ms project 2013 lesson 3[1]

Upload: santuchetu

Post on 20-Feb-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    1/28

    Copyright 2012-2014, Simplilearn, All rights reserved.

    Microsoft Project 2013

    Lesson 03

    Project Tasks

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    2/28

    Copyright 2012-2014, Simplilearn, All rights reserved.

    Objectives

    By the end of this lesson, you will be able to:

    Add new tasks in Microsoft Project 2013

    Create a project outline

    Schedule tasks manually

    Create task dependencies with links

    Create project milestones

    Rearrange tasks

    Set tasks as active or inactive

    Display project summary in Microsoft Project 2013

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    3/28

    Copyright 2012-2014, Simplilearn, All rights reserved.

    Tasks are added by entering appropriate task names in the Task Sheetavailable in the Gantt Ch

    Add New Tasks in Microsoft Project 2013

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    4/28

    Copyright 2012-2014, Simplilearn, All rights reserved.

    Entering a task name in the Task Sheet or the Gantt Chart adds a new task to the project.

    Add New Tasks in Microsoft Project 2013 (contd.)

    Task Name

    Start

    Predecessors

    IndicatorsIndicators column reveals if the task or a resource has notes or hyperlinto provide additional information.

    Task Name column contains the name of the task or resource.

    Start column indicates the task start date.

    Predecessors column indicates the task that precedes the given task.

    Task ModeTask Mode column indicates if a task is manually or automaticallyscheduled.

    Duration Duration column indicates the total working time required for a task .

    Finish Finish column indicates the task finish date.

    Resource NamesResource Names column contains details of materials or human resourneeded for the task.

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    5/28

    Copyright 2012-2014, Simplilearn, All rights reserved.

    A task can be scheduled manually or automatically.

    In case of manually scheduled tasks, you need to enter the duration and start date of the

    calculated according to the duration entered.

    In case of auto scheduled tasks, you need to enter the duration of the task. The start and

    automatically. The start date of the first task is by default set to the project start date.

    Manually Scheduled Tasks vs. Auto Scheduled Tasks

    Auto Scheduled

    Manually Scheduled

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    6/28Copyright 2012-2014, Simplilearn, All rights reserved.

    While creating a Task List, the Project Manager can create a project outline by grouping tasks.

    Tasks are grouped as summary tasks and subtasks.

    Project Outline

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    7/28Copyright 2012-2014, Simplilearn, All rights reserved.

    Related tasks are grouped under an appropriate title. This tittle is called a summary task.

    In Microsoft Project 2013, the summary tasks are easily recognized as they are in bold. Th

    encapsulates details of all subtasks.

    Expand or collapse arrow next to the summary task can be used to collapse and expand t

    Project Outline (contd.)

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    8/28Copyright 2012-2014, Simplilearn, All rights reserved.

    A summary task consists of several subtasks. In Microsoft Project 2013, the subtasks are indent

    task.

    Project Outline (contd.)

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    9/28Copyright 2012-2014, Simplilearn, All rights reserved.

    Sometimes the tasks in a project are dependent on other tasks. This dependency can be projec

    2013 by linking these tasks.

    Create Task Dependencies with Links

    Start-to-Start

    Finish-to-Finish

    Start-to-Finish

    Finish-to-Start

    P

    S

    P

    S

    P

    P

    S

    S

    Predecessor task has to finishsuccessor task to start.

    Predecessor task has to start,successor task to start.

    Predecessor task has to finishsuccessor task to finish.

    Predecessor task has to start, successor task to finish.

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    10/28Copyright 2012-2014, Simplilearn, All rights reserved.

    Milestones in a Project are the significant events, either reached within the plan or are depend

    Milestones can be created to highlight the critical points of the project.

    Milestones can be recognized in Microsoft Project 2013 as tasks that have zero duration

    Create Project Milestones

    1

    k

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    11/28Copyright 2012-2014, Simplilearn, All rights reserved.

    Tasks and subtasks can be rearranged in the project plan using the cut and paste commands.

    Rearranging Tasks

    21

    Cut Select row

    R i T k ( d )

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    12/28Copyright 2012-2014, Simplilearn, All rights reserved.

    Rearranging Tasks (contd.)

    Rearranging auto scheduled tasks and tasks with dependencies:

    When the auto scheduled tasks are rearranged, the start and finish dates ge

    adjusted accordingly.

    When tasks with dependencies are rearranged, the links will be lost, unless

    dependent tasks are shifted along with the main tasks.

    I ti T k

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    13/28Copyright 2012-2014, Simplilearn, All rights reserved.

    Inactive Tasks

    All tasks added in Microsoft Project 2013 are entered as Active Tasks. Tasks that are on hold or

    tasks can be set as Inactivate Tasks.

    1

    Ti li Vi

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    14/28Copyright 2012-2014, Simplilearn, All rights reserved.

