as3959 marysville pto
TRANSCRIPT
-
8/6/2019 AS3959 Marysville PTO
1/21
New Bushfire Construction Regulations
David Kearsley
Senior Technical Advisor, Technical and Research Services
February 2009
Overview
Regulatory Framework
Introduction of AS 3959 - 2009
Construction Requirements
BAL Assessments
Worked Example - BAL Assessment
Attached Structure and Shielding
AS 1530.8 Testing Private Bushfire Shelters
Guidance Information
Regulatory Framework and Background
-
8/6/2019 AS3959 Marysville PTO
2/21
Building Legislation Hierarchy
STATE & TERRITORY BUILDINGACTS
STATE & TERRITORY BUILDINGREGULATIONS
TECHNICALSTANDARDS
ADMINISTRATIVE MATTERS
AdministrationAppealsRegistrationsRefurbishmentsBuilding standard
Building Code of Australia
Takes effect 1 May each year
BCA is the communitys minimum standard for new buildingwork
Referenced in State & Territory building law
Developed by Australian Building Codes Board (ABCB)
Amended annually
Not best practice
To overcome market failure
Solutions must be cost effective
Building Code of Australia (BCA)
Building Solutions
Performance Requirement
Functional Statement
Objective
Alternative SolutionDTS Provisions
Guidance
Mandatory
Methods ofachievingcompliance
Documentary Evidence
Verification Method
Expert Judgement
Comparative Analysis
Prescriptivemeasures
Assessmentmethods
-
8/6/2019 AS3959 Marysville PTO
3/21
AS 3959 2009 Construction in BushfireProne Areas
History of AS3959
Ash Wednesday 1983
First Edition 1991
Second Edition 1999 (current in BCA) - 2 levels of construction
Amendment No. 1 2000 (Level 3 construction)
Amendment No. 22001 (Fire retarded-treated timber)
Third Edition (2009) under revision
Interim Standard for Victoria February 2009
Fast track publication 11 March 2009
-
8/6/2019 AS3959 Marysville PTO
4/21
Enacted in Victorian buildinglegislation 11 March 2009
Applies to all new residentialbuildings and includes a newsystem of Bushfire AttackLevels, from BAL-Low to BAL-FZ
Does not apply to existinghomes or private bushfireshelters (bunkers)
Will apply throughout Australiafrom May 2010
Australian Standard AS3959-2009
AS 3959 2009 Design Objectives
A structure should be able to withstand ember attack prior tothe arrival of the fire front with minor levels of assistance fromoccupants
The structure should be able to provide a safe refuge whilstthe fire front passes
Provide the building with a level of protection while the frontpasses
Any residual burning of elements of construction after the front
has passed should be capable of being extinguished easily byresidents once external conditions are tenable
These Measures cannot guarantee building survival due to theunpredictable nature of fire, and difficulties associated withextreme weather conditions and protecting a typical house (forexample, window breakage, falling trees, impact of debris)
Structure of AS3959-2009
Preface
Foreword
Scope
Objectives
Disclaimer
Assessment (Section 2)
Construction (Sections 3 to 9)
Appendices Worked example, Assessment Method 2 etc
-
8/6/2019 AS3959 Marysville PTO
5/21
Structure of AS3959-2009
General (Section 3)
Low (Section 4) no requirements
BAL 12.5 (Section 5)
BAL 19 (Section 6)
BAL 29 (Section 7)
BAL 40 (Section 8) BAL FZ (Section 9)
Comparison of Structure of AS3959-2009
Bushfire Attack
Level
Radiant heat Exposure
AS 3959- 2009AS 3959-1999
Low Insignificant Insignificant
12.5 0 to 12.5kW/m2 Level 1
19 12.5 to 19 kW/m2
29 19 to 29 kW/m2
40 29 to 40 kW/m2 Level 3
FZ40 kW/m2 plus
(flame contact)Silent
Improvements to AS3959-2009
1. Increased number of construction levels (6) based on heat fluxexposure thresholds defined as Bushfire Attack Levels (BAL)
2. Two options for determining BAL
1. Simple step by step approach with tables or
2. Detailed calculation procedure (compatible with fire safetyengineering approaches)
3. Both methods account for climate, slope of ground andvegetation variations in States and Territories
3. The slope of ground definition has been clearly specified
4. Improved formatting / clarity5. Construction sections have been reorganised to group specific
construction requirements by Bushfire Attack Levels
-
8/6/2019 AS3959 Marysville PTO
6/21
Improvements to AS3959-2009 (Cont)
6. Construction requirements revised based on defined exposurelevels (BALs) - measurable - allowing prescribed solutions tohave consistent performance
7. Nomination of test methods AS 1530.8
1. Allows innovative and proprietary products to be evaluatedagainst test methods AS 1530.8 removing major barrier toinnovation
