A review of schools completed in the West Midlands by Lend Lease in 2012.

TRANSCRIPT

Page 1: Lend Lease Photobook

Birmingham Lend Lease Partnership

an education journeyan education journeyan education journey

Page 2: Lend Lease Photobook
Page 3: Lend Lease Photobook

cont

ents4 Four Dwellings Primary

6 Summerfield Primary

8 George Dixon Primary

10 Holte/Mayfield/Lozells

12 George Dixon International School

14 Moseley School

16 Stockland Green School

18 Broadway School

20 The International School

22 Park View School

24 Four Dwellings Secondary

26 Saltley School

28 Birmingham Ormiston Academy

30 Shenley Academy

32 Heartlands Academy

34 Aston University Engineering Academy

36 Dorrington Academy

As Western Europe’s largest local authority, Birmingham City Council’s vision of transforming its ageing schools into sophisticated and technology-led centres of education, fit for the next generation and beyond, was a challenge on a global scale.

Lend Lease was chosen as the authority’s development partner, designing, building and delivering 20 separate projects; primaries, secondaries and academies, both refurbishments and new-build, with a capital value of £330 million.

Lend Lease have also delivered managed services for Information & Communications Technology in 13 schools and Facilities Mangement for 10 locations.

The massive programme undertaken by the Birmingham Lend Lease Partnership - a public-private collaboration between council and developer - has achieved nothing short of a renaissance, to the delight of pupils, teachers - and the city council.

Page 4: Lend Lease Photobook
Page 5: Lend Lease Photobook

Four Dwellings PrimaryDESCRIPTION | PRIMARY NEW BUILDAPPROX PUPIL NUMBERS | 427CONTRACT SUM | APPROX £13 MILLIONSTART ON SITE DATE | 04.07.11COMPLETION DATE | 11.01.13TIME TO BUILD | 14 MONTHS

Page 6: Lend Lease Photobook

Summerfield Primary

DESCRIPTION | PRIMARY REFURBISHMENTAPPROX PUPIL NUMBERS | 302

CONTRACT SUM | APPROX £2 MILLIONSTART ON SITE DATE | 06.12.10

COMPLETION DATE | 04.11.11TIME TO BUILD | 10 MONTHS

Page 7: Lend Lease Photobook

Summerfield Primary

Page 8: Lend Lease Photobook
Page 9: Lend Lease Photobook

George Dixon PrimaryDESCRIPTION | PRIMARY NEW BUILDAPPROX PUPIL NUMBERS | 216CONTRACT SUM | APPROX £19 MILLIONCOMPLETION DATE | 06.02.13TIME TO BUILD | 17 MONTHS.

Page 10: Lend Lease Photobook
Page 11: Lend Lease Photobook

Holte | Mayfield | LozellsDESCRIPTION | HIGH SCHOOL/PRIMARY/SPECIAL NEEDS NEW BUILD

APPROX PUPIL NUMBERS | H 922M 161L 467

CONTRACT SUM | APPROX £34 MILLIONSTART ON SITE DATE | 02.02.09

COMPLETION DATE | 19.12.11TIME TO BUILD | 35 MONTHS

Page 12: Lend Lease Photobook
Page 13: Lend Lease Photobook

DESCRIPTION | HIGH SCHOOL REFURBISHMENTCONTRACT SUM | APPROX £19 MILLIONCOMPLETION DATE | 06.02.13TIME TO BUILD | 17 MONTHS.

George Dixon International School

Page 14: Lend Lease Photobook

DESCRIPTION | HIGH SCHOOL REFURBISHMENT AND NEW BUILD

APPROX PUPIL NUMBERS | 1381CONTRACT SUM | APPROX £17 MILLION

START ON SITE DATE | 06.06.11COMPLETION DATE | 15.02.13TIME TO BUILD | 15 MONTHS

MoseleySchool

Page 15: Lend Lease Photobook

DESCRIPTION | HIGH SCHOOL REFURBISHMENT AND NEW BUILD

APPROX PUPIL NUMBERS | 1381CONTRACT SUM | APPROX £17 MILLION

START ON SITE DATE | 06.06.11COMPLETION DATE | 15.02.13TIME TO BUILD | 15 MONTHS

MoseleySchool

Page 16: Lend Lease Photobook
Page 17: Lend Lease Photobook

Stockland Green School

DESCRIPTION | HIGH SCHOOL NEW BUILDAPPROX PUPIL NUMBERS | 679

CONTRACT SUM | APPROX £17 MILLIONSTART ON SITE DATE | 02.02.09

COMPLETION DATE | 01.04.11TIME TO BUILD | 26 MONTHS

Page 18: Lend Lease Photobook

Broadway SchoolDESCRIPTION | HIGH NEW BUILD & REFURBISHMENTAPPROX PUPIL NUMBERS | 1300CONTRACT SUM | APPROX £18 MILLIONSTART ON SITE DATE | 02.02.09COMPLETION DATE | 19.05.11TIME TO BUILD | 28 MONTHS

Page 19: Lend Lease Photobook
Page 20: Lend Lease Photobook

The InternationalSchool

DESCRIPTION | HIGH SCHOOLAPPROX PUPIL NUMBERS | 911

CONTRACT SUM | APPROX £11 MILLIONSTART ON SITE DATE | 31.01.11COMPLETION DATE | 30.06.12TIME TO BUILD | 18 MONTHS

Page 21: Lend Lease Photobook
Page 22: Lend Lease Photobook
Page 23: Lend Lease Photobook

