green field project making of production plant

225
17/ JAN/ 2012 TO 31 SEPT 2012 EIGHT MONTH RECORD TIME WORK Experience serves not only to confirm theory, but differs from it without disturbing it, it leads to new truths which theory only has not been able to reach. BY LT COLONEL VIKRAM BAKSHI (RETD) PROJECT HEAD GREEN FIELD PROJECT FOR SETTING UP A LEAN WORLD CLASS MANUFACTURING PLANT

Upload: vikram-bakshi

Post on 17-Feb-2017

1.629 views

Category:

Documents


1 download

TRANSCRIPT

  • 17/ JAN/ 2012 TO 31 SEPT 2012EIGHT MONTH RECORD TIME WORK

    Experience serves not only to confirm theory, but differs from it without disturbing it,

    it leads to new truths which theory only has not been able to reach.

    BY LT COLONEL VIKRAM BAKSHI (RETD) PROJECT HEAD

    GREEN FIELD PROJECT FOR SETTING UP A

    LEAN WORLD CLASS MANUFACTURING PLANT

  • Safety OathSafety Oath

    We individually and jointly take an oath that, for We individually and jointly take an oath that, for

    the observance of safety cause, for ourselves, our the observance of safety cause, for ourselves, our

    family, our organization and our societyfamily, our organization and our societys welfare, s welfare,

    we will adhere to our safety norms, rules and we will adhere to our safety norms, rules and

    instructions to prevent accidents.instructions to prevent accidents.

    We individually and jointly take an oath that, for We individually and jointly take an oath that, for

    the observance of safety cause, for ourselves, our the observance of safety cause, for ourselves, our

    family, our organization and our societyfamily, our organization and our societys welfare, s welfare,

    we will adhere to our safety norms, rules and we will adhere to our safety norms, rules and

    instructions to prevent accidents.instructions to prevent accidents.

  • Introduction

    Purpose of this presentation Objective: To present different phases of

    a plant construction

    Outcome: It will help in deciding the time lines and preparation for future green and brown field plant

  • PART ONE:BASIC INFORMATION FOR GREEN FIELD PROJECT

  • Vendors

    Consultant

    OWNER SHIP VALUE OWNER SHIP VALUE NET NET PROJECT WORK WITH OTHER FUNCTIONAL DEPARTMENTSPROJECT WORK WITH OTHER FUNCTIONAL DEPARTMENTS

    PROJECTPROJECTPROJECT Purchaser

    SystemHR/Safety

    Finance

    Internal Customer

    University of Pretoria

  • PROJECT MANAGEMENT

    Initiation ActivityGot over in 2011

    FROM JAN 2012 TILL DEC 2012

  • The quality management plan describes how the project will comply with the companys quality policy in terms of the project procedures for quality assurance (QA), quality control (QC), and continuous process improvement.

    QA is the planned processes the project will follow to make certain that the quality policy is met through: QA audits to examine whether project activities are in compliance with project procedures,and process analysis to examine the effectiveness of project activities, learn from experience and problems encountered and thereby improve the process.

    QC is the monitoring of specific project results to determine whether they meet with predetermined quality standards and metrics. Continuous process improvement is the iterative application of process analysis over the length of the project and from project to project.

    Each consultant and construction contractor performing work on the project must have a QA plan that is acceptable to the Agency, so that the company can assess that the contractors quality standards meet the Agencys quality management plan.

    The risk management plan describes how the project is organized and the procedures used to manage the project risks, addressing in the plan:

    Roles and responsibilities of project staff in risk management

    Identification of project risks

    Categorization of risks in terms of probability of occurrence and impact on project cost, schedule, scope, and/or quality

    Risk handling should the risk event occur, through either

    Assumption Accepting the consequences of the risk.

    Avoidance Changing the project deliverable design or work methods that lead to the risk.

    Control Developing measures to reduce the risks probability of occurrence, continually re-evaluating the risk, and having in place contingency plans to adopt that mitigate the impacts of the risk.

    Transfer Sharing or transferring the consequences of the risk with others, for example, through insurance or warranty provisions

  • Contract Procurement Planning

    Procurements for most projects are undertaken by the company procurement department that has in place associated procurement procedures. The project managers role is tomake certain that the departments procurement activities on behalf of the project fit in with the project plan. The contract management plan sets out how this is to be achieved, by addressing:

    Types of contracts to be used. Choice of contract type depends on the nature of service/product purchased and choices on the division of risk between the owner and contractor;

    Who estimates the expected contract price.

    Who develops the scope of work statement for the contract.

    Use of standardized procurement documents and any special documents needed.

    Integration of procurement lead times into the project schedule.

    Incorporating contractual delivery dates into contracts that coordinate with the project schedule.

    Use of performance bonds and/or insurance contracts to meet the projects risk management objectives, including liability and insurance conditions and minimum limits to be met by the contractor.

    Establishing evaluation criteria to assess the selection of contractors;.

    Definition of the procurement procedures for: preparation of procurement documents, advertising, bidder conferences, any bidder prequalification, receipt of proposals/bids, bidder interviews, selection, contract price negotiation, contract award and handling of protests. (In many instances the procedures used for project procurements will be those the company already has in place.)

  • The contract management plan sets out how this is to be achieved, addressing:

    Who has the authority to direct and approve the contractor to perform work

    How the contractors work is monitored and performance reported

    Process by which changes to the contractors work are requested, approved, and the contract modified

    What inspections and audits are to be conducted of the contractors work

    How the contractor requests payment and payment requests are reviewed and approved

    What financial audits are to be conducted on contractor payments

    How contract documents, correspondence, and other records are managed. good project documentation for handling important contract administration activities such as contract changes and request for payment.)

  • Purchasing and receiving

    A. Procuring - Locating, buying, ordering, and receiving materials, supplies, and equipment Purchasing - involves locating and buying of

    materials, supplies, and equipment; there is a great need for discipline in the purchasing process

    Purchase orders Responsibility for purchasing Terms and conditions of the purchase to be specified

    in the purchase order Purchase control system Office and field purchasing Short form P.O. (used mostly for field purchases)

  • Purchasing and receiving(Contd)

    B. Expediting - Coordinating the ordering and receiving of purchased items Responsibility for expediting must be clearly

    defined Expediter must have ALL information required Expediting is a key coordination function; it

    requires experience and skills

  • Purchasing and receiving(Contd)

    C. Receiving materials and supplies - 5 steps Jobsite unloading - be careful to minimize

    handling Material inventory - count! Material inspection - for damages, conformance

    with the order Delivery receiving report Logging in delivery

  • Cost Control Cost control is based on continually refining the projects cost estimate at

    completion as the project progresses and taking management action to address adverse variances in the cost estimate compared to the baseline budget.

    As with the scope baseline, the cost baseline isdeveloped at the conclusion of preliminary engineering.

  • Schedule ControlThe WBS is again the starting point for schedule control. Work activities are identified for each of the WBS work package elements and formthe building blocks of the project schedule. For relatively simple projects you can represent the activities using a bar chart schedule and thetime from the beginning of the first bar (start) and the end of the last bar (finish) is the duration of the project

  • Subcontractor management

    A. Issuing a subcontract A contract creates obligations for both parties; to deal effectively with all contractual obligations, all team members must fully know and understand the contract

  • Subcontractor management(Contd)

    B. Subcontractor management: a big part of the job - 5 major areas Analyzing bids and issuing subcontracts Review of subcontractor site requirements Processing submittals and change orders Scheduling and coordinating Controlling quality, safety, and payments

  • Subcontractor management(Contd)

    C. Subcontractor coordination meetings Purpose

    Keep communications between GC and subs open and candid

    Maintain communications among the subs give all contractors an opportunity to discuss their

    problems and learn about the problems others are facing

    Help to schedule and coordinate the project

  • Subcontractor management(Contd)

    Types of meetings Management meetings

    Monthly or bi-monthly meetings with a set agenda for an in-depth status review of job progress, schedule, submittals, quality, and safety, and any special problems

    Attendance - Owner, A/E, project manager, superintendent, and major subs

    Minutes should be taken and sent to all who attended plus everybody involved in the subjects discussed

  • Subcontractor management(Contd)

    Weekly project meetings These meetings are centered primarily on scheduling and coordination, but can also cover cleanup, quality, safety, etc.