8. Operational specification for shutters
9. Concessions for non-exposed facades are included.
10.Attached structures, such as garages, have been included.
AS 3959 - 2009 BAL Assessment
Flow Chart provided in Handouts
Identifies the BAL level andassociated construction sections
-
8/6/2019 AS3959 Marysville PTO
7/21
BAL Assessment Simplified Method
Step Clause Procedure
Step 1 2.3Determine the relevant Fire Danger Index (FDI) Table2.1
Step 2 2.4Determine the vegetation classification type(s) - Table 2.3and Figure 2.3
Step 3 2.5Determine the distance of the site from the classifiedvegetation site(s) Figure 2.1
Step 4 2.6Determine the effective slope(s) under the classifiedvegetation types(s) Figure 2.2
Step 5 2.7Determine the Bushfire Attack Level (BAL) from theappropriate table Tables 2.4.1 to 2.4.4 & Table 2.5
Excluded Vegetation
Vegetation of any type which is more than 100 m from the site.
Single areas of vegetation less than 1 ha in area, not within 100 m ofother areas of vegetation being classified.
Multiple areas of vegetation less than 0.25 ha in area and not within20 m of the site, or each other.
Strips of vegetation less than 20 m in width regardless of length andnot within 20 m of the site or each other, or other areas of vegetationbeing classified.
Non-vegetated areas including waterways, roads, footpaths, buildingsand rocky outcrops.
Low threat vegetation including managed grassland, maintainedlawns, golf courses, maintained public reserves and parklands,botanical gardens, vineyards, orchards, cultivated ornamentalgardens, commercial nurseries, nature strips and wind breaks.
BAL Assessment Worked Example
-
8/6/2019 AS3959 Marysville PTO
8/21
Determine the distance to the classified vegetation
Determine the slope under the classified vegetation
Slope - refers to the slope under the classified vegetation in relation tothe building not the slope between the vegetation and the building
Determine the classified vegetation
-
8/6/2019 AS3959 Marysville PTO
9/21
1. Relevant FDI..802. Slope >0 to 53. Vegetation Class .Forrest4. Building Location ..30m
BAL Assessment - Detailed Method
Determine the relevant FDI in accordance with Clause B2.
Determine the predominant vegetation classification, fuel loads andvegetation height in accordance with Clause B3.
Determine the effective slope of the predominant vegetation classification inaccordance with Clause B4.
Determine the site slope of the building site in accordance with Clause B5.
Determine the distance of the site from classified vegetation in accordancewith Clause B6.
Determine the elevation of receiverin accordance with Clause B7.
Determine flame width in accordance with Clause B8.
Calculate the flame length in accordance with Clause B9.
Calculate the radiant heat flux in accordance with Clause B10.
Determine the Category of Bushfire Attack (BAL) in accordance ClauseB11.
ANY QUESTIONS
-
8/6/2019 AS3959 Marysville PTO
10/21
AS 3959 Construction
BAL and Corresponding Construction Sections
BushfireAttack Level (BAL)
Classified Vegetationwithin 100m of the site &
Heat flux exposurethresholds
Description of predicted bushfire attackand levels of exposure
ConstructionSection
BALLOW See Clause 2.4.2There is insufficient risk to warrant specificconstruction requirements.
4
BAL 12.5 12.5 kW/m2 Ember attack 3 and 5
BAL19 >12.5 kW/m219 kW/m2Increasing levels of ember attack andburning debris ignited by windborneembers together with increasing heat flux.
3 and 6
BAL29 >19 kW/m229 kW/m2Increasing levels of ember attack andburning debris ignited by windborneembers together with increasing heat flux.
