measurements, transportation and storage 504 eng. fathi morgan

Upload: ali105

Post on 03-Jun-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    1/93

    MINING STUDIES AND RESEARCH CENTER (MSRC)

    FACULTY OF ENGINEERING CAIRO UNIVERSITY

    NATURAL GAS ENINEERING DIPLOMA

    Measurements,

    Transportation &

    Storage

    NG 504

    1

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    2/93

    Fathy Ibrahim Emam Morgan

    Engineering Consultant

    Oil/Gas Piping and PipelinesEngineering Consultants Group (ECG)

    E-mail: [email protected]

    Cell No 0122 475 5741

    Contact Information

    2 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    3/93

    For successful implementation of a pipeline project,

    the following steps are to be considered in general:

    1. Market survey-Present & Future demand

    2. Map of the preliminary selected pipeline route(L)

    3. Selection of ROW

    4. Detailed survey and Preparation of alignment

    drawings

    5. MAOP & Design pressure

    Pipeline Design

    3 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    4/93

    6. Pipe Size (D)

    7. Pipe specification / grade

    8. Wall Thickness (t)9. Bill of Materials

    10. Total cost estimate

    Pipeline Design (Contd.)

    4 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    5/93

    Load Consideration:

    Presently pipeline design is being done

    considering the present load as well as the

    assumed gas load of the that particular area for

    the next 20 years (effective life of the pipeline)

    Now-a days, the use of natural gas increased

    tremendously. As a result the concept of

    pipeline design has also changed.

    Pipeline Design (Contd.)

    5 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    6/93

    Line Pipe Wall Thickness Calculation:t= DP/(2YFLJT)

    Where,

    t = Pipe wall thickness, mm

    P= design pressure, psigD= outside dia of pipe in mm

    Y= minimum yield strength, psig

    F= Design factor

    L= Location factor based on class locationJ= welding joint factor

    T= Temp. derating factor

    Pipeline Design (Contd.)

    6 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    7/93

    Grade Minimum yield

    strength (MPa)

    Minimum Tensile Strenght

    (Mpa)

    B 241 413

    X42 289 413

    X46 317 434

    X52 358 455

    X56 386 489

    X60 413 517

    X65 448 530

    X70 482 565

    X80 551 620

    Line Pipe : API 5L Grades

    7 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    8/93

    Canadian Standards association(CSA) suggests

    design factor of 0.8 While location Factors are:

    Design and Location Factor

    Area Class Location ASME CSA

    Deserted 1 0.72 0.80

    Village 2 0.60 0.72

    City 3 0.50 0.56Metropolis 4 0.40 0.44

    8 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    9/93

    Weld type ASME B31.8

    Seamless 1

    ERW 1SAW 1

    But Welled 0.6

    Spiral seam 0.8

    Joint Factor

    9 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    10/93

    Temperature ( F) ASME B31.8

    Up to 250 1.00

    251-300 0.97301-400 0.93

    401-450 0.91

    451 and above 0.87

    Temperature Factor

    10 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    11/93

    DPP

    Land acquisition & Requisition

    Tender Document Preparation

    Tender Bid Evaluation

    Tender Award

    Procurement

    Mobilization

    Clearing, Grading and Stringing

    Pipeline Construction Process

    11 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    12/93

    Welding and NDT

    Trenching, Lowering and Backfilling

    Tie-in Hydrostatic Testing

    Cleaning

    Commissioning

    Operation

    Pipeline Construction Process

    (contd.)

    12 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    13/93

    Row Acquisition and Requisition

    ROW SELECTION

    DC Office

    Compensation

    Crop Compensation

    Pre Construction

    13 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    14/93

    Minimize overall pipe length

    Parallel existing utility corridors (Highway, High tensionElectric transmission line).

    Avoid areas of high population density Minimize highways, railways, river, khals, canals, ponds,

    hills & mountains corssing to reduce the project cost.

    Cross highways, railways, river, khals, canals at or close

    to 90 deg. Angle Minimize crossover of existing facilities

    Provide adequate construction area.

    Pre Construction (Contd.)

    General Guideline For Pipeline Routing

    14 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    15/93

    Avoid the following areas:

    Swamps and Wetlands

    Rocky areas

    Unstable soil Populated areas

    Historical areas

    Environmental sensitive areas ( Forest, Tea garden,

    Rubber garden etc.) Religious sensitive areas ( Mosque, Graveyard, temple

    etc.)

