1 © the delos partnership 2004 welcome to the project management foundation course based on the...

238
1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the Project Management Institute (PMI®).

Upload: howard-griffith

Post on 16-Dec-2015

215 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

1 © The Delos Partnership 2004

Welcome to the Project Management Foundation Course

Based on the Project Management Body of Knowledge (PMBOKTM) from the

Project Management Institute (PMI®).

Page 2: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

2 © The Delos Partnership 2004

The Project Management Institute (PMI®) is project

management’s leading global professional

association, and as such, it administers a

globally accepted and recognised, rigorous,

examination-based, professional certification

programme of the highest calibre.

Page 3: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

3 © The Delos Partnership 2004

The course is designed to support both the

immediate practical challenges you face

implementing projects within your organisation

and also to provide you with a solid foundation in

recognised good project management practice

for all your future endeavours.

Page 4: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

4 © The Delos Partnership 2004

Expectations!

Page 5: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

5 © The Delos Partnership 2004

Course ObjectivesCourse Objectives

• To provide you with a strong foundation in good project management practices

• To improve the management of the current projects you are working on for the benefit of the company

• To fulfil the eligibility criteria (and prepare students) for the PMI’s® Certified Associate in Project Management (CAPM®) Exam

Page 6: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

6 © The Delos Partnership 200418/04/23

Active Learning Approach – Active Learning Approach – The Project Management Life CycleThe Project Management Life Cycle

• Presentation on Key Concepts/Techniques

• Case Study to reinforce key learnings

• Case Study Feedback with interactive Q&A

• Learning Review

Theory&

Practice

Page 7: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

7 © The Delos Partnership 2004

IntroductionIntroduction

• At the end of this session you will have an understanding of the following:-

• The definition of a project

• Projects versus Programmes

• The PMI lifecycle and knowledge areas

Page 8: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

8 © The Delos Partnership 2004

The Project Life CycleThe Project Life Cycle

InitiatingProcesses

InitiatingProcesses

PlanningProcesses

PlanningProcesses

ControllingProcesses

ControllingProcesses

ClosingProcesses

ClosingProcesses

ExecutingProcesses

ExecutingProcesses

Page 9: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

9 © The Delos Partnership 2004

And The PMI® Project And The PMI® Project Management Knowledge AreasManagement Knowledge Areas

All numbering refers to the PMI® Project Management Body of Knowledge (PMBOK) Knowledge Areas

4. Project4. ProjectIntegration Integration

ManagementManagement

4. Project4. ProjectIntegration Integration

ManagementManagement

5. Project5. ProjectScopeScope

ManagementManagement

5. Project5. ProjectScopeScope

ManagementManagement

6. Project6. ProjectTimeTime

ManagementManagement

6. Project6. ProjectTimeTime

ManagementManagement

7. Project7. ProjectCostCost

ManagementManagement

7. Project7. ProjectCostCost

ManagementManagement

8. Project8. ProjectQualityQuality

ManagementManagement

8. Project8. ProjectQualityQuality

ManagementManagement

9. Project9. ProjectHuman ResourceHuman Resource

ManagementManagement

9. Project9. ProjectHuman ResourceHuman Resource

ManagementManagement

10. Project10. ProjectCommunicationsCommunications

ManagementManagement

10. Project10. ProjectCommunicationsCommunications

ManagementManagement

11. Project11. ProjectRiskRisk

ManagementManagement

11. Project11. ProjectRiskRisk

ManagementManagement

12. Project12. ProjectProcurementProcurementManagementManagement

12. Project12. ProjectProcurementProcurementManagementManagement

Page 10: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

10 © The Delos Partnership 200418/04/23

What is a Project?What is a Project?

A project is a group of related work activities, organized under the direction of a project manager, which when carried out, will achieve certain objectives. A project has stated scope, deliverables, work steps, duration, and budget.

Page 11: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

11 © The Delos Partnership 200418/04/23

What is a Project?What is a Project?