    Pre-construction planning meetings To discuss scope of work, long lead time items, material handling and storage requirements, and activity duration

  • Subcontractor management(Contd)

    D. Subcontractor default Be sensitive to early warning signs Follow notification requirements if

    subcontractor performance falls below acceptable standards

    Follow contract provisions exactly for termination procedures

    Try to work problems out with banks, bonding company, etc., so no new subcontractor has to be employed

  • GUIDELINES FOR MACHINE COMMISSIONING

    Task of Project and Production Maintenance team

    Verifies operation of components under various conditions

    Verifies interaction between systems and subsystems

    Documents performance of systems to design criteria

    Instructs building personnel on proper operation of systems

    Ongoing after building occupancy as requirements change

    Documentation Required

    Owners Project Requirement Document Commissioning Plan Basis of Design Contract Documents FAT Report Draft of the Final Commissioning Report Warranties O & M Manuals

    Approved Change Orders AS-Built Drawings All testing data verification and

    documentation. Sequence of Operation Minutes of Meetings Local jurisdictional inspection documentation

    and records

  • INDUCTION IN NEW EQUIPMENT

    O & M Manuals Should be received within

    60 days after approved submittals have been returned

    Review with owner and give comments back to contractor for compliance

    Use this training Bible Be careful what we get

    in the O & M You do not need

    installation material

    TRAINING

    Factory witness testing on major pieces of equipment

    Get factory training out of way up front

    Training should be in a classroom setting and also at the respective piece of equipment

    Use factory trainers not the local sales rep

  • LIST OF DUTIES TO BE DONE FOR PLANT MAKING

    Conceptual Planning of the Project

    Planning and Estimation of Site Infrastructure

    Resource Mobilization

    Overall administration of the Project.

    M.I.S. (Management Information System )

    Timely submission of monthly RA bills, labour bills, purchase bills preparation and certification of Final

    Bills and reconciliation of material.

    Minimize wastage of Construction Material.

    liaison with Client / Consultants

    Motivating and managing site personnel as team leader.

    Timely completion of project within the given time frame and maintaining quality

    Execution of structural and Architectural works as per relevant drawing.

    Micro planning to deliver the project.

    Planning day to day activities of Project.

    Coordination with architects and consultants.

    Monitoring of construction activities as perform by contactors/other agencies with quality norms.

    Interaction with prime contractors and other agencies.

  • LIST OF DUTIES TO BE DONE FOR PLANT MAKING

    Review contractor's structural change order proposals. Prepare recommendations to t Engineer for review. If warranted, assist in negotiations with contractors regarding changes in contract value or project duration.

    Review contractors' claims related to structural works. Prepare recommendations for claims approval or rejection. Assist in negotiations with contractors regarding the value of claims or changes in schedules.

    Witness testing and commissioning of the works.

    Approve the contractors' as-built drawings and O&M manual submittals. Assist with the final inspection of the work. Review the adequacy and accuracy of punch lists.

    Monitor final completion of the work.

    Review of structural drawings for projects designed by others.

    Review is to be undertaken for code compliance.

    Work out the quantities of material used in projects.

    Material requirements.

    Documentation and MIS related to Project. Bar bending Schedules.

    Serve as the Senior Site Representative for all matters related to construction quality assurance of structural works.

    Monitor the structural works for conformance with the provisions of the Contract Documents and the Procedures manual.

    Review, approve and process all structural technical submittals.

    Coordinate and supervise the work of all structural activities and operations.

    Liaise with local authorities and ministerial agencies having jurisdiction over the project.

    Receive/action Request for Information (RFI) that apply to structural works. RFI's requiring design feedback will be directed to the Designer for response. Review the responses for adequacy.

  • LIST OF DUTIES TO BE DONE FOR PLANT MAKING

    Close coordination with Architectural and MEP trade designs

    Planning, monitoring & controlling all site activities including manpower planning, resource planning & material planning of multiple project sites.

    Ensuring all site activities of various project sites are carried out as per SOPs (standard operating procedures), as per ISO 9000, OSHO, site quality plan.

    Approving the Project construction & erection Schedule prepared as per the Contract guidelines using Primavera for all projects under execution. Providing guidance in developing

    the site progress calculation sheet & monitoring the same.

    Analyzing the major scope of work at site (as per the Contract) and discussing with various disciplines for criticalities & strategies for timely completion of site work of various projects under execution.

    Attending major site coordination meetings with client for reviewing site progress & resolving pending problems for various projects under execution

    Implementing a periodic MIS reporting of site progress, customer invoicing & payment voucher collection at site of various projects under execution.

    Making important correspondences with Client to build Customer relationship and sort out any disputes (technical or commercial) occurring at various project sites.

    Responsible for Project Cost control and analysis for site activities

    Control on-site activities for erection progress through site-in-charge and resolving site discrepancy reports with engineering.

    Coordinating with Procurement department for shortage/ damage report.

    Identifying the training needs for own department and arrange for the same, through Personnel Department, as and when required.

    Leadership, delegation, communication, interfacing and presentation skills. Experience in handling multi-functional management role is mandatory

  • LIST OF DUTIES TO BE DONE FOR PLANT MAKING

    Banking Construction loans Financial Structure Legal matters Business organization Auditors & audits General books of account Subsidiary records Cost records and reports Financial reports Tax returns and payments

    Payment of invoices Billing Collections Assignments Bank deposits Personnel records Payrolls and records Wage and personnel reports to

    public agencies Office services Construction Material Testing Geotechnical Investigations Petrography Radar Non-destructive testing at sites

  • DUTIES OF PROJECT HEAD Conceptual Planning of the Project

    Planning and Estimation of Site Infrastructure

    Resource Mobilization

    Overall administration of the Project.

    M.I.S. (Management Information System )

    Timely submission of monthly RA bills, labour bills, purchase bills preparation and certification of FinalBills and reconciliation of material.

    Minimize wastage of Construction Material.

    liaison with Client / Consultants

    Motivating and managing site personnel as team leader.

    Timely completion of project within the given time frame and maintaining quality

    Execution of structural and Architectural works as per relevant drawing.

    Micro planning to deliver the project.

    Planning day to day activities of Project.

    Coordination with architects and consultants.

    Monitoring of construction activities as perform by contactors/other agencies with quality norms.

    Interaction with prime contractors and other agencies.

    Work out the quantities of material used in projects.

    Material requirements.

    Documentation and MIS related to Project. Bar bending Schedules.

    Planning, monitoring & controlling all site activities including manpower planning, resourceplanning & material planning of multiple project sites.

    Ensuring all site activities of various project sites are carried out as per SOPs (standard operating procedures), as per ISO 9000, OSHO, site quality plan

  • DUTIES OF PROJECT HEAD Approving the Project construction & erection

    Schedule prepared as per the Contract guidelines using Primavera /MSP for all projects under execution. Providing guidance in developing the site progress calculation sheet & monitoring the same.

    Analyzing the major scope of work at site (as per the Contract) and discussing with various disciplines for criticalities & strategies for timely completion of site work of various projectsunder execution.

    Attending major site coordination meetings with client for reviewing site progress & resolving pending problems for various projects under execution.

    Implementing a periodic MIS reporting of site progress, customer invoicing & payment voucher collection at site of various projects under execution.

    Making important correspondences with Client to build Customer relationship and sort out any disputes (technical or commercial) occurring at various project sites.

    Control on-site activities for erection progress through site-in-charge and resolving site discrepancy reports with engineering.

    Coordinating with Procurement department for shortage/ damage report.

    Identifying the training needs for own department and arrange for the same, through HRl Department, as and when required.

    Leadership, delegation, communication, interfacing and presentation skills. Experience inhandling multi-functional management role is mandatory.

    Responsible for Project Cost control and analysis for site activities

  • DUTIES OF CIVIL/ELECTRICAL AND STRUCTURAL ENGINEER Serve as the Senior Site Representative for

    all matters related to construction qualityassurance of structural works.

    Monitor the structural works for conformance with the provisions of the Contract

    Documents and the Procedures manual.

    Review, approve and process all structural technical submittals.

    Coordinate and supervise the work of all structural activities and operations.

    Liaise with local authorities and ministerial agencies having jurisdiction over the project.

    Receive/action Request for Information (RFI) that apply to structural works. RFI'srequiring

    design feedback will be directed to the Designer for response.

    Review the responses for adequacy.

    Review contractor's structural change order proposals

    Prepare recommendations to Resident Engineer and or Client for review. If warranted, assist in negotiations with contractors regarding changes in contract value or project duration.

    Review contractors' claims related to structural works. Prepare recommendations for claims approval or rejection. Assist in negotiations with contractors regarding the value of claims or changes in schedules.

    Witness testing and commissioning of the works.

    Approve the contractors' as-built drawings and O&M manual submittals. Assist with the final inspection of the work. Review the adequacy and accuracy of punch lists. Monitor final completion of the work.

    Review of structural drawings for projects designed by others

    Review is to be undertaken for code compliance.

    Close coordination with Architectural and MEP trade designs

  • ARCHITECT

    Furnishing the contractor with drawings and information

    Issue of variation orders altering extent, nature or quantity of the works

    Suspension of the works

    Nomination of sub-contractors and suppliers

  • DESIGN HEADFinalize project scope of work and budget.

    Make certain that the design team is performing the work and services required by the scope.

    Provide assistance and guidance to the design consultant.

    Prepare and monitor the project schedule.

    Monitor project cost including cost of design, ROW acquisition, utility relocations, construction, etc., to keep costs within budget.

    Review and coordinate reviews of all design submissions, preliminary and final real property and ROW plans, design drawings, special provisions, specifications, and estimates.

    Accept and evaluate the quality of deliverable. Verify adherence of the design consultant to the QA/QC plan.