    Pre Construction (Contd.)

    General Guideline For Pipeline Routing

    15 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    16/93

    Land acquisition / Requisition

    Normally 10m wide strip along the proposedpipeline route is to be acquisition and a 15 mwide strip on one side of the acquisition strip is tobe requisition.

    Acquisition is permanent possession for use ofland but requisition is completely a temporaryaffair, only for the working period.

    For scraper station and Valve station separateblock lands of required size have to beacquisition.

    Pre Construction (Contd.)

    16 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    17/93

    Submission of proposal for land acquisition & requisition:

    The company submit the proposal with requisite no. ofdrawings ( Normally mouza map) showing acquisition& requisition strip in two distinct colors (red foracquisition & green for requisition) to DC office.

    The process of acquisition and requisition in ourcountry is done through the DC office of the particulardistinct.

    The whole process continues in accordance withOrdinance, Arts, Rules and Regulation issued by thegovernment from time to time.

    Pre Construction (Contd.)

    17 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    18/93

    Tender

    Floating

    Bid Receiving & Evaluation

    Contract Award & Contract Management

    Procurement

    Mobilization

    Pre Construction (Contd.)

    18 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    19/93

    Cleaning & Grading the ROW

    Stringing the pipe along ROW

    Welding the pipe joints together

    NDT of welding joints

    Coating and Wrapping Ditching / Trenching

    Holiday test

    Lowering & backfilling

    Pigging Hydro Test

    Commissioning

    Major steps for pipeline

    Construction

    19 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    20/93

    Bulldozer- Used to clearing & grading of ROW.

    Excavator- Used to trenching, pipe lifting, pullingthe welding machine etc.

    Side boom- Used to lift the pipe during weldingand lay the pipeline in the trench.

    Crane- Used to handle heavy equipment andmachineries.

    Welding generator Trailer/ Truck- used to carry the line pipe fromstore yard to the working site.

    Equipment used for Pipeline

    Construction

    20 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    21/93

    Pipeline Construction

    Equipment

    21 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    22/93

    ROW is cleared of barriers and

    graded for movement ofconstruction equipment,

    materials and ultimately

    construction of pipeline.

    ROW Clearing and Grading

    22 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    23/93

    Welders test- an example for the weldersbefore going to production weld.

    Selection Criterion- Visual inspection & NDT

    (API 1104) PQR / WPS Test

    Tensile strength test

    Face bend test Root bend test

    Charpy V notch test

    Pre Welding Activities

    23 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    24/93

    Stringing is aligning the pipe

    along the ROW ready for

    welding.

    Trailer, Side boom etc. are

    used to stringing the pipe.

    Stringing

    24 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    25/93

    Root pass/ Stringer pass

    Hot pass

    Filling pass

    Cap pass

    Cleaning the welds

    Welding

    25 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    26/93

    Dye penetrant test

    Magnetic particle test

    Eddy current test Radiographic test

    Ultrasonic test

    NDT personnel certification ( level 1, 2

    &3)

    NDT (Non Destructive Test)

    26 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    27/93

    Radiographic test

    Equipment

    Method

    Source

    Film examination as Per API 1104Standard

    NDT (Non Destructive Test)

    27 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    28/93

    Ultrasonic test

    EquipmentMethod

    Source

    Weld examination

    NDT (Non Destructive Test)

    28 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    29/93

    Porosity Cluster porosity

    Slag inclusion

    Lack of fusion

    Lack of penetration

    Internal concavity Burn through

    Crack

    Common welding defects

    29 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    30/93

    Welding defects:

    30 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    31/93

    The final weld to join two separatesection together.

    Should be properly aligned withoutuse of jacks or any external force.

    Should be done within operating

    temp (5-30 deg. Celsius).

    NDT test.

    Tie-in welds

    31 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    32/93

    Two different ways

    Thurst boring/ horizontal boring method

    Drill a hole under the roadway without disturbing

    the road / rail surface.

    A casing pipe is placed through the hole and then

    the pipeline is placed inside the casing.

    Spacer is used to center the pipeline within thecasing pipe.

    Open Cut method.

