java high speed train project

26
HIGH SPEED TRAIN PROJECT IN INDONESIA (JAKARTA – SURABAYA CORRIDOR) HERMANTO DWIATMOKO Directorate General of Railways Ministry of Transportation Republic of Indonesia Jakarta, 2010

Upload: kekipi

Post on 25-Oct-2014

108 views

Category:

Documents


6 download

DESCRIPTION

Presentation about High Speed Train project in Java, Indonesia

TRANSCRIPT

 

  

 

 

HIGH SPEED TRAIN PROJECT IN INDONESIA (JAKARTA – SURABAYA CORRIDOR)

HERMANTO DWIATMOKO

Directorate General of RailwaysMinistry of Transportation

Republic of IndonesiaJakarta, 2010

High Speed Train Project in Indonesia  

(Jakarta ‐ Surabaya Corridor) 1 

 

HIGH SPEED TRAIN PROJECT IN INDONESIA (JAKARTA – SURABAYA CORRIDOR) 

  

Hermanto Dwiatmoko  

Director of Safety and Technical Rolling Stock. Directorate General of Railways, Ministry of Transportation. 

Republic of Indonesia   

SUMMARY  Indonesia is accelerating industrialization and urbanization, perticulary in the suburbs of large cities such as  Jakarta and Surabaya. The High Speed Train  is a  technological break‐through  in passenger transport  which  has  allowed  to  increase  railways  share  in  modal  split,  competing  with  others transport mode.  Some  benefits  of  High  Speed  Train  project  in  Indonesia  for  Jakarta  –  Surabaya Corridor, approximately 685 km, have been identified as cost saving such as the value of time saved by  passengers  traveling  on High  Speed  Train,  the  foreign  exchange  saved  due  to  decrease  in  oil import  as  result  of  a  decrease  in  freight  transportation  by  commercial  trucks  due  to  increase  in freight trains as passengers shift from conventional trains and airplanes to High Speed Train and the foregin  exchange  earned  by  selling  the  surplus  CO2  emission  right  that  results  from  decrease  in conventional trains and airplanes as passengers shift to High Speed Train. It will  increase economic growth and trading due to increasing of people movement and regional development, coincide with decreasing  of  cars  or  petrol  usage,  and  resulting  improvement  of  environment.  Accordingly,  the investment  of  the  project will  not  faces  a  profitability  problem  from  the  financial  viewpoint  and appropriate as a PPP  (Public Private Partnerships) project  to be  implemented by mainly  Indonesia government and the private sectors.  1. Introduction 

 In order to improve the economic growth, not only the software aspect such as laws, social systems, social safety, labor, but also the hardware aspect especially, the transportation sector is important. Transportation  sector  plays  a  great  role  among  measures  for  sustainable  economic  growth. Transportation  sector  is  an  important  component  of  the  economy  impacting  on  development, especially between large city such as Jakarta and Surabaya as a main artery, to make a substitute city for  Jakarta  area  as  the  center  of  development.  Jakarta  and  its  surrounding  cities  (Jabodetabek) contributed about 20% to Indonesia’s GDP (Gross Domestic Product), followed by greater Surabaya 6%, greater Bandung 3%, and Makassar 1%. The  railway  section between  Jakarta and Surabaya  is connected by  conventional double  tracking between  Jakarta – Cirebon and Pemalang –  Larangan, integrated with single tracking between Cirebon – Pemalang and Larangan – Surabaya, while the line capacity between this two cities is limited and the number of passenger is increasing.  The traveling time between this two cities by a train is about 10 ‐ 14 hours and by a bus is more than 18 hours due to the traffic jam, which means a wasting time for businees people and very tired for the passengers. However, although currently there  is one air flight every hour between  Jakarta and Semarang, the runway of the Soekarno Hatta Airport is expected to reach the capacity limit by 2015.    

Better  solution  should  be  achieved  by  developing  an  efficient  transportation  system  and environmentally  friendly  between  Jakarta  and  Surabaya, which will  take  only  2.5  hours  traveling time. If travel range in a day is expanded by an efficient transportation system, human and material distribution will become active, and opportunities  to utilize  resources  in  local  regions, which carry high added  values but  tend  to be  centralized  in  Jakarta, will be effectively utilized.  Thus  regional development and human resource development target in Indonesia will be achieved. As a result, the cities dotting along the north shore of Java with independent economic activities can be integrated into a line‐shaped region, and become capable of efficient economic activities while sharing tasks in their  respective  realms of expertise. This  leads  to economic development of  the whole  integrated area, and at the same time, the development is more efficiently. 

