temporary slope repair for highway...

10
CAPSTONE CEEn-2017CPST- Temporary Slope Repair for Highway Expansion April 20, 2018 1 006 Stephen Isaacson Amanda McFarland Mary Ririe McKay Parkinson

Upload: others

Post on 07-Jun-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Temporary Slope Repair for Highway Expansioncecapstone.groups.et.byu.net/.../CEEn-2017CPST-006_FinalPresentat… · CAPSTONE CEEn-2017CPST-Temporary Slope Repair for Highway Expansion

CAPSTONE

CEEn-2017CPST-

Temporary Slope Repair for Highway Expansion

April 20, 2018 1

006

Stephen Isaacson

Amanda McFarland

Mary Ririe

McKay Parkinson

Page 2: Temporary Slope Repair for Highway Expansioncecapstone.groups.et.byu.net/.../CEEn-2017CPST-006_FinalPresentat… · CAPSTONE CEEn-2017CPST-Temporary Slope Repair for Highway Expansion

CAPSTONE

IntroductionAnalysis of the Problem Soil profiles were constructed by interpolation of boring logs from holes 7310 and 7370.

April 20, 2018 2

Figure 1. Soil profile from boring logs, station 489+50 Figure 2. Boring Hole Locations

Page 3: Temporary Slope Repair for Highway Expansioncecapstone.groups.et.byu.net/.../CEEn-2017CPST-006_FinalPresentat… · CAPSTONE CEEn-2017CPST-Temporary Slope Repair for Highway Expansion

CAPSTONE

IntroductionAnalysis of the Problem Soil properties

April 20, 2018 3

Soil Type Unit Weight Cohesion Friction

AngleClay (Sandy, tan) (CL) 135 959 29Sand (tan) 125 30Clay (CL) 120 2867Sand (tan) 125 36Clay (sandy, tan, and gray)(CH) 135 1922Shale (gray) 150

Table 1: Soil Properties

Page 4: Temporary Slope Repair for Highway Expansioncecapstone.groups.et.byu.net/.../CEEn-2017CPST-006_FinalPresentat… · CAPSTONE CEEn-2017CPST-Temporary Slope Repair for Highway Expansion

CAPSTONE

Design, Analysis & ResultsSlope failure was found to be on the upper clay layer after several iterations and study of all stations. Lowest factor of safety was 0.874.

April 20, 2018 4

Figure 2. Slope Failure Analysis

Page 5: Temporary Slope Repair for Highway Expansioncecapstone.groups.et.byu.net/.../CEEn-2017CPST-006_FinalPresentat… · CAPSTONE CEEn-2017CPST-Temporary Slope Repair for Highway Expansion

CAPSTONE

Design, Analysis & ResultsAnalysis of possible solutions

April 20, 2018 5

Ratings Table:1 = lowest (worst), 4 = highest (best) Drill Shafts Driven Piles Shotcrete Steel Mesh

Cost (weighting = 0.85) 1 2 3 4

Ease of Construction (Weighting = 0.3 1 4 3 2

Capacity Design Load (Weighting = 0.5) 4 2 3 1

Meets Design Life (Weighting = (0.25) 1 2 3 4

Aesthetic/Environment (Weighting = 0.15) 1 3 2 4

Sum of (Rating Times Weighting) 3.55 4.85 6 6.1

Table 2: Cost Comparison Analysis

Page 6: Temporary Slope Repair for Highway Expansioncecapstone.groups.et.byu.net/.../CEEn-2017CPST-006_FinalPresentat… · CAPSTONE CEEn-2017CPST-Temporary Slope Repair for Highway Expansion

CAPSTONE

Design, Analysis & ResultsSolution DesignNail parameters from FHWA:

• 20 ft. in length• #6 bar• 15° from horizontal• Pullout resistance: 1000 k/fto Ultimate: 2000 k/fto FS: 2

• Spacing:o Vertical: 5 ft.o Horizontal: 4 ft.

April 20, 2018 6

Figure 3. Reinforced Slope Analysis

Page 7: Temporary Slope Repair for Highway Expansioncecapstone.groups.et.byu.net/.../CEEn-2017CPST-006_FinalPresentat… · CAPSTONE CEEn-2017CPST-Temporary Slope Repair for Highway Expansion

CAPSTONE

Design, Analysis & ResultsSolution Design Facing and Grout from FHWA:

• Plate size: 8”x 8” x 3/4”• 6” grout diameter• 4” initial facing• 6” final facing

April 20, 2018 7

Figure 4. Slope Stability Design Detail

Page 8: Temporary Slope Repair for Highway Expansioncecapstone.groups.et.byu.net/.../CEEn-2017CPST-006_FinalPresentat… · CAPSTONE CEEn-2017CPST-Temporary Slope Repair for Highway Expansion

CAPSTONE

Conclusions & Recommendations

April 20, 2018 8

Page 9: Temporary Slope Repair for Highway Expansioncecapstone.groups.et.byu.net/.../CEEn-2017CPST-006_FinalPresentat… · CAPSTONE CEEn-2017CPST-Temporary Slope Repair for Highway Expansion

CAPSTONE

Conclusions & Recommendations

April 20, 2018 9

Page 10: Temporary Slope Repair for Highway Expansioncecapstone.groups.et.byu.net/.../CEEn-2017CPST-006_FinalPresentat… · CAPSTONE CEEn-2017CPST-Temporary Slope Repair for Highway Expansion

CAPSTONE

Conclusions & Recommendations Soil nails with shotcrete facing Total cost estimate: $167,000Duration: 4 weeks

April 20, 2018 10

Cost Estimation6x6x.105 Wire Mesh: $1,675Grade 60 Rebar (#8): $20,0008x8x3/4 Steel Plates: $10,710

Shotcrete: $3,031Material Subtotal: $35,416

Installation: $121,584Contingency: $10,000Project Total: $167,000

Table 3: Final Cost Estimate