    Roads and Railway Crossing

    32 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    33/93

    All except a portion (about 6 inch) of each pipe isoften coated in the factory before deliver to thesite

    Three types of coating 3LPE coating

    FBE coating

    Polyethylene coating

    3LPE coating Apply adhesive on clean pipe surface Epoxy paint (40-100 micron)

    Polyethylene coating

    Pipe Coating

    33 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    34/93

    Bare pipe

    34 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    35/93

    Features:Cleaning (sand Blasting)

    Apply AdhesiveApply epoxy paint ( 40 100

    micron thick)

    Polyethylene coating

    3 LPE Coated Pipe

    35 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    36/93

    Apply 3LPE Coating

    Set wire mesh above 3LPE

    Coating

    Apply Concrete coating

    Provide

    Ve buoyancy forceApply on ditch, canal, pond, khal,

    small river

    Features:

    Concrete Coated Pipe

    36 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    37/93

    Put on above 3LPE

    coated pipe

    One on each pipe

    Provide Ve buoyancy

    forceApply on Marchy area

    Features:

    Set-on-Weight

    37 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    38/93

    Heat shrink sleeves

    Approx. 14 inch length and dialarger than pipe dia.

    Shrink on applying heat and fitted

    to the pipe.

    Joint coating

    38 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    39/93

    Ditching

    Holyday test

    Apply 10 KV on coated pipe surface Any coating defect will result an audible

    sound.

    Lowering Lay pipeline on Trench of approx. 1.2m depth

    Put set-on-weight on buried pipe for anti

    buoyancy force.

    Ditching, Holyday test, Lowering

    and Backfilling

    39 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    40/93

    Bruch/ cup pigClean internal rust

    Gauge pig

    To check pipe ovality

    Foam Pig

    To dry internal surface

    Testing:

    40 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    41/93

    Natural Gas Equipment

    Distribution System

    Each time the pressure is reduced,

    over pressure protection is providedby a relief valve or automatic shut off

    A relief valve venting gas to the atmosphere is

    performing its proper function and should never becut off or restricted until the gas company arrives

    and makes corrections to the system

    41 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    42/93

    Properties of Natural Gas

    Odorless Colorless - Tasteless

    Methyl Mercaptan is added to give it its

    distinguishable rotten egg odor

    Odorized natural gas is detectable at

    concentrations significantly less than 1%

    42 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    43/93

    Natural Gas Equipment

    Distribution SystemType of System Pressure

    Transmission Line

    (High Pressure)3001000 psig

    Distribution Main

    (High Pressure)60300 psig

    Distribution Main

    (Modified High Pressure)560 psig

    Distribution Main(Low Pressure)

    psig

    Service / Customer Line psig

    43 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    44/93

    Natural Gas Equipment

    Material Color Size Pressure

    Bare Steel - - - - - - 2 6 Up to 60 psi

    Wrapped Steel Yellow / brown 20 Up to 1000 psi

    Wrought Iron - - - - - - 2 6 Up to 60 psi

    Polyethylene PlasticBlack / orange /

    yellow 6Up to 60 psi

    Cast Iron - - - - - - 4 20 psi

    Copper - - - - - - - psi

    Piping

    44 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    45/93

    Natural Gas Equipment

    Polyethylene pipe is buried with a 12 gauge

    wire for ease of locating it has nothing todo with grounding or bonding

    POLYETHYLENE PIPE

    Piping

    45 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    46/93

    Natural Gas Equipment

    Distribution piping is normally buried between 12 and 18

    below ground level

    Piping

    46 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    47/93

    Natural Gas Equipment

    Shut-off Valves

    Square - Handle

    L - Handle

    T - Handle

    Side View

    47 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    48/93

    Natural Gas Equipment

    Shut-off Valves

    Closed Position

    Open Position

    Top View

    48 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    49/93

    Natural Gas Equipment

    Typical Residential Installation

    49 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    50/93

    Natural Gas Equipment

    Typical Residential Installation

    Regulator

    Relief Valve

    Valve

    50 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    51/93

    Natural Gas Equipment

    Typical Residential Installation

    Meter

    51 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    52/93

    Natural Gas Equipment

    Commercial Installation

    Meter

    Valve

    Regulator

    52 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    53/93

    Natural Gas Emergencies

    Types of EmergenciesOdors / Leaks

    Fire

    53 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    54/93

    Natural Gas Emergencies

    Emergency ResponseOdors / LeaksInside:

    1) Approach incident from upwind, if possible.