 2. Condition on Various Aspects of the Project  a. Location and Geographical Features  Indonesia  is  the world's  largest archipelagic  country,  Indonesia  is made up  from 17,508  large and small islands, of which approximately 6,000 are inhabited. Its land area extends roughly 1.86 million km2, making Indonesia the world's 16th largest country [Figure 1.]. Among the islands, the largest is Kalimantan  (539,000 km2),  followed by Sumatra  (426,000 km2),  Irian  Jaya  (422,000 km2), Sulawesi (174,000 km2), and Java (129,000 km2). DKI Jakarta is the capital of Indonesia, and is located on the northwest coast of  Java  island,  forming  the main city of  Indonesia. Surabaya  is  Indonesia's second largest city, and  is  located at  the eastern end of  Java  Island. Other  largest cities  include Bandung, Medan,  Semarang,  Yogyakarta,  Denpasar,  Padang,  Palembang, Makassar, Manado,  Banjarmasin, Balikpapan, and Jayapura.  

High Speed Train Project in Indonesia  

(Jakarta ‐ Surabaya Corridor) 2 

 

  

Figure 1. Map of Indonesia  b. Population 

 The  total  population  of  Indonesia was  approximately  222 million, making  it  the world's  4th most populous  country.  Looking  at  the  share  of  population  for  each  region,  more  than  half  of  the population  (58.5%)  is  concentrated  in  Java  Island, which has only 7% of  Indonesia's  land  area.  In contrast, the shares of the other islands were all single digit figures between 2.2% and 7.2%, except for Sumatra Island at 21.1%. The population density per unit area is highest on Java Island, showing a figure  roughly 8  times higher  than  the national average. The highest population density  region on Java Island is found in DKI Jakarta, where the density of 1,005 persons/km2 is about 12 times higher 

High Speed Train Project in Indonesia  

(Jakarta ‐ Surabaya Corridor) 3 

 

than the overall density for Java  Island. More than 60% of  Indonesian population are  living on the Java  Island which accounts only 7% of the national  land, especially, concentration of population  in the Jakarta metropolitan area is extreme.   c. Economic Condition 

 Between  1987  and  1997,  as  a  result of  implementation of measures by  the  administration  at  that period that placed the highest priority on promoting the creation of job opportunities and  increasing exports in non‐oil related fields, Indonesia achieved a high average economic growth rate of nearly 7% per year. However, the 1997 Asian currency crisis caused Indonesia to experience extensive economic damage. This included the weakening of the rupiah against the dollar, a drop in new investments, and a reduction in imports caused by the unstable currency rates. As a result, Indonesia's 1998 GDP growth rate  dropped  to minus  13%.  Following  this,  due  to  the  implementation  of  various  reforms  by  the government and favorable domestic consumption, the GDP rate has recently reached 5% or more. The Indonesian  government  is  now  implementing  an  economic  growth  package  focused  on  promoting investment and trade, and on increasing employment opportunities. In addition, the government has also  listed  up measures  as  a  high  priority  subject  such  as  infrastructure  development  and  energy management  including  research  and  development  of  alternative  fuels  in  cooperation with  private sector.  d. Transportation Situation  The number of passengers and volume of freight throughout Indonesia by each transportation mode including  road,  rail,  sea, air,  and  inland waterways  (ferries  and  rivers)  in 2005,  together with  the shares of each, are shown in [Table 1].   

Table 1. Transportation Volume and Share for Each Mode in Indonesia  

Mode Passenger Transport  Freight Transport 

Volume (106 People)

Sharing (%)  Volume(106 ton)

Sharing (%) 

1. Road  2,021.1 85.05 2,514.1 91.24 2. Railway  150.3 6.32 17.4 0.63 3. Ferry  116.0 4.88 27.4 0.99 4. Sea  42.3 1.78 194.8 7.07 5. Air  36.5 1.54 1.4 0.05 6. River  10.3 0.43 0.3 0.01 

Total  2,376.5 100 2,755.4 100 (Source) Ministry of Transportation 

 1) Railway Transportation  In  Java,  passenger  trains were much more  important  than  freight  trains.  But  in  Sumatra,  freight traffic is an important customer of railway services. The number of passengers increased 10.9% from 175 million to 194 million in 2008. The passenger traffic volume showing an average annual increase of 2.4% over the five year period. The vast majority (98%) of passengers are carried on Java Island, where a large part of the population is concentrated and large and medium size cities are located in succession from west to east, which means that Java is an ideal location for railway transportation. The  freight  traffic  volume  is  approximately  17  million  tons  annually,  and  maintains  an  almost constant  level.  In  consistent  with  the  government  policy  of  saving  fuel  consumption,  it  is  also 

