robert ioffrida - lend lease

51
NorthConnex Technical Presentation 13 th Australian Tunnelling Conference Presented by Robert Ioffrida, Project Director

Upload: informa-australia

Post on 14-Jan-2017

17.989 views

Category:

Business


3 download

TRANSCRIPT

Page 1: Robert Ioffrida - Lend Lease

NorthConnex Technical Presentation13th Australian Tunnelling Conference

Presented by Robert Ioffrida, Project Director

Page 2: Robert Ioffrida - Lend Lease

Project Overview

Page 4: Robert Ioffrida - Lend Lease

Project - Key Stakeholders

• Transurban, Canada Pension Plan and QIC

Client (Project Co.)

• Lendlease Bouygues JV (50/50)Contractor

• Aurecon SMEC JV (50/50)Designers

Lendlease Bouygues Joint Venture

Page 5: Robert Ioffrida - Lend Lease

Project - Key Dates

• 13 January 2015Project Approval

• 18 June 2015Start Construction

• 3rd Qtr 2015Start Tunnelling

• 4th Qtr 2019Completion

Lendlease Bouygues Joint Venture

5

Page 6: Robert Ioffrida - Lend Lease

Project – Expected Project Personnel

• 400 +LLBJV Staff

• 160+LLB/UGL Alliance

Staff

• 500+ 300+ Tunnelling and 200+ Civil Employees

LLBJV Direct Labour

• 800+ (including M&E)Contractor

Partners

Lendlease Bouygues Joint Venture

Page 7: Robert Ioffrida - Lend Lease

What is NorthConnex?

• NorthConnex will provide the vital

link between Hills M2 Motorway

and the M1 Pacific Motorway.

• Two key components – Tunnel and

M2 Integration Works

• Australia’s longest and deepest road

tunnel – longer than the Eastern

Distributor, M5 East and Cross City

tunnels combined

Lendlease Bouygues Joint Venture

7

Page 8: Robert Ioffrida - Lend Lease

Project scope

• Twin motorway tunnels - nine kilometres in

length / two lanes plus a breakdown lane in

each direction, and a speed limit of 80 km/h (or

90?)

• Each tunnel will be built with future capability to

provide three lanes in each direction at reduced

speed

• A northern interchange connecting with the M1,

the Pacific Highway & Pennant Hills Road

• A southern interchange connecting with the Hills

M2 Motorway and Pennant Hills Road

Lendlease Bouygues Joint Venture

8

Page 9: Robert Ioffrida - Lend Lease

• A motorway control centre and ancillary

buildings, southern and northern ventilation

outlets and water treatment plant near the

southern interchange

• Ancillary facilities for operation, such as

electronic tolling facilities, ventilation

facilities as well as fire and life safety

systems

• Two additional smoke exhaust shafts in the

event of an underground fire

• Modifications to service utilities and

associated work at surface roads near the

two interchanges

Lendlease Bouygues Joint Venture

9

Project scope cont.

Page 10: Robert Ioffrida - Lend Lease

Pioneer Avenue Construction Compound

M2 Integration Works

Project Map

Page 11: Robert Ioffrida - Lend Lease

Tunnelling – Basic schemeMain construction sites

Southern Interchange – M2 Portal

Wilson Road – Smoke Extraction Shaft

Trelawney Street – Smoke Extraction Shaft

Northern Interchange - M1 Portal

Southern InterchangeM2 Portal

WILSON SHAFT

TRELAWNEYSHAFT

M1 InterchangeNorth Portal

11

Page 12: Robert Ioffrida - Lend Lease

Tunnelling – major quantities

Scope Quantity

Tunnel length - mainline tunnel 16,313 m

Tunnel length - cross passage only 1,375 m

Tunnel length - on and off ramp 3,177 m

Tunnel length - Y Junctions 1,050 m

Quantity - cross passages 75 pc

Quantity - substation underground 2 pc

Quantity - low point sumps underground 1 pc

Quantity - shafts 4 pc

Excavation total 2,250,000 m3

Page 13: Robert Ioffrida - Lend Lease

Project Design Features

Page 14: Robert Ioffrida - Lend Lease

Standard Cross Section Main Carriageway

2 lane tunnel designed for future 3 lane use

Dynamic envelope = 10.5m x 5.3m

Tunnel Concept :

- Mechanized excavation using road headers / rock boltings and shotcrete

- Drained tunnel: 1l/s/km allowable water inflow limit.

