INVESTOR News June 2017 BPM Project update Development Highlights Wesizwe projects executive, Mr. Jacob Mothomogolo presents at the Junior Indaba 2017 Bakubung Platinum Mine Safety Stats May 2017 Media Round-Up News highlights from the month

Upload: others

Post on 18-Jun-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: INVESTOR News - wesizwe.co.za€¦ · Events INVESTOR News June 2017 Joburg Indaba: 05 – 06 October 2017, Johannesburg Find out how the industry is managing key pressure points

INVESTOR News June 2017

BPM Project update Development Highlights

Wesizwe projects

executive, Mr.

Jacob

Mothomogolo

presents at the

Junior Indaba

2017

Bakubung

Platinum Mine

Safety Stats May

2017

Media Round-Up

News highlights

from the month

Page 2: INVESTOR News - wesizwe.co.za€¦ · Events INVESTOR News June 2017 Joburg Indaba: 05 – 06 October 2017, Johannesburg Find out how the industry is managing key pressure points

As the BPM project progresses it is becoming more important that we

get feedback about the systems we are putting in place. This is to ensure

practices that are not only beneficial for the mine’s sustainability but for

the Bakubung Ba Ratheo community as well.

One of the sounding boards for the mining sector is the parliament’s

Portfolio Committee on Mineral Resources. The BPM project has had an

honour of getting a visit from a delegation of this committee led by its

Chairperson, Mr. Luzipho. The visit, which took place on Tuesday, 27

June, afforded us an opportunity to showcase what the company does

to build relations with its key stakeholders.

In providing details about the company and the project, a presentation

gave a background on where the project is currently, giving details on

funding, Capital (CAPEX) and operational costs (OPEX), performance

against SLP, transformation as well as the technical aspects of the

project.

The company also had an opportunity to raise some of the challenges

experienced being a junior miner in the current economic state and

building a mine within a community.

The visit was what the company needed to confirm that BPM as a mine

that is not tainted by the legacy of the past, is on the right track in

building towards sustainable futures for the benefit of all involved.

We hope you enjoy reading this edition of Investor news and we look

forward to keeping you updated on all the latest project developments.

Hamlet Morule

Welcome

Hamlet Morule

Executive: Corporate

Affairs & Investor Relations

[email protected]

Copyright©2017

All rights reserved.

02

Page 3: INVESTOR News - wesizwe.co.za€¦ · Events INVESTOR News June 2017 Joburg Indaba: 05 – 06 October 2017, Johannesburg Find out how the industry is managing key pressure points

BPM Project update Development Highlights

05

04

08

Wesizwe projects executive, Mr.

Jacob Mothomogolo presents at

the Junior Indaba 2017

Bakubung Platinum Mine (BPM)

Safety Stats May 2017

In the media

Highlights from recent media coverage

featuring Bakubung Platinum Mine and

Wesizwe Platinum

Events calendar

Information on some of the

forthcoming mining conferences and

events to look out for

07

06

03

INVESTOR News June 2017

Page 4: INVESTOR News - wesizwe.co.za€¦ · Events INVESTOR News June 2017 Joburg Indaba: 05 – 06 October 2017, Johannesburg Find out how the industry is managing key pressure points

BPM Phase 1 commissioning

Work at the BPM project is progressing well towards the project’s

commissioning of Phase 1. The Phase 1 commissioning strategy involves

two parts: Part A and Part B. Part A is the commissioning of the hoisting

system and Part B is the commissioning of the ground handling system

from 69 to 72 to 77 level and onto the loading box feed conveyor. Each

system is explained in detail in the following section:

Part A: Shaft Hoisting System.

This system involves the following sub-systems:

- 77 Level tail end conveyor loading arrangement

- 77 Level Conveyor CV-002

- 77 Level Loading Box

- Skips installed and roped up

- Surface Rock Silo

- Surface Conveyor CV-001

Commissioning of this system will allow hoisting of rock from 77 level to

surface and is currently forecast for September 2017.

Part B: 69/72 Leave Ore Transport System

This system involves the following sub-systems:

- Ore Pass from 72 to 77 level raisebored

- Ore Pass from 69 to 72 level raisebored

- Tip and rock breaker on 69 level

- Tip and rock breaker on 72 level

- Box front on 77 level ore pass.

- 77 level conveyor CV-001 (feeding CV-002)

Commissioning of Part B will allow hoisting of rock from 69 and 72 level

out the main shaft and will allow a total production of 50 000 tonnes per

month when the system is fully proven. This is currently forecast for

March 2018.