High Speed Train Project in Indonesia  

(Jakarta ‐ Surabaya Corridor) 4 

 

planned  to  increase coal production, and  that  railways should be used  to  transport  the additional coal.   2) Road Transportation  The  total  length  of  road  nationwide  is  approximately  380,000km,  meanwhile,  the  registered numbers for each type of vehicle over the  last five year period was 63 million. The average annual growth rate over the seven year period was 21.2% for all vehicles, which is an extremely large figure compared with the mere 1.1% growth of the road length expansion rate over the five year period. As a result of this rapid increase in the number of vehicles, the road traffic situation particularly in the main  cities  is  worsening  every  year  following  the  severe  traffic  jams  and  traffic  accidents.  In particular, the poor traffic morals of motorcycle riders are confusing the flow of traffic and causing even more  traffic  jams  and  accidents. Due  to  this over‐large number of  accidents  and  casualties, traffic accidents have now become a major social problem, and not only are  improvements to the road  infrastructure  required,  but  also  changes  in  traffic  morals,  such  as  observing  the  traffic regulations.  3) Air Transportation  Currently,  there  are  31  airlines  on  domestic  routes,  including  those  operating  non‐scheduled services and both large and small companies, which are operating 195 routes linking 101 cities. The majority of the domestic routes currently link Jakarta with other major cities. The number of flights from  Jakarta and a  list of  the  top destinations  for domestic passengers was Surabaya both  for the number of  flights  and  the number of passengers. Other destinations  in  Java  island,  such  as  from Jakarta to Semarang or to Yogyakarta, each made up 5% of the total.  On the other hand, the runway of the Soekarno Hatta Airport is expected to reach the capacity limit by 2015.   4) Sea and Inland Waterways Transportation Situation  For  Indonesia,  as  the  world's  largest  archipelagic  nation  made  up  of  17,500  islands,  sea transportation can be said to be an indispensable transportation means. Sea transportation has large advantages vis‐a‐vis air transportation which has common function of linking two points directly. The passenger numbers of domestic passengers carried on sea transportation declined approximately by 40%  from 8.4 million  in 2003 to 5.1 million  in 2007,  it  is believed that  this was due  to the shift of passengers to fare discounted air transport.   3. Railway Services in Indonesia  There are currently four unconnected railway systems in Indonesia, one in Java Island, and three  in Sumatra Island, consisting more than 6,900 kms track and around 4,800 kms is in operation. Railway network of 1067 mm (3' 6") gauge that existed in Indonesia generally were the ones that were built during  the Netherlands Colonial era  (1864).  In  the  recent  years  the  Indonesian  railway has  faced tough challenges. There are a number of  types of  rails used  for  railway  tracks with  the maximum design  speed of 120  km/hr, but  the high maintenance  costs,  aged  conditions  and  safety purpose caused the maximum operational speed to be reduced to less than 100 km/hr. The railway networks also have limited carriage capacity due to limited axle load of 15 ton in Java and 18 ton in Sumatera. The availability and  reliability of service are  low, due  to backlog of maintenance and  lack of spare parts both of  infrastructure  and  rolling  stock.  The  railway  required  subsidies  to  keep operations, many  lines  could  not  be  run  at  a  profit,  obtaining  sufficient  spare  parts  for  rolling  stock  and infrastructure that was concerned as a major problem in Indonesia.    

High Speed Train Project in Indonesia  

(Jakarta ‐ Surabaya Corridor) 5 

 

4. High Speed Train Project in Jakarta – Surabaya Corridor  a. Project Overview  High  Speed  Train  system  is  introduced  into  railway  between  Jakarta  and  Surabaya,  and  thereby traveling time is reduced to 3 hours or less. The introduction expects demands induced by the High Speed Train and transfer of passengers between transport modes. Based on these, estimations are made of economic benefits such as efficiently developing economy, promotion of regional economy, utilization  of  local  human  resources,  reduction  of  environmental  load  and  effective  utilization  of existing  lines. At the same time the project aim at reduction of public  load by encouraging private sectors to enter the railway operation business. The following [Table 2] summarizes the project.  

