appendix i - maintenence and inspection

Upload: clay-stevens

Post on 10-Apr-2018

226 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 Appendix I - Maintenence and Inspection

    1/13

    Changing Lives One Bridge at a Time

    Volume 3: Suspended Pedestrian Bridg

    Part 4: Maintenance and Inspectio

    First Editon 20

  • 8/8/2019 Appendix I - Maintenence and Inspection

    2/13

    Bridge Committee Annual Inspection Form

    In order to keep your bridge in the optmum conditon, contnual upkeep is required. An annual

    inspecton is essental to maintenance. Following the end of the rainy season, one or more

    representatves of the Bridge Commiee must visit the bridge site and go through the following

    checklist and complete corresponding maintenance.

    Remove any excess mud and debris from the bridge deck.

    Ensure weeds and plants growing beneath the bridge do not obstruct the bridge.

    Ensure all bolts, screws and nails are in place and tghtened.

    Replace deterioratng wood deck panels.

    Replace deterioratng crossbeams.

    Ensure that fencing is secure. Should any wires be loose or fencing missing, repair or replaceto original conditon.

    Check for erosion. Should erosion or scour occur, causing the water to reroute toward the

    anchor or approach, contact the local supportng agency and request assistance with a

    drainage structure.

    Measure the distance between the paint on the cable and the saddle guides (inset boom

    right). If more than half meter, local supportng agency immediately and if possible, Bridges

    to Prosperity (contact at www.BridgestoProsperity.org).

    Additonal Inspecton Notes:

    Paint LinePaint Line

    SaddlesSaddles

    Annual Inspection Pg 1

  • 8/8/2019 Appendix I - Maintenence and Inspection

    3/13

    16 Volume 3: Suspended Part 4 Maintenance

    Section 3:Quality Control Inspection

    To ensure an adequate inspecton has been completed for each bridge, a Quality Control Inspecton

    & Picture Inventory are required for all quality control inspectons completed on behalf of Bridges to

    Prosperity. For those tracking bridges within their own agencies, a filed report is useful to ensure the

    contnued maintenance needs are met. Bridges may be inspected without the design engineer on-site and furthermore, by someone without an engineering background. To ensure the evaluaton is

    adequate, the submission of pictures provide a visual confirmaton of wrien statements. An As-Built

    picture inventory should be on file with the Bridge Registry, which can be located in the final pages of

    this manual.

    To complete the quality control inspecton, prepare yourself by reading the As-Built Bridge Registry

    and spend tme looking through pictures. Take special note of the size of the cables, for this will dictate

    the size of torque wrench socket required. If a previous quality control review has been completed,

    also review the inspectors comments and concerns. If not familiar with how to use and read a torque

    wrench, reference Volume 3, Part 3: Constructon Manual.

    3.1 Materials Required

    3 meter measuring tape

    Digital Camera

    Torque Wrench

    Socket (sized to correspond to cable diameter)

    Pen & paper

    Copy of Quality Control Inspecton (Form)

    How to read aHow to read atorque wrenchtorque wrench

  • 8/8/2019 Appendix I - Maintenence and Inspection

    4/13

    17 Volume 3: Suspended Part 4 Maintenance

    3.2 Quality Control Overview

    Following the completon of the bridge, a follow-up quality control inspecton must be completed

    a minimum of two tmes during the lifetme of the bridge. The first should be completed between

    three (3) to five (5) years afer completon, and the second inspecton between five (5) and ten (10).

    If the pedestrian bridge contnues to be used beyond 10 years, the quality control inspecton should

    be completed every five (5) years. Beyond 30 years, the bridge must be reviewed by an engineer to

    ensure safety of cables, structure and decking.

    The Quality Control Inspecton Report in Secton 5 includes the following items;

    Overall Site Evaluaton

    Foundaton Tiers & Towers

    Anchors

    Cable Conditon

    Cable Clamps

    Approach Walls & Ramp

    Decking

    For each sub-secton, an adjoining chapter is included in Secton 4: Maintenance; Secton 4 must be

    referenced for both mandatory upkeep items as well as retrofit solutons for bridge concerns found

    during the inspectons. Please keep one copy of each report and send a copy to Bridges to Prosperity

    (contact at www.BridgestoProsperity.org).

