from implementation agency shall help Pipeline team
to select one system for applying complete work process.
Does the complete work process include
Mechanical Integrity for Pipeline also, if so
please give count of PFDs and P&IDs for
BORL pipeline.
SME to help during FDS for system selection.
TCS 3 65 Annexure-2,F,5, aReliability Analytics Facilitators from the implementation agency shall facilitate BORL to
perform Root Cause Analysis - RCA / Reliability Analytics-RA for
equipment as per Annexure-D.
Please clarify which of Reliability Analysis
process(PA, SRA, SA, RDA, PDA, RGA) for
BORL 45 systems has to be followed.
SME to identify during hand holding and perform
one or multiple type of analysis as recommeded
by SME.
TCS 22 66 Annexure-2, G, 9Notification update in SAP and Meridium BORL wants to update the Notification history in SAP from Inspection event
document in Meridium as existing in MR. The Inspection event document
should be able to close the Notification both in Meridium and SAP, and update
the Inspection Task. Observation and failure codes etc. shall be populated to
SAP to the respective table.
This feature should be available in
standard Meridium APM software. We
assume TCS to configure the feature
available in the software. Please confirm.
Update of notification history is supported as
standard. Additional fields may be configured
using avaialble free fields during implementation.
Closure of notification will be supported as
standard.
TCS 23 66 Annexure-2, G, 11Custom formulae and stress value Provision shall be made for addition of the custom formulae and stress values. This query has to be sent to software OEM
and please check software shall have
provison for addition of the custom
formulae and stress values.
Custom formulae to be created as defined during
FDS and to be configured by implementation
agency.
TCS 24 66 Annexure-2, G, 12T-min calculator for ASME Sec-VIII Div.2 In addition to existing T-min calculators, implementation agency shall add T- min
calculator for ASME Section VIII Division 2 and add relevant PV stress values for
all code years.
This query has to be sent to software OEM
to check for Tmin calculator for ASME
Section VIII Division 2 is available in
Meridium APM software.
We assume that BPCL shall provide
relevant PV stress values in excel format
for all code years. Please confirm.
Custom formulae to be created as defined during
FDS and to be configured by implementation
agency. BORL will provide the PV stress values
and implementation agency shall upload the
same using data loaders.
TCS 25 66 Annexure-2, G, 15Risk ranking of each process unit Meridium to formulate a calculation of ranking of each process unit based on
each plant risk and place in Corporate Risk Matrix of respective site. The process
unit may contain few plants.
Meridium software has capability for risk
ranking process unit by default?
Implementing agency to carry out risk
ranking of each process unit in BORL?
As a standard, Risk analysis of each unit, system,
asset will have to be carried out in ACA, which
follows Corporate Risk Matrix (CRM). ACA allows
to drill down and roll up the risk ranking.
TCS 26 69 Annexure-2, G, 32, cCorrosion looping SME shall conduct the corrosion loop finalization work shop at BORL for 5 days
minimum and finalize the corrosion loops with BORL team. SME shall be
available at BORL Refinery site at the time of corrosion looping study.
Implementation agency shall identify, mark & verify corrosion loops and
damage mechanisms for both equipment & piping on P&ID based on existing
operating conditions, stream flows, corrosive fluids, fluid characteristics,
material specifications & damage mechanisms. Corrosion study is inclusive of
the scope.
Corrosion loops are identified at PFD level. Implementation agency shall mark corrosion
loops on both PFDs and P&IDs for all sites of BPCL
group refineries.
E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries
Bidder Sr
No
Tender
Page
No
Clause
No
Clause Clause details Bidder's Query BPCL response to bidder's queries
TCS 27 69 Annexu
re-2, G,
32, i
RBI Implementation All the process equipment (viz. columns, exchangers, pressure vessels, furnace
coils, piping, pressure relieving devices etc.) of HGU and HCU- DHDT shall be
covered in scope for RBI Implementation.
Generally PRVs are not part of corrosion
study.
Acceptable.
TCS 28 76 Annexure-2, MTime of Completion The completion period for the entire scope of work for MR and KR shall be 15
months from the date of purchase order.
TCS request BPCL to revise the completion
period to 18 Months based on our
evaluaiton of total project scope.
The completion period for the entire scope of
work for BORL shall be 18 months
from the date of purchase order. The stabilization
period of 6 months is in
addition to the completion period.
TCS 29 79 Annexu
re-3, B,
7(a)
APM SAP Interfaces APM interfaces with SAP through RFC or direct for the following to be done:
a. Equipment - Interfacing from SAP to APM
b. Functional Location - Interfacing from SAP to APM
c. Work History & work history detail - Interfacing from SAP to APM
d. Equipment Technical Characteristics - Interfacing from SAP to APM
e. Functional Location Technical Characteristics - Interfacing from SAP to APM
f. Work Management - Interfacing from SAP to APM
g. Notification Management - Interfacing from APM to SAP
h. Work Order Management - Interfacing from APM to SAP
i. ACA Adaptor - Direct Interfacing from APM to SAP
j. ASI Adaptor - Direct Interfacing from APM to SAP
This query has to be sent to software OEM
to confirm whether interfaces listed under
this clause are compatible with NRL SAP
ECC versions
TCS assumes the functionalities are built-
in and compatible with NRL SAP software
and We will facilitate Deploy,
configure,Deploy ,Data transfer,Test and
Validate of existing interface in APM
software as required by NRL, Please
confirm.
Yes all the adaptors are avilable as product
functionality. Configuration will have to be done
by implementation agency. This is compatible
with SAP ECC 6 EHP 5.0 and above. BPCL to
provide version compatibility
E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries
Bidder Sr
No
Tender
Page
No
Clause
No
Clause Clause details Bidder's Query BPCL response to bidder's queries
TCS 30 80 Annexu
re-3, B,
7(b)
APM Interfaces APM interfaces with the following to be done:-
a. Aspen IP21,
b. LIMS,
c. GE System 1,
d. DMS,
e. OLEMS
f. PROGNOST t
This query has to be sent to software OEM
to confirm whether interfacing facility to
the listed softwares available by default in
Meridium APM software. TCS assumes the
functionalities are built-in the software
and will facilitate configuration of existing
interface in APM software as required by
BPCL, Please confirm.
a. The following standard adaptors will be
available with APM.