Table 2. High Speed Train Project Overview  

Items  Results  Remarks 

Dedicated line extension  km  685  Jakarta ‐ Semarang ‐ Surabaya

Purpose of transportation   

High Speed Train 

exclusive for passengers 

The number of stations  locations 9 

① Jakarta station (Manggarai/or alternative) 

② Cikampek station (or alternative) ③ Cirebon station ④ Tegal station ⑤ Pekalogan station ⑥ Semarang station (Poncol) ⑦ Gambringan station ⑧ Cepu station ⑨ Surabaya station (Pasarturi) 

Rolling stock  maintenance yard  locations 4 

① Karawang depot ② Cirebon depot ③ Semarang depot (Purjankang) ④ Surabaya depot (Sidotopo) 

Construction period  years 

9 (3 for designing + 5 

for construction + 

1 for trial operation) 

Due to time constrain , the study will be made on the assumption of simultaneous operation start of whole line, however, realistic partial operation start will be studied in F/S. 

The number of cars for a train sets  (The number of cars accommodated in railway facility) 

cars  8 (12) 

Since a ten‐car train accommodates 814 passengers, accommodation of about 600 passengers is planned in consideration of demands. However, the effective length of a platform is provided for a 12‐car train for future increase (actual platforms are constructed for 8‐car trains). Substations are provided at intervals based on a 12‐car train.  

High Speed Train Project in Indonesia  

(Jakarta ‐ Surabaya Corridor) 6 

 

Construction standard 

Gauge  mm  1,435 Standard gauge. No through operation with existing lines (1,067m) is available. 

Maximum design speed  km/h  350 Maximum commercial speed 

km/h  300 

Minimum radius of plane curve 

m  6,000 Radius of a planar curve enabling stable traveling at 350km/h. 

Minimum radius of profile curve 

m  25,000 Radius of a profile curve enabling stable traveling at 350km/h. 

Maximum cant  mm  180 Allowable deficiency of cant 

mm  110 

Maximum gradient  ‰  25 

Basically, 25‰, and partially 35‰. TGV uses 25‰ for Atlantic Ocean line and North Europe line, 35‰ for South East line and Mediterranean line. Railway in Taiwan basically uses 25‰, and partially 35‰. 

Track center distance  m  4.5 4.5 m is determined because of higher speed in this project  

Body width  m  3.4 Maximum axle load (= design axle load) 

kN  140 (=130+10)Ten (10) is added in consideration of full passengers. 

Formation level width  m  11.6  Switch machine in station yard 

#  18 

Inner cross‐section of tunnel of standard double track 

m2  83 This contributes to reduction in construction costs. 

Structure type breakdown 

Cut and embankment  km  380 This reduces the area of the right of way and simultaneously increases the slab track section. 

Bridge and viaduct  km  270 Extension of viaducts is increased in order to employ the slab track as much as possible. 

Tunnel  km  39 

Track structure  Slab/Ballasted 

Rail type  Kg/m  JIS60 

Power feeding 

Power feeding voltage AC 2×25kV 

50Hz Power feeding system  AT Number of substations 

locations 15 Provided approximately every 50 km. 

Overhead contact line 

Overhead contact line system 

Simple 

Total tension  kN  39.2 Total cross‐section 

mm2  260 

Span  m  50 Wave propagation 

Km/h  520 

speed of contact wire 

Signal 

Signaling system  Cab signal 

Block system Automatic 

block 

Train control ATC single‐step brake 

Pattern following system 

Train detection Insulated 

track circuit 

Telecommunication/operation 

Basic transmission 

Digital transmission by optical cable 

Ground‐train talk system Digital space 

wave  Reverse operation  Not available 

Tracking to existing lines  Not available 

Earthquake rapid alarm  UrEDAS An urgent brake works at intensity 4 upper to stop power supply. 

 b. Total Cost and Implementation Schedule  The total cost including costs of the consulting services, tax, general administration, land acquisition, price escalation, and contingency  is about 21,369 million US$. The Project will be started  in 2011, however, that actual start of operation for the High Speed Train will be in around year 2020.  c. Demand Forcast  The operation of High Speed Train will  impact  the use of  the conventional  line, which  is obviously decreasing as mentioned above. The demand forecast for the conventional line is multiplied by the modal shift rate between transport modes. Then, the modal shift volumes to High Speed Train are estimated as follows [Figure 2].  

