Project NamePharmaceuticalManufacturing Facility
Project LocationCovington, Georgia
Project Team
Central Plants
Markets
Specializations
Owner: Biopharmaceuticals Manufacturer
Building Information ModelingPipe Shop Prefab
Science & Technology
Industrial
General Contractor: Fluor CorporationArchitect: Flad ArchitectsEngineers: AEI Corporation,CRB Consulting EngineersSubcontractor: McKenney’s, Inc.
McKenney’s completed a large-scale HVAC and plumbing installation at a new manufacturing plant on a 100-acre campus in Covington, Georgia.
The ChallengeFrom the outset, the owner had an aggressive timeline for completing its new campus to manufacture drugs for treating unusual diseases.Our team faced an immense project scope, a large number of trade workers in a confined space, design changes, rigorous quality control requirements and the emergence of an outside main instrument valve vendor.
The SolutionTo navigate design changes and meticulously track costs, McKenney’s held weekly—sometimes daily—meetings to identify the scope of changes, evaluate pricing and inform the owner of overages. Our quality control team addressed onsite issues and procured a third party firm to ensure welding in our prefab pipe shop and field installations met the owner’s standards. For much of the project, all trades deployed two shifts along with extended work hours to stay on schedule.
The content of this document is not intended as an endorsement.
The ResultsOur attentiveness to detail kept the project on track and met the owner’s timeline and quality control standards.