    Coordinate and oversee design review meetings, constructability reviews, and plan checks.

    Coordinate between the Agency and involved third parties (e.g., environmental agencies, municipal officials, municipal authorities, utility companies).

  • PART TWO

    SAVLI PROJECT

  • AIM: Project completion of manufacturing plant by 31 Sept 2012 and production operational with first product delivery on 12/12/12.

    Scope : Civil work/PEB/ Elect Work/ Mechanical work/ Machine Commissioning/ Utilities

    Terms of Reference: Master Schedule Plan

    KEY MILE STONES DATES DECIDED BY MANAGEMENT

    Construction of Plant Shed: 02 Oct 2012

    Procurement of Electrical Items and Utilities: 27Aug 2012

    Procurement of Machinery and Installation:12Dec 2012

    Production of First product Unit:12Dec 2102

    PROJECT CHARTER

  • Civil & Elect Consultant : Shah & TalatiConsultantCivil Contractor : Shri Ganesh Engineers & fabricatorsPre-engineered Building Contractor : Lloyd InsulationCrane: AnupamElectrical : Rama Engineering

    Project HeadT Remesan

    Project HeadT Remesan

    Head Engg &ContractingN V Belsare

    IJ M Muthe

    Head Engg &ContractingN V Belsare

    IJ M Muthe

    Group Head ProjectVikram Bakshi

    Group Head ProjectVikram Bakshi

    Procurement Committee *

    Nitin V BelsareBhaskar Pathak

    Nagesh Shekhdar

    Procurement Committee *

    Nitin V BelsareBhaskar Pathak

    Nagesh Shekhdar

    Proj.Eng. CivilBhavik Sheth Bhatt

    Proj.Eng. CivilBhavik Sheth Bhatt

    Proj.Eng. MechSantosh ( yet to Join)

    Proj.Eng. MechSantosh ( yet to Join)

    Proj. Eng ElectriTapan Desai

    Proj. Eng ElectriTapan Desai

    Ofiice Assistant.

    Smit Joshi

    Ofiice Assistant.

    Smit Joshi

    RESPONSIBILITY ASSIGNED MATRIX

    Other key Note Contributors

    Safety officers > Neeraj Sharma and AlpishBhatt and Pragnesh ParikhCommercial > Sriram Kadam/DigvijayPharkate/ Gaurav GediaFinance> Anirudh and Nehal

  • Savli front end site team

    No one can whistle a symphony. It takes a whole orchestra to play it.But You need a good Conductor

    Mr T RemesanLt Col Vikram Bakshi

    Civil vendorMr Viral

    Fantastic Front end team

    Civl Vendor Engr KapilThermax Mech Engineer Sachan

    Thermx Civil Engineer BhavikSafety officer and for any task NeerajPEB Looyd engineer Harry and Anish

    Crane Team from Anupam

    Crane engineer Alpsih

    Eectrical Engoneer Tapan

    Project Adminand Mech engineer Smit

    None of us is as smart as all of us. "

    Alone we can do so little; together we can do so much."

  • SNAP SHOTMASTER SCHEDULE PLAN

    ID Task Name Finish

    0 final Savli execution plan 0990611R2 Wed 12/12/121 Bi Drum Project at a glance ( Plant construction to first unit Invoice)Wed 12/12/12

    Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar AprQtr 2, 2011 Qtr 3, 2011 Qtr 4, 2011 Qtr 1, 2012 Qtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 2013

    ID Task Name Finish

    39 Release Cloumn reaction design to client for structure consultant approval Tue 1/31/1240 Revise based on comments and release for PEB manufacturing & civil wrokFri 2/10/1241 Manufacturing of Bi drum PEB structure Sat 6/16/1242 Civil construction of shed for Bi-Drum at Savli Vadodara Wed 12/12/1243 Civil consultant finalisation and release of civil drawings Thu 1/12/1244 First Round of discussion with all consultants / agencies Mon 10/17/1145 Shortlist people and have interaction Mon 11/7/1146 Finalise the consultant scope and Release LOI Thu 10/20/1147 Get Column reaction from PEB structure supplier Thu 1/12/1248 Release civil design work for Bi drum mfg set-up Fri 12/30/1149 Manpower planning & Recruitment Mon 1/2/1250 Prepare the organisation structure for the Bi drum Tue 10/4/1151 Identify people from Thermax, Pune Wed 10/12/1152 Prepare recruitment plan for balance local people Thu 10/20/1153 Conduct interviews and select right Staff people Fri 11/11/1154 Approach the development zone to get skilled workers Mon 11/21/1155 Recruit workers Mon 1/2/1256 Construction of plant shed Tue 10/2/1257 Prepare comparative statement and fair price estimation Fri 10/7/1158 Finalise the contractor Wed 10/12/1159 Release LOI / PO Thu 1/12/1260 Civil Construction of plant Bi drum shed Wed 5/30/1261 Errection of PEB structure Thu 8/16/1262 Civil construction of Flooring,wall & windows , paintingMon 9/10/1263 Bi drum shed readyness after water and LPG piping Tue 10/2/1264 Construction of office and utilities & interiors Fri 6/22/1272 Procurement of machinery for Bi- Drum and Installation Wed 12/12/12

    Jan 27 Jan 31

    Feb 1 Feb 10

    Feb 13 Jun 16

    Oct 4 Oct 17

    Oct 18 Nov 7

    Oct 20

    Jan 4 Jan 12

    Nov 28 Dec 30

    Oct 4 Oct 4

    Oct 5 Oct 12

    Oct 13 Oct 20

    Oct 21 Nov 11

    Nov 14 Nov 21

    Nov 22 Jan 2

    Oct 4 Oct 7

    Oct 10 Oct 12

    Jan 6 Jan 12

    Mar 23 May 30

    May 31 Aug 16

    Jun 20 Sep 10

    Sep 11 Oct 2

    Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar AprQtr 1, 2011 Qtr 2, 2011 Qtr 3, 2011 Qtr 4, 2011 Qtr 1, 2012 Qtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 2013

  • SITE WORK PREPRATIONS

    FOUNDATION BOLTTEMPLATES

    MISC CIVIL WORK

    PEB RAFTERSMISC CIVIL WORK

    PEB CLADDING /ROOF

    CRANE FITMENTS

    10 SEPTCIVIL WORK COMPLETE

    PRODUCTION FROM

    BIDRUM AND PANLE

    PEB COLUMNSANCILLARY BUILDING

    WORK AND MISC CIVIL

    WORK

    PEB CRANE BEAMS/ROOF MISC CIVIL WORK

    :MACHINE FOUNDATION LAYOIUT

    CRANE COMMISSIONING

    PEB COMPLETION

    Coil PEB WorkAncillary Building

    completed

    COIL SHOP PEB CRANE AND MACHINE WITH

    ELECTRICAL WORK

    12/12/12

    Productiionoutput

    CIVIL FOUNDATIONSMISC CIVIL WORK

    MILE STONES FOR BIDRUM PANEL SHOP TILL 12/12/12

    PROJECT TRUISM > You can con a sucker into committing to an impossible deadline, but you cannot con him into meeting it.

    CivilConstruction

    Of plantShed/LPG/Water

    02 0ct 2012

    ErectionOf PEB Structure

    16 Aug 2012

    CIVILCONSTRUCTIONOF FLOORING

    WALLWINDOWPAINTING

    CompleteInside

    Civil workWith windows

  • Example text

    CIVIL FOUNDATIONS.

    10 SEPT

    20 OCT

    PEB WORKCOMPLETION.

    30 OCT

    FLOOR & M/CFOUNDATIONS.COIL MACHINEINSTALLATION

    10 NOV

    CRANE FITMENT.RADIOGRAPGHY WALL

    10 NOV

    PRODUCTION START

    12 /12/12

    FINAL OUT PUT

    MILE STONES FOR COIL SHOP TILL 12/12/12

  • SOME RULES OF THE GAME Good Planning: forward planning, which includes detailed planning of the

    process implementation stages, task timeliness, fall-back positions, and re-planning

    Clear Responsibility and Accountability of Team Members: We had a clear understanding of their roles and duties in the project. They must understand how expectations vs. achievements will be measured and graded .

    Schedule Control: We had continual monitoring and measurement of time, milestones, people, and equipment schedules

    Guard Against Lack of Efficient Internal Communication Links, Lack of Efficient External Communication Links, Lack of Responsive Decision Making Lack of Effective Teamwork

    Communications was kept honest and open between team members and vendor to know exact status of situation.