1) ASPEN IP21.
2)SYSTEM-1. Enterprise impact shall be needed
from System1 side.
APM Connect studio is being supplied for creating
custom interfaces. Implementation agency shall
build custom interfaces for the following during
implementation using APM connect studio based
on functional requirement analysis.
1) LIMS.
2) DMS.
3) OLEMS.
4) PROGNOST.
During FDS, implementation agency shall identify
the requirement and specification for all interface
adaptors on other third party software/systems.
Adaptors identified on third party system side
shall be made available by BPCL/BORL/NRL.
However, installation and required configuration
shall be done by implementation agency with no
additional cost.
TCS 31 80 Annexu
re-3, B,
7, d
Additional data for Integration The additional data that is required to be integrated in Meridium is available in
different applications, as defined in this section.
Need details on system to be integrated. Together with GE System1, very recently NRL is
using Bently Nevda (GE) make vibration Analyzers
Scout, which uses Ascent 2015 Level2/R2
v15.1.65
(Windows 7, 64bit, SP1). Though this is to be
shortly integrated with System1, direct interfacing
of APM with Ascent 2015 Level2/R2 v15.1.65 may
also be required.
E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries
Bidder Sr
No
Tender
Page
No
Clause
No
Clause Clause details Bidder's Query BPCL response to bidder's queries
TCS 32 80 Annexu
re-3, B,
8
Bulk uploading Bulk uploading facility.
The following bulk uploading using excel sheets shall be made available
a. TML bulk creation and upload.
b. Bulk up load of asset data.
c. TML measurement data.
d. Asset Criticality Analysis upload.
e. RBI component creation, analysis and re-analysis.
f. Task creation in bulk.
g. PV stress including addition, deletion or modification to look up table for
stress values for TM evaluation.
h. Template for inspection profiles and inspection methods.
i. Functional Aspects - building, modification and provide access control for
the following.
I. Query, Report, Graphs etc
II. Dash board, score card
III. Alerts
IV. Scheduling of task, data extraction scheduler
j. Mapping fields for interfacing the Meridium with third party software
k. Bulk upload of check list
l. Bulk upload of Vibration reading from vibration data collector
m. Asset Criticality Analysis data.
n. Measurement location and their IOW limits.
Generally these data loaders given under
Bulk Uploading facility to be available in
Meridium APM software by defult .
If already available in software, TCS will
facilitate Bulk Upload of data as required
by BPCL.
If data loaders are not available additional
effort estimation is required by TCS.
Base line data loader will be available for TML
bulk creation and upload, Bulk up load of asset
data, TML measurement data, Asset Criticality
Analys upload, RBI component creation, analysis
and re-analysis, RBI Components and RBI analysis,
Task creation in bulk, PV stress including addition,
deletion or modification to look up table for
stress values for TM evaluation (Can be done
using APM Family loader, some configuration
expected), Template for inspection profiles and
inspection methods, Asset Criticality Analysis
data, Measurement location and their IOW limits
(Loader available for ML Limits), Bulk upload of
Vibration reading from vibration data collector
(can be uploaded as reading against
measurement location).
• Bulk upload of check list - No loader for
uploading checklists eixists. For existing checklists
we can use APM Family Loader, some
configuration expected. But, creating new
checklist is configuration and not possible
through a data loader.
Beyond these, there are generic data loaders
available for any other data to be loaded.
Data loaders are not applicable for the below:TCS 33 81 Annexu
re-3, C,
1, f
KPI Apart from the standard KPIs, 30 nos. KPIs as defined by NRL (Min. nos. for 5
each of the work processes) to be generated by the implementation agency.
Implementation agency to generate total
30 KPIs as defined by BPCL apart from the
KPI's already existing in Meridium APM.
Please confirm.
Yes. Confirmed.
TCS 34 82 Annexu
re-3, C,
3
Email alerts Configuring the fields and email alerts as per ANNEXURE – C. This query has to be sent to software OEM
to check the feasiblity of Annexure-C
functionalities. TCS will configure the fields
and email alerts if the facilites are
available in Meridium APM software. If
not available, Please confirm.
It is possible to populate the text of multiple
required fields into the email alert body, will have
to be configured by implementation agency.
TCS 35 83 Annexure-3, C, 15, b/cAsset count forACA, RCM and FMEA Perform Asset Criticality Analysis for assets Hydrocracker Unit (HCU) of
NRL.Implementation agency shall carry out the following for all the rotary
equipment at HCU of NRL (approx. 100 systems).
Need to clarify the counts for
Hydrocracker Unit (HCU) for ACA..?
Rotating Equipment Trains (Driver + Driven+
Intermediate Speed Variation Equipment, if any ):
120 Nos.
E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries
Bidder Sr
No
Tender
Page
No
Clause
No
Clause Clause details Bidder's Query BPCL response to bidder's queries
6 84 Annexure-3,D,4,aOperator Round Implementation agency shall configure the software for handheld device
and configure the interface with handle held device with Meridium and is
for 30 numbers of routes having 10 nos. equipment in each route with 15
tags per equipment.
1. What are make and model of the
handheld devices used by BPCL for
operator rounds.
2. Does Meridium software has capability
for custom configuration and interface
adaptor for BPCL procured handheld
devices? (Query to be sent to OEM).
3. Does BPCL wants implementing agenty
to develop Meridium interface adaptor for
handheld device?
1. Make and model of hande held devices will be
informed during FDS.
2. Meridium software will be compatible to
Android 6 and above with screen size 5.2 inches
and above.
3. No.
TCS 36 87 Annexu
re-3, G,
9
Notification update in SAP and Meridium NRL wants to update the Notification history in SAP from Inspection event
document in Meridium as existing in MR. The Inspection event document
should be able to close the Notification both in Meridium and SAP, and update
the Inspection Task. Observation and failure codes etc. shall be populated to
SAP to the respective table.
This feature should be available in
standard Meridium APM software. We
assume TCS to configure the feature
available in the software. Please confirm.