A project:– Is unique– Has a beginning and an end– Is defined by specific objectives– Is conducted by a well-defined organization– Has a single project manager who is

responsible for its success– Is defined by identifying the starting point

and the goal and the route between them

Page 12: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

12 © The Delos Partnership 200418/04/23

What is Project What is Project Management?Management?Project Management is the application of knowledge,

skills, tools and techniques to project activities in order to meet or exceed stakeholder needs and expectations from a project. Meeting or exceeding needs invariably involves balancing competing demands among:– Scope, time, cost, and quality– Stakeholders with differing needs and

expectations– Identified requirements (needs) and unidentified

requirements (expectations)Source:Project Management Institute 1996

Page 13: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

© The Delos Partnership 200418/04/23

Programme vs ProjectsProgramme vs Projects

– A programme is a group of projects managed in a coordinated way

– A programme is a set of activities / initiatives that need to come together to achieve a major business change

Page 14: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

© The Delos Partnership 200418/04/23

Without a Programme MgmtFramework

•Strategic Imperatives

•Mergers & Acquisitions

•Business Process Changes

•Regulatory Changes

•Market Driven Changes

Change Drivers

?

Many projects, little alignment

Organisation Goal

Past Future

Page 15: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

© The Delos Partnership 200418/04/23

With a Programme MgmtWith a Programme Mgmt Framework Framework

Past Future

•Strategic Imperatives

•Mergers & Acquisitions

•Business Process Changes

•Regulatory Changes

•Market Driven Changes

Change Drivers

?

Programme Mgmt

Focus on closinggap and seekingother improvementopportunities

Programme co-ordination

Organisation Goal

Page 16: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

16 © The Delos Partnership 2004

Project InitiationProject Initiation

At the end of this session you will have an understanding of the following:-

• 4 Stages within Project Initiation

• The Business Filters

• Project Charter(s)

Page 17: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

17 © The Delos Partnership 2004

The PMI® Project The PMI® Project Management Life CycleManagement Life Cycle

InitiatingProcesses

InitiatingProcesses

PlanningProcesses

PlanningProcesses

ControllingProcesses

ControllingProcesses

ClosingProcesses

ClosingProcesses

ExecutingProcesses

ExecutingProcesses

Page 18: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

18 © The Delos Partnership 2004

PMI® Initiating ProcessesPMI® Initiating Processes

5.1 Initiation

5.1 Initiation

Business Case

Business Case CharterCharterInitial

Invest.

Initial Invest.IdeaIdea

Page 19: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

19 © The Delos Partnership 2004

Ideas - Pick the WinnersIdeas - Pick the Winners

BIs

UIs

GIs

(Business Imperatives)

(Good Ideas)

(Useless Ideas)

Page 20: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

20 © The Delos Partnership 2004

Potential for Potential for GlobalisationGlobalisation

Supports Supports Regional Regional customer basecustomer base

Supports Supports country country customer customer basebase

LLocal ocal customerscustomers

Geographic Geographic ScopeScope

Significantly Significantly enhances enhances skillsskills

Builds on Builds on current skills current skills to growto grow

Contributes Contributes to strategic to strategic planplan

Does not Does not enhance enhance skillsskills

Competency Competency ImproveImprove`̀tt

Could be Could be applied widely applied widely across the across the businessbusiness

Could be Could be adapted adapted to to several several programmesprogrammes

CCould be ould be applied to applied to another another programmeprogramme

SSingle ingle progprog..

Synergy Synergy with Other with Other ProgsProgs

Opens up new Opens up new OpportunityOpportunity

Potential for Potential for diversificationdiversification

OOpportunity pportunity for business for business extensionextension

Dead-end, Dead-end, Platform for Platform for GrowthGrowth

StrongStrongGoodGoodModestModestPPeripheraleripheralFit to Fit to StrategyStrategy

RATINRATINGG STRATEGIC FITSTRATEGIC FIT 1 1 4 4 7 7 1 100

KEY KEY FACTORSFACTORS

Page 21: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

21 © The Delos Partnership 2004

Uses Uses existing existing sales & sales & distribdistrib..