  • Define scope of project Identify stakeholders, decision-

    makers, and escalation procedures

    Develop detailed task list (work breakdown structures)

    Estimate time requirements Develop initial project

    management flow chart Identify required resources and

    budget Evaluate project requirements

    Identify and evaluate risks Prepare contingency plan Identify interdependencies Identify and track critical

    milestones Participate in project phase

    review Secure needed resources Manage the change control

    process Report project status

    HOW WE ALL WENT ABOUT THE PROJECT WORK

  • Functions of project management for construction Specifying project objectives and plans which include the delineation of

    scope, budgeting, scheduling, setting performance requirements, and selecting project participants

    Maximizing efficient resource utilization through procurement of labor, material, and equipment according to the prescribed schedule and plan

    Implementing various operations through proper coordination and control of planning, design, estimating, contracting, and construction in the entire process

    Developing effective communication and other mechanisms for resolving conflicts among the various project participant

  • SUMMARY OF TASK

    ID Task Name Start Finish % Complete Baseline Finish Milestone

    0 Tue 1/17/12 Wed 10/10/12 86%Wed 10/10/12 Yes2 1 CONSTRUCTION OF PLANT SHED BI DRUM Tue 1/17/12 Fri 8/31/12 86%Tue 10/2/12 Yes4 1.1 JAN /FEBURARY NO I TASK :

    PREPARATORY WORKMon 1/30/12 Fri 3/9/12 100% No

    20 1.2 JAN/FEBURARY NO 2 TASK : CIVIL CONSTRUCTION OF BIDRUM SHED TILL FOUNDATION

    Wed 1/25/12 Sat 4/14/12 100%Wed 5/30/12 Yes

    22 1.2.1 A: SITE INITIAL WORK Mon 1/30/12 Wed 3/28/12 100% No30 1.2.2 B: CIVIL WORK FOUNDATION BOLT Thu 2/2/12 Sat 4/7/12 100%Wed 5/30/12 Yes44 1.3 FEB TO AUG NO 3 TASK

    :CONSTRUCTION OF OFFICES UTILITIES ANDINTERIORS

    Wed 2/1/12 Fri 8/31/12 85%Fri 8/31/12 Yes

    46 1.3.1 UG TANK Fri 2/10/12 Fri 3/30/12 100% NA Yes53 1.3.2 WELDING AND MAINTENANCE SHOP Fri 3/23/12 Wed 8/22/12 85% Yes66 1.3.3 SERVICE OFFICE Wed 3/28/12 Fri 8/31/12 55% Yes78 1.3.4 TOILET No 1 Fri 3/23/12 Thu 8/30/12 83% NA Yes91 1.3.5 TOILET No 2 Wed 5/30/12 Thu 8/30/12 96% NA Yes

    104 1.3.6 RADIO GRAPHY Wed 2/1/12 Thu 8/2/12 96% NA Yes117 1.4 NO 4 TASK> ERECTION

    OF PEB STRUCTURE Wed 2/1/12 Thu 8/16/12 99% Thu 8/16/12 Yes

    119 1.4.1 Prepration Wed 2/1/12 Sat 4/14/12 100% No125 1.4.2 ERECTION GRID 1 TO 13 Tue 4/10/12 Mon 4/30/12 100% Yes135 1.4.3 ERECTION Grid 13 to 23 Tue 5/1/12 Sat 5/19/12 100% NA Yes145 1.4.4 FIXING OF ROOF SHEETS Sat 6/16/12 Sat 6/30/12 100% NA No154 1.5 NO 5 TASK> BRICK

    WALL ON PLINTH BETWEEN PEB COLUMNSat 3/31/12 Mon 9/10/12 89% NA Yes

    167 1.6 NO 6 TASK Electrical Works

    Tue 5/1/12 Wed 10/10/12 68% Mon 8/27/12 No

    174 1.6.7 Installation & commissioning Fri 8/17/12 Wed 10/10/12 6% NA No190 1.7 < JUN TO AUG > NO 7 TASK >

    CONSTRUCTION OF MACHINE FOUNDATION BEFORE FLOOR WORK

    Fri 6/1/12 Thu 8/30/12 100% NA Yes

    192 1.7.1 PLATE BENDNG Fri 6/15/12 Sat 6/30/12 100% NA Yes201 1.7.2 PANEL BENDING Fri 6/15/12 Sat 6/30/12 100% NA Yes210 1.7.3 SHOT BLASTING Wed 6/6/12 Thu 8/30/12 100% NA Yes219 1.7.4 PEMA Fri 6/15/12 Sat 6/30/12 100% NA Yes220 1.7.4.1 EXCAVATION Fri 6/15/12 Sat 6/30/12 100% NA No244 1.8 NO 8 TASK > FLOOR

    WORKSat 4/14/12 Fri 8/31/12 94%Mon 9/10/12 Yes

    246 1.8.1 GRID 1 to 13 Sat 4/14/12 Wed 5/30/12 100% NA No250 1.8.2 GRID 23 to 13 Tue 5/1/12 Thu 5/31/12 100% NA No255 1.8.3 RCC FLOORING FROM GRID 1 TO 23Fri 6/1/12 Fri 8/31/12 90% NA Yes260 1.9 TASK NO 9 >

    WALL WINDOW AND DOOR FITMENTSMon 7/2/12 Thu 8/30/12 85%Tue 10/9/12 Yes

    280 1.13 NO14 TASK >CRANES FITMENTS AFTER PEB CRANE BEAM COMPLETION

    Mon 7/2/12 Wed 8/29/12 35% Yes

    8/31

    4/14

    4/7

    8/31

    3/308/22

    8/318/308/30

    8/28/16

    4/30100%5/19100%

    100%9/10

    8/30

    6/30100%6/30100%

    8/306/30100%100%

    8/3194%

    100%100%

    8/3190%8/3085%

    8/29

    Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep4th Quarter 1st Quarter 2nd Quarter 3rd Quarter

    CIVIL FOUNDATIONS

    ANCILLARY BUILDINGS

    PEB WORKS

    PLINTH WALL

    MACHINE FOUNDATIONS

    FLOOR

    WINDOWS AND PAINT

    CRANE

    PRE LIMINARY WORK

    ELECTRICAL

  • Green Field Project layout

    A. Organizing the project layout Proper placement of yard,

    office, roads, material storage and fabrication

    60% to 70% of all labor cost to install materials is spent to get the materials to the location where it is installed

    Items to consider Site access and

    security, number and location of entrances

    On-site access roads: materials, drainage, maintenance, etc.

    Job office: location and layout

    material storage areas: include subs!

    Stockpiling of dirt for backfill

    Fabrication areas Trash removal

  • X. Project layout (Contd)B. Material storage and

    protection Storing materials so

    they can be found; record the location

    Protection from weather; follow manufacturers instructions

    Allow for mechanized handling

    Protection from theft; lights, locks, security devises

    Controlling its use; define responsibilities for control

    C. Controlling small tools and supplies Limit access to small

    tools and supplies Limit the way they can

    be obtainedD. Material handling and

    fabrication Mechanize when

    possible Use assembly line

    techniques: plan the location, plan the flow of materials, plan the special tools and equipment needed

  • X. Project layout (Contd) The secrets of efficient

    prefabrication Minimize the moves for

    materials and workers Minimize the hand labor Remember that the shortest

    distance between two points is a straight line

  • PART THREE

    RISK MANAGEMENT

  • Outstanding Risks and Issues PROJECT DELIVERBALE RISKS

    ELECTRIC PANEL DELIVERY LATE FOR ELECTRICAL WORK

    Solution :Risk resolved by visit and liaison but needs follow up. Delivery commited by 10Sept

    MACHINE DELIVERY LATE FOR COMMISSIONING

    Solution: Needs Follow Up

    PEB COIL DELIVERY TIME LINES

    Solution: Clear time lines to be followed wrt design to production to delivery to erection .Closing Committed by 30 Oct 2012

    PROJECT ISSUE RISK

    SAFETY ISSUE BEING NEGLECTED

    COORDINATION OF PEOPLE WORKING TO PREVENT ANY OVER LAP OF ANY MOVEMENTS

    - AREA EARMARKED FOR MATERIAL

    - WATER AND GLUCOSE ARRANGEMENTS FOR PREVENTING DEHYDRATION

    - SAFETY KITS AND MEASURES UNDER SAFTEY OFFICER

    - CLEARANCE BY CIVIL AND MECH ENGR FOR OVER TIME WORK AND ENSURING SAFETY ASPECTS.

    NO WORK AT HEIGHT AFTER DARKNESS

    TRAINING

  • CIVIL FOUNDATION BOLT Start: 2/1/12 ID: 2

    Finish: 4/13/12 Dur: 53 days

    Res:

    PEB COLUMNStart: 4/16/12 ID: 3

    Finish: 5/25/12 Dur: 30 days

    Res:

    PEB SHEET/ROOFStart: 5/28/12 ID: 4

    Finish: 6/27/12 Dur: 23 days

    Res:

    FLOORINGStart: 5/28/12 ID: 5

    Finish: 6/30/12 Dur: 25 days

    Res:

    CRANEStart: 5/28/12 ID: 6

    Finish: 6/29/12 Dur: 25 days

    Res:

    ELECTRICALStart: 4/16/12 ID: 7

    Finish: 7/13/12 Dur: 65 days

    Res:

    FOUNDATIONStart: 4/16/12 ID: 8

    Finish: 6/13/12 Dur: 43 days

    Res:

    MACHINE FITMENTStart: 6/18/12 ID: 9

    Finish: 7/31/12 Dur: 32 days

    Res:

    ANCILLARIESStart: 4/16/12 ID: 10

    Finish: 7/30/12 Dur: 76 days

    Res:

    RADIO GRAPHYStart: 4/16/12 ID: 11

    Finish: 6/30/12 Dur: 55 days

    Res:

    INAUGRATION Start: 8/15/12 ID: 13

    Finish: 8/15/12 Dur: 1 day?

