power transformer ( summer training presentation bhel )

Download Power Transformer ( Summer Training presentation BHEL )

Post on 20-Aug-2015

5.778 views

Category:

Education

0 download

Embed Size (px)

TRANSCRIPT

  1. 1. Summer Training Report onPower Transformer Presented by : Dheeraj Upadhyay Electrical & Electronics Engineering
  2. 2. POWER TRANSFORMERThey have rating above 200 Kva and used in generating station and substation used for power transmission line for stepping up and stepping down the voltage.
  3. 3. Stages of Power Transformers manufacturing are : Design & Drawing Winding Manufacturing Core Building Unlacing of Core Fitting Bottom insulation Core Coil Assembly Fitting of Top insulationRelacing of core Terminal Gear Mounting Final Tanking Testing Despatch
  4. 4. Design & Drawing : 1Phase3 MVARatingKVA 66 kv Voltage Class 11 kv
  5. 5. 50 Hz Frequency 60 Hz ConnectionPurposeY Generating Substation Distribution
  6. 6. Winding Used : R-S Coil : reverse section winding. Helical coil : winded in shape of spring. Spiral coil : simply wounded on the base. Interleaved coil : winding current rotates in same conductor Composite winding : more than one conductor winded with each other.
  7. 7. Helical winding Interleaved
  8. 8. Core of Transformer : Material Used : CRGO : Cold rolled grain oriented silicon steel is used to build the core. Purpose of using CRGO is to reduce the Hysteresis losses. Laminations of these sheets minimizes eddy current loss.
  9. 9. Unlacing of core : This is basically the phenomena of removal of top end frame of the core assembly so that the coils can be mounted on the core.
  10. 10. Core Coil Assembly : Core coil assembly consists of assembling the windings to the core assembly. Core assembly is placed on a suitable leveled platform. Tighten the three limbs with webbing tape. Top channels and top yoke laminations are removed and placed on a table in the same sequence. Bottom insulation items like pressboard rings, petals; perma wood rings are placed on bottom yoke on each core limb. Core wraps as specified in the design details are covered to the core limbs and tightened with cotton tape. L.V Coil : primary coil for step down transformer, made in order to allow the flow of large current through it . H.V Coil : Secondary coil for step down transformer, made in order to allow high voltage and hence small current through it. T.V Coil : this is known as the tertiary voltage coil.
  11. 11. Relacing Of Core : The top yoke is again attached to The Rest of the Core, the sheets Are attached one by one or in Packets (generally 2 to 4 in numbers) to the core limb in erect position. Then the job is dipped in oil and then heated to remove any kind of moisture in it. After that the job is compressed i.e. pressure is applied from the top to compress the coil and achieve the required CD of the coil as specified in design.
  12. 12. Processing and DRY OUT : The presence of the moisture brings about the reduction in the electric strength of material and also increases its volume. Dry out is necessary in this condition. The final drying out is commenced either when the core and winding are placed or when they are fitted in to there tank, all main connections made and the tank placed in an oven and connected to the drying system
  13. 13. Final Tanking : Tanking means.. assembling the core coil assembling job into transformer tank with all necessary accessories according to bill of material and design diagram.
  14. 14. Testing of Power Transformer Tests during manufacture : Core plate checks Core frame insulation resistance Core loss measurement Winding copper checks Tank tests
  15. 15. Final Testing : Routine Tests Voltage ratio and polarity. winding resistance. impedance voltage, short-circuit impedence and load loss dielectric tests. (a) separate source AC voltage. (b) Induced voltage. no-load losses and current. on-load tap changers, where appropriate.
  16. 16. TYPE Tests : Temperature rise test. noise level test. lightning impulse tests.
  17. 17. EQIPMENTS USED FOR THE PROTECTION OF POWER TRANSFORMER Lightning Arrester. Over Current Relay. Buccholz relay. Earth fault relay. Oil level indicator. Over fluxing relay.