  • 8/8/2019 Appendix I - Maintenence and Inspection

    5/13

    Quality Control Review& Picture Inventory FormDate: __________

    Country: __________________________

    Bridge Name:

    Name of Inspector: ___________________________

    Date: __________

    Region: ___________________________

    Village: ___________________________

    GPS coordinates: ___________________________

    Directons to site: _______________________________________________________

    _______________________________________________________

    Contact informaton of person in community: __________________________

    Bridge Span: ________meters

    Contact informaton of inspecton partcipants: ___________________________

    Observed traffic level: Number of persons: ____________ Time Lapse: ____________

    Type of use (bicycle, pedestrian, livestock, etc.) ________________________________

    Notes:

    Quality Control Pg 1

  • 8/8/2019 Appendix I - Maintenence and Inspection

    6/13

    Site Evaluation

    Inspect the area surrounding the bridge, on both abutments.

    Take special note if erosion has occurred and what the

    drainage path of run-offwater appears to take. If the erosion

    has caused scour, undercung the anchor, approach or

    foundat

    on structure, reference the maintenance sect

    on.For all following sectons, reference Secton 4: Maintenance

    to address any possible concerns. If the manual does

    not address the specific issue, please contact Bridges to

    Prosperity (contact at www.BridgestoProsperity.org).

    Include the following pictures on disk or in printed form and

    aach to Quality Control Inspecton report;

    Profile (from both up and down stream)

    Lef and Right abutment general picture

    Pictures of bridge in use (people, livestock etc.)

    Notes on site evaluaton, include drainage concerns:

    Foundation Tiers & Towers

    Inspect the foundaton ters and towers. Note the masonry

    conditon of towers. Is one able to pick out aggregate with hands?

    On either side, verify the base foundaton layer is level (see black

    line on picture to right). Note if the foundaton structure appears to

    be dipping (orange) towards the water, or slipping (green arrow). If

    structure has seled in either manner creatng change of elevaton

    of line greater than 30 cm, contact agency responsible for bridge.

    Notes on foundaton ters & towers:

    Include the following pictures with report:

    Concerning masonry degradaton, if any

    Pictures from both sides, either abutment

    Picture of selement, if any

    Quality Control Pg 2

    Figure above: Profile picture

    Figure above: Abutment picture

  • 8/8/2019 Appendix I - Maintenence and Inspection

    7/13

    Anchors

    Inspect the area surrounding the anchors (far back side

    of approach, on both abutments. Take special note if

    erosion has occurred and what the drainage path of run-

    offwater appears to take. If the erosion has caused scour,

    undercung the anchor, reference the maintenance

    secton.

    Walk behind the approach, if possible. The view should be

    similar to that in the picture to the right. For soil conditons,

    the anchor is a large beam, as shown in the picture to the

    right. Note if the cable is kinked at the saddles, implying

    the cable is not wrapped directly behind the corresponding

    cable saddle (handrail on outsides, walkway on inside, as

    shown to right).

    For rock conditons, the anchor is a cylindrical drum. The

    cables also should come straight off the saddles, as shownin the diagram to the boom right. Note is the cable is

    kinked.

    Include the following pictures with report:

    Picture from behind abutment & ramp, on either

    abutment

    Lef and Right abutment general picture

    Picture/s of erosion or drainage concerns, if any

    Notes on anchor, sketch area if drainage concerns:

    Quality Control Pg 3

  • 8/8/2019 Appendix I - Maintenence and Inspection

    8/13

    Cable Condition

    Inspect the cable at all points of inserton into concrete, the

    approach or the ground. Inspect general cable conditon and

    note if loose strands occur anywhere along the cable.

    Note the slide of the cable. Reference the colored mark on

    the cable, which originated between guides on saddles. Ifthe amount of movement exceeds 1 % of length of cable

    (see Span on Quality Control Page 1), cable slip or excessive

    cable stretch has occurred (assume 2% equally divided

    between two sides as an upper limit of concern). Please

    contact B2P immediately (contact informaton at www.