    Res:

    TRIAL PRODUCTIONStart: 8/1/12 ID: 12

    Finish: 8/14/12 Dur: 10 days

    Res:

    BIDRUM PLANTPROJECT EXECUTION

    START : 2/2/12FINISH; 15/9/12

    TOTAL:141 DAYS

    CRITICAL PATH

  • Impact of Risk on success/failure for Balance Project

    HOW FAILURE OF MACHINES CAN BE PREVENTED IN LONG

    RUN WRT NEW FACILITY

    5 S Strictly followed by Production team with proper upkeep of Equipment.

    Separate TEAM for Maintenance of machines

    Enforce Production Team to do daily preventive maintenance

    Plan its own Corrective and Schedule Maintenance

    HOW SUCCESS CAN BE USED BY TIMELY CONSTRUCTION OF

    NEW FACILITY

    Completing Civil/PEB work 10 Sept will give One month advance preparation time as original 10 Oct.

    Enough time for coordination of various activities of Manpower training / Processes of production line to align start by 12/12/12 and make it a sustainable production line

    If need be advance production also before 12/12/12

  • PART FOUR: QUALITY AND SAFETY MANAGEMENT

    Work Smart Not Hard !!!

  • QUALITY

    DPR FILE TEST CERTIFICATE DRAWING FILE RA BILL FILE LEGAL DOCU OF CONTRACTOR CONCRETE POUR CARD FILE

  • QUALITY COMPLIANCEExecution and Quality Control procedures

    As per Construction Quality requirements In compliance with Contract Documents.

    Latest issues of applicable drawings and documents

    Activities performed according to relevant execution procedures .

    No stage started without the previous one verified.

    Responsibility for each control task is clearly identified

    Control of the quality identification of incoming materials.

    Control of non-conforming materials.

    Surveillance and control of work processes.

    Communication between personnel involved in quality and those involved in material control and Construction.

    Inspections and tests Documents

    DPR file

    Excavation and Lay out measurements

    Test certificateFine AggregateCoarse AggregateReinforcement SteelCube Test and Compressive StrengthConcreteConcrete Reinforcement bars

    Drawing fileRA bill fileLegal documents of contractorConcrete pour card file

  • SAFETYTRAINING PREVENTION AND PRECAUTIONS

    LECTURES ON SAFETY WORKING AND EQUIPMENT TRAINING DEMO REGISTER FOR OBSERVATION OF ANY DONTS DOES AND DONTS GLUCOSE AND WATER ARRANGEMENT REST AND RECOUP MEDICAL

  • Part Five: Budget High Light

    THE TEAM HAS SAVED APPRX 35 LACS ON SITE WORK IN CIVIL WORK TILL DATE .

    THE TEAM ALSO FINISHED WORK MUCH IN ADVANCE AT LEAST ONE MONTH BEFORE TO ENABLE PRODUCTION TEAM TO SET UP INETRNAL SHOP AND PROCESSES ALSO

  • PART SIX

    Areas of Concern in Savli Unit RoadSTPFire Hydrant around the PlantPlantation as per GIDC NormsSpace for Storage , Packing and Dispatch

  • PART SEVEN: PROJECT RECOMMENDATION AND LESSONS LEARNED

  • Learning From Negatives

    We could have closed the Project on 15 Aug instead of 10 Sept

    Poor Communication Between Designer/Purchasers and Project /Vendor team

    Solution: They should be Positioned in site once a month to resolve issue and then only clear off

    Lack of IT management to speed up work

    Lack of User Input wrt existing Plant records of Shell shop led to couple of Incomplete requirements . ( Records of Shell Shop were not there)

    Solution: Bidrum / Panel/ Coil records will be there in soft and hard copy

    CHANGES CHANGES CHANGES THEY ARE THE REAL KILLERSChanging requirements and Specifications led to many Restarts/Cost overruns/ Time overruns

    Solution : Proper Planning with all stake holders with one to onemeeting with fixed time schedule for closing issues.

    TOO MANY COOKS AND SOUP GETS SPOILED

    Slow Executive Support for almost everything : Ownership was not there and taken as additional task.

    Solution: Clear defined Structure to be filled up before Project starts and support staff in back end to be integrated for some kind of parallel reporting and feedback on response

    Lengthy Processes for Approvals: Solutions: Less Bureaucracy stops and reduced number of people in Approvals.A study can be undertaken to reduce the process and make it Lean way under Six Sigma

  • CONCLUSION

    A successful project must be on time, on budget, and deliver quality (features and functions) as promised.

    Anything less will be either a failed project or a challenged project.

    Resolution Type 1 is a Project Success it completed on time and budget, with all features and functions as specified. Only 16.2% of projects fell in this category.

    Resolution Type 2 is Project

    Challenged. These were completed, but were over cost, over time, and/or lacking all of the features and functions that were originally specified. 52.7% of all studied projects fell into this Resolution Type 2 (Challenged) category.

    Resolution Type 3 is termed Project Impaired/Failed. These projects were abandoned or cancelled at some point and thus became total losses. A disturbing 31.1% of all studied projects fell into this category.

  • PROJECT CLOSE OUT PREPARE A PUNCH LIST OF

    INCOMPLETE CONTRACTOR ITEMS.

    LEAD A FINAL WALK THROUGH INSPECTION OF CONSTRUCTED FACILITY.

    RESOLVE OUTSTANDING CHANGES/CLAIMS.

    DEVELOP A PLAN TO DEMOBILIZE AGENCY AND CONSULTANT STAFF.

    KEEP PROJECT TEAMS ATTENTION

    FOCUSED ON CLOSEOUT ACTIVITIES.

    ASSESS AND DOCUMENT LESSONS

    LEARNED ON PROJECT.

    OBTAIN PROJECT ACCEPTANCE FROM PRINCIPAL STAKEHOLDERS.

    CELEBRATE PROJECT COMPLETION.

    A CONTRACTS TERMS AND CONDITIONS SPECIFY THE ACTIONS NEEDED FOR FINAL SETTLEMENT AND CLOSURE.

    A CONTRACT IS SUBSTANTIALLY COMPLETE WHEN THE PERMITTING AUTHORITY ISSUES

    CERTIFICATE OF BENEFICIAL OCCUPANCY.

    A CONTRACT AUDIT IS NEEDED TO VERIFY APPROPRIATENESS OF COSTS INVOICED ON COST PLUS TYPE CONTRACTS.

    A CONTRACT AUDIT EXAMINES DIRECT LABOR, OTHER DIRECT COST, AND INDIRECT OVERHEAD CHARGES.

  • Important administrativecloseout items

    Demobilization of project team.

    Closure of project funding and financing.

    Securing the disposition of project records.

    Conducting a lessons learned project evaluation.

    Achieving closure with stakeholders.

    Celebrating project success.

    Typical closeout activities for a professional service contract include:

    Verification of Scope Completion Confirm that the professional service contractor has satisfactorily delivered the services called for in the contract scope of work.

    Contract Audit Where contract payments are on a cost plus fee basis, the contract provisions should give the Agency the right to audit the contractors costs. The audit should verify items such as direct labor rates, support for time charges, support for other direct costs, and justification for overhead rates.

    Final Payment and Release of Retention With scope completed satisfactorily and audit completed, you can approve the final payment and release of any retention held back from prior contract payments pending satisfactory completion of services and audit of costs

  • SNAP SHOTS GREEN FIELD

    PROJECT SAVLI

  • BHOOM PUJAN BY MANAGEMENT IN 2011

  • BHOOMI PUJANBY PROJECT TEAM IN JAN 2012

  • Site Preparation

    Remove trees and any debris

    Remove top soil (4-6 below surface)

  • PREPARATORY WORK

    Guard Cabin under completion.

    Barricading Work under wayWater tank for site

    Industrial official documentation and liaison over Legal Documents for Workers handed over to HR dept. PO and Contract documents completed Initial safety training completed Dumping of Barricading material Dumping of water pit /office site Positioning of JCB and Construction Equipment Meeting with Consultants for drawings

  • SITE LAYOUT

    Corner Footing Marking

    Ensure lot lines are known & setbacks are complete

    Layout building perimeter

    Use batter boards

    Establish building corners & building perimeter

    Auto level used to determine floor level with existing shed

    SURVEY AND AUTOLEVEL

  • SURVEY

    9.430 NET FALL

    1.131 1.57

    0.439

    2.16 2.55

    0.39

    3.068 3.488

    0.42

    3.071 3.231

    0.16

    FALL(m) FORESIGHT (m)

    BACKSIGHT (m)

    BENCHMARK --- Benchmark was taken as a nearby road as 0.0m level.LAYOUT---Layout is done in order to locate exact position of building components on the site as mentioned in

    drawingGRID LINESThese are the reference lines in which whole plot is divided symmetrically. So its easy to locate

    and communicate about any particular point by referring it with respect to Grid Lines.