- Waterproof membrane to divert water away from tunnel crown

14

Page 15: Robert Ioffrida - Lend Lease

Mechanical and Electrical Design

Electrical Systems• High voltage reticulation

• Low voltage reticulation

• Tunnel lighting

• Street lighting

• Emergency exit lighting

• Fire detection

Control Systems• Control room & video wall

• Plant management & control system

• Traffic management & control system

• Closed circuit television / Video incident detection

• Electronic signage

Mechanical Systems

• Tunnel ventilation

• Drainage

• Mechanical ventilation & air conditioning

• Tunnel air monitoring include air dispersion

• Fire and life safety strategy

• Fire suppression and tunnel fire doors Lendlease Bouygues Joint Venture

Communication systems

• Phones

• Public address

• Radio rebroadcast

• Mobile phone rebroadcast

Page 16: Robert Ioffrida - Lend Lease

Additional site investigation

Geology

16

Page 17: Robert Ioffrida - Lend Lease

Geology

Competent geology / with localized features

Largely in Hawkesbury sandstone with some Ashfield shale

17

Soil and extremely weathered

rock

Ashfield shale

Mittagong

Formation

Hawkesbury

sandstone

Page 18: Robert Ioffrida - Lend Lease

Permanent Lining - Cast in situ

Typical Cross Section – Shale only

Volume Kicker = 1.6m3/m

Volume Vault = 7.16m3/m

Perimeter = 22.7m

18

Page 19: Robert Ioffrida - Lend Lease

Permanent Lining – Sprayed Shotcrete

Typical Cross Section – Hawkesbury Sandstone

Volume Vault = 2.72m3/m

Perimeter = 16.6m

19

Page 20: Robert Ioffrida - Lend Lease

Tunnel Construction

Page 21: Robert Ioffrida - Lend Lease

Southern Portal and Ramps - Sequence of Excavation

21

Page 22: Robert Ioffrida - Lend Lease

Typical Tunnel Sections

22

Page 23: Robert Ioffrida - Lend Lease

Environmental Layout - Wilson Shaft

23

Page 24: Robert Ioffrida - Lend Lease

Shaft depth

Shaft Depth (collar to invert)

Southern Interchange 12/30m

Wilson Road 81.3m

Trelawney 56.6m

M1 Interchange 43.7m

24

Page 25: Robert Ioffrida - Lend Lease

Excavation Sequence – Wilson Shaft

25

Page 26: Robert Ioffrida - Lend Lease

Typical Noise Shed arrangement / Conveyor

26

Page 27: Robert Ioffrida - Lend Lease

Shaft access to tunnel

Lendlease Bouygues Joint Venture

Page 28: Robert Ioffrida - Lend Lease

Shaft access to tunnel

Lendlease Bouygues Joint Venture

Page 29: Robert Ioffrida - Lend Lease

Excavation Sequence – Shafts

Page 30: Robert Ioffrida - Lend Lease

Excavation Sequence – Tunnel Level

30

Page 31: Robert Ioffrida - Lend Lease

Excavation Sequence – Tunnel Level

31

Page 32: Robert Ioffrida - Lend Lease

Excavation Sequence – Tunnel Level

32

Page 33: Robert Ioffrida - Lend Lease

Excavation Sequence Tunnel - Cut

33

Page 34: Robert Ioffrida - Lend Lease

Different Excavation Activities in the tunnel

34

Page 35: Robert Ioffrida - Lend Lease

Shotcrete Trials

35

Page 36: Robert Ioffrida - Lend Lease

Plant (Shaft Jumbo)

36

Page 37: Robert Ioffrida - Lend Lease

Tunnel Procurement - Plant

(Roadheader Fabrication in Japan)

37

Page 38: Robert Ioffrida - Lend Lease

Tunnel Procurement - Plant (Road header Fabrication in

Austria)

