software project management (intro) scheduling. introduction in addition to the effort forecast for...
Post on 22-Dec-2015
214 views
TRANSCRIPT
IntroductionIntroduction
In addition to the effort forecast for a project, a detailed In addition to the effort forecast for a project, a detailed plan for the project must include a plan for the project must include a scheduleschedule indicating indicating the start and completion times, which will enable us:the start and completion times, which will enable us:
Ensure that appropriate resources will be available precisely Ensure that appropriate resources will be available precisely when requiredwhen required
Avoid different activities competing for the same resources at the Avoid different activities competing for the same resources at the same timesame time
Produce a detailed schedule showing which staff carry out each Produce a detailed schedule showing which staff carry out each activityactivity
Produce detailed plan against which actual achievent may be Produce detailed plan against which actual achievent may be measuredmeasured
Produce a timed cash flow forecastProduce a timed cash flow forecast Re-plan the project during its life to correct drift from the targetRe-plan the project during its life to correct drift from the target
Objectives of activity planningObjectives of activity planning
Feasibility assessmentFeasibility assessment
Resource allocationResource allocation
Detailed costingDetailed costing
MotivationMotivation
Co-ordinationCo-ordination
When to plan?When to plan?
Throughout the project, monitoring and re-Throughout the project, monitoring and re-planning must continue to correct any drift that planning must continue to correct any drift that might prevent meeting the time or cost targetsmight prevent meeting the time or cost targetsPlanning is an ongoing process of refinement, Planning is an ongoing process of refinement, each iteration becoming more detailed and more each iteration becoming more detailed and more accurate than the lastaccurate than the lastPurpose of project planning:Purpose of project planning: During the feasibility study and project start up During the feasibility study and project start up
Estimates timescales and the risks Estimates timescales and the risks Beyond feasibility study:Beyond feasibility study:
The production of activity plans to ensure resource The production of activity plans to ensure resource availability and cash flow controlavailability and cash flow control
Project schedulesProject schedules
Creating project schedules comprises four Creating project schedules comprises four main stages:main stages: Decide what activities need to be carried out Decide what activities need to be carried out
and in what order they are to be doneand in what order they are to be done Construct an ideal activity planConstruct an ideal activity plan
That is, no constraint on resourcesThat is, no constraint on resources Allocate resource Allocate resource Produce scheduleProduce schedule
Project and activitiesProject and activities-- What are they?-- What are they?
A project is composed of a number of inter-related A project is composed of a number of inter-related activitiesactivitiesA project may start when at least one of its activities is A project may start when at least one of its activities is ready to startready to startA project will be completed when all of the activities have A project will be completed when all of the activities have been completedbeen completedAn activity must have a clearly defined start and end-pointAn activity must have a clearly defined start and end-pointResource requirement of an activity must be forecast-able Resource requirement of an activity must be forecast-able Duration of an activity must be forecast-ableDuration of an activity must be forecast-ableSome activities might require that others are completed Some activities might require that others are completed before they beginbefore they begin
Identifying activitiesIdentifying activities
Three approaches:Three approaches:
1.1. The activity based approachThe activity based approach
2.2. Product-based approachProduct-based approach
3.3. Hybrid approachHybrid approach
Activity based approachActivity based approach
Creating a list of all involved activities in the Creating a list of all involved activities in the project project
Work Breakdown Structure (WBS)Work Breakdown Structure (WBS) The WBS can be conceived as a tree, The WBS can be conceived as a tree,
with the project as the root node, with the project as the root node,
major components of the project as the main branches, and major components of the project as the main branches, and
tasks/subtasks branch off from these. tasks/subtasks branch off from these. A WBS may be a diagram or a text list.A WBS may be a diagram or a text list.