  • Excavation, Layout and Foundation

    Excavation is a process of making trenches by digging up of earth for the construction of foundations and basements.

    Excavation level at escape site is 219.825 mm Excavation is done by the JCB on the hourly basis After the excavation the surface is leveled called

    surface dressing Layout is done on the PCC poured over leveled

    surface. Column and foundation (raft ) steel is then laid as

    per drawings.

  • Points to take care:- layout should be checked properly. Check any difference between architectural and

    structural drawings regarding location of column. After excavation check the stability of temporary

    structures built near the excavated ground. Before laying raft reinforcement, shuttering wall which is

    mainly brick wall should be built and should be filled with soil on other side.

    Check the direction of chair bars in the raft

  • Excavation

    Excavate foundation along line created by batter boards

    Excavate remainder of soil inside perimeter

    Dont excavate inside soil if slab on gradeIf deep foundation, taper edges to prevent collapse

    If soil unstable, or very deep - use shoring

  • EXCAVATION

  • LAYOUT

  • RAFT FOUNDATION

  • EXCAVATION

    Total Depth of Excavation to be done---10.2 meters Total Excavation to be done---53409 cubic meters .

  • FOUNDATIONS

    Isolated footings Strip footings Combined footings

    Grade of concrete--- M25.

    Clear Cover--- 50 mm.

  • 16 FEBCONCRETING WORK STARTS

    POOJA BEFOREFIRST FOOTING RCC

    POUR CONCRETE FOOTINGSSMOOTH / FINISH SURFACE

  • STEEL

    For Reinforcing Concrete now a days HYSD (High Yielding Strength Deforming) steel bars are used. Steel can handle both tensile and compressive stresses. Mainly steal in R.C.C is used to take Tensile stresses but can also be used to take Compression if Concrete in a section is not enough to take Compressive stresses.

    Now a days TMT (Thermo Mechanically Treated) Bars are used. Thermo mechanically treated steel known as TMT steel can be described as new-generation-high-strength steel having superior properties such as weldability, strength, ductility and bendability meeting highest quality standards at international level

    Brands Of Steel Used At SiteBHUSHAN STEEL

    JYOTI STEEL

    32mm

    28mm

    25mm

    16mm

    12mm

    10mm

    8mm

    Diameter of bars required on site on Site

  • 16 FEBCONCRETING WORK APART FROM FOOTING EXCAVATION /PCC/ STEEL

    FOUNDATION SHUTTERING

  • Pour Concrete Foundation Walls

    Construct formwork (include sleeves / doors / windows)

    Install reinforcement into formwork

    Pour concrete foundation wall

    Install anchor bolts into semi-cured concrete

  • Pour Concrete Foundation Walls

    Allow concrete to cure adequately (7-10 days)

    Strip forms

    Apply waterproofing

    Install perimeter drain tile

    Backfill

  • Install Concrete Block Foundation Walls

    Allow concrete footing to properly cure

    Install first course of concrete block on bed of mortar

    Continue to lay block on top of first course until desired height reached

    Install horizontal reinforcement as courses proceed

  • Install Concrete Block Foundation Walls

    Install vertical reinforcement at significant heights

    Install grout into cells with vertical reinforcement

    Tool joints and clean masonry

    Install waterproofing

  • Rules of Thumb

    Footing shall be below frost line

    Footing width usually 2x height

    Typical size (24 wide x 12 tall)

    Rebar is usually 3 from edge of concrete

    Crawl spaces should have rigid insulation along the interior face of the foundation wall

  • DESIGN MIX

    182.3 kgWATER

    644 kgSAND(Badarpur)

    372 kg10 mm COARSE AGGREGATES

    691 kg20 mm COARSE AGGREGATES

    475 kgCEMENT

    It is a mix which have calculated quantities of Cement, Coarse Aggregates, Fine Aggregates and Water to have required strength of concrete as per IS:456-2000 .

    Grades of Concrete used M20 for Slabs and Beams M25 for Foundations and Retaining Walls M40 for Columns and Shear Walls

    181.6 kgWATER

    630 kgSAND(Badarpur)

    472 kg10 mm COARSE AGGREGATES

    708 kg20 mm COARSE AGGREGATES

    352 kgCEMENT

    DESIGN MIX OF M40 GRADE CONCRETE DESIGN MIX OF M25 GRADE CONCRETE

  • READY MIX CONCRETE

    Ready-mix concrete is a type of concrete that is manufactured in a factory or batching plant, according to a set recipe, and then delivered to a worksite by truck mounted transit mixers

  • 17 FEBMEASUREMENTS AND QUALITY

  • Foundation Components

    Footing

  • FITTING FOUNDATION BOLT

    POURING CONCRETE

    CURINGBACK FILLING

    FOUNDATION BOLTFOR ERECTION OF PEB

    COMPLETED IN FEB

    1

    43

    2

  • Foundation Components

    (to attach wood stud sill plate)

    (to keep water off of foundation wall)

    (separates slab from foundation wall)

    (to keep water off of slab)

    (to keep water off of slab & moisture barrier)(moves water away from building)

    (moves water away from building)

  • Foundation Types

  • Pour Footings

    Construct formwork (if required)

    Install reinforcement (rebar) for footings

    (protrudes above footing to tie-into foundation wall)

    Pour concrete footings

    Smooth / finish surface

  • Pour Slab on Grade

    Install gravel base (to keep water off of slab)

    Install moisture barrier (to keep water off of slab)

    Install reinforcement (welded wire fabric)

    Pour concrete slab

    Finish slab surface

  • CONCURRENTOTHER ACTIVITY IN MARCH

    Text

    ANCILLARYBUILDING FOUNDATION

    EXCAVATION

    FLOOREXCAVATION

    AND PCC

    SITE ACTIVITY APARTFROM

    FOUNDATION WORK

    PLINTH BEAM FOR BOUNDARY WALL

    CLOSINGLOI /PO / VISITS

    AND LIASION

    PEBMANUFACTURERS

    CRANE MANUFACTURER

    MACHINEMANUFACTURER

    ELECTRICAL

  • COULMN CASTING On the raft the column layout is done. Layout for starter. The column ties and link bars are provided as per

    column reinforcement drawings and general specifications.

    Displacement of main bars should be provided with L bar

    The plumb of formwork should be checked. Height of cast should be calculated accurately. Avoid caps as far as possible.

  • LAYOUT , PEDESTAL & STARTER

  • LINKS & TIES

  • PLUMB & FORMWORK, CASTING,CURING

  • PLINTH BEAM WORK CONNECTING ALL FOUNDATIONS FOR WALL WORK TO START

  • RETAINING WALL

    Grade of concrete--- M25.Clear Cover--- 25 mm.

  • COLUMN

    Grade of concrete--- M40.Clear Cover--- 50 mm.

  • SHEAR WALLS

    Clear Cover--- 50 mm.Grade of concrete--- M40.

  • Foundation Bolt work under Completion

  • Excavation Work of Ancillary Building ( Bathrooms/ Service office/ Welding )

  • UG TANK

  • FLOOR FROM GRID 1 TO 23 EXCAVATION AND COMPACTING

  • LLOYD PEB INSPECTION

  • MACHINE INSPECTION

  • CRANE INSPECTION

  • SAFETY EQUIPMENTS

    HELMETCAUTION SIGNALS

    SAFETY BELT

    SAFETY GLOVESSAFETY SHOES

  • SCAFFOLDING

    Scaffolding is a temporary framework used to support people and material in the construction or repair of buildings and other large structures

    The purpose of a working scaffold is to provide a safe place of work with safe access suitable for the work being done.

