green infrastructure retrofit opportunities

Upload: green-action-sustainable-technology-group

Post on 29-May-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    1/31

    1

    Green InfrastructureRetrofit Opportunities

    May 13, 2010

    Dallas, TXDaniel P. Christian, PE, D.WRETetra [email protected]

    2

    Agenda

    Introduction Why Retrofit? Retrofit Basics

    Objectives and criteria Desktop analysis Quantity estimation Field assessment and prioritization

    IdeasCase Examples

    Summary

    1

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    2/31

    3

    4

    Solve ChronicFlooding Problems

    Fix Past Mistakes &Maintenance Problems

    Demonstration &Education

    Reduce Pollutants ofConcern

    3Photos: CWP

    Reduce StormwaterRunoff Volumes

    Support StreamRestoration Projects

    Trap Trash &Floatables

    Reduce DownstreamChannel Erosion

    4Photos: CWP

    2

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    3/31

    Retrofit verse New DevelopmentIntroduction

    Retrofit New Development Higher costs

    Sized to meet restoration objectives

    Typically installed on public land

    Compacted soils

    Limited locations

    Need neighborhood acceptance

    Most are publicly maintained and thepublic expects that they will be

    Not all candidate sites are feasible

    Often tied into existing stormwaterconveyance system

    Public investment dollars

    Site visit is prerequisite for design

    Designers seek least costly options

    Sized to meet local design standards

    Installed at new development projects

    Soils are typically better

    More location flexibility

    More aesthetics flexibility

    More options on maintenance, oftenrequire private maintenance

    Nearly all sites are made to work

    Usually creates the new stormwaterconveyance system

    Private investment dollars

    Design may occur without site visit

    5

    Agenda

    Introduction Why Retrofit? Retrofit Basics

    Objectives and criteria Desktop analysis Quantity estimation Field assessment and prioritization

    Ideas Case Examples Summary

    6

    3

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    4/31

    Private land willingnessby property ownersRoads (ROW)Open green spacesExisting BMPs that may bemodifiedIn-line storageopportunitiesLarge parking lotsHotspots

    8

    Look For Basemaps for field

    assessmentUse GIS

    Topography Hydrology Aerial photographs

    Utilities Soils Parcel boundaries Land use

    Define ObjectiveRetrofit Basics

    Clearly identify the overall objective, for example Store 1-inch of surface runoff and release over 24-hours

    Infiltrate the first 1-inch of rainfall

    Match natural hydrology

    Reduce TSS by 80 percent

    Capture 90% of trash and debris

    Objectives may come from Watershed or storm water management plans

    Permit requirements Modeling

    Define general locations

    7

    Desktop AnalysisRetrofit Basics

    Prepare

    4

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    5/31

    99

    Estimate QuantityRetrofit Basics

    Estimate area or volume needed for retrofits Example

    Store the first 0.5-inches of runoff from a 1-acre parking lot Storage volume needed is 1,815 cubic feet Assume bioretention with 8-inches surface storage plus 4-foot of

    engineered soil (25% void space) BMP yields 1.7 cubic feet of storage per square foot of area Therefore need = 1090 square feet or 2.5% of the parking area

    Field Assessment and PrioritizationRetrofit Basics

    Ownership

    Access

    Utility conflicts (up and down)

    Soils

    Topography water flowsdownhill

    Inline verse offline

    Existing stormwater BMPs

    Education opportunitiesMaintenance

    Brainstorming

    Nearby vegetationPhotographsPublic acceptance

    5

    10

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    6/31

    11

    Field Assessment and PrioritizingRetrofit Basics

    12

    Field Assessment and PrioritizationRetrofit Basics

    6

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    7/31

    14

    13

    Agenda

    Introduction Why Retrofit? Retrofit Basics

    Objectives and criteria Desktop analysis Quantity estimation Field assessment and prioritization

    Ideas

    Case Examples Summary

    Green Roofs Individual PropertyIdeas

    14

    7

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    8/31

    16

    15

    Downspout Disconnect Individual PropertyIdeas

    15

    Rain Barrel / Cistern Individual PropertyIdeas

    16

    8

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    9/31

    17

    18

    Rain Gardens Individual PropertyIdeas

    Photo: Ward Wilson Tt17

    Porous Pavement Impervious to PerviousIdeas

    Photo: Abby Hall USEPA18

    9

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    10/31

    19

    20

    Porous Pavers Impervious to PerviousIdeas

    Photos: Abby Hall19

    Green Impervious to PerviousIdeas

    20

    10

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    11/31

    21

    22

    Photo: LID Center Photo: LID Center

    Photo: LID Center

    Photo: Abby Hall

    21

    Parking LotsIdeas

    Parking LotsIdeas

    Photo: Abby Hall USEPA

    Photo: Abby Hall USEPA

    Photo: Abby Hall USEPA22

    11

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    12/31

    23

    24

    Increased InfiltrationSpecific Ideas

    Soil amendmentsSoil replacementsTilling/rippingVegetationIncreased residence time

    Longer flow path Increased storage Increased resistance

    Photo: Ward Wilson23

    Between the curband the sidewalk

    Photo: City of Vancouver Photo: Abby Hall USEPAPhoto: Bob Domm Tt24

    12

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    13/31

    25

    26

    Into the Street

    Photo: Abby Hall USEPA25

    Swale StorageSpecific Ideas

    Photo: Scott Struck Tt

    26

    13

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    14/31

    27

    Roadway Boulevard

    Photo: Abby Hall USEPA

    28

    Increased Local/Regional StorageSpecific Idea

    14

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    15/31

    29

    Agenda

    Introduction Why Retrofit? Retrofit Basics

    Objectives and criteria Desktop analysis Quantity estimation Field assessment and prioritization