Update of notification history is supported as
standard. Additional fields may be configured
using avaialble free fields during implementation.
Closure of notification will be supported as
standard.
TCS 37 87 Annexu
re-3, G,
10
Custom formulae and stress value Provision shall be made for addition of the custom formulae and stress values. This query has to be sent to software OEM
and please check software shall have
provison for addition of the custom
formulae and stress values.
Custom formulae to be created as defined during
FDS and to be configured by implementation
agency.
TCS 38 87 Annexu
re-3, G,
11
T-min calculator for ASME Sec-VIII Div.2 In addition to existing T-min calculators, implementation agency shall add T- min
calculator for ASME Section VIII Division 2 and add relevant PV stress values for
all code years.
This query has to be sent to software OEM
to check for Tmin calculator for ASME
Section VIII Division 2 is available in
Meridium APM software.
We assume that BPCL shall provide
relevant PV stress values in excel format
for all code years. Please confirm.
NRL Response:
Custom formulae to be created as defined during
FDS and to be configured by implementation
agency. NRL will provide the PV stress values and
implementation agency shall upload the same
using data loaders.
TCS 39 88 Annexu
re-3, G,
12
T-min calculator for Storage Tanks Implementation agency shall add T-min calculator for storage tanks and add
relevant PV stress values for the same.
This query has to be sent to software OEM
to check for T-min calculator for storage
tanks is available in Meridium APM
software.
We assume that BPCL shall provide
relevant PV stress values for the same in
excel format for all code years. Please
confirm.
Custom formulae to be created as defined during
FDS and to be configured by implementation
agency. NRL will provide the PV stress values and
implementation agency shall upload the same
using data loaders.
E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries
Bidder Sr
No
Tender
Page
No
Clause
No
Clause Clause details Bidder's Query BPCL response to bidder's queries
TCS 40 88 Annexu
re-3, G,
14
Risk ranking of each process unit Meridium to formulate a calculation of ranking of each process unit based on
each plant risk and place in Corporate Risk Matrix of respective site. The process
unit may contain few plants.
Meridium software has capability for risk
ranking process unit by default?
Implementing agency to carry out risk
ranking of each process unit in NRL?
As a standard, Risk analysis of each unit, system,
asset will have to be carried out in ACA, which
follows Corporate Risk Matrix (CRM). ACA allows
to drill down and roll up the risk ranking.
TCS 41 88 Annexu
re-3, G,
23
RBI Analysis RBI analysis of PSVs of Hydro-cracker Unit. Please provide the number of total PSV's
for Hydro-cracket unit.
NRL Response:
There are 226 nos. of PSVs in Hydrocracker unit.
TCS 42 90 Annexure-3, G, 31, cCorrosion looping SME shall conduct the corrosion loop finalization work shop at NRL for 5 days
minimum and finalize the corrosion loops with NRL team. SME shall be available
at NRL Refinery site at the time of corrosion looping study. Implementation
agency shall identify, mark & verify corrosion loops and damage mechanisms
for both equipment & piping on P&ID based on existing operating conditions,
stream flows, corrosive fluids, fluid characteristics, material specifications &
damage mechanisms. Corrosion study is inclusive of the scope.
Corrosion loops are identified at PFD level Implementation agency shall mark corrosion
loops on both PFDs and P&IDs for all sites of BPCL
group refineries.
TCS 43 91 Annexu
re-3, G,
31, i
RBI Implementation All the process equipment (viz. columns, exchangers, pressure vessels, furnace
coils, piping, pressure relieving devices etc.) of HGU and HCU- DHDT shall be
covered in scope for RBI Implementation.
Generally PRVs are not part of corrosion
study. Whether BPCL is looking for doing
the RBI Analysis of all Pressure Relieving
devices of HGU and HCU- DHDT units. If
yes, please provide the count for the
same.
NRL Response:
RBI study also to be carried out for all 226 nos.
PSVs of HCU unit in NRL.
TCS 44 97 Annexure-3, MTime of Completion The completion period for the entire scope of work for MR and KR shall be 15
months from the date of purchase order.
TCS request BPCL to revise the completion
period to 18 Months based on our
evaluaiton of total project scope.
The completion period for the entire scope of
work for NRL shall be 18 months
from the date of purchase order. The stabilization
period of 6 months is in
addition to the completion period.
PwC General
query
Genera
l query
What is the amount of customisation in the existing implementation ? What are
the functionalities being currently used ?It can not be explicitely mentioned herein. You
may see existing system.
PwC General
query
Genera
l query
Would the training in KR & MR be conducted seprately in different locations or
would it be a common trainingTraining shall be conducted separately for MR
and KR.
PwC General
query
Genera
l query
Do you envisage any changes to the technical charecteristics maintained in SAP
system against functional location & equipment for any of the sites ?This can be known during FDS.
PwC General
query
Genera
l query
Please highlight any challenges and issues in previous implementation of
Meridium at MR & KR - change management, existing enterprise architecture,
integration issues, KPIs, workflows etc
This information can not be shared at this stage.
This is to be discussed during FDS.
PwC General
query
Genera
l query
How much of the customised features that are likely to be removed when you
upgrade to the new version. For instance a customization that’s done could be a
new feature in the latest version of meridium can be ignored. Can you please list
such functions.
This is to be studied by implementation agency
and to be discussed with site personel during FDS.
E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries
Bidder Sr
No
Tender
Page
No
Clause
No
Clause Clause details Bidder's Query BPCL response to bidder's queries
PwC General
query
Genera
l query
How much of customization documentation available currently for
implementation team to understand and migrate?Existing customization documents not available.
PwC General
query
Genera
l query
For the existing product, can we please look at the customisation data model and
new changes in the data models? You can visit and see existing Meridium system to
understand your requirement.
PwC General
query
Genera
l query
Regarding data migration, are there any existing scripts that can be used or the
implementation team has to prep up scripts from scratch.No scripts exist. Implementation agency to work
on this requirements.