EExisting sales xisting sales operationsoperations

Existing skills Existing skills in new in new channelchannel

SSkills kills needed, needed, in new in new channelchannel

Sales & Sales & DistributionDistribution

Positive Positive impactimpact

FavourableFavourableNeutralNeutralNegativeNegativeCommunity Community RelationsRelations

Large Large margins; margins; large large marketmarket

Large Large margins; margins; small marketsmall market

Small Small margins; large margins; large marketmarket

Small Small margins; margins; small small marketmarket

Target Target Market Market OpportunityOpportunity

LowLowModerate/LowModerate/LowModerate/HighModerate/HighHighHighCompetitive Competitive IntensityIntensity

High High Growth Growth expectedexpected

Modest Modest growthgrowth

Mature or Mature or EmbryonicEmbryonic

DecliningDecliningMarket Market MaturityMaturity

AAhead of head of marketmarket

‘ ‘me too’me too’Need must be Need must be highlightedhighlighted..

LLittle ittle apparent apparent needneed

Market NeedMarket Need

RATINGRATING MARKET ATTRACTIVENESSMARKET ATTRACTIVENESS 1 1 4 4 7 7 1010

KEY KEY FACTORSFACTORS

Page 22: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

22 © The Delos Partnership 2004

Widely Widely practised in practised in the companythe company

Selectively Selectively practised in practised in the the companycompany

Some Some experienceexperience

Technology Technology new to new to businessbusiness

Technology Technology Skill BaseSkill Base

Available Available and readyand ready

Available, Available, need need advance advance planningplanning

Current Current systems systems require require mods.mods.

No No appropriate appropriate systems/systems/

facilitiesfacilities

Availability Availability of of Systems/Systems/

FacilitiesFacilities

People People immediately immediately availableavailable

People People availableavailable

Shortage in Shortage in key areaskey areas

No No appropriate appropriate peoplepeople

Availability Availability of Peopleof People

Straight Straight ForwardForward

Challenge, Challenge, but do-ablebut do-able

Easy to Easy to definedefine

Difficult to Difficult to definedefine

Project Project ComplexityComplexity

Incremental Incremental ImproveImprove`t`t

Step Step changechange

Major step Major step changechange

Large gapLarge gapTechnical Technical GapGap

RATINGRATINGTTECHNOLOGY FITECHNOLOGY FIT 1 1 4 4 7 7 1010

KEY KEY FACTORSFACTORS

Page 23: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

23 © The Delos Partnership 2004

No No detrimental detrimental effect. effect.

Rescheduling Rescheduling requiredrequired

Disruption.Disruption.

InconvenientInconvenient

Major Major disruptiondisruption

Effect on Other Effect on Other Company Company ProgrammesProgrammes

Resouces Resouces immediately immediately available.available.

Could be Could be rescheduledrescheduled

Some Some resource resource availableavailable

No No ResourceResource

Availability of Availability of PeoplePeople

Clear Clear Focused Focused Commit.Commit.

Functional Functional commitment.commitment.

Lukewarm. Lukewarm. Little Little Business Business CommitmentCommitment

Detached Detached from Prog.from Prog.

Stakeholder Stakeholder Commitment & Commitment & Buy-InBuy-In

Quantifiable Quantifiable Attractive Attractive BenefitsBenefits

Quantifiable in Quantifiable in specific areasspecific areas

Difficult to Difficult to substantiatesubstantiate

Cannot be Cannot be substant-substant-iatediated

Benefits to the Benefits to the CompanyCompany

AvailableAvailableCould be Could be made made availableavailable

Partially Partially AvailableAvailable

Not Not AvailableAvailable

Availability of Availability of FundingFunding

RATINRATINGG BUSINESS IMPACTBUSINESS IMPACT

1 1 4 4 7 7 1 100

KEY KEY FACTORSFACTORS

Page 24: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

24 © The Delos Partnership 2004

Self Self SustainingSustaining

From From Compliance to Compliance to CommitmentCommitment

PartialPartialNot Not availableavailable

Cultural FitCultural Fit

Competent Competent team up and team up and runningrunning

Team in place Team in place but skills need but skills need to be to be developeddeveloped

PartialPartialNo No resources resources availableavailable