    Ideas Case Examples

    Summary

    30

    Tetra Tech Lansing Office (2006)Project by K&L Acquisitions, LLC and Tetra Tech

    BEFORE

    15

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    16/31

    31

    32

    Tetra Tech Lansing, MI Office (2006)Project by K&L Acquisitions, LLC and Tetra Tech

    Tetra Tech Lansing Office (2006)Project by K&L Acquisitions, LLC and Tetra Tech

    16

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    17/31

    33

    NE Siskiyou Street (2003)Project by the City of Portland, designed by Kevin Perry

    BEFORE

    34

    NE Siskiyou Street (2003)Project by the City of Portland, designed by Kevin Perry

    17

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    18/31

    35

    36

    NE Siskiyou Street (2003)Project by the City of Portland, designed by Kevin Perry

    NE Siskiyou Street (2003)Project by the City of Portland, designed by Kevin Perry

    18

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    19/31

    0.00

    0.05

    0.10

    0.15

    0.20

    0.25

    0.30

    0.35

    0.40

    09:30 09:45 10:00 10:15 10:30Time

    Flow

    (cfs)

    InletOutlet

    37

    NE Siskiyou Street (2003)Project by the City of Portland, designed by Kevin Perry Area

    10,000 square foot total drainage area 600 square foot landscaping area (6% of drainage area)

    Hydrology Modification (25-year flow test) 81% peak flow reduction

    82% peak volume reduction

    16 minute additional peak flow delay

    Cost $17,000

    Maintenance Semi-annual visits

    Neighbors help at will

    Successes

    Incredible community acceptance of project Successful as a catalyst project for other green streets

    Challenges Juncuspatensgrows too tall, needs annual trimming Unequal distribution of runoff due to crown of street

    38

    ProjectSW 12thby the City of Portla

    Avenue (2005)nd, designed by Kevin Perry

    BEFORE

    19

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    20/31

    39

    40

    SW 12th Avenue (2005)Project by the City of Portland, designed by Kevin Perry

    SW 12th Avenue (2005)Project by the City of Portland, designed by Kevin Perry

    20

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    21/31

    41

    SW 12th Avenue (2005)Project by the City of Portland, designed by Kevin Perry

    42

    SW 12th Avenue (2005)Project by the City of Portland, designed by Kevin Perry

    Area 7,500 square foot total drainage area 300 square foot landscaping area

    (4% of drainage area)

    Cost $35,000 ($117/sf)Maintenance - semi-annual visitsSuccesses Successful as a catalyst project for other urban green streets

    Nobody has tripped yet (good to have 3 egress zone and 2landscape buffer zone at carriage walks)

    Challenges Juncuspatensgrows too tall, needs annual trimming High loading of sediment requires more frequent cleaning

    21

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    22/31

    44

    43

    Michigan AvenueLansing MI, by Tetra Tech and C2AE

    Before

    Michigan AvenueLansing MI, by Tetra Tech and C2AE

    22

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    23/31

    45

    MichiganAvenue

    Lansing MIby Tetra Tech and C2AE

    Michigan AvenueLansing MI, by Tetra Tech and C2AE

    4 city blocks, both sides

    Typical garden, no overflow for 1-inch event

    600 block north side, no overflow for4.1-inches (25-year event)

    $122/square foot 46

    23

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    24/31

    47

    Sandy Boulevard (2007)Project designed by Nevue Ngan Associates and URS

    48

    Sandy Boulevard (2007)Project designed by Nevue Ngan Associates and URS

    15th Street and Sandy Blvd

    After

    After

    Before

    24

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    25/31

    49

    Sandy Boulevard (2007)Project designed by Nevue Ngan Associates and URS

    21st Street and Sandy Blvd

    Before

    After

    After

    50

    Sandy Boulevard (2007)Project designed by Nevue Ngan Associates and URS

    22nd Street and Sandy Blvd

    Before

    After

    After

    25

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    26/31

    51

    Sandy Boulevard (2007)Project designed by Nevue Ngan Associates and URS

    39th Street and Sandy Blvd

    Before

    After

    After

    52

    Sandy Boulevard (2007)Project designed by Nevue Ngan Associates and URS

    Harold Kelley Plaza and Sandy Blvd

    Before

    After

    After

    26

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    27/31

    School Courtyard Entry

    53

    Mount Tabor Middle School (2006)Project by the City of Portland, designed by Kevin Perry and Brandon Wilson

    54

    Mount Tabor Middle School (2006)Project by the City of Portland, designed by Kevin Perry and Brandon Wilson

    27

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    28/31

    56

    55

    Mount Tabor Middle School (2006)Project by the City of Portland, designed by Kevin Perry and Brandon Wilson

    Mount Tabor Middle School (2006)Portland OR, designed by Kevin Perry and Brandon Wilson

    28

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    29/31

    58

    57

    Mount Tabor Middle School (2006)Project by the City of Portland, designed by Kevin Perry and Brandon Wilson

    School Parking Lot

    Before

    Mount Tabor Middle

    School (2006)Project by the City of Portland,designed by Kevin Perry and

    Brandon Wilson

    29

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    30/31

    Agenda

    Introduction Why Retrofit? Retrofit Basics

    Objectives and criteria Desktop analysis Quantity estimation Field assessment and prioritization

    Ideas Case Examples Summary

    59

    Summary Retrofits work to reduce problems in developed watersheds

    When identifying retrofits begin by: Clearly identifying the objective and criteria

    Start in the office gathering and organizing available information

    Walk the site and look for opportunities

    Think Reduce imperviousness

    Increase infiltration and water uptake by plants

    Provide storage Consider maintenance

    Communicate your ideas

    60

    30

  • 8/9/2019 Green Infrastructure Retrofit Opportunities

    31/31

    61

    Questions