PwC General
query
Genera
l query
What is the size of the data to be migrated approximately ? MR Database Size - 19 GB including indexes
KR Database Size - 24 GB including indexes
PwC General
query
Genera
l query
Will there be any KT sessions provided on the customisation done in the product
so far ? We woud like to have some dedicated support from existing team for us
during the implementation phase. Can this be organised ?
During FDS, AS IS study to be done to arrive at TO
BE processes. Whatever available documents
available will be shared during FDS.
PwC General
query
Genera
l query
Are there any front end app level customisations done ? Like in the look and feel
of the app etc ? No.
PwC General
query
Genera
l query
Given the scale of the project, in order to enable us to complete our internl
formalities, we request you to please extend the bid submission date from 8th
December by 2 weeks
Kindly refer corrigendum.
PwC General
query
Genera
l query
Given the extensive handholding requirements, we also request you to please
extend the total timline for completion from the present 15 months to 22
months so as to enable proper training as well as handholding activities to be
performed
The completion period for the entire scope of
work for MR and KR, BORL and NRL shall be 18
months from the date of purchase order. The
stabilization period of 6 months is in addition to
the completion period.
BHGE 1 Page 35 F Identify the best option available in
solution offered based on the inputs given
by BPCL core team and identify those
processes, which have a “straight fit” in
solution offered. In case, there is no
straight fit in solution, offer ‘work around’
solution for such processes.
Requirements fit-gap For requirements that are not met
through a "straight fit", or through a
configurable work around and a
customization / development is required,
how is the additional
development/customization cost to be
handled?
As such additional development/cutomozation is
not envisaged.
BHGE 2 Page 36 A) I & J i) FAT to be carried out and approved by
BPCL before migrating all the
configurations/data to Quality
environment.
j) Pilot room testing shall be carried out
based on FDS and implementation agency
shall obtain approval from BPCL core team.
Any changes if required shall be
incorporated in the system
FAT and Pilot room testing What is Pilot Room testing, how is it
different from FATs ? How many rounds of
FAT and Pilot Room Testing is expected for
MR, KR, BORL, NRL, and Pipelines?
Pilot room testing is nothing but User Acceptance
Test (UAT) based on test cases identified.
E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries
Bidder Sr
No
Tender
Page
No
Clause
No
Clause Clause details Bidder's Query BPCL response to bidder's queries
BHGE 3 Page 42 12 Implementation agency shall help BPCL to
select and create 30 Policies to take
intelligent actions based on the IOW limits
of Health Indicators.
Create 30 policies Is it 30 policies for each site? 30 policies for each site.
BHGE 4 Page 42 14 Data for Mumbai, Pipeline and Kochi
refinery shall be filtered, the Data visibleto
a user shall only be restricted to that of his
site. Administrator should beable to
provide read only access to each other’s
data on internal approval.
Data Filtering Do we require Data Filtering between MR,
KR and Pipelines? To what extent do we
want data to be visible?
Data shall be visible to MR, KR and Pipeline.
However, edit option shall be restricted and with
administrator of respective site.
BHGE 5 Page 42 15c Implementation agency shall carry out the
following for 75 nos. rotary systems
consisting driver and driven equipment at
MR and 75 nos. rotary systems consisting
driver and driven equipment at KR
Perform RCM/FMEA for 75 systems at MR and 75 systems at KR Please provide breakdown of
High/Medium/Low critical assets.
This shall be based on ACA output.
BHGE 6 Page 42 15c Implementation agency shall carry out the
following for 75 nos. rotary systems
consisting driver and driven equipment at
MR and 75 nos. rotary systems consisting
driver and driven equipment at KR
Perform RCM/FMEA for 75 systems at MR and 75 systems at KR Please provide list of 75 assets for MR and
75 assets for KR.
The list of assets can be give during FDS.
BHGE 7 Page 43 D) 3 The Asset Health Management Module
shall be configured for both sites to add
health indicators based on strategic actions
for the asset.
ASPEN IP21 Is it possible for BPCL to setup a Dedicated
IP21 Server(s) or Matrikon GDA Servers
for Interfacing with APM? This will be
applicable for Interfacing with any Process
Historian.
BPCL Response:
Separate IP21 server exists for MR and KR at
respective sites. However, it will not be dedicated
for APM. OPC server will be provided by BPCL.
BHGE 8 Page 43 D.4.a Implementation agency shall configure the
software for handheld device and configure
the interface with handle held device with
Meridium and is for 30 numbers of routes
having 10 nos. equipment in each route
with 15 tags per equipment.
30 number of routes having 10 equipment Please confirm if it is 30 routes each for
MR and KR or consolidated 30 routes
30 routes having 10 equipment for each site.
BHGE 9 Page 44 4 Communicate the following information
that
was documented in previous steps of the
work process:
- The updated strategy profile.
- What changed from the original strategy?
- Why the updated strategy was selected.
- The return on investment value.
- The risk reduction numbers.
Strategies for Pipelines Is this for ASM Implementation only? This is part of ASM strategy.
E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries
Bidder Sr
No
Tender
Page
No
Clause
No
Clause Clause details Bidder's Query BPCL response to bidder's queries
BHGE 10 Page 46 5.a Facilitators from the implementation
agency shall facilitate BPCL to perform 10
(Ten) Root Cause Analysis (RCA) for
Mumbai Refinery, 10 (Ten) RCA analysis at
Kochi Refinery and 2 (two) RCA analysis for
Pipelines. These shall be suitably selected
from various disciplines like static, rotary,
electrical, instrumentation & process etc.
Perform RCA for MR/KR/Pipeline There are many dependencies on BPCL
internal team. While SME will facilitate
during the process, however successful
completion shall depend on data
collection by BPCL.
Noted.
BHGE 11 Page 48 18 Carry out RBI analysis of 10 (ten) PSVs at
each site
RBI for PSV's at each site` Does it also include Pipelines? PSVs of each site shall include some PSVs of
respective pipelines.
BHGE 12 Page 48 22d Implementation Agency shall help to bring
15 tags each from Process Historian and set
the IOW limits and also to add these as
health indicators for MR and KR refinery
pipelines.
Bring 15 tags from Process Historian AH is also suggesting 15 tags - is it same or
separate 15 tags?