    BridgestoProsperity.org).

    Include the following pictures with report:

    Cable inserton into approach, if any corrosion or rust

    appears

    Pictures of all four (4) handrail saddle pictures: look for

    amount of slide for mark on cable.

    Cable fraying, if any

    Cable Clamps

    Inspect all clamps that are visible above ground. Using torque

    wrench, document existng torque on each above-ground

    clamp. For torque standards, first measure the diameter of

    the cable or reference As-Built Bridge Register. Reference the

    corresponding minimum torque from the torque requirements

    on the following page.

    If the measured torque is less than 80% torque required,

    re-tghten all above-ground clamps to specified torque. If

    actual is less than 60% of specified required torque, notfy

    implementng agency immediately to discuss need to rip out

    approach or return with additonal clamps.

    Include the following pictures with report: Clamp conditon (before re-torque, if required)

    If re-torqued, torque technique used for each

    Figure above: Handrail saddle

    Figure above: Cable at concrete

    Quality Control Pg 4

    Figure above: cable clamps

    Figure above: Re-torque clamps

  • 8/8/2019 Appendix I - Maintenence and Inspection

    9/13

    Notes on cable and clamps (include existng torque for

    every above-ground clamp):

    Approach Walls & Ramp

    Inspect the conditon of the approach walls and ramp.

    Evaluate and document extent of cracking on concrete

    approach ramp. Typical source of crack propagaton is the

    inserton point of cable, or selement within the approach.

    Note opinion on source of cracks. If cracks between rock

    walls exist, look into the approach to evaluate if excessive selement has occurred inside. Note if any

    usage issues occur. This may include water pooling, excessive

    cracks or bumps in the approach or connecton to ground etc.

    Include the following pictures with report:

    Cable inserton into approach if cracks

    If separaton between tower and approach, if more than 30cm separaton, note if selement occurred with tower or ap-

    proach.

    Notes on approach walls and ramp:

    Quality Control Pg 5

    Table above: Clamp torque requirements

    Figure above: Cracking ramp side-view

    Figure above: Cracking

  • 8/8/2019 Appendix I - Maintenence and Inspection

    10/13

    Decking

    Rate the conditon of the deck panels. Note if any

    longitudinal deck panels are missing. Note if rot has

    occurred and to what extent. Document with pictures,

    quantty and extent of rot and opinion of current usability.

    Rate conditon of cross beams (transverse beams, likely

    will need to go below deck). Note if any cracking between

    suspender drill hole and end of beam. Note any structural

    damage (split beams, missing sectons of beams etc.).

    Note if rot has occurred and to what extent. Document

    with pictures, quantty and extent of rot and opinion of

    current usability.

    Include the following pictures with report:

    General decking conditon

    General crossbeam conditon

    Decking/crossbeam pictures if rong or other

    issues

    Notes on approach walls and ramp:

    Full-Bridge Photos

    CrossbeamsCrossbeams

    Quality Control Pg 6

  • 8/8/2019 Appendix I - Maintenence and Inspection

    11/13

    24 Volume 3: Suspended Part 4 Maintenance

    Section 4:Maintenance

    This secton includes mandatory upkeep items to be completed during every Quality Control Inspecton,

    as well as solutons to repair bridge components found to be substandard during inspectons.

    The Maintenance chapter includes the following sectons:

    4.1 Overall Site Conditon

    4.2 Foundaton Tiers & Towers

    4.3 Anchors

    4.4 Cable & Clamps

    4.5 Approach Walls & Ramp

    4.6 Decking

    4.1 Overall Site Condition

    If the Quality Control Inspecton notes that erosion and scour are undermining the bridge structure,

    a drainage structure may allow the water to reroute, thus saving the structure from further damage.

    Slope protecton and drainage systems are required at sites when excess run-offmay influence the

    slope stability. It is recommended to avoid sites where any instability is prevalent. If unavoidable, it is

    necessary to drain out the runoffand seepage to ensure the stability of the slope and to avoid under-

    scour of structures. Water should be collected as closely as possible to its origin and navigated away

    from the bridge structures. A surface catch drain on a slope may be required, drainage around the

    structure or both.

