ms project 2013 lesson 2[1]
TRANSCRIPT
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 1/31
Copyright © 2012-2014, Simplilearn, All rights reserved.
Microsoft® Project 2013
Lesson 02
Creating a Project Plan
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 2/31
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 3/31
Copyright © 2012-2014, Simplilearn, All rights reserved.
The Project Manager needs to define basic project details at the commencement of a new proj
Basic Information for a New Project
Start date of a project
Finish date of a project
Project Calendar
Project Schedule
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 4/31
Copyright © 2012-2014, Simplilearn, All rights reserved.
Microsoft® Project 2013 Interface
There are different methods to create a project in Microsoft® Project 2013.
From a
Microsoft®
SharePoint
task list
From an
existing
project
From a
Microsoft®
Excel
workbook
As a blank
project
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 5/31
Copyright © 2012-2014, Simplilearn, All rights reserved.
Create Project from a Blank Project Template
A new project can be initiated in Microsoft® Project 2013 by creating a blank project and then a
into it.
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 6/31Copyright © 2012-2014, Simplilearn, All rights reserved.
Components of a Blank Project Template
The important components of a Blank Project template are shown here.
Quick Access
Toolbar
Ribbon
View
Gantt Chart
Zoom
Status Bar
Task Name and
Description
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 7/31Copyright © 2012-2014, Simplilearn, All rights reserved.
Create Project from an Existing Template
New Product launch Market Research
Schedule
ResidentialConstruction
Commercial
Construction
Merger or Acquis
Evaluation
Microsoft® Project 2013 has many pre-installed templates that can be used to create a new pro
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 8/31© 2014 Simplilearn Solutions. All Rights Reserved.
Create Project from an Existing Project
A new project can be created from an existing project.
• A similar project can be used from the previous history to enter the new project details to it
• When a project is created this way, the existing project acts as the foundation for the new p
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 9/31© 2014 Simplilearn Solutions. All Rights Reserved.
Create Project from Microsoft® Excel Workbook
New project can be created from an Excel workbook.
f f ® l kb k ( d )
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 10/31© 2014 Simplilearn Solutions. All Rights Reserved.
Create Project from Microsoft® Excel Workbook (contd.)
If the project information is in Microsoft® Excel Workbook format, it can be imported into Micro
losing the data or format.
C P j f Mi f ® Sh P i T k Li
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 11/31© 2014 Simplilearn Solutions. All Rights Reserved.
Create Project from Microsoft® SharePoint Task List
If the development team is using SharePoint for a project, the Project Manager can synchronize
SharePoint without using the Project Web App.
• This will allow the team members to view the project schedule on SharePoint.
• Any updates on SharePoint will be reflected in the Microsoft® Project plan.
S l Sh P i t T k Li t
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 12/31© 2014 Simplilearn Solutions. All Rights Reserved.
Sample SharePoint Task List
Sample task list from SharePoint Project tasks is shown here.
I t d ti t B C l d
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 13/31© 2014 Simplilearn Solutions. All Rights Reserved.
Introduction to Base Calendar
When planning a schedule, knowledge about working days and hours, down time, vacations, hol
project manager.
• These details allow the project manager to plan the project resourcefully.
• Hence, the project manager can set up a base calendar to plan his project in a better way.
Base Calendar
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 14/31© 2014 Simplilearn Solutions. All Rights Reserved.
Base Calendar
The key elements of a base calendar are as follows:
This helps in assigning the right resources for the project.Resource Allocation
This helps in scheduling the project.Project Scheduling
This helps in identifying the working time to determine when the resources are available toResource Availability
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 15/31
Create New Base Calendar
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 16/31Copyright © 2012-2014 Simplilearn All rights reserved
Create New Base Calendar
When the project team is spread across geographies, with each region having its own set of wo
days, the Project Manager can create a new calendar for each geographical region.
• He can apply these calendars to the resources and tasks.
Click Change Working
Time. Cr
Ca
dis
Click Create New
Calendar…
1
2
Set Baseline
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 17/31Copyright © 2012-2014 Simplilearn All rights reserved
Set Baseline
The ‘Set Baseline’ command can be used to compare the status of the project with the original
• Baseline records the project plan and the resource allocation.
• Microsoft® Project 2013 permits eleven benchmarks.
Create a Template from a Completed Project
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 18/31Copyright © 2012-2014 Simplilearn All rights reserved
Create a Template from a Completed Project
Microsoft® Project 2013 allows you to save the completed project plans as project templates.