38

Page 39: Robert Ioffrida - Lend Lease

Tunnel Excavation

Lendlease Bouygues Joint Venture

Page 40: Robert Ioffrida - Lend Lease

Tunnel Procurement - Plant (Shotcrete Machines)

40

Page 41: Robert Ioffrida - Lend Lease

Tunnel Procurement - Plant (Mobile Agitator and Bolter)

41

Page 42: Robert Ioffrida - Lend Lease

Ventilation Fan

– Ventilation: Forced Overlap system chosen with 35and 50 M3/s de-Dusters

42

Page 43: Robert Ioffrida - Lend Lease

Program of Works

Page 44: Robert Ioffrida - Lend Lease

Tunnelling – Basic scheme

General sequence of excavation:

1- RH excavation 1- XP Excavation 2- Benching 3- Lining / waterproofing

(1 activity in the program)

4- Drainage/Cable pit 5- Paving (no fine, asphalt, CRCP)

excavation ducts install backfill

Access to M&E Blue: Civil Activities

7- Cable Pulling Red: M&E Activities

7- M&E 1st Fix (cable trays, fans, cables)

6- Traffic Barriers fundation 7- Cladding frame support 8- Install Traffic Barriers

Access to M&E 11- Commissioning

9- Infill Concrete 10- M&E 2nd Fix (cable termination) 11- Cladding installation

11- Low noise diamond grind, pavement, line mark

together

Benching starts once excavation for full length of regular section is

completed by Road header

Enlarged section will be excavated once full length of regular section

is completed by road header

1- RH excavation 1- XP Excavation 2- Benching 3- Lining / waterproofing

(1 activity in the program)

4- Drainage/Cable pit 5- Paving (no fine, asphalt, CRCP)

excavation ducts install backfill

Access to M&E Blue: Civil Activities

7- Cable Pulling Red: M&E Activities

7- M&E 1st Fix (cable trays, fans, cables)

6- Traffic Barriers fundation 7- Cladding frame support 8- Install Traffic Barriers

Access to M&E 11- Commissioning

9- Infill Concrete 10- M&E 2nd Fix (cable termination) 11- Cladding installation

11- Low noise diamond grind, pavement, line mark

together

Benching starts once excavation for full length of regular section is

completed by Road header

Enlarged section will be excavated once full length of regular section

is completed by road header

M2 WILSON TRELAWNEY M1

NB Entry Ramp (M1C0)M1C0N1 M1C0N2

M2 ACCESS SHAFT FOR M110 & M120 S110N OUT M1C0N2 OUT T110N OUT T110N OUT

NB (M110) S110N M1C0N2 W110S W110N T110S T110N N110S N110N

M2W110S OUT T110S OUT N110S OUT

M1S120N OUT M1C0N1 OUT W120N OUT T120N OUT

SB (M120) M1D0N S120N M1C0N1 W120S W120N T120S T120N N120S N120NM1D0N OUT W120S OUT T120S OUT N120S OUT

N110N NB EXIT RAMP (M1P0)

SB Exit Ramp (M1D0) M1C0N1 M1D0N

N110N OUT

N120N SB ENTRY RAMP (M1Q0)N120N OUT

TEMPORARY

ACCESS TO SB &

M1D0 (XP13)

XP83 ACCESS

FOR ROAD

HEADER TO

M1DO

M1

C0

N1

44

Page 46: Robert Ioffrida - Lend Lease

Community Benefits

Page 47: Robert Ioffrida - Lend Lease

Hornsby Quarry (before)

Lendlease Bouygues Joint Venture

Page 48: Robert Ioffrida - Lend Lease

Hornsby Quarry (after)

Lendlease Bouygues Joint Venture

Page 49: Robert Ioffrida - Lend Lease

Local Engagement

Lendlease Bouygues Joint Venture

• Promote opportunities for local businesses

• Promote opportunities for local employees

Page 50: Robert Ioffrida - Lend Lease

Contact the NorthConnex team

Lendlease Bouygues Joint Venture

Project Information Line – 1800 997 057 (free call)

Page 51: Robert Ioffrida - Lend Lease

Questions?