 Figure 2. High Speed Train Passenger Volume Forecast 

 

0

20

40

60

80

100

120

2020 2025 2030 2035 2040 2045

Pas

seng

er V

olum

e (M

illio

n)

Year

High Speed Train Project in Indonesia  

(Jakarta ‐ Surabaya Corridor) 7 

 

High Speed Train Project in Indonesia  

(Jakarta ‐ Surabaya Corridor) 8 

 

. Financial and Economic Analysis 

. Financial FIRR Analysis 

itial investment cost was estimated at 26 billion US$ including risk inflation hedge on the basis of 

. Economic IRR Analysis 

ased  on  the  financial  cost,  the  economic  cost was  estimated  at  18.5  billion US$, while  transfer 

he  following  [Table  3]  shows  FIRR  and  EIRR  on  the  assumption  that  (i)  prospected  benefits  is 

Table 3. FIRR and EIRR Analysis 

 

5 a Inphysical contingency  ratio and contingency  ratio by  international and  local currencies.  In addition, the maintenance cost was estimated at an amount equivalent to 3.0% of the initial investment cost (base  cost  +  physical  contingency).  The  financial  benefits  were  estimated  at  1.70  billion  US$ (expected to reach this value  in 2019 and will  increase as demands grow year after year) and 0.20 billion US$ (expected to reach this value in 2019 and will increase as demands grow year after year) for operational and non‐operational profits. The FIRR was estimated at 10.4% all through the project life of 40 years, whereas the FIRR was estimated at 11.0%  in a case of substantial 5% tariff change every 5 years. Since the opportunity cost of capital (OCC)  in Indonesia  is presumably set at 8.6%  in view, the Project is evaluated as financially viable. Likewise, the NPV associated with the concerned Project was figured out positive at 4.94 billion US$ with the discount rate of 8.6%, thus leading to the same conclusion as the FIRR analysis. Meanwhile, the owner’s equity FIRR turned out to be 22.8%, around twice the commercial bank  lending rate, revealing the High Speed Train Project has a high return to the private sector investors.  b Bpayments and opportunity  cost were estimated at  zero, price  contingency was excluded, and  the domestic costs were converted to the international economic cost. The economic benefits include (i) time value of prospective High Speed Train passengers, (ii) foreign exchange saved due to reduction of operations of commercial  trucks  resulting  from  the  increase of cargo  train capacity and due  to downsized  fuel oil  (diesel oil)  imports, and  (iii)  foreign exchange earned  through  reduction  in CO2 

emission related to reduction of flight and passenger train schedules accompanying transfer from air planes  to  High  Speed  Train  and  earned  through  international  CO2  emission  trading  on  the international market. The economic profits were estimated at  (i) 7.58 million US$,  (ii) 9.95 million US$, and (iii) 46.72 million US$ for the above three types of benefits, respectively, and total to 64.24 million US$ (as of year 2019, and will gradually increase thereafter). c. Sensitivity Analysis  Treduced by 10%, (ii) initial investment is increased by 10%, and (iii) first project benefits are obtained one year later than expected.  

  Base case  ‐10% benefit  + 10% cost  1‐year delay 

FIRR  10. 9 9.4% .6 % 7% 9.8 % Owner’s equity FIRR 22.8% 21.5% 21.6% 21.1% 5  %  tariff  change  (every  5 years) 

11.0% 9.9 % 10.4% 10.6% 

EIRR  NA  NA NA NA LRMC pricing EIRR     7.2% 6.2% 6.3% 6.7%

   

High Speed Train Project in Indonesia  

(Jakarta ‐ Surabaya Corridor) 9 

 

ith regard to financial viability, FIRR exceeds the OCC, thus leading to the positive conclusion of go 

6. nvironmental and Social Impacts 

he environmental and social impcats of the High Speed Train construction are expected as follows.  

lized in the Jakarta metropolitan area will be distributed to some suburbs, for 

elopment, and 

es sake, energy 

planes  will  result  in  reduction  of  nitrogen  oxide  (NOX)  of 

s will result  in reduction of 

7. nclusion 

An  ficient transportation system with High Speed Train favors many economic changes and most 

r S

Wahead. Furthermore,  the owner’s equity FIRR shows about  twice as high profitability as bank  loan interests, and therefore fulfills the condition of the Indonesian private sector investment criterion on financial return. In view of the foregoing, the evaluation of the project in terms of policy in financial and economical aspects, and arrived at a conclusion that the Project is appropriate as a PPP project to be implemented by mainly Indonesia government and the private sectors. 

 E

 T1) Increase  economic  growth  and  trading  due  to  increasing  of  people movement  and  regional

development, coincide with decreasing of cars or petrol usage, and and resulting improvement of environment. 

2) Population centraexample, to Semarang, and therefore environmental problem will be alleviated. 