    Scaffolding used for supporting shuttering of slab is called Staging

  • APRIL

    SITE

    FLOORRUBBLE WORK

    RADIOGRAPGHY

    ANCY BUILDING

    ERECTION

    TRAININGON HEIGHT

    UNLOADING

    GRID 13 TO 23

    GRID1 TO 13

  • CIVIL WORK IN ROGRESS

    IN APR

    ANCILLARYBUILDING

    FOUNDATION

    UG TANK IN

    PROGRESS

    PLINTH BEAM WORK IN PROGRESS

    FLOORCOMPACTNESS

    TEST

    FLOORRUBBLELAYING

    RADIOGRAPGHY WORK START WITH DIGGING AND RUBBLE LAYING

  • PEB WORK STARTS IN APR

    THE FIRST

    COLUMN

    Text

    PEB

    UNLOADING

    & STACKING WITH WOODEN

    BRACKET

    POOJACEREMONY

    FOR SAFETY

    EARLY MORNING WORK

  • COIL SHOP PHASE ONE BEGINS

  • COIL FLOOR

    DIGGING OF FLOORYELLOW SOIL

    PREPARING FIRST LAYER RUBBLE NEXT LAYER

  • ACTIVITY IN MAY

  • APR TO

    MAY

    ERECTION OF COLUMN LIFTING OF RAFTERS

    JOINING RAFTERS AND COLUMN ADDING PURLINE FOR CONSOLADTION

  • MUTUALDISCUSSION

    ON BEST PRACTICES

    WORKING ATHEIGHT

    WITH FALLARRESTOR

    SITE SAFETYAUDIT

    SPECIAL TRAINING CONDUCTED

  • PEB ERECTION WORK

  • Personal Protective Equipments

    BEING USED

  • BY LAST WEEK OF MAYDIVISION OF AREA BETWEEN PEB AND CIVIL WORK

    CIVIL WORK AND HEIGHT PEB WORKDIVIDED BETWEEN TWO ZONES WITH BARRICADING TO PREVENT CROSS MOVEMENT OF WORKERS AND ALSO WORK ON TWO ENDS TO SAVE TIME

    PEB ERECTION FROM GRID 1 TO 13

    PCC WORK IN GRID 13 TO 23

  • CIVIL WORK IN MAY

    Text

    Text

    Text

    M/CFDN

    RADIOGRAPGHY

    WALL

    PCC INFLOOR

    BRICK WORK ON PLINTH

    ANCYBUILDING

    FDNS

    CONCURRENTCIVIL WORK

    IN MAY

    SAND FILLINGIN RADIGRAPGHY PIT

    UG WATER TANK ANCY/ SERVICE OFFICE FOUNDATION

    BRICK WORK ON PLINTH

    PCC ON FLOOR IN GRID 13 TO 23

    PLATE AND PANEL BENDING M/C FDN

  • STATUS IN LAST WEEK OF MAY

    PEB WORK IN FULL SWING ALONG WITH CIVIL WORKAIM WAS TO COMPLETE ROOF AND PCC BEFORE RAINS

  • MULTI TASKING IN JUN

    PEB WORK

    CIVIL WORK ANCILLARY BUILDING

    MACHINE FOUNDATIONS

    STORAGE ROAD/BAY WORK

    COORDINATION FORDRAWINGS AND

    EXECUTION

    CONCURRENTLY COIL SHOP

    EXCAVATION WORK AND FLOOR WORK

    BIDRUM

    ADMIN BUILDING INTERIOR AND IT CABLE LAYING

  • PEB WORK IN JUN

    Text Text

    Text

    Text

  • Ancillary Building Bidrum

    SERVICE OFFICE SLAB Maintenance shed WallWIP

    Welder Plinth WorkToilet Slab

    JUN

  • BIDRUM SHOP FLOOR

    STEEL BINDING FOR RADIOGRAPHY WALL

    SHOT BLASTING PIT WIP -PCC

    PLATE ROLLINGPIT COMLPETED

    PANEL BENDING PIT COMPLETED

    PEMA Machines Foundation PIT

    WIPCNC Machine PIT WIP

  • ROAD WORK IN FRONT OF BI DRUM-WIP

    WBM work

  • ALL 50 FOUNDATION DONE TILL SECOND STAGE LESS ONE

    DUE TO IT CABLE PASSING THROUGH

  • ADMIN BUILDING INTERIOR WIP

  • IT CABLE PIPE LINE WIP

  • JUL

  • MISC ITEMS OF PEB

    Polycarbonate sheet Turbo ventilator

    Walk way /Cage ladder

  • PEB STATUSROOF AND CLADDING 98 % OVER

    ANCILLARY BUIDLING SIDE

    FRONT 5 % LEFT CLADDINGAS CRANE WERE BEING FITTED

    ROAD SIDE

  • CRANE INSTALLATIONS

    PANEL SHOP

    10 T AND 20 T

    BIDRUM30 T AND 20 T

  • ANCILLARY BUILDINGS

    MAINT SECTIONMILE STONE> FLOOR DONE

    WALL IN WIP

    SECOND BATHROOM

    SLAB WIPFIRST

    BATHROOM COMPLETED WALL 10 % LEFT IN WIP

    SERVICE OFFICE SLAB

    WALL AND FLOOR IN WIP

    WELDING SHOP

    MILE STONE> FLOOR COMPLETED

    WALL IN WIP

  • MULTI TASKING PROJECT MANAGEMENT

    MILESTONE>BIDRUM SHOPTWO CRANES FITTED

    FLOOR WORK 25%IN PANEL SHOP WALL COMPLETED

    70%

  • MULTI TASKING PLAN

    HALF BAY OF BIDRUM AND PANEL SHOPMACHINE FOUNDATION

    HALF BAY OF BIDRUM AND PANEL SHOP

    RADIOGRAPGHYSECOND RCC LIFT

    FLOOR IN HALF PORTION OF PANLE SHOP

    CRANE IN HALF PORTION

    OF BIDRUM

  • MACHINE FOUNDATIONS IN WIP

    MILESTONE> FOUR COMPLETEDREST IN LAST STAGES

  • MACHINE FOUNDATIONS

  • COIL SHOP FOUNDATION BOLT WORK AGAINST RAIN DEWATERING

    MILESTONE >PCC FLOORCOMPELETED

    FOUNDATION BOLTWIP IN RAINS

  • AUGUST

  • COMPLETE ROOFING AND CLADDING DONE AND MISC ACCESSORIES UNDER FITMENT

    DRAINAGE PIPE FITTED

  • CAGE LADDER FITTEDTHREE MORE IN WIP

  • VIEW FROM TOP

    TURBO AND RIDGE VENTILATORS FITTED

    TURBO VENTILATOR

    RIDGE VENTILATOR

  • CRANE COMMISSIONING

  • CRANE COMMISSIONING

  • WALL WORK 90 PERCENTCOMPLETED ON SHOP FLOOR

  • FLOOR WORK85 PERCENT COMPLETED

  • MACHINE FOUNDATIONCLOSING ON SHOP FLOOR

  • WINDOWS UNDER FITMENTIN SHOP FLOOR

  • CONCURRENT WORK ALSO ON SLAB STAGES IN OFFICE BUILDING

  • IMPORTANT COMPONENTS

    Key in column

    Water bar

    Binding materials

    Expansion joint

  • KEY IN COLUMN

    since the height of column is very large, hence it is not possible to cast the column at one time, to cast the column later the key is made at the junction so that the proper bond between the old concrete and new concrete is formed.

  • KEY IN COLUMN

  • EXPANSION JOINT Since concrete is subjected to volume change. Provision

    must be made to cater for the volume change by way of joint to relieve the stresses produced.

    Expansion joint is function of length Buildings longer than 45 m are generally provided with

    one or more expansion joints. Material used as expansion joint material is armour

    board whose thickness is 25 mm.

  • EXPANSION JOINT

    Expansion joint material, size is 25 mm

    Expansion joint in building

  • WATER BAR

    Water bar is provided in the retaining wall o that the moisture cant move from the soil to the joint. Water bar is basically provided at the constructions joints of retaining wall of two different towers

  • WATER BAR

  • BINDING MATERIALS

    Since the thermal expansion of concrete is different from that of masonry. The interface between the concrete and the masonry is liable to crack. To avoid this crack the chicken wire mesh is used to avoid the crack and also provides the better grip for Masonrywith concrete.

    Similarly when the drainage pipes are laid along with the outer wall then again the connection between the pipe and the wall hasdifferent coefficient of temperature change hence they are joint to the concrete by lead keys.

    In the toilets and kitchen sunken portion the joints in any caseare packed by water proof and non shrinkable material.

  • BINDING MATERIALS

    Chicken wire mesh between brick masonry and concrete

    Connection of pipes with concrete

    Chicken wire mesh in conduits through concrete

  • WATER PROOFING Water proofing has remained as an unsolved complex

    problem

    Use of plasticizers, super plasticizers, air-entraining agents helps in reducing the permeability of concrete by reducing the requirement of mixing water, hence can be also be regarded as waterproof material.

    Some of approved water-proofing compound by the companyare:- pidilite, cico, fosroe, baushimine, unitile.

    Water-proofing cement paint:- super snoweem

  • WATER PROOFING

    Water proofing in sunken portion of kitchen and bathroom

    WP in sunken portion at ground level

    WP in retaining wall

  • WATER PROOFING IN GARDEN AREA

    For water proofing in garden area the soil is first leveled and then rammed to achieve the maximum density

    The PCC is then laid down mixed with tape Crete (a water proofing compound)

    After PCC the plaster of fibrous material is done. the bituminous sheets are laid by heating it with the welder. On those

    sheets the drainage pipes are laid down with suitable slope and these pipes are covered with geo-fabric sheets.

    Again the plaster is done. On the plaster the 40 mm aggregates are laid. On the aggregate the geo-fabric sheets are laid down on which the sand is

    placed & on the sand the soil ,along with fertilizers, is placed on which the gardening is done for the non tower area.