    2) Position apparatus at least150 from scene.

    3) Investigate for the source of the odor with the GasTrac & Mini-Gas.

    4) If a strong odor is encountered or leak is confirmed, evacuate thebldg. of all occupants.

    54 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    55/93

    Natural Gas Emergencies

    Emergency ResponseOdors / LeaksInside:

    5) Notify BC GAS - Gas Op's to respond.

    6) Ventilate the bldg. by opening doors & windows. Remember toopen windows on top.

    7) Do not operate electrical switches / telephones.

    55 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    56/93

    Natural Gas Emergencies

    Emergency ResponseOdors / Leaks

    9) If a leak is confirmed, the IC should determine if it can be stoppedor if the gas needs to be shut off at the valve.

    Inside8) Use only intrinsically safe radios / handlights.

    56 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    57/93

    Natural Gas Emergencies

    Emergency ResponseOdors / Leaks

    11) Gas valves turned OFF by FD personnel SHOULD NEVER be turnedback on without BC GAS - Gas Op's on scene.

    12) No one should re enter the bldg. until BC GAS - Gas Op's hassecured the leak and determined that it is safe to enter.

    Inside10) Hand tools should be spark-proof (1663 /1665).

    57 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    58/93

    Natural Gas Emergencies

    Emergency ResponseOdors / LeaksOutside

    1) If unignited gas is escaping from the ground, either from an

    excavation site or from an open pipe outside of a bldg., notify BCGAS - Gas Op's immediately.

    2) Establish a safe area around the incident scene.

    3) Extinguish all open flames.

    4) Check surrounding bldgs., especially basements, for the presence

    of gas.

    Gas can migrate through the ground, following pipes or naturalstratifications in the earth.

    58 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    59/93

    Natural Gas Emergencies

    Emergency ResponseOdors / LeaksOutside

    5) Restrict or re-route traffic until BC GAS - Gas Op's personnel can

    bring the gas flow under control.

    6) Although water fog streams can be used to disperse escaping

    vapors, they are usually ineffective since the lighter-than-air gas

    naturally rises.

    7) If water fog is used, caution must be exercised to avoid filling

    excavation sites with water.

    59 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    60/93

    Natural Gas Emergencies

    Emergency ResponseOdors / LeaksOutside

    8) FD personnel should never clamp or crimp a gas line. Static

    electricity could ignite escaping gas, resulting in a suddenand violent ignition.

    9) Hand tools should be spark-proof (1663 / 1665).

    60 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    61/93

    Natural Gas Emergencies

    Emergency ResponseFiresInside:

    1) Notify BC GAS - Gas Op's immediately upon receipt of alarm.

    2) The IC should determine if the gas can safely be shut off inside thebldg. or at the meter.

    61 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    62/93

    Natural Gas Emergencies

    Emergency ResponseFiresInside:

    3) In certain industrial / commercial settings, turning off the gas supplycan seriously interrupt important and costly industrial processes andshould only be done upon evaluation with company personnel and BCGAS - Gas Op's.

    4) If the gas supply cannot be shut off, the surrounding combustiblesshould be kept wet with a fog stream.

    62 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    63/93

    Natural Gas Emergencies

    Emergency ResponseFiresOutside:

    1) Notify BC GAS - Gas Op's immediately upon receipt of alarm.

    2) The best method of controlling outdoor gas fires is to shut off the

    gas flow.

    3) In most cases, FD personnel should not attempt to extinguish the

    fire while the gas is still escaping.

    4) BURNING GAS WILL NOT EXPLODE.

    63 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    64/93

    Natural Gas Emergencies

    Emergency ResponseFiresOutside:

    5) Secure the area and protect exposures, if necessary.

    6) IF it is necessary to extinguish the fire before the gas flow can be

    stopped, use a Dry Chem extinguisher aimed at the base of the

    flame and wet the surrounding area with water fog to prevent the

    re-ignition of combustibles.

    64 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    65/93

    Natural Gas

    An OperationalPerspective

    65 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    66/93

    EXPLORATION AND

    PRODUCTION

    66 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    67/93

    GATHERING AND

    PROCESSING

    67 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

    Natural gas has to go from

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    68/93

    Natural gas has to go from

    Point A to Point B.

    Point A involves getting the gas outof the ground and into the pipeline.