3 and 7
BAL40 >29 kW/m240 kW/m2
Increasing levels of ember attack andburning debris ignited by windborneembers together with increasing heat fluxwith the increased likelihood of exposure toflames.
3 and 8
BALFZ > 40 kW/m2Direct exposure to flames from fire front inaddition to heat flux and ember attack.
3 and 9
1. Sub-floor supports
2. Floors
3. External walls
4. Glazing & doors
6. Verandas,decks, steps,ramps & landings
7. Water & gas pipes
5. Roofs
Roofs includeveranda and attachedcarport roofs,penetrations, eaves,fascias & gables; andgutters & downpipes
-
8/6/2019 AS3959 Marysville PTO
11/21
-
8/6/2019 AS3959 Marysville PTO
12/21
Attached Structures
Where any part of a garage, carport, veranda or similar roofedstructure is attached to, or shares a common roof space with abuilding required to comply with this Standard, the entiregarage, carport, veranda or similar roofed structure shall
comply with the construction requirements of this Standard, as
applicable to the subject building, or
Attached Structures
Be separated a wall that extends to the underside of a non-combustible roof covering; and
Has an FRL of not less than 60/60/60 for load bearing walls and -/60/60 for non-load bearing walls when tested from the attachedstructure side; or
Is of masonry, earth wall or masonry-veneer construction with themasonry leaf being not less than 90 mm in thickness; and
Has openings protected as follows
Doorways by /60/30 self closing fire doors. Windows by /60/ fire windows permanently fixed in the closed
position.
Other openings by construction with an FRL not less than /60/.
Control and construction joints, sub-floor vents, weepholes andpenetrations for pipes and conduits need not comply with the above.
Shielding
The construction requirements for the next lower Bushfire Attack
Level (BAL) than determined for the site may be applied to an
elevation of the building where the elevation is not exposed to the
source of bushfire attack.
An elevation is deemed not to be exposed to the source of bushfire
attack if all of the straight lines between that elevation and the source
of bushfire attack are obstructed by another part of the building. This
is shown in Figure 3.1.
The construction requirements for a shielded elevation must not be
less than that required for BAL12.5, except where the exposedelevations have been determined as BALLOW.
-
8/6/2019 AS3959 Marysville PTO
13/21
Testing to AS1530.8
AS1530.8 Testing
AS 1530.8.1 & 2 - Methods for full scale fire tests on building
materials, components and structures
Tests on elements of construction for buildings exposed to
radiant heat and small flaming
Test elements such as
Windows, Doors, Service Penetrations, Eaves/Gutter Details,Roofs, Verandas and Decks, Exposed Structural Elements (eg
Posts/Columns), Sub Floor Spaces, and Roof lights
AS1530.8 Testing
The outcome of the testing will be a rating similar to:
AS 1530.8.1 - BAL 12, BAL 19, BAL 29, BAL 40
AS 1530.8.2 - BAL FZ
Where the number refers to the peak radiant heat flux appliedduring a test and FZ refers to a specimen exposed to thestandard heating regime of AS 1530.4
A BAL19 system would have satisfied the performance criteriawhen subjected to an AS 1530.8.1 test at a peak heat flux of19kW/m2
A BAL FZ system would have satisfied the performance criteriawhen subjected to a test in accordance with AS 1530.8.2.
-
8/6/2019 AS3959 Marysville PTO
14/21
AS1530.8 Testing
0
10
20
30
40
0 2.5000 5.0000 7.5000 10.0000
Draft AS 1530.8.1 Idealised Exposure Conditions
Rad
iantHeat-kW/m2
Time - s
BAL 40BAL 29BAL 19BAL 12
AS1530.8 Testing
-
8/6/2019 AS3959 Marysville PTO
15/21
ANY QUESTIONS
-
8/6/2019 AS3959 Marysville PTO
16/21
Private Bushfire Shelters
Government monitoring activity in new market
Dubious products on market
Sales increase dramatically after acknowledgment ofpotential danger of upcoming fire season
ACCC takes action against some manufacturers foradvertising that products are Standards compliant
Royal Commission urged action Building Amendment (Private Bushfire Shelter
Construction) Further Interim Regulations 2009introduced November 11th 2009
Building Amendment (Private Bushfire SheltersConstruction) Interim Regulations 2009
%of
buildingssurviving
Bushfire Severity
AS 3959-2009Private Bushfire Shelter
BAL 40 & FZ& Beyond ?