These 15 nos. are separate for pipelines.
BHGE 13 Page 49 28c Meridium shall help BPCL to bring 15 tags
from Process Historian and set the IOW
limits and also to add these as health
indicators
Bring 15 tags from Process Historian AH is also suggesting 15 tags - is it same or
separate 15 tags?
These 15 nos. are for RBI.
BHGE 14 Page 53 25 There may be incidences of work getting
affected due to site team members not
available for some time due to exigencies,
emergencies and plant shutdowns for a
maximum period of one month.
Implementation agency shall plan the
activities accordingly such that there is no
involvement of our site member during
such period.
Unavailability of BPCL Delay in project due to unavailability of
BPCL Team shall not be accounted for LD.
No change in tender clause. You may plan job
accordingly.
BHGE 15 Page 61 14 Data for BORL Refinery, COT & VBPL shall
be filtered, the Data visible to a user shall
only be restricted to that of his site.
Administrator should be able to provide
read only access to each other’s data on
internal approval.
Site Filtering What is COT and VBPL? Is site filtering
required within BORL instance?
COT is Crude Oil Terminal and VBL is Vadinar Bina
Pipeline. No filtering is required.
BHGE 16 Page 64 7 15 equipment from each site i.e. BORL, COT
and VBPL shall be linked to ASM
ASM for 45 assets Is this different from the Assets defined in
Annexure D?
No. They are different.
BHGE 17 Page 65 5c Facilitators from the implementation
agency shall facilitate BORL to create 2
(Two) Reliability Distribution Analysis each
for HGU and HCUDHDT Complex
2 RA for HGU and HCU-DHDT Does that mean that these are 4 additional
RA's apart from the list of 45 RA's as
defined in Annexure-D?
No. They are different.
BHGE 18 Page 67 24 RBI analysis of 10 nos. PSVs each in HGU
and HCU-DHDT complex
RBI for PSV's at each site` Is this really applicable since point 28
contains the breakdown where RBI needs
to be performed?
RBI analysis of 10 PSVs to be done which is not
covered in point no. 28.
E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries
Bidder Sr
No
Tender
Page
No
Clause
No
Clause Clause details Bidder's Query BPCL response to bidder's queries
BHGE 19 Page 67 27 In combination with Metrics and
scorecards, BORL intends to create Key
Performance Indicators to be displayed on
the dashboards. Those KPIs shall be for the
entire work process. With the help of
implementation agency, BORL shall create
10 (Ten) KPIs that are to be monitored on a
scheduled basis at each site. The
implementation agency should suggest
best practice followed and suitable KPIs
suitable for BORL work processes.
10 KPI's for each Is this in addition to the 30 KPI's that we
have already defined in Metrics on Page
59?
These are separate in addition to 30 KPIs.
BHGE 20 Page 68 31 Hand holding shall include the following.
Handholding shall start only after software
go-live
Handholding Is this in scope in addition to Point 28? Or
this is in addition to RBI Scope defined?
Not connected to point no. 28.
BHGE 21 Page 70 M Site teams will provide the data initially in
Microsoft word/excel format. All required
conversions of provided data in to other
required formats/templates shall be carried
out by Implementation agency. BORL core
team will not carry out any conversion of
data in to other required formats.
Data in Excel Sheets If the data conversion is far complicated
compared to initially estimated, will BPCL
approve change requests for the same?
No changer request will be entertained.
BHGE 22 Page 80 7B APM Interface with other sources OLEMS Integration What is the use case to integrate to
OLEMS?
OLEM( On Line Energy Management) System
(Siemens SENTRON Power manager V3.1) will be
helpful to validate the health of equipment
through monitoring the power consumption at
feeder/equipment level.
BHGE 23 Page 83 14a The implementation agency shall create
one dashboard each for all the work
processes. The dashboard content shall be
discussed with NRL during the FDS
workshops. Role based Dash board or
home page is to be created for different
users of different departments
Role Based Dashboard For each work process, one dashboard is
required for one role only?
For each work process, one dash board is
required and content shall be given rolewise.
BHGE 24 Page 84 3d Handheld devices for rounds for identified
parameters. (Presently NRL plans to
develop the functionality for this
requirement. Actualimplementation shall
be done at later stage.)
Handheld Devices Which handheld to be interfaced and it
should be compatible to Meridium.
This can be discussed during FDS.
BHGE 25 Page 85 E6 Subject matter experts from
implementation agency shall help NRL
team for applying complete work process
for HCU unit.
Complete Work Process for HCU Unit Repetition of Pg83 14c. Both should be done together.
E-tender : 31011 - Corrigendum 1 - Reply to Bidder Queries
Bidder Sr
No
Tender
Page
No
Clause
No
Clause Clause details Bidder's Query BPCL response to bidder's queries
BHGE 26 Page 88 23 RBI analysis of PSVs of Hydro-cracker Unit PSV of HCU Repetition of Point 27 in Page 89 RBI analysis of 10 PSVs to be done which is not
covered in point no. 27.
BHGE 27 Page 88 26 In combination with Metrics and
scorecards NRL intends to create Key
Performance Indicators to be displayed on
the dashboards. Those KPIs shall be for the
entire work process. With the help of
implementation agency, NRL shall create 10
(Ten) KPIs that are to be monitored on a
scheduled basis at
each site. The implementation agency
should suggest best practice followed
and suitable KPIs suitable for NRL work
processes
Create 10 KPI's Considering Repitition - Already covered in
Page 81 C1f
These are separate in addition to 30 KPIs.
E-tender : 31011 : Corrigendum 1 - Reply to Bidder Queries
Bidder Technical/
non-technical
Sr No Tender
Page No
Clause
No
Clause Query BPCL Response
Wipro Non-technical 7 6 OFFER VALIDITY- The Offers shall be
valid for a period of 180 days from Tender
Due Date / Extended
Tender Due Date for placement of order.
The Offers shall be valid for a period of 180
days from Tender Due Date / Extended
Tender Due Date for placement of order.
BPCL Tender condition prevails.