3) In other cities, population influx leads to tax income increase and economic devthis enables them to search for financial resources for environmental measures. 

4) Environmental load will be reduced by saving energy consumption. For referencconsumption per passenger  in “Shinkansen” accounts  for 60% of that per passenger of a bus; 30%, an air plane; and 20%, a car. 

5) Transfer  of  passengers  from  air 

362,000 tons, carbon monoxide (CO) of 258,000 tons, sulfur dioxide (SO2) of 31,000 tons in 31 

years calculated by subtracting 9 years of construction period from 40 years of the project  life based on IPCC Guidelines for National Greenhouse Gas Inventories. 

6) Transfer of cargo transportation from trucks to existing railway  linehydrocarbon  (HC)  of  43.1  tons,  CO  of  356.7  tons,  NOX  of  42.1  tons  in  the  same  31  years. 

Although the amount of air pollution materials is reduced by a smaller amount by the transfer from  trucks  than  by  the  transfer  from  air  planes,  it  is  significant  to  reduce  the  air  pollution materials along the line particular.  Co ef

of them are positive. The investment in High Speed Train will impact the growth of national as well regional  economic  development,  due  to  reduction  of  travelling  time  and  more  efficient transportation.  The  total  cost  of  High  Speed  Train  project  in  Indonesia  fo   Jakarta  –  urabaya Corridor including costs of the consulting services, tax, general administration, land acquisition, price escalation, and contingency  is about 21,369 million US$.   The cost‐benefit analysis of the project  is carried out based on the best available  information about demand and cost with data provided by government  institution and operators.  It has been  identified as  cost  saving. The Financial  Internal Rate  of  Return  (FIRR)  along  the  40  year  project  life  has  been  estimated  at  10.4%,  while  the Opportunity Cost of Capital  (OCC)  in  Indonesia  for  recent year  is estimated at 8.6%. Likewise,  the NPV  associated with  the  concerned  Project was  figured out positive  at  4.94  billion US$ with  the discount rate of 8.6%, thus leading to the same conclusion as the FIRR analysis. Since FIRR is higher than  OCC,  it  cannot  said  that  the  investment  faces  a  profitability  problem  from  the  financial viewpoint. In view of the foregoing, the evaluation of the project  in terms of policy in financial and economical aspects, and arrived at a conclusion that the Project is appropriate as a PPP project to be implemented  by  mainly  Indonesia  government  and  the  private  sectors,  especially  in  the international framework, judging from its nature of a public project and sufficient profitability. 

 

 

 

 

 

 

 

 

APPENDIX 

 

 

 

 

 

 

 

Existing Railway Map  

 

