contractor's claims under the riai form of contract - a

22
Technological University Dublin Technological University Dublin ARROW@TU Dublin ARROW@TU Dublin Other Resources School of Surveying and Construction Management 2020-03-04 Contractor's Claims Under the RIAI Form of Contract - A Lecture Contractor's Claims Under the RIAI Form of Contract - A Lecture Presentation Presentation Tony Cunningham Technological University Dublin, [email protected] Follow this and additional works at: https://arrow.tudublin.ie/beschreoth Part of the Architectural Engineering Commons Recommended Citation Recommended Citation Cunningham, T. (2020) Contractor's Claims under the RIAI Form of Contract - A Lecture Presentation, Technological University Dublin. This Presentation is brought to you for free and open access by the School of Surveying and Construction Management at ARROW@TU Dublin. It has been accepted for inclusion in Other Resources by an authorized administrator of ARROW@TU Dublin. For more information, please contact [email protected], [email protected]. This work is licensed under a Creative Commons Attribution-Noncommercial-Share Alike 4.0 License

Upload: others

Post on 18-Apr-2022

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Contractor's Claims Under the RIAI Form of Contract - A

Technological University Dublin Technological University Dublin

ARROW@TU Dublin ARROW@TU Dublin

Other Resources School of Surveying and Construction Management

2020-03-04

Contractor's Claims Under the RIAI Form of Contract - A Lecture Contractor's Claims Under the RIAI Form of Contract - A Lecture

Presentation Presentation

Tony Cunningham Technological University Dublin, [email protected]

Follow this and additional works at: https://arrow.tudublin.ie/beschreoth

Part of the Architectural Engineering Commons

Recommended Citation Recommended Citation Cunningham, T. (2020) Contractor's Claims under the RIAI Form of Contract - A Lecture Presentation, Technological University Dublin.

This Presentation is brought to you for free and open access by the School of Surveying and Construction Management at ARROW@TU Dublin. It has been accepted for inclusion in Other Resources by an authorized administrator of ARROW@TU Dublin. For more information, please contact [email protected], [email protected].

This work is licensed under a Creative Commons Attribution-Noncommercial-Share Alike 4.0 License

Page 2: Contractor's Claims Under the RIAI Form of Contract - A

1

Claims for additional time and

money

Page 3: Contractor's Claims Under the RIAI Form of Contract - A

2

Page 4: Contractor's Claims Under the RIAI Form of Contract - A

3

Upon the happening of any such event

causing delay the Contractor shall

immediately give notice in writing to the

Architect.

The Contractor shall nevertheless use

constantly the Contractor’s best efforts to

prevent delays and to proceed with the

Works.

The Architect shall as soon as possible,

make a fair and reasonable extension of

time for completion of the Works

The Architect will consider the conduct of the

Contractor in terms of negligence, omission or

default which caused the loss or damage to

the Works or ancillary items

Page 5: Contractor's Claims Under the RIAI Form of Contract - A

4

Clause 28 - Deferred Possession

“If the “Date for Possession” is deferred by

the Employer then the Contractor shall

be entitled to receive from the Employer

compensation for any loss incurred due

to dislocation of the Contractor’s

organisation and any time lost from this

cause shall be ascertained and certified by

the Architect.”

Clause 29(b) - Employer Default

“If any act or default of the Employer delays

progress of the Works then the Contractor

shall within five working days of the act

or default give notice in writing to the

Architect to this effect and any time lost

from this cause shall be ascertained and

certified by the Architect and the Employer

shall pay or allow to the Contractor

such damages as the Contractor shall

have incurred by the delay.”

Page 6: Contractor's Claims Under the RIAI Form of Contract - A

5

Standard forms of contract typically

contain detailed provisions under

which the Contractor can claim

against the Employer for loss and

expense suffered as a result of

disruption due to certain specified

causes.

The vast majority of contractual

provisions, which compel an

Employer to pay compensation to

the Contractor, are based on causes

of disruption for which the Employer

or the Employer’s agents may

reasonably be blamed.

Additional costs which arise from the

Employer’s or the Employer’s agents

actions or failings.

Page 7: Contractor's Claims Under the RIAI Form of Contract - A

6

Employer Default Architect’s Instructions Late Instructions

Delays by direct employeesLate Possession

The contractor should include the extra

cost claimed in the next payment progress

application

Page 8: Contractor's Claims Under the RIAI Form of Contract - A

7

The claim must be properly

documented

Site records must be kept for the time

the relevant work was executed

Must link cause to effect

Full Details

Proper records.

Master programme

Dated photos or videos

Site diaries, daily labour, plant

and staffing levels.

Drawing register

Correspondence

Minutes

Notices

Recorded measurements

Adequate Notice.

Contemporaneous records,

records, records

Page 9: Contractor's Claims Under the RIAI Form of Contract - A

8

Loss and expense claims are based on

delay in completion and also because

the regular progress of the works have

been disrupted.