Wipro Non-technical 24 Section 5 (1) The Bidder declares that no previous
transgression occurred in the last 3 years
with any other Company in any country
conforming to the TI approach or with any
other
Public Sector Enterprise in India that could
justify his exclusion from the tender
process.
The Bidder declares that no previous
transgression occurred in the last 3 years with
any other Government Company in any country
India conforming to the TI approach or with
any other
Public Sector Enterprise in India that could
justify his exclusion from the tender process.
BPCL Tender condition prevails.
Wipro Non-technical 54 N The scope of services shall be completed as
per the time schedule and to the full
satisfaction of site teams and in case the
Implementation agency fail to complete the
whole work within the stipulated period
from the date of purchase order, they shall
be liable to pay Liquidated Damages (LD)
of 0.5% of the lump sum fee per week or
part thereof of delay subject to a maximum
of 5% of the lump sum fee or part thereof.
The scope of services shall be completed as per
the time schedule and to the full satisfaction of
site teams and in case the Implementation
agency fail to complete the whole work within
the stipulated period from the date of purchase
order, they shall be liable to pay Liquidated
Damages (LD) of 0.5% of the lump sum fee of
the undelivered portion per week or part
thereof of delay subject to a maximum of 5% of
the lump sum fee or part thereof.
BPCL Tender condition prevails.
Wipro Non-technical 76 N The scope of services shall be completed as
per the time schedule and to the full
satisfaction of site teams and in case the
Implementation agency fail to complete the
whole work within the stipulated period
from the date of purchase order, they shall
be liable to pay Liquidated Damages (LD)
of 0.5% of the lump sum fee per week or
part thereof of delay subject to a maximum
of 5% of the lump sum fee or part thereof.
The scope of services shall be completed as per
the time schedule and to the full satisfaction of
site teams and in case the Implementation
agency fail to complete the whole work within
the stipulated period from the date of purchase
order, they shall be liable to pay Liquidated
Damages (LD) of 0.5% of the lump sum fee for
the undelivered portion per week or part
thereof of delay subject to a maximum of 5% of
the lump sum fee or part thereof. Attributable
to MR and MK implementation value
BPCL Tender condition prevails.
E-tender : 31011 : Corrigendum 1 - Reply to Bidder Queries
Bidder Technical/
non-technical
Sr No Tender
Page No
Clause
No
Clause Query BPCL Response
Wipro Non-technical 76 N The scope of services shall be completed as
per the time schedule and to the full
satisfaction of site teams and in case the
Implementation agency fail to complete the
whole work within the stipulated period
from the date of purchase order, they shall
be liable to pay Liquidated Damages (LD)
of 0.5% of the lump sum fee per week or
part thereof of delay subject to a maximum
of 5% of the lump sum fee or part thereof.
The scope of services shall be completed as per
the time schedule and to the full satisfaction of
site teams and in case the Implementation
agency fail to complete the whole work within
the stipulated period from the date of purchase
order, they shall be liable to pay Liquidated
Damages (LD) of 0.5% of the lump sum fee for
the undelivered portion per week or part
thereof of delay subject to a maximum of 5% of
the lump sum fee or part thereof. Attributable
to BORL implementation value
BPCL Tender condition prevails.
Wipro Non-technical 97 N The scope of services shall be completed as
per the time schedule and to the full
satisfaction of site teams and in case the
Implementation agency fail to complete the
whole work within the stipulated period
from the date of purchase order, they shall
be liable to pay Liquidated Damages (LD)
of 0.5% of the lump sum fee per week or
part thereof of delay subject to a maximum
of 5% of the lump sum fee or part thereof.
The scope of services shall be completed as per
the time schedule and to the full satisfaction of
site teams and in case the Implementation
agency fail to complete the whole work within
the stipulated period from the date of purchase
order, they shall be liable to pay Liquidated
Damages (LD) of 0.5% of the lump sum fee for
the undelivered portion per week or part
thereof of delay subject to a maximum of 5% of
the lump sum fee or part thereof. Attributable
to NRL implementation value
BPCL Tender condition prevails.
E-tender : 31011 : Corrigendum 1 - Reply to Bidder Queries
Bidder Technical/
non-technical
Sr No Tender
Page No
Clause
No
Clause Query BPCL Response
Wipro Non-technical 116 13 To ensure performance of the contract and
due discharge of the contractual
obligations, the successful contractor will
have to provide security deposit of 10% of
the contract
value within 30 days of receipt by him of
the notifications of acceptance of tender.
This Security deposit may be furnished in
the form of an Account payee Demand
Draft payable to BPCL or Bank Guarantee
in the prescribed format. The contractor
shall have
the option to adjust any Earnest Money
Deposit (EMD), if paid in forms other than
Bank Guarantee, towards security deposit if
he so desires.
In the case of security deposit submitted in
the form of Bank guarantee, the Bank
Guarantee shall be valid and remain in
force till the completion of contractual
completion
period, defect liability period of 12 months
plus a claim period of 3 months. The Bank
Guarantee shall be in the form prescribed.
The security deposit will be retained till the
successful completion of the work and
thereafter till the expiry of the defect
To ensure performance of the contract and due
discharge of the contractual obligations, the
successful contractor will have to provide
security deposit of 10% of the contract
value within 30 days of execution of Contract
receipt by him of the notifications of acceptance
of tender.
This Security deposit may be furnished in the
form of an Account payee Demand Draft
payable to BPCL or Bank Guarantee in the
prescribed format. The contractor shall have
the option to adjust any Earnest Money Deposit
(EMD), if paid in forms other than Bank
Guarantee, towards security deposit if he so
desires.
In the case of security deposit submitted in the
form of Bank guarantee, the Bank Guarantee
shall be valid and remain in force till the
completion of contractual completion
period, defect liability period of 12 months plus
a claim period of 3 months. The Bank Guarantee
shall be in the form prescribed.
The security deposit will be retained till the
successful completion of the work and thereafter
till the expiry of the defect liability period, if
applicable. This retention
money/Bank guarantee held shall be released
BPCL Tender condition prevails.
