10 year performance of an unbonded concrete...
TRANSCRIPT
10 Year Performance of an Unbonded Concrete Overlay
- A Case Study
City of Toronto
Mark Berkovitz P.Eng., Senior Engineer
Transportation Services
February 21, 2016
Introduction & Acknowledgements
Background & Project Location
Design & Construction
Pavement Instrumentation & Performance
Maintenance Repairs
Pros, Cons & Further Work
Future Applications
2
PRESENTATION OUTLINE
3
INTRODUCTION Definition
Unbonded Concrete Overlay is essentially a new concrete pavement
constructed over an existing concrete pavement. A flexible interlayer,
typically constructed of hot-mix asphalt (HMA), separates the concrete
layers. The flexible interlayer acts as a shear zone, allowing the concrete
layers to move independently of each other, and preventing reflective
cracking in the concrete overlay. For this reason, the term “unbonded” is
used, although the layers do bond in the sense of adhering together.
First unbonded concrete overlay built in the City of Toronto
Built on a composite arterial road
Constructed in the summer of 2003
A three-way research partnership between the City, the Cement Association of Canada and Centre for Pavement and Transportation Technology (CPATT) at the University of Waterloo
Researched via ongoing live monitoring of stress-strain gauges within the pavement structure and occasional site visits to perform non-destructive testing and visual inspections
4
INTRODUCTION
Acknowledgements Aleks Kivi Masters Candidate Waterloo Engineering
Susan Tighe, PhD, P.Eng Sponsor Professor, Canada Research Chair, Norman W. McLeod Chair In Sustainable Pavement Engineering Centre for Pavement and Transportation Technology Department of Civil and Environmental Engineering University of Waterloo
Rico Fung, P.Eng Sponsor Structural Engineer Cement Association of Canada
Jozef Grajek, P.Eng. Senior Engineer & Project Manager City of Toronto
5
6
BACKGROUND Site Location: Bloor St W & Aukland Road
BACKGROUND Pre-Existing Conditions
2003 Aerial
Arterial Roads
Major transit connection
High volume of bus & truck traffic
Aged and heavily distressed composite pavement
8
BACKGROUND April 24, 2003
9
PAVEMENT DESIGN Bloor Street Section
150 mm Granular Base
200 mm PCC
80 mm HMA
Existing Pavement
150 mm Granular Base
200 mm PCC
150 mm PCC
25 mm HMA
(High stability HL3)
New Pavement
Bloor Street West
Grid pattern short joint spacing of 1.5 m maximum; cut ¼ depth
Short joint spacing reduces load-related stresses and prevents corner cracking
Load transfer provided by aggregate interlock
Dowels and/or tie bars are generally not required, but were used close to the intersection to provide additional reliability for heavy turning and/or stopped buses
Aukland Road
Existing flexible pavement structure
Remove existing HMA surface full depth
Replace 150 mm granular base course with fresh material and
re-grade to design elevation
Place 225 mm conventional Jointed Plain Concrete Pavement
10
PAVEMENT DESIGN Aukland Road Section
260 mm Granular Base
190 mm HMA
Existing Pavement
110 mm Granular Base (old)
150 mm Granular Base (new)
225 mm PCC
New Pavement
11
CONSTRUCTION Staging
Construction took about 1 month
Concrete pavement placed in 3 stages over 2 weekend closures
Construction staging minimized traffic delays
12
CONSTRUCTION Bloor Street Section
13
CONSTRUCTION Bloor Street Section
14
CONSTRUCTION End Product
Bloor St.
(Westbound)
Bloor St.
(Eastbound)
Sensor Street
Name
Traffic
Direction
Depth (mm)
Below PCC
Surface
1
Bloor
Street
West
WBD 50
2 WBD 150
3 WBD 50
4 EBD 50
5 EBD 50
6 EBD 50
7 EBD 150
8
Aukland
Road
SBL 50
9 SBL 225
10 SBL 50
11 NBT 50
12 NBD 50
15
SENSOR INSTALLATION Sensor Layout
N
Bloor Street West
Aukland Road
WBD
WBP
EBP
EBD
SBL NBT NBD Sensor
Data Logger
Trench
8 & 9 10 11 12
1 & 2
3
4
5
6 & 7
TToo DDaattaa--llooggggeerr
FFllaannggee
FFllaannggee
GGaauuggee BBooddyy
((eelleeccttrroommaaggnneett ccooiill))
TToo DDaattaa--llooggggeerr
FFllaannggee
GGaauuggee BBooddyy
((eelleeccttrroommaaggnneett ccooiill))
PAVEMENT PERFORMANCE Sensor Data
Unbonded overlay: overall trend of increasing compression is observed both at the bottom and top of the concrete layer
Considerable remaining pavement service life is expected
Clear daily cycles in strain are observed coinciding with daily temperature cycles
Measured strains remain fairly low (i.e., well below cracking thresholds)
17
Structural Evaluation
Falling Weight Deflectometer (FWD) testing was performed
to evaluate the existing structural capacity, November 2013
PAVEMENT PERFORMANCE Falling Weight Deflectometer Data
Load Transfer
Bloor St – excellent (87%)
Aukland Rd – good-excellent (80%)
Deflections / Elastic Modulus Values
Bloor St – 115 microns / 3516 MPa
Aukland Rd – 182 microns / 1921 MPa
18
PAVEMENT PERFORMANCE Typical Distresses
Typical pavement condition
19
PAVEMENT PERFORMANCE Field Observations
Looking westbound on Bloor St.
Looking SB on Aukland
WB on Bloor at Aukland
August 2011
WB on Bloor at Ashbourne, August 2011
PAVEMENT PERFORMANCE Field Comparative Locations
August 2011, WB on Bloor at Ashbourne
PAVEMENT MAINTENANCE 2015 Repairs
Cracked and spalled
panels and repair
(full depth with dowels)
Full depth concrete repair in
accordance with OPSS
Special Provision 399S43
August 2011, WB on Bloor at Ashbourne
PAVEMENT MAINTENANCE 2015 Repairs
Damaged Catchbasin
and Repair
23
PROS, CONS
AND FURTHER WORK
+ Maintains investment in old pavement
+ Excellent performance under heavy traffic loads and harsh
Canadian environmental conditions
+ Can be rapidly constructed
- Concrete surface requires more frequent repainting
- Utility cut repairs and patching are more costly
? Cost-effectiveness / life-extension to be determined
? Future rehabilitation considerations
24
PROS, CONS
AND FURTHER WORK
Cost-effectiveness / life-extension to be determined:
(2003 Construction Costs, Unit Cost)
Unbonded Concrete Overlay: $230,000. , $150./m2
Jointed Plain Concrete Pavement: $140,000. , $200./m2
Standard Composite Pavement Rehabilitation $75./m2
Future Maintenance & Rehabilitation considerations:
Consider crack and joint sealant program
Develop a crack & spall repair program when needed
Double dowelling for utility cut repairs?
25
For further research:
Climate change adaptation – albedo, heat island effect
Greenhouse gas emissions – reduced material and construction demands
PROS, CONS
AND FURTHER WORK
26
MUNICIPAL APPLICATIONS For Consideration
Highly distressed areas
characterized by:
heavy traffic
poor soil conditions
Limited underground utilities
Examples:
turn lanes
bus bays & pads
Intersections
Industrial roads
27
THANK YOU
QUESTIONS?