Evaluation is considered under

prolongation and disruption

'Loss' would relate normally to

preliminaries, head office overheads,

on costs and profit margins which

the Contractor would have assumed

to be protected under the contract

provisions, and 'expense' would

relate to an unexpected item in

performing a variation. (Keane 2001)

The Contractor’s mismanagement of the

delay is nor recoverable

Page 10: Contractor's Claims Under the RIAI Form of Contract - A

9

Extensions of time for Employer’s and

his/her agents’ default arereimbursable

•Architects instructions, late instructions, deferred possession, delay by direct employees, and Employer default.

Critical path activities are delayed.

Page 11: Contractor's Claims Under the RIAI Form of Contract - A

10

Page 12: Contractor's Claims Under the RIAI Form of Contract - A

11

Claims evaluation requires

• a sound knowledge and experience

of building;

• careful study of contract conditions

and an understanding of their

application,

• knowledge of the relevant case law.

This may be difficult because it

involves an element of blame against

either the Employer or the consultants

for causing the additional claimed

costs.

• Aggressive / defensive stances are

possible.

Page 14: Contractor's Claims Under the RIAI Form of Contract - A

13

• Supervision, co-ordination, site

administration

• Plant, tools and vehicles

• Scaffolding

• Security, hoardings, protecting the public

• Transport for work people

• Protecting the works

• Water for the works.

• Temporary lighting and power.

• Temporary roads, hard-standings,

• Site accommodation and welfare facilities

• Site storage areas

• Temporary telephones

• Health and safety provisions

• Disbursements employment of operatives

• Maintenance of public and private roads

• Removing rubbish, waste management

• Cleaning the works on completion,

• Temporary fencing and the like

Page 15: Contractor's Claims Under the RIAI Form of Contract - A

14

The most accurate way of estimating the likely additional cost a contractor might bear is to obtain a priced preliminaries budget against which the delay effects may be evaluated.

The Contractor is entitled to the Time-related charges impacted by the Delay

•Additional salaries, hire costs, utilities, attendance and standing charges.

Page 16: Contractor's Claims Under the RIAI Form of Contract - A

15

Acceleration costs if instructed by theArchitect

• additional labour costs overtime, shiftwork, weekend working to make up losttime; These result in uneconomic uselabour and/or plant.

Time is money - overtime is more

money

Page 17: Contractor's Claims Under the RIAI Form of Contract - A

16

No set rules. QS would identify the matter

which caused the disruption, and how it

affected the work and examine any

correspondence related to it.

Compare a ‘normal’ period to a disrupted

period if possible.

Total cost of the disruption = the additional

hours of labour and plant @ the appropriate

‘all-in’ hourly rates.

Page 18: Contractor's Claims Under the RIAI Form of Contract - A

17

Can recover additional general office overheads

for the delay period.

• Contract is making a smaller contribution to

these business than it should.

• The organisation is being tied up for a

longer period, preventing it from earning

overhead on other projects

Hudson’s Formula: Head office overheads and

profit are expressed as a percentage of the

contract sum per day and are applied pro-rata

to the period of the delay.

Page 19: Contractor's Claims Under the RIAI Form of Contract - A

18

Same rate of interest as the Contractor paid

(provided it is not unreasonable).

Rates “at which (contractors) in general borrow

money.” If Contractor pays well above or below

market rates Tate & Lyle v GLC (1983)

Where the Contractor provides self-finance the

appropriate rate of interest is that earned by

money on deposit.

Page 20: Contractor's Claims Under the RIAI Form of Contract - A

19

Keane (2001)

“The various cases have established; that

interest would be payable on a loss and

expense claim if payment were delayed (FG

Minter Ltd v Welsh TSO [1981] 13 BLR 1);

that the phrase 'loss and expense' can be

equated to damages at common law (Wraight

Ltd v PH&T (Holdings) Ltd [1968] 13 BLR

26); that an allowance can be included for

office overheads (Tate & Lyle Food and

Distribution Ltd v GLC [1982] 2 AC 509),and

finally, that loss of profit would be a

permissible item for loss and expense

claims, but only if the Contractor could

prove that he could have employed his

resources profitably elsewhere (Peak

Construction v McKinney Foundations [1970]

1 BLR 111).”

Page 21: Contractor's Claims Under the RIAI Form of Contract - A

20

Remember

Delays are seldom one party’s fault.

Frequently the shortcomings of the

consultants are compounded by the

mismanagement of the Contractor.

Accept a reasonable offer – a lean

compromise is better than a fat lawsuit.

Page 22: Contractor's Claims Under the RIAI Form of Contract - A

21

Ashworth, A. Hogg, K. and Higgs, C. (2013) Willis’s Practice and

Procedure for the Quantity Surveyor, 13th ed. Wiley Blackwell,

Chichester West Sussex.

Hughes, W. Champion, R. and Murdoch, J. (2015) Construction

Contracts: Law and Management, 5th ed. Routledge, Abindon

Oxon.

Recommended Reading