Wipro Non-technical 117 14 Forfeiture of Security Deposit Whenever any claim against the Consultant for
the payment of a sum of money arises out of or
under the contract, the BPCL shall be entitled to
recover such sum from the amount due to the
consultant and if still there is any amount over
and above the the sume due, same has to be
intimated to the consultant if consultant haven't
responded with in 30 days of notice same can be
forfeited from security deposit.
BPCL Tender condition prevails.
Wipro Non-technical 1. Can BPCL provide accommodation for
Project team member at NRL township
guesthouse?
NRL Response : No accomodation shall
be provided by NRL.
E-tender : 31011 : Corrigendum 1 - Reply to Bidder Queries
Bidder Technical/
non-technical
Sr No Tender
Page No
Clause
No
Clause Query BPCL Response
TCS Non-technical 45 4/148 5.1 The interest-free Earnest Money Deposit
(EMD) of Rs 1.00,000/- (Rupees One
Lakh Only) to be submitted by way of
crossed account payee Demand Draft
drawn
on any nationalized / scheduled bank in
favour of "BHARAT PETROLEUM
CORPORATION LTD" payable at
Mumbai. The EMD shall be arranged prior
to
the due date & time of opening of the "Pre-
qualification Bid".
Kindly reduce the EMD amount to Rs 50,000. BPCL Tender condition prevails.
TCS Non-technical 46 7/148 6.0 The Offers shall be valid for a period of
180 days from Tender Due Date / Extended
Tender Due Date for placement of order
Kindly reduce the validity to 90 days. BPCL Tender condition prevails.
TCS Non-technical 47 54/148 L) a) PAYMENT TERMS FOR MR & KR Kindly provide 15% advance at the time of
project kick off & 100% by Go Live.
BPCL Tender condition prevails.
TCS Non-technical 48 75/148 L)A) PAYMENT TERMS FOR BORL Kindly provide 15% advance at the time of
project kick off & 100% by Go Live.
BPCL Tender condition prevails.
TCS Non-technical 49 97/148 L)A) PAYMENT TERMS FOR NRL Kindly provide 15% advance at the time of
project kick off & 100% by Go Live.
BPCL Tender condition prevails.
TCS Non-technical 50 116/148 13 In the case of security deposit submitted in
the form of Bank guarantee, the Bank
Guarantee shall be valid and remain in
force till the completion of contractual
completion
period, defect liability period of 12 months
plus a claim period of 3 months. The Bank
Guarantee shall be in the form prescribed.
Kindly accept a validity till contract completion
+ 3 months claim period.
BPCL Tender condition prevails.
TCS Non-technical 51 116/148 13 To ensure performance of the contract and
due discharge of the contractual
obligations,
the successful contractor will have to
provide security deposit of 10% of the
contract
value within 30 days of receipt by him of
the notifications of acceptance of tender
Kindly reduce the security deposit to 5% of
contract value
BPCL Tender condition prevails.
E-tender : 31011 : Corrigendum 1 - Reply to Bidder Queries
Bidder Technical/
non-technical
Sr No Tender
Page No
Clause
No
Clause Query BPCL Response
TCS Non-technical 5.7 EMD of other unsuccessful bidders shall be
released after declaration of the successful
bidder issuance of FOA/LOA/contract Order
against this tender. However, in case of
successful bidder the EMD shall be released on
receipt of performance bank guarantee.
Noted.
TCS Non-technical 5.9 The Earnest Money deposited by successful
tenderer shall be forfeited if the successful
tenderer fails to sign the mutually agreed
contract. honour the offer terms prior to ordering
and Contractual terms after issuance of
FOA/LOA/contract Order.
BPCL Tender condition prevails.
TCS Non-technical 53 13 15.12 Firm Prices Subject to the cost escalation provision agreed
by the parties, tThe Contract Price shall remain
firm and fixed till the completion of Work in all
respects and no escalation in prices on any
account shall be admissible to the BIDDER /
CONTRACTOR
BPCL Tender condition prevails.
TCS Non-technical All invoices and bills will be raised by Bidder as
per the Payment Terms and will become due for
payment within thirty (30) days of presentation.
All payments due for more than thirty (30) days
will attract an interest at the rate of 2 percent
per month on the invoice amount calculated
from the date the payment became due until the
recovery is made in full with interest. Without
prejudice to the other rights available, Bidder
also reserves the right to withhold the provision
of Services till such time all the payments due to
it under this Agreement have been made by
Bank and any such withholding by the Bidder
shall not be treated as breach by it of the
provisions of this Agreement.
TCS Non-technical
TCS Non-technical The scope of services shall be completed as per
the time schedule and to the full
TCS Non-technical satisfaction of site teams and in case the
Implementation agency fail to complete
52 7-Apr 5 Earnest Money Deposit (EMD)
57 54/76/97 Annexure-
1/Annexure-
2/Annexure-3
N: Liquidated Damages
BPCL Tender condition prevails.
BPCL Tender condition prevails.
E-tender : 31011 : Corrigendum 1 - Reply to Bidder Queries
Bidder Technical/
non-technical
Sr No Tender
Page No
Clause
No
Clause Query BPCL Response
TCS Non-technical the whole work within the stipulated period
from the date of purchase order, they
TCS Non-technical shall be liable to pay Liquidated Damages (LD)
of 0.5% of value of goods/equipment or the
particular phase/part of the contract in relation
to which delay has occurred the lump sum fee
per
TCS Non-technical week or part thereof of delay subject to a
maximum of 5% of the value of
goods/equipment or the particular phase/part of
the contract in relation to which delay has
occurred lump sum fee or
TCS Non-technical part thereof.
TCS Non-technical
TCS Non-technical The Liquidated Damages will be applicable
provided the delay is due to the reasons solely
and directly attributable to the Bidder and not
due to BPCL or its vendors/customers and Force
Majeure conditions.
PwC Non-technical 1 112 Sec 2 of GCC Proprietary information and data: The
standard exclusion to confidentiality have
not been documented.
Survival – There is no outer boundary for
survival of confidentiality obligations
This restriction shall be applicable for a period
of six (6) months from the termination or expiry
of the contract. The confidentiality obligations
under the contract will not apply to information
already in the public domain or available to us
independently of this contract
Further, it is clarified that ownership of any Pre-
exisitng work by Bidder shall vest in Bidder.