• Strategies from past projects can be shared and can be applied to future projects.
1
2
3
4
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 19/31
Quiz 1
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 20/31
Copyright © 2012-2014 Simplilearn All rights reserved
Quiz 1
Which of the following provides the overall information of the project?
Select the answer.
a. Project Schedule
b. Base Calendar
c. Pre-Installed Templates
d. Project Information
Quiz 1
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 21/31
Copyright © 2012 2014 Simplilearn All rights reserved
Quiz 1
Answer: d. Project Information
Which of the following provides the overall information of the project?
Select the answer.
a. Project Schedule
b. Base Calendar
c. Pre-Installed Templates
d. Project Information
Explanation: ‘Project Information’ option in Microsoft® Project 2013 provides the overall infor
project to the user.
Quiz 2
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 22/31
Copyright © 2012 2014 Simplilearn All rights reserved
Quiz 2
Which of the following provides option to create benchmarks to compare project performanc
Select the answer.
a. Gantt Charts
b. Project Schedule
c. Set Baseline
d. Standard Calendar
Quiz 2
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 23/31
Copyright © 2012 2014 Simplilearn All rights reserved
Quiz 2
Answer: c. Set Baseline
Explanation: ‘Set Baseline’ command is used to create a base point, which acts as a benchmar
the project performance.
Which of the following provides option to create benchmarks to compare project performance
Select the answer.
a. Gantt Charts
b. Project Schedule
c. Set Baseline
d. Standard Calendar
Quiz 3
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 24/31
Copyright © 2012 2014 Simplilearn All rights reserved
Q
Which of the following calendar is used from 8:00 a.m. to 5:00 p.m.?
Select the answer.
a. Base Calendar
b. Standard Calendar
c. Night Shift Calendar
d. 24-Hour Calendar
Quiz 3
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 25/31
Copyright © 2012 2014 Simplilearn All rights reserved
Q
Answer: b. Standard Calendar
Explanation: ‘Standard Calendar’ is the type of calendar which is used from 8.00 AM to 5.00 P
Which of the following calendar is used from 8:00 a.m. to 5:00 p.m.?
Select the answer.
a. Base Calendar
b. Standard Calendar
c. Night Shift Calendar
d. 24-Hour Calendar
Quiz 4
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 26/31
Copyright © 2012-2014, Simplilearn, All rights reserved.
How many benchmarks can be created with ‘Set Baseline’ command?
Select the answer.
a. 5
b. 7
c. 11
d. 15
Quiz 4
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 27/31
Copyright © 2012-2014, Simplilearn, All rights reserved.
Answer: c. 11
Explanation: You can create up to 11 benchmarks using ‘Set Baseline’ command.
How many benchmarks can be created with ‘Set Baseline’ command?
Select the answer.
a. 5
b. 7
c. 11
d. 15
Quiz 5
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 28/31
Copyright © 2012-2014, Simplilearn, All rights reserved.
Which of the following can be used to synchronize the task list, without using the Project Web
Select the answer.
a. Existing Projects
b. Microsoft® SharePoint
c. Existing Templates
d. Microsoft® Excel Workbooks
Quiz 5
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 29/31
Copyright © 2012-2014, Simplilearn, All rights reserved.
Answer: b. Microsoft® SharePoint
Explanation: You can synchronize the task list from the SharePoint without using the Project W
Which of the following can be used to synchronize the task list, without using the Project Web
Select the answer.
a. Existing Projects
b. Microsoft® SharePoint
c. Existing Templates
d. Microsoft® Excel Workbooks
Summary
7/24/2019 MS Project 2013 Lesson 2[1]
http://slidepdf.com/reader/full/ms-project-2013-lesson-21 30/31
Copyright © 2012-2014, Simplilearn, All rights reserved.
Here is a quick recap of what was covered in this lesson:
● Information such as, project information, project schedule, project calendar, start
date, and finish date of the project are important to create a new project.
● In Microsoft® Project 2013, a new project can be created using a blank template,
an existing project, an existing template, a Microsoft® Excel workbook, and a
Microsoft® SharePoint tasks list.
● A base calendar is the main calendar used in a project. The types of base calendar
are standard, night-shift, and 24-hour calendar.
● The Set baseline command can be used to create a base point that acts as a
benchmark to compare the project performance.
● Microsoft® Project 2013 provides option to save an existing project, as a template