    Below right if an example subsurface drainage systems, and boom right are example surface drainage

    systems. For further details, reference Volume 2.

    Surface Drainage

    Subsurface Drainage

  • 8/8/2019 Appendix I - Maintenence and Inspection

    12/13

    25 Volume 3: Suspended Part 4 Maintenance

    4.2 Foundation Tiers & Towers

    If the quality control inspecton finds that the masonry structure is degrading, use a cement mortar to

    patch the areas. If severe degradaton, consider replacing when possible.

    If the structure is found to be slipping (either slipping downhill, or tpping forward), hire a local

    engineer to evaluate the stability of the slope. If considered unsafe, close the bridge. It is possible to

    reconstruct the structure of the failing side using many of the scrapped materials, but do not relocate

    at such a distance that the cables create a lateral load on the opposing side towers.

    4.3 Anchors

    If the Quality Control Inspecton notes that erosion and scour are undermining the anchor, a drainage

    structure may allow the water to reroute, thus saving the structure from further damage. See secton

    4.3.1 and reference Volume 2 for further details on drainage structures.

    4.4 Cables & Clamps

    If the cable is found to be corroding or fraying, estmate the percentage of the cable cross-secton

    that has been damaged. If greater than 10% of cable is fraying, evaluate the extent of the damage. If

    localized in one point, consider a splice. Reference cable-

    manufacturing materials for details. If evaluated to have

    extensive damage, close the bridge untl cable can be

    replaced with new cables. If this occurs, contact Bridges

    to Prosperity to describe situaton, providing pictures and

    details when possible (contact at www.BridgestoProsperity.

    org).

    If the clamps are found to have less than 80% of required

    torque, each above-ground clamp must be re-tghtened.

    The picture to the top right depicts the cross-sectonal

    reducton that is required when the clamps are fully

    torqued (assuming drop-forged, not malleable. For more

    informaton, see Volume 3, Part 3). Boom

    right shows the proper length of the breaker

    bar or torque wrench required to apply the

    adequate amount of torque.

    If the clamps are found to have less than60% of the required torque, additonal

    clamps must be added. In severe cases the

    approach should be removed to tghten

    clamps below ground.

    SaddleSaddle

    DeadDeadcablecable

  • 8/8/2019 Appendix I - Maintenence and Inspection

    13/13

    26 Volume 3: Suspended Part 4 Maintenance

    4.5 Approach Walls & Ramp

    If the quality control inspecton finds that the approach structure is degrading, use a cement mortar to

    patch the areas. If severe degradaton, consider patching with wedge stones.

    If the approach ramp is separatng from the tower structure, a method to te back the structures

    together is required or the bridge must be closed. This method is beyond the scope of this basic

    manual as it will require engineering consultaton.

    If the ramp is cracking from selement (not just localized cracking around the inserton points of the

    cable), rip out the 5 cm thick concrete ramp top, backfill the approach with additonal well-graded

    large aggregate and stone and recover with a fresh layer of concrete, 5 cm thick.

    4.6 Decking

    If any decking panels are rong through or missing

    entrely, they must be replaced. The standard

    thickness of a decking board is 5 cm, but verify withthose on site before purchasing. Reference Volume 3,

    Part 2 Drawings, specifically the decking drawings for

    complete details. Note that the paern of laying the

    deck panels requires an alternaton, as shown in the

    picture to the right.

    If any crossbeams are in need of replacement, either

    an additonal board must be aached to the boom as

    reinforcement or the beam must be replaced.

    If replacement is chosen, start by removing the deck

    panels directly above the crossbeam in queston.

    Unwrap the fencing in the direct locaton; cung may

    be required. Secondly, unwrap the suspenders from

    the top of the cable, which likely will require a pipe.

    Unwrap the suspender from the crossbeam, originally

    with the configuraton shown to the right. Remove

    the suspenders completely and aempt to straighten

    for reuse. Take new pre-drilled crossbeam and fit into

    place. Reference Volume 3, Part 3 Constructon for

    details. Complete the process by screwing and nailingthe deck boards back into place. Replace and repair

    any damaged fencing before leaving.