Activity based approach (2)Activity based approach (2)
WBS ExampleWBS Example
Project
Analyze ProjectDesign
Data design Process design Physical design
Relational data analysis
Logical data analysis
Activity based approach (3)Activity based approach (3)Example of Textual WBSExample of Textual WBS
33.01 MOBILIZATION AND PREPARATORY WORK33.01.01 MOBILIZATION OF CONSTRUCTION EQUIP. AND FACILITIES33.01.02 MOBILIZATION OF PERSONNEL33.01.03 PRECONSTRUCTION SUBMITTALS/IMPLEMENTATION PLANS33.01.03.01 Erosion Control Plan33.01.03.04 Environmental Protection Plan(etc)33.01.03.14 Construction Quality Control Plan33.01.04 SETUP/CONSTRUCT TEMPORARY FACILITIES(etc)33.01.05 CONSTRUCT TEMPORARY UTILITIES
33.02 MONITORING, SAMPLING, TESTING, AND ANALYSIS33.02.03 AIR MONITORING AND SAMPLING(etc)
33.03 SITE WORK33.03.04 ROADS/PARKING/CURBS/WALK33.03.04.03 Aggregate Surfacing(Source: US Army Corps of Engineers)
Product Based ApproachProduct Based Approach
Producing Producing Product Breakdown Structure (PBS) Product Breakdown Structure (PBS)
identifies all the productsidentifies all the products Product Flow Diagram (PFD)Product Flow Diagram (PFD)
shows how products interrelateshows how products interrelate
Product Based Approach (2)Product Based Approach (2)
PBS ExamplePBS ExampleRequirement Specification
Data catalogue Processing specificationRequirement catalogue
Attribute/Data Itemdescription
Grouped domaindescription
Logical data model
User Role/Function Matrix
Functiondefinition
Entity lifeHistory
Enquiry Access Path
I/OStructure
Elementary Process Description
Product Based Approach (2)Product Based Approach (2)
The Product Flow Diagram shows which products must The Product Flow Diagram shows which products must be complete before the next can be producedbe complete before the next can be produced
Most items in the diagram are things the customer needs, Most items in the diagram are things the customer needs, eg. design documentation, software, manualseg. design documentation, software, manuals
indicated by boxesindicated by boxes Some items are intermediate products, needed only to help Some items are intermediate products, needed only to help
produce other products, produce other products, eg. first cut database design eg. first cut database design
indicated by boxes indicated by boxes Some items will exist already,Some items will exist already,
eg. feasibility study report, terms of referenceeg. feasibility study report, terms of reference
indicated by ellipses (ovals)indicated by ellipses (ovals) Arrows indicate that one product is required in order to produce Arrows indicate that one product is required in order to produce
the next the next
Hybrid ApproachHybrid ApproachCreate a WBS that is based upon the project’s products, Create a WBS that is based upon the project’s products, which is in turn based on a simple list of deliverables and which is in turn based on a simple list of deliverables and a set of activities for each deliverablea set of activities for each deliverable
Project
Installed System User manualSoftware component
Analyze req.
Outline design
Training course
Integrate system
Test system
review req.
Outline design
Code software
Test software
Sequencing and Scheduling Sequencing and Scheduling ActivitiesActivities
To sequence the task according to their To sequence the task according to their logical relationship, andlogical relationship, and
To schedule them taking into account To schedule them taking into account resources and other factorsresources and other factors
Events versus activitiesEvents versus activities
Event Event = a point in time= a point in time has no durationhas no duration e.g the e.g the startstart or or end end of an activityof an activity
ActivityActivity = a task or an action with a = a task or an action with a recognizable recognizable startstart and and finishfinish and a and a durationduration
Prepare breakfast Eat breakfast
activities
events
Start and finish timesStart and finish times
Activity ‘write report software’Activity ‘write report software’
Earliest start (ES)Earliest start (ES)
Earliest finish (EF) = ES + durationEarliest finish (EF) = ES + duration
Latest finish (LF) = latest task can be Latest finish (LF) = latest task can be completed without affecting project end completed without affecting project end Latest start = LF - durationLatest start = LF - duration
Earliest start
Latest start
Latestfinish
Earliest finish
activity
ExampleExample
earliest start = day 5earliest start = day 5
latest finish = day 30latest finish = day 30
duration = 10 daysduration = 10 days
earliest finish = ?earliest finish = ?
latest start = ? latest start = ?
Float = LF - ES - duration
What is it in this case?
Critical pathCritical path
Note the path through network with zero Note the path through network with zero floatsfloatsCritical path: any delay in an activity on Critical path: any delay in an activity on this path will delay whole projectthis path will delay whole projectCan there be more than one critical Can there be more than one critical path?path?Can there be no critical path?Can there be no critical path?Sub-critical pathsSub-critical paths