Park View SchoolDESCRIPTION | HIGH SCHIOOL REFURBISHMENT AND NEW BUILDAPPROX PUPIL NUMBERS | 604CONTRACT SUM | APPROX £8 MILLIONSTART ON SITE DATE | 31.01.11COMPLETION DATE | 11.06.12TIME TO BUILD | 18 MONTHS

Page 24: Lend Lease Photobook

Four Dwellings Secondary

DESCRIPTION | HIGH SCHOOL REFURBISHMENTAPPROX PUPIL NUMBERS | 592

CONTRACT SUM | APPROX £13 MILLIONSTART ON SITE DATE | 04.07.11

COMPLETION DATE | 11.01.13TIME TO BUILD | 14 MONTHS

Page 25: Lend Lease Photobook
Page 26: Lend Lease Photobook
Page 27: Lend Lease Photobook

SaltleySchoolDESCRIPTION | HIGH SCHOOL REFURBISHMENT AND NEW BUILDAPPROX PUPIL NUMBERS | 936CONTRACT SUM | APPROX £11 MILLIONSTART ON SITE DATE | 23.06.11COMPLETION DATE | 25.10.12TIME TO BUILD | 14 MONTHS

Page 28: Lend Lease Photobook
Page 29: Lend Lease Photobook

Birmingham OrmistonAcademyDESCRIPTION | ACADEMY NEW BUILDAPPROX PUPIL NUMBERS | 950CONTRACT SUM | APPROX £23 MILLIONSTART ON SITE DATE | 12.04.10COMPLETION DATE | 07.10.11TIME TO BUILD | 18 MONTHS

Page 30: Lend Lease Photobook
Page 31: Lend Lease Photobook

Shenley AcademyDESCRIPTION | ACADEMY NEW BUILD

APPROX PUPIL NUMBERS | 1150CONTRACT SUM | APPROX £22 MILLION

START ON SITE DATE | 21.02.11COMPLETION DATE | 12.07.13TIME TO BUILD | 19 MONTHS

Page 32: Lend Lease Photobook
Page 33: Lend Lease Photobook

Heartlands AcademyDESCRIPTION | ACADEMY NEW BUILDAPPROX PUPIL NUMBERS | 755CONTRACT SUM | APPROX £19 MILLIONSTART ON SITE DATE | 21.02.11COMPLETION DATE | 23.07.13TIME TO BUILD | 19 MONTHS

Page 34: Lend Lease Photobook
Page 35: Lend Lease Photobook

Aston University Engineering Academy

DESCRIPTION | ACADEMY NEW BUILDAPPROX PUPIL NUMBERS | 600

CONTRACT SUM | APPROX £14 MILLIONSTART ON SITE DATE | 28.03.11

COMPLETION DATE | 03.09.12TIME TO BUILD | 17 MONTHS

Page 36: Lend Lease Photobook
Page 37: Lend Lease Photobook

DorringtonAcademy

DESCRIPTION | MODULAR NEW BUILDAPPROX PUPIL NUMBERS | 552

CONTRACT SUM | APPROX £1 MILLIONSTART ON SITE DATE | 13.02.12

COMPLETION DATE | 01.06.12TIME TO BUILD | 5 MONTHS

Page 38: Lend Lease Photobook
Page 39: Lend Lease Photobook

PROJECT DESCRIPTION APPROX PUPIL NUMBERS

CONTRACT SUM (APPROX)

START ON SITE DATE

COMPLETION DATE

TIME TO BUILD

HML (PFI) High/Primary/Special Needs New Build H 922 M 161 L 467

£34 million 02.02.09 19.12.11 35 months

STOCKLAND GREEN (PFI) High New Build 679 £17 million 02.02.09 01.04.11 26 months

BROADWAY High New Build & Refurb 1300 £18 million 02.02.09 19.05.11 28 months

GREET Primary Refurb 709 £3 Million 06.12.10 19.08.11 9 months

REGENTS PARK Primary Refurb 486 £3 million 06.12.10 05.09.11 9 months

SUMMERFIELD Primary Refurb 302 £2 million 06.12.10 04.11.11 10 months

DORRINGTON Modular New Build 552 £1 million 13.02.12 01.06.12 5 months

ORMISTON High 950 £23 million 12.04.10 07.10.11 18 months

INTERNATIONAL High 911 £11 million 31.01.11 30.06.12 18 months

PARK VIEW High Refurb and New Build 604 £8 million 31.01.11 11.06.12 18 months

FOUR DWELLINGS High Refurb/Primary New Build Primary 427 High 592

£13 million 04.07.11 11.01.13 14 months

MOSELEY High Refurb and New Build 1381 £17 million 06.06.11 15.02.13 15 months

GEORGE DIXON High Refurb/Primary New Build Primary 216 High 1050

£19 million 28.03.11 06.02.13 17 months

SALTLEY High Refurb and New Build 936 £11 million 23.06.11 25.10.12 14 months

ASTON Academy New Build 600 £14 million 28.03.11 03.09.12 17 months

HEARTLANDS Academy New Build 755 £19 million 21.02.11 23.07.13 19 months

SHENLEY Academy New Build 1150 £22 million 21.02.11 12.07.13 19 months

ST ALBANS Academy New Build 203 £17 million 27.06.11 05.08.13 25 months

NORTH BIRMINGHAM Academy New Build 1011 £23 million 25.07.11 04.11.13 28 months

WAVERLEY (PFI) Academy New Build 768 £27 million 23.01.11 12.09.14 40 months

SHELDON HEATH Academy New Build 1100 £25 million 09.11.11 20.06.14 30 months

TOTAL £328 million

Project Handover Inform

ation