BAL-Low-19? BAL-29?
What Are the regulations trying to achieve?
-
8/6/2019 AS3959 Marysville PTO
17/21
What should the design of a Private Bushfire Shelter achieve ?
Protection from fireSafe access and
egress
Space forall essential
items
A senseof safetyand well-
being
Adequateair supply
Adequatefacilities
A way of knowingwhats going on
outside
A means ofidentification
Amends both the Regulations and the BCA
A new BCA classification (Class 10c)
New Performance Requirement P2.3.4A
NO Deemed-to-Satisfy provision (or Australian Standard)
Building Amendment (Private Bushfire SheltersConstruction) Interim Regulations 2009
New definit ion
Private bushfire shelter means a building or part of a building that
may, as a last resort, provide shelter for people from the immediate
life threatening effects of a bushfire,
New classification
Class 10c a building being a private bushfire shelter.
The period of the bushfire event is the reasonably estimated period of
time beginning from entry into the building by occupants prior to the
fire front arriving and concluding when the fire front has passed and
the external environmental conditions are no longer untenable.
Building Amendment (Private Bushfire SheltersConstruction) Interim Regulations 2009
-
8/6/2019 AS3959 Marysville PTO
18/21
New Performance Requirement P2.3.4A Private bushfire shelter
The design and construction of a Class 10c building associatedwith a Class 1 building provided for use during the event of abushfire must take into account the requirements necessary tomake reasonable provision for the amenity of the Class 10cbuilding and the safety and health of people using that building
during the period of a bushfire event.
Building Amendment (Private Bushfire SheltersConstruction) Interim Regulations 2009
The design and construction of a Private Bushfire Shelter(Class 10c) must provide for
1. safe access to the building; and
2. appropriate sanitary and other facilities; and
3. a means of determining the external environmentalconditions; and
4. safe egress from the building; and
5. a means of identification of the location of the building for thepurpose of rescue.
Building Amendment (Private Bushfire SheltersConstruction) Interim Regulations 2009
The design and construction must have regard to
1. the number of occupants likely to use the building; and
2. actions to which the building may be subjected; and
3. the effects of nearby permanent features such as topography,vegetation and other buildings; and
4. the potential external fire intensity; and
5. the prevention of conditions within the building that areuntenable.
Building Amendment (Private Bushfire SheltersConstruction) Interim Regulations 2009
-
8/6/2019 AS3959 Marysville PTO
19/21
Regulation limits the circumstances in which a buildingsurveyor can issue a permit to that which relies on:
A Building Regulatory Advisory Committee (BRAC) accreditedproduct, or
A Building Appeals Board (BAB) determination under s160A ofthe Act, or
A Certificate of Compliance from fire safety engineer who didnot do the design
Building Amendment (Private Bushfire SheltersConstruction) Interim Regulations 2009
Guidance Information
Owner-builder
Certificate of Consent (from BPB)
Insurance (for works > $12k onsale)
Registration required forsub-contracted works > $5k
Training courses available
Need time, expertise &experience!
-
8/6/2019 AS3959 Marysville PTO
20/21
Registered Builder
Registration number (DB-)
Insurance (on work > $12k)
Contract (on work > $5k)
Continuing education (CPD)
Dispute resolution (BACV)
Memberships (HIA, MBA)
get 3 quotes & referee details.
For more information:
www.buildingcommission.com.au /publications
Available from SAI Global
http://infostore.saiglobal.com/store/default.aspx
Currently $97.30
HB 330 - Living in BushfireProne Area also available
T | 131 242 F | 1300 65 49 49
Unit 3 18 Salmon Street
Port Melbourne
Australian Standard AS3959-2009
-
8/6/2019 AS3959 Marysville PTO
21/21
Contact Us
Building CommissionGoods Shed North733 Bourke StDocklands VIC 3008
P.O Box 536Melbourne VIC 3001
T | 1300 815 127
ANY QUESTIONS