    Point B is where the gas eventually

    ends up, so you can cook your food andheat your home.

    The line that connects Point A to Point B is

    where the midstream industry takes over.

    68 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    69/93

    Gas Processing connecting

    A to BRaw natural Gas consists of hydrocarbons:

    Methane

    Propane

    Butane

    Pentane

    plus many more

    It also contains undesired materials: sulfur compounds,

    water, mercury, etc.

    69 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    70/93

    That raw natural gas must be purified, or

    processed, to meet quality standards and

    specifications set by the major pipeline and

    distribution companies

    70 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    71/93

    A more detailed view

    71 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    72/93

    72 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    73/93

    TRANSMISSION ANDSTORAGE

    73 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    74/93

    74 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    75/93

    Natural Gas Equipment

    Distribution piping is normally buried between 12 and

    18 below ground level

    Piping

    75 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    76/93

    Agenda

    Transporting Gas

    Interruptible

    Pipeline Map

    Basic Rules of Interstate Transportation

    Services

    Business Processes

    76 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    77/93

    What is Gas Transportation?

    Gas Transportation - service provided by the pipeline

    for the party that has requested the transportation

    service. The pipeline is the link between the gas

    supplies and the markets.

    Involves the receipt of the gas by the transporter, the

    movement of gas through the transporters system and

    the delivery of gas by the transporter for the shippers

    account.

    Service can be firm or interruptible.

    77 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    78/93

    Interruptible Service

    Firm Service is a service that is offered on a guaranteed basis. Thepipeline, also known as the Transportation Service Provider (TSP),

    warrants that it will make the service available on every day of the

    contract unless prevented by an act of Force Majeure.

    For this firm service, the customer, also known as the Service Requester

    (SR), will generally pay a demand and a commodity charge. The total

    charge is generally higher than interruptible services.

    Firm services have a higher priority than interruptible services. Firm

    service contracts generally have a term of over a year.

    78 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    79/93

    Interruptible Service

    Interruptible Service is a service that is not a guaranteed service. The

    TSP can generally cease the performance of the service with short or no

    notice. The TSP will interrupt if the pipeline space used for interruptible

    service is required to serve a higher priority customer.

    The SR of the interruptible service will generally pay only a commodity

    charge when the service is utilized. The total cost of the service is usually

    less than the cost of a firm service. The interruptible service is less

    reliable by definition.

    79 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    80/93

    80 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504

    Eng. Fathy Morgan

    Basic Rules of Interstate Transportation

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    81/93

    Basic Rules of Interstate Transportation

    When Crosses state boundaries. As such, the service:

    - Must be offered on a non-discriminatory basis.

    - Must allow firm contract holders to release to other parties so some of the

    reservation costs paid by the firm shipper ma be recovered when the capacitywould otherwise not be used.

    - Customers must be able to change their firm receipt and delivery points. All

    other receipt points must be made available to the customers on an interruptible

    basis.

    - Customers have rights beyond their contract path but within the same rate zone.

    81 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504

    Eng. Fathy Morgan

    Services Offered by Pipelines

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    82/93

    Services Offered by Pipelines

    Firm TransportationThe highest quality transportation service offered to customers under a filed rate schedule

    that anticipates no planned interruption.

    No-Notice Service

    A bundled, city-gate service that allows customers to receive gas on demand to meet peakservice needs subject to delivering supplies into the pipeline.

    Interruptible TransportationTransportation service subject to interruption at the option of the pipeline.

    Storage ServiceA firm or interruptible service that allows customers to store natural gas that has been

    transferred from its original location

    82 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504

    Eng. Fathy Morgan

    Services offered by Pipelines

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    83/93

    Services offered by Pipelines

    (continued)

    Pooling Service

    A firm or interruptible service that allows customers to aggregate natural gas from many receipt points to

    serve a number of contracts without tying a particular receipt point to a particular contract.

    Parking ServiceAn interruptible service which allows a customer to request that the pipeline hold on its system, gas

    quantities that have been delivered by the customer under any transportation agreement between the

    pipeline and the customer, and then return such gas quantities at thecustomers request.

    Loan Service

    An interruptible service which allows a customer to receive gas quantities from the pipeline and then

    return such loaned quantities of gas to the pipeline at the point in which the gas was borrowed.