Wesizwe Update

04

About the BPM Project Frequently asked questions

INVESTOR News June 2017

Fencing at the mine Housing

project

The Housing project is starting

to take shape as viewed from

the top of the Main shaft

headgear

The BPM workshop

Page 5: INVESTOR News - wesizwe.co.za€¦ · Events INVESTOR News June 2017 Joburg Indaba: 05 – 06 October 2017, Johannesburg Find out how the industry is managing key pressure points

The annual Junior Indaba, for explorers, developers and

investors in junior mining in Africa, took place on Wednesday,

07 and Thursday, 08 June 2017 at the Johannesburg Country

Club. The conference saw CEOs, entrepreneurs, investors

and mining professionals who all contributed to making it an

experience, both with the engaging discussions and the

informal networking.

Wesizwe’s Projects executive, Mr. Jacob Mothomogolo was

also part of the thought provoking discussions that took

place in the conference. Presenting on a topic - Being a

Junior Miner in the current economy: Wesizwe Platinum’s

Bakubung Platinum Mine project, his presentation provided

a status of the BPM project, guidelines for other junior miners

and explorers intending to be junior miners. Also, he touched

on investment highlights, production profile as well as

resources and reserves for the BPM.

Some of the highlights included Lessons from the Legends,

which had the audience fascinated by their life and career

experiences, words of wisdom and many industry insights.

Amongst all the good cheer and engaging discussions was

a more serious note about South Africa’s future. Amongst the

attendees were the Chamber of Mines’ CEO, Mr. Roger

Baxter, who joined in the constructive engagement with his

vision and proactive initiatives of South Africa’s Chamber of

Mines.

The message left by delegates in the conference was a very

clear one – no time for pessimism, let’s get on with the

business.

Sustainability

05

Wesizwe projects executive presents at the

Junior Indaba 2017

INVESTOR News June 2017

Projects Executive, Mr. Jacob Mothomogolo

Presenting on a topic -

Being a Junior Miner in the

current economy:

Wesizwe Platinum’s

Bakubung Platinum Mine

project.

Page 6: INVESTOR News - wesizwe.co.za€¦ · Events INVESTOR News June 2017 Joburg Indaba: 05 – 06 October 2017, Johannesburg Find out how the industry is managing key pressure points

There were two (2) medical treatment cases reported for the month of

May 2017. 69 Level, On 12 May 2017, a PTV was transporting the TSL

cement pump from the Tip Cross Cut to the Workshop when he allegedly

sprained his back. 77 Level, On 18 May 2017, a Pecker Operator was

passing by the diamond drill operation area when the core from the

diamond drill shot out and struck him on the right upper limb and chest.

There were three (3) visits from the DMR during the month of May and no

instruction was issued. The project has worked 1 182 409 shifts to date.

Category Target

2017

Actuals

2017

Project

to Date

Report

Period

(1May–

31May)

Minor

Injuries-MI

23 108 335 2

Lost Time

Injuries-LTI

7 2 51 0

Serious

Injuries

3 2 31 0

DMR Sect 54s 4 0 15 0

Fatalities 0 0 2 0

Fatality free

shifts worked

- 93 161 450 285 16 537

Shifts Worked - 93 161 1 182 409 16 537

LTIFR 0.86 0.45 0.91 0.00

Excellence

06

BPM project safety stats – May 2017

INVESTOR News June 2017

The project has worked

1 182 409 shifts to date.

Page 7: INVESTOR News - wesizwe.co.za€¦ · Events INVESTOR News June 2017 Joburg Indaba: 05 – 06 October 2017, Johannesburg Find out how the industry is managing key pressure points

INVESTOR News June 2017 Media Round-Up

News highlights for the month

06 07

There were mentions of Wesizwe Platinum in the period between 15 May and 14 June 2017.

81 hits were recorded from Global coverage, while 7 came from the social media and 2 from

Print media articles. These were recorded on Social Media: Twitter, Facebook, Blogs and

comments.

Mediums covered Wesizwe Global

Coverage

Wesizwe Social

Media

Wesizwe Print

Hits 81 7 2

Wesizwe website activity

Page 8: INVESTOR News - wesizwe.co.za€¦ · Events INVESTOR News June 2017 Joburg Indaba: 05 – 06 October 2017, Johannesburg Find out how the industry is managing key pressure points

FEEDBACK

We are committed to

shareholder engagement.

We therefore encourage

your comments or

feedback relating to this

investor newsletter are

welcome. Send your

comments via our website -

www.wesizwe.com

EDITORIAL TEAM

Managing Editor

Hamlet Morule

Editor

Thandiwe Mapi

Subscription

You can subscribe to this

free newsletter and have it

delivered direct to your

email inbox each month by

contacting us via our

website -

www.wesizwe.com

Events Calendar

Events INVESTOR News June 2017

Joburg Indaba: 05 – 06 October 2017, Johannesburg

Find out how the industry is managing key pressure points and

investors are currently going about their investment decisions.

7th International Platinum Conference: 18 – 19 October 2017

The Platinum conference series has covered a range of

themes since inception in 2004, and traditionally addresses

the opportunities and challenges facing the platinum

Industry.