    Timeline View

    Timeline View allows a Project Manager to view all the project related information at a glance

    Project Summary

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    15/28Copyright 2012-2014, Simplilearn, All rights reserved.

    Project Summary

    Project Summary summarizes the timeline of the entire project. Project summary is automatic

    Project 2013, however, it is hidden by default.

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    16/28Copyright 2012-2014 Simplilearn All rights reserved

    Knowledge Check 1

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    17/28Copyright 2012-2014 Simplilearn All rights reserved

    Knowledge Check 1

    What does the indicator column in the task sheet reveal?

    Select the answer.

    a. Notes, hyperlink, or other additional information

    b. Task mode used

    c. Milestone task

    d. Summary task and subtask

    Knowledge Check 1

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    18/28Copyright 2012-2014 Simplilearn All rights reserved

    Knowledge Check 1

    Answer: a. Notes, hyperlink, or other additional information

    What does the indicator column in the task sheet reveal?

    Select the answer.

    a. Notes, hyperlink, or other additional information

    b. Task mode used

    c. Milestone task

    d. Summary task and subtask

    Explanation: Indicator column reveals if the task has notes, hyperlink, or other additional info

    Knowledge Check 2

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    19/28

    Copyright 2012-2014 Simplilearn All rights reserved

    Knowledge Check 2

    While creating a Task List, how can a Project Manager create a project outline?

    Select the answer.

    a. As summary tasks

    b. As active tasks

    c. By grouping tasks

    d. By creating subtasks

    Knowledge Check 2

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    20/28

    Copyright 2012-2014 Simplilearn All rights reserved

    Knowledge Check 2

    Answer: c. By grouping tasks

    Explanation: While creating a Task List, the Project Manager can create a project outline by g

    While creating a Task List, how can a Project Manager create a project outline?

    Select the answer.

    a. As summary tasks

    b. As active tasks

    c. By grouping tasks

    d. By creating subtasks

    Knowledge Check 3

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    21/28

    Copyright 2012 2014 Simplilearn All rights reserved

    Knowledge Check 3

    Ideally, which of the following is needed while auto scheduling the task?

    Select the answer.

    a. Task start date

    b. Task finish date

    c. Task duration

    d. Task resources

    Knowledge Check 3

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    22/28

    Copyright 2012 2014 Simplilearn All rights reserved

    Knowledge Check 3

    Answer: c. Task duration

    Explanation: In case of auto scheduled tasks, you need to enter the duration of the task. The s

    date is calculated automatically.

    Ideally, which of the following is needed while auto scheduling the task?

    Select the answer.

    a. Task start date

    b. Task finish date

    c. Task duration

    d. Task resources

    Knowledge Check 4

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    23/28

    Copyright 2012 2014 Simplilearn All rights reserved

    Knowledge Check 4

    When tasks are linked in a project, which of the following dependency is created by default?

    Select the answer.

    a. Finish-to-Start

    b. Start-to-Start

    c. Finish-to-Finish

    d. Start-to-Finish

    Knowledge Check 4

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    24/28

    Copyright 2012 2014 Simplilearn All rights reserved

    g

    Answer: a. Finish-to-Start

    Explanation: When tasks are linked, finish-to-start dependency is created by default.

    When tasks are linked in a project, which of the following dependency is created by default?

    Select the answer.

    a. Finish-to-Start

    b. Start-to-Start

    c. Finish-to-Finish

    d. Start-to-Finish

    Knowledge Check 5

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    25/28

    Copyright 2012 2014 Simplilearn All rights reserved

    g

    Which of the following summarizes the timeline of the entire project?

    Select the answer.

    a. Project tasks

    b. Project milestone

    c. Project outline

    d. Project summary

    Knowledge Check 5

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    26/28

    Copyright 2012-2014, Simplilearn, All rights reserved.

    g

    Answer: d. Project summary

    Explanation: Project Summary summarizes the timeline of the entire project.

    Which of the following summarizes the timeline of the entire project?

    Select the answer.

    a. Project tasks

    b. Project milestone

    c. Project outline

    d. Project summary

    Summary

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    27/28

    Copyright 2012-2014, Simplilearn, All rights reserved.

    Here is a quick recap of what was covered in this lesson:

    Tasks are added by entering appropriate task name in the task Sheet, available in

    the Gantt Chart view.

    A project is outlined as summary tasks and subtasks.

    Tasks can be scheduled either manually or automatically.

    Milestones in a project are used to highlight critical points of the project.

    Cut and paste tools are used to rearrange tasks.

    The tasks that are on hold or not a part of active tasks can be set as Inactive

    Tasks.

    Project summary summarizes the timeline of the entire project.

  • 7/24/2019 MS Project 2013 Lesson 3[1]

    28/28

    Copyright 2012-2014, Simplilearn, All rights reserved.

    Thank You