Bidder shall transfer the ownership of the
deliverables and reports upon receiving the
payments thereof.
BPCL Tender condition prevails.
PwC Non-technical 2 113 Sec 3 of GCC IPR infringement indemnity The references to indemnity should be deleted,
the reason being in the event of a dispute the
aggrieved party will have adequate recourse to
court/arbitration.
BPCL Tender condition prevails.
E-tender : 31011 : Corrigendum 1 - Reply to Bidder Queries
Bidder Technical/
non-technical
Sr No Tender
Page No
Clause
No
Clause Query BPCL Response
PwC Non-technical 3 118/119 Sec 16 & 19
of GCC
Time is of essence of the contract. LDs -
In case the contractor fails to complete the
whole work within the stipulated period, he
shall be liable to pay liquidated damages of
0.5% of the value of contract per week and
or part thereof of the delay subject to a
maximum of
5% of the value of the contract.
It is clarified that delivery of goods & serives
shall be as per mutually agreed delivery
schedule. LDs shall be applicable only for
delays solely attributable to PwC. Further, LD
shall be the sole remedy for Client in case of
delay in delivery.
BPCL Tender condition prevails.
PwC Non-technical 4 120 Sec 24 & 25
of GCC
BPCL has the right to employ a 3rd party to
have the work done at the cost & risk of
Bidder
It is clarified that PwC does not assume a
liability for any part of our scope of work which
is performed by anyone else, or for the payment
obligations to such person/ entity.
BPCL Tender condition prevails.
PwC Non-technical 5 121 Sec 26 Liabilities: Unlimited liabilities for
following:
(a) In the event of breach of any Applicable
Law;
(b) In the event of fraud, willful misconduct
or illegal or unlawful acts, or gross
negligence of the Contractor or any person
acting on behalf of the Contractor; or
(c) In the event of acts or omissions of the
Contractor which are contrary to the most
elementary rules of diligence which a
conscientious Contractor would have
followed in similar circumstances; or
(d) In the event of any claim or loss or
damage arising out of infringement of
Intellectual Property; or
(e) For any damage to any third party,
including death or injury of any third party
caused by the Contractor or any person or
firm acting on behalf of the Contractor in
executing the Works.
Our overall liability shall not exceed the amount
of fees paid to us under the engagement without
any exceptions. We will not be liable for
indirect/consequential losses.
BPCL Tender condition prevails.
E-tender : 31011 : Corrigendum 1 - Reply to Bidder Queries
Bidder Technical/
non-technical
Sr No Tender
Page No
Clause
No
Clause Query BPCL Response
PwC Non-technical 6 121 Sec 28 Industrial & Intellectual property:
Indemnity obligations and ownership rights
fo BPCL for all documents, reports,
information, data collected and prepared by
Consultant in connection with the scope of
work submitted to BPCL
As clarified above, references to indemnity
should be deleted, the reason being in the event
of a dispute the aggrieved party will have
adequate recourse to court/arbitration.
Further, ownership of any Pre-exisitng work by
Bidder shall vest in Bidder. Bidder shall transfer
the ownership of the deliverables and reports
upon receiving the payments thereof.
BPCL Tender condition prevails.
PwC Non-technical 7 122 Sec 29 Liens: If, at any time, there should be
evidence or any lien or claim for which
BPCL might have become liable and which
is chargeable to the Consultant, BPCL shall
have the right to retain out of any payment
then due or thereafter to become due an
amount sufficient to completely indemnify
BPCL against such lien or claim and if such
lien or claim be valid, BPCL may pay and
discharge the same and deduct the amount
so paid from any money which may be or
may become due and payable to the
Consultant.
It is clarified that lien on any amounts payable to
PwC is not acceptable.
BPCL Tender condition prevails.
PwC Non-technical 8 126 Sec 35 Risk Purchase clause It is clarified that Risk Purchase is not
acceptable as PwC does not assume a liability
for any part of our scope of work which is
performed by anyone else, or for the payment
obligations to such person/ entity.
BPCL Tender condition prevails.
PwC Non-technical 9 Right to Audit We will retain our records as per our record
retention policies. Upon reasonable notice we
will allow client to inspect our invoicing records
under this engagement; such inspection shall be
done in a pre agreed manner and during normal
business hours. For avoidance of doubt, such
inspection should not cause us to be in breach of
our organisational confidentiality requirements
BPCL Tender condition prevails.
E-tender : 31011 : Corrigendum 1 - Reply to Bidder Queries
Bidder Technical/
non-technical
Sr No Tender
Page No
Clause
No
Clause Query BPCL Response
PwC Non-technical 10 Conflict Nothing in this engagement shall affect our or
other PwC firms’ ability to perform services for
our other clients so long as we do not use or
disclose your confidential information
BPCL Tender condition prevails.
PwC Non-technical 11 Subcontracting We may take assistance from our contractors or
other PwC firms (each of which is a separate
and independent) legal entity and may share
confidential information with them in
connection with this engagement. However we
remain solely liable to client for their acts;
claims (if any) in relation to this engagement
will be routed solely through client and us
BPCL Tender condition prevails.
BHGE Non-technical 28 Page 122 30 The Consultant shall not sub-let or assign the
work or any part thereof to another party
without the written consent of BPCL and no
such sub-letting or assignment shall relieve
the Consultant from full and entire
responsibility of his obligation under the
Agreement.
As part of our proposal, OEM would like to sublet to
other agencies to give the best and most optimum
proposal to BPCL. We will clearly state in the
proposal which external parties we are subletting
the work to. If BPCL finds external agencies in
Holiday Listing, BPCL has the right to cancel our bid.
While we will be sub-letting the work to other
partner agencies, we will own the entire delivery of
the project and BPCL shall hold us liable for
execution of this project.For execution ease &
utililize our internal best resources effectively and
to offer our best & optimal proposal, we will
subcontract this order to its affiliate group entity as
clearly stipulated in our proposal. Hence
consulatant will have right to sub-contract/ sublet
this order to any of their affiliate group entity
without BPCL approval..
BPCL Tender condition prevails.