  • WATER PROOFING IN GARDEN AREA

    Sandy soil PCC mixed with tape

    Crete (water proof compound)

    Texas (bitumen) sheet

    Drainage pipe 40 mm aggregate Geo-fabric sheet Sand

  • BEAMS AND SLABGrade of concrete--- M 20.

    Clear Cover--- 25 mm for BeamsClear Cover--- 20 mm for Slab

  • RADIOGRAPGHY 5 TH LIFT RCC

  • ELECTRIC CABLE TRAYS ELECTRIC CABLE LAYING

  • ARRIVAL OF MACHINES

  • COIL SHOP AREAD2 FOUNDATION BOLT WORK UNDER WIP

    AMDIST RAIN

  • D1 & D2 FOUNDATION BOLT WORK UNDER WIPAMDIST RAIN

    TOTAL 14 LAST STAGE FOUNDATION DONE

    26 FOUNDATION LEFT

  • MACHINE INSTALLATIONS AS PER PLANT LAY OUT

    IN SEPT AND OCT AND HANDED OVER TO

    PRODUCTION TEAM FOR FIRST PRODUCT

  • Fixed product layoutAdvantages Limitations

    Reduced material moves Highly flexible Job enrichment Promotes pride & quality Responsibility

    Personel-equipment moves Equipment duplicates Greater skill Close control& coordination Increased space & greater

    work-in-process

  • Product LayoutAdvantages Limitations

    Smooth, simple, direct flow Small work-in-process inv. Short production time/unit Reduced material handling Less skill Easy production control

    Line stoppage Product design changes Slowest station paces the line General supervision High equipment investment

  • Product-Oriented Layout

    BeltConveyor

    Operations

  • A

    Precedence Diagram

    Draw precedence graph (times in seconds)

    C

    FD

    B

    E

    H

    G

    I J20

    515

    125 10

    8

    3

    7

    12

  • Cycle Time

    The more units you want to produce per hour, the less time a part can spend at each station.

    Cycle time = time spent at each spot

    C = 800 min / 32 = 25 min

    CT =Production Time in each day

    Required output per day (in units)

  • Number of Workstations

    Given required cycle time, find out the theoretical minimum number of stations

    Nt = 97 / 25 = 3.88 = 4 (must round up)

    Nt =Sum of task times (T)

    Cycle Time (C)

  • Assignments

    Assign tasks by choosing tasks:with largest number of following tasksOR by longest time to complete

    Break ties by using the other rule

  • Number of Following TasksNodes # after

    C 6D 5A 4

    B,E,F 3G,H 2

    I 1

    Choose C first, then, if possible,add D to it, then A, if possible.

  • A

    Precedence Diagram

    Draw precedence graph (times in seconds)

    C

    FD

    B

    E

    H

    G

    I J20

    515

    125 10

    8

    3

    7

    12

  • Number of Following TasksNodes # after

    A 4B,E,F 3G,H 2

    I 1

    A could not be added to firststation, so a new station must becreated with A.

    B, E, F all have 3 stations after,so use tiebreaker rule: time.B = 5E = 8F = 3 Use E, then B, then F.

  • Group LayoutAdvantages Limitations

    By grouping, higher machine utilizations

    Smoother flow lines and shorter travel distances

    Team spirit and job enlargement

    Greater labor skills for team Balancing individual cells Unbalanced flow may result in

    work-in-process

  • Process LayoutAdvantages Limitations

    Increased machine utilization General purpose equipment Highly flexible Diversity of tasks

    Increased material handling Complicated production

    control Increased work-in-process Longer production lines Higher skills required

  • Plant layout procedure

    1. Procure the basic data.2. Analyze the basic data.3. Design the productive process.4. Plan the material flow pattern.5. Consider the general material handling plan.6. Calculate equipment requirements.7. Plan individual workstations.8. Select specific material handling equipment.9. Coordinate groups of related operations.10. Design activity interrelationships.11. Determine storage requirements.12. Plan service and auxiliary activities.13. Determine space requirements.14. Allocate activities to total space.15. Consider building types.16. Construct master layout.17. Evaluate, adjust, and check the layout with the appropriate persons.18. Obtain approvals.19. Install the layout.20. Follow up on implementation of the layout.

  • ACTIVITY

    RELATIONSHIP

    CHART

  • Process-Oriented LayoutFloor Plan

    Office

    Tool Room

    Drill Presses

    Table Saws

    1995 Corel Corp.

    1995 Corel Corp.

  • Process Layout+ Allows specialization - focus on one skill+ Allows economies of scale - worker can

    watch several machines at once+ High level of product flexibility-- Encourages large lot sizes-- Difficult to incorporate into JIT-- Makes cross-training difficult

  • Product-Oriented Layout

    Facility organized around product Design minimizes line imbalance

    Delay between work stations Types: Fabrication line; assembly line Examples

    Auto assembly line Brewery Paper manufacturing.

  • Cellular Layout (Work Cells) Special case of process-oriented layout Consists of different machines brought

    together to make a product May be temporary or permanent Example: Assembly line set up to produce

    3000 identical parts in a job shop

  • Work Cell Floor Plan

    Office

    Tool RoomWork Cell

    Saws Drills

  • Work Cell Advantages

    Reduces:InventoryFloor spaceDirect labor costs

    Increases:Equipment

    utilizationEmployee participationQuality

  • Work Cell Layout+ Facilitates cross-training+ Can easily adjust production volumes+ Easy to incorporate into JIT-- Requires higher volumes to justify-- May require more capital for equipment

  • Process-Oriented ExampleYou work in facilities engineering. You want to find the cost of this layout. The cost of moving 1 loadbetween adjacent dept. is $1. The cost between nonadjacent dept. is $2.

    60 ft.

    40 ft.Dept. 1 Dept. 2 Dept. 3

    Dept. 4 Dept. 5 Dept. 6

    There are 6! or 720 possibilities! Clearly, we cant look at them all.

  • 50 100 0 0 20

    30 50 10 0

    20 0 100

    50 0

    0

    From-to-Matrix

    5

    1 2 3 4 5 6Department

    Dept.

    1

    234

    6

    Number of Trips

  • 20

    100

    50 30

    50

    50

    10

    20

    Schematic Diagram & CostDept. Dept.Cost

    1 3 $200

    1 2 $501 6 $404 2 $504 3 $404 5 $502 5 $102 3 $303 6 $

    Total Cost $570

    1 2 3

    64 5100

  • 20

    30

    50 100

    50

    50

    10

    20

    Schematic Diagram & CostDept. Dept.Cost

    1 2 $501 3 $

    1001 6 $204 2 $504 3 $404 5 $502 5 $102 3 $603 6 $

    Total Cost $480

    2 1 3

    64 5

    100

  • Line Balancing

    Situation: Assembly-line production. Many tasks must be performed, and the

    sequence is flexible Parts at each station same time Tasks take different amounts of time How to give everyone enough, but not too

    much work for the limited time.

  • MACHINE INSTALLATIONSPRODUCTION SET UP

  • Manufacturing Industry Transformation Operations

    Machine Processing Assembly

    Adding value* Other Operations

    Material handlingInspection and testingCoordination and control

    Transformation ProcessRaw

    MaterialPart or Product

    PowerTools

    MachinesLabour

    Scrap or Waste

  • Classification of manufacturing processes

  • Processing Operations Shaping operations

    Solidification processes Particulate processing Deformation processes Material removal processes

    Property-enhancing operations (heat treatments)

    Surface processing operations Cleaning and surface treatments Coating and thin-film deposition

  • Assembly Operations Joining processes

    Welding Brazing and soldering Adhesive bonding

    Mechanical assembly Threaded fasteners (e.g., bolts and nuts,

    screws) Rivets Interference fits (e.g., press fitting, shrink

    fits) Other

  • Material Handling Material transport

    Vehicles, e.g., forklift trucks, AGVs, monorails

    Conveyors Hoists and cranes

    Storage systems Unitizing equipment Automatic identification and data

    capture Bar codes

  • Time Spent in Material Handling

  • Inspection and TestingInspection conformance to design

    specifications Inspection for variables - measuring Inspection of attributes gauging

    Testing observing the product (or part, material, subassembly) during operation

  • Coordination and Control Regulation of the individual processing

    and assembly operations Process control Quality control

    Management of plant level activities Production planning and control Quality control

  • Manufacturing Capability Technological processing capability - the

    available set of manufacturing processes Physical size and weight of product Production capacity (plant capacity) -

    production quantity that can be made in a given time

  • Lean Production

    Operating the factory with the minimum possible resources and yet maximizing the amount of work accomplished

    Utilisation of Resources - workers, equipment, time, space, materials

    Minimising time Maximising quality (accuracy) Minimising cost

  • Programs Associated with Lean Production

    Just-in-time delivery of parts Worker involvement Continuous improvement Reduced setup times Stop the process when something is

    wrong Error prevention Total productive maintenance

  • 12 DEC 2012SAVLI NEW PLANTS PROJECT ENDS

    AND PRODUCTION BEGINS

  • THANKS