Cilegon 134+267

SERANG 113+446

Rangkasbitung 79+694

Pandeglang

Tangerang 19+297

JAK

AR

TA

Bek

asi 2

6+55

2

Cik

aran

g 43

+289

Kar

awan

g 62

+710

Cik

ampe

k 84

+007

Purwakarta 103+070

Sukabumi 57+173

Bogor 54+8100+000 Boo-Yk

Cia

njur

95+

774

BANDUNG 155+134

Padalarang

Hau

rgeu

lis 1

37+9

61

Bayah

Cile

geh

148+

410

Kedo

kan

Gab

us 1

56+3

36

Teris

i 162

+336

Tela

gasa

ri 17

0+52

4

Tanj

ung

Ras

a 93

+100

Pab

uara

n 97

+898

Prin

gkas

ap 1

03+6

00

Cik

aum

115

+404

Pega

den

Baru

124

+404

Cip

uneg

ara

131+

564

Cibungur 91+643

Sadang 97+778

Ciganea 109+636

Plered 120+941

Sukatani 116+871

Cisomang 127+164

Cikadongdong 132+869

Rendeh 135+946Maswati 140+006

Sasaksaat 144+711Cilame 151+767C

iranj

ang

108+

078

Sela

jam

be 1

04+8

88

Mal

abar

99+

686

Tago

g A

pu 1

34+9

04

Cip

atat

127

+071

Raj

a M

anda

la 1

19+5

01

Cip

euye

um 1

13+2

65

Andi

r 152

+405

Cim

indi

150

+405

Cim

ahi 1

46+9

57

Cik

udap

ateh

157

+772

Kiar

acon

dong

160

+124

Ged

ebag

e 16

5+33

2

Cim

ekar

168

+125

Ran

caek

ek 1

72+9

77

Hau

rpug

uh 1

78+4

27

Cicalengka 182+271

Nagrek 190+756

Lebakjero 196+560

Lele

s 20

2+96

0

Knai

207

+000

Leuw

igoo

ng

210+

000

Cib

atu

213+

631

War

ung

Band

rek

219+

575

Bum

i Wal

uya

228+

350

Cip

ende

uy 2

34+5

88 Cia

wi 2

48+1

78Cibeber 82+410

Cilaku 88+167

Lam

pega

n 73

+252

Cire

ugas

70+

142

Gan

daso

li 64

+296

Daw

uan

80+8

11

Klar

i 69+

864

Kosa

mbi

73+

774

Ked

ungg

edeh

56

+621

Lem

ah A

bang

47

+639

Tam

bun

33+3

59

Maja 62+546

Serpong 30+203

Tanah Abang 6+925

0+00

0

Depok 32+804Citayam 37+716

Nambo 51+990

Cibinong

Man

ggar

ai

9+89

0

Merak 148+319

Tenjo 55+006

Cibadak 39+884

Cicurug 26+715

Parung kuda 34+539

Batu Tulis 4+378

Ciomas 9+306

Maseng 14+096

Cigombong 19+622

Kr tengah 44+774

Pd. L

eung

sir

48+4

50C

isaa

t 52

+352

Krenceng 138+049

Tonjong 126+556

Karangantu 121+621

Walantaka 104+908

Cikeusal 94+370

Catang 90+647

Jamburab 87+648

Labuan

Anyer Kidul

TebetCawangDuren KalibataPasar Minggu BaruPasar Minggu

Cilebut

Bojonggede

Depok BaruPondok Cina

U ILenteng AgungTanjung Barat

Raj

apol

ah 2

57+5

10

PalmerahKebayoran

Pondok RanjiSudimara

Cisauk 32+987Pr. Panjang 41+463

Cilejit 48+503

Tigaraksa 58+600

PesingKalideres

Poris

Citeras

Cip

inan

gK

lend

erKl

d. B

aru

Cak

ung

Kra

nji

Cira

hayu

Ciwidey

Pangalongan

Soreang

Banjaran

Pam

ongp

euk

Cip

aray

Maj

alay

a

DayeuhKolot

Tanjungsari

Jatinangor

Ciamis 288+696

Jatib

aran

g 17

9+12

0

Kertas

emay

a

187+

334

Kaliwed

i

194+

716

Arjowina

ngun

202+

493

Bangu

duwa

207+

493

Cangk

ring

212+

349

Tasik 270+193

Awipari 276+848

Manonjaya 279+978

Boj

ong

297+

329

Kara

ngpu

cung

30

4+94

0

Indi

hian

g 26

5+42

5

Kadi

pate

n

Duri

DAOP I

DAOP III

DAOP II

DAOP II

DAOP I

Km.58+400

Km.85+400

Km.85+500

DAOP I

11+

750

Indramayu

Garut

Cikajang

Bantalan Beton

Bantalan Besi

Bantalan Kayu

Rel R 54

Rel R 42

Rel R 50

Rel R 38

Rel R 25

Rel R 33

LEGENDA

Jalur Ganda

Jalur Tunggal

Batas Propinsi

SaketiMenes

Jamblang

Jatiw

angi

Tj.P

riok

Der

mag

aP

asos

o

Pwk-Pdl 159+072Si-Pdl-Bd 140+472

Pasi

r Bun

gur 1

09+6

46

Jatin

egar

a

 

 