    83 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504

    Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    84/93

    LocalDistribution

    84 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504

    Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    85/93

    85 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504

    Eng. Fathy Morgan

    How the Natural Gas Distribution Syste

    W k

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    86/93

    Works

    Local Gas Distribution Companies Overview

    Natural gas distribution is the last step in the delivery process

    What is a natural gas LDC?

    Generally state regulated entities which operate gas distribution piping systems

    that serve

    gas locally to homes, businesses and industrial customers

    Some are municipally-owned

    Operate in defined, exclusive service territories

    Statutorily obligated to provide reliable natural gas service to customers at just

    and reasonable rates, terms and conditions

    Local distribution is exempt from FERC jurisdiction under NGA 1(b)

    NGPA definition

    86 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504

    Eng. Fathy Morgan

    H th N t l G Di t ib ti S t

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    87/93

    Where does transportation end and local distribution begin?

    No bright line from FERC; but generally movement through large diameter

    pipelines at higher pressure (over 350 psia) is considered transportation;

    particularly if the line is not regulated by a state PUC

    Supreme Court decision in FPC v. East Ohio Gas Co., 338 U.S. 464 (1950)

    Congress responded with Hinshaw exemption NGA 1(c)

    How the Natural Gas Distribution System

    Works contn.

    87 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504

    Eng. Fathy Morgan

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    88/93

    Differences from Interstate Pipelines

    Generally, LDCs operate at lower pressures, use smaller diameter pipes, and

    the distribution pipes directly connect to the house lines of local homes and

    businesses

    LDC systems differ among themselves, but generally consist of:

    high pressure transmission lines, lower pressure mains and service lines,regulators, a wide variety of meters, and odorization equipment

    May include on-system storage, LNG storage, and propane-air

    88 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504

    Eng. Fathy Morgan

    LDC Customers and Services

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    89/93

    LDC Customers and Services

    Types of LDC customers: retail, commercial, and industrial

    Types of LDC services:

    Sales Service to Core/Retail (firm and interruptible services)

    Transportation Service (firm and interruptible)

    Retail unbundling (customers purchase gas commodity directly from

    suppliers/marketers)

    LDCs connect to interstate pipelines at citygate points

    LDCs purchase natural gas commodity at wholesale from

    producers/marketers

    Receive the gas from the supplier at the citygate; and/or

    Receive the gas at upstream points and move the gas on interstatepipeline capacity

    89 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504

    Eng. Fathy Morgan

    LDC Resources Used to Serve Core

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    90/93

    LDC Resources Used to Serve Core

    Customers

    Typical LDC resources include:

    Gas purchased outside of the LDCs service territory

    Supplies previously purchased and held in storage facilities outside of the

    LDCs service territory

    Supplies previously purchased and held in peaking facilities inside the LDC

    service territory

    Supplies purchased from local production wells in the state

    Diversion of supplies from interruptible customers understate-approved tariff

    curtailment provisions

    90 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504

    Eng. Fathy Morgan

    LDC Operating System

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    91/93

    LDC Operating- System

    Movement on LDC systems involves moving smaller volumes of gas at lowerpressures to numerous individual customers.

    To ensure flow, gas may be perioducally compressed at compressor stations,

    but the pressure required on LCD systems is much lower than on an interstate

    pipeline.

    Supervisory control and SCADA systems monitor gas flow on the distributionnetwork.

    To detect leaks, gas is odorized at the citygate with mercaptan

    Piping system is steel for higher pressure main and polyethylene(plastic) in

    lower pressure mains and service lines.

    91 MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504

    Eng. Fathy Morgan

    LDC Operations Service

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    92/93

    LDC Operations - Service

    Generally, customers do not make nominations.

    Gas consumed at the residance or business is measured by a onsite

    meter.

    Customers are billed according to use and rate schedule.

    Storage or on-system needle peaking storage is used as an additional

    resource to meet core needs.

    92MSRC - Natural Gas Engineering Diploma - Measurements, Transportation & Storage NG 504 Eng. Fathy Morgan

    LDC Focus on Safety

  • 8/12/2019 Measurements, Transportation and Storage 504 Eng. Fathi Morgan

    93/93

    LDC Focus on Safety

    LDC safety programs include:

    Leak detection response

    Safety education

    One Call Systems

    Emergency plans and responsiveness

    State statutes and regulations adopt DOT

    safety requirements