SURABAYASbi 229+573Sgu 0+000

Jember 197+285

Ram

bipu

ji 18

6+58

8

Man

gli 1

90+5

43

Banyuwangi 18+484

Kalib

aru

37+3

90

Gle

nmor

e 44

+752

Rog

ojam

pi 7

2+19

7

Leces 123+726

Klakah 135+384

Lawang 31+114

Singosari 39+172

Kepanjen 68+122

Rej

otan

gan

135+

971

Ker

toso

no 9

6+80

8

Car

uban

14

9+56

9

Ran

dubl

atun

g 65

+471

Wad

u 76

+935

Kap

uan

83+1

87

Kalit

idu

110+

310

Tobo

96+

526

Cepu 88+713

Kap

as 1

30+8

42

Boj

oneg

oro

125+

670

Sum

ber R

ejo

138+

798

Baur

eno

150+

995

Babat 159+943

Gem

bong

165

+999

Pucu

k 17

1+26

1

Sum

lara

n 17

7+04

1

Lam

onga

n 18

8+14

4

Dud

uk 2

00+2

97

Cer

me

210+

584

Kandangan20+840

Tand

es 2

24+2

23

Wonokromo 17+3617+880

Waru 13+651

Gedangan 17+679

Sidoarjo 25+509

Tanggulangin 31+071

Porong 34+650

Gn. Gangsir 40+650

Sepanjang 25+111

Boharan 34+811

Kriyan 39+274Kadinding 44+012

Tarik 48+601

Mojokerto 58+300

MojosariC

urah

Mal

ang

65+1

42

Bangil 47+0380+000 Bg - Ml

Wonokerto 8+758

Sukorejo 16+971

Sengon 21+237

Blimbing 44+344

Malang 49+234

Malang Kt. Lama 51+370

Pakis Aji 60+455

Wlingi 104+770

Nge

bruk

75+

114

Talu

n 10

8+49

0

Sum

ber P

ucun

g 79

+467

Kesa

mbe

n 95

+454

Gar

um 1

16+7

74

Blitar 122+895

Ngu

nut 1

43+8

61

Sum

ber G

empo

l 15

1+63

8

Tulungagung 156+820

Ngujang 163+249

Keras 170+979

Ngadiluwih 177+321

Kediri 186+866

Susuhan 192+084

Minggiran 198+123

Papar 202+337

Purwoasri 208+329

Sem

bung

89+

307

Jom

bang

81

+497

Pete

rong

an 7

6+16

1

Sum

obito

69+

307

Bar

on 1

08+8

10

Suk

omor

o 11

4+44

5

Nganjuk 118+842

Bag

or 1

25+2

30

Wila

ngan

13

2+26

5

Sar

adan

14

1+06

3

Bab

adan

15

7+88

9

Madiun 165+783

Bar

at 1

76+3

32

Gen

eng

184+

344

Paro

n 19

1+70

7

Pasuruan 62+976

Probolinggo 101+451

Rej

oso

71+8

57

Gra

ti 77

+537

Bay

eman

89

+924

Malasan 121+740

Ranuyoso 130+481

Randuagung 146+890

Jatiroto 156+000

Tanggul 167+050

Bangsal Sari 177+584

Arjoso 203+170

Kotok 207+405Ledokombo 8+320

Garahan 20+271

Mra

wan

29+

880

Sum

ber W

adun

g 50

+954

Kal

iset

ail 5

4+76

6

Tem

ugur

uh 6

6+31

6

Tuban

Lumajang Km. 17

BondowosoKm. 27

SitubondoKm. 62

PanarukanKm. 70

Argopuro 12+630

Karang Asem 6+806

P. MADURA

Ben

owo

215+

801

Lasem

Wal

ikuk

un

210+

197

Ked

ungg

alar

20

0+70

7

Sulu

r 45

+517

Dop

lang

52

+928

Rembang

DAOP VII

DAOP VIII

DAOP VII

DAOP VIII

DAOP IV

DAOP VIII

DAOP IX

DAOP VIIIKm.48+400

Km.126+100

Km.64+200

Km.134+300

Kamal Km. 0

Bangkalan

Socah

Telang Km. 6

Labang Km. 13

Kwanyar Km. 25

Balega Km. 58Modung Km. 36

Torjun Km. 75

Tanjung Km. 100

PamekasanKm. 113

Panji

Pasirian Km. 36

Balung

Km. 64

Srono

Gondonglegi

Dampit

Ponorogo

Slahung

Blora

Ngawen

Kunduran

Gre

sik

Tulangan

Sampang Km. 82

Krik

ilan

Sin

goju

ruh

Kabat 76+557

Jatigoro

Ngimbang

Ploso

Pagutan

Jetis

Yosowilangun Km. 34

Sukawono Km. 8

Tamanan Km. 16

Grujugan Km. 21

Bonosare Km. 35

Prajekan Km. 49

Kedungdung Km. 47

Grobogan Km. 8

Tempeh Km.27

Tekung Km. 27

KancongKm. 43

GumukmasKm. 49

KasijamlorKm. 57

Klabang

Indr

o 9

+ 85

0

Bantalan Beton

Bantalan Besi

Bantalan Kayu

Rel R 54

Rel R 42

Rel R 50

Rel R 38

Rel R 25

Rel R 33

LEGENDA

Jalur Ganda

Jalur Tunggal

Batas Propinsi

U

Sempolan 16+020Kalisat 214+462

0+000

 

 

High Speed Train Map 

(Jakarta – Surabaya Corridor)

 

 

 

 

 

 

 

 

Route Profile  

 

 

 

 

 

 

 

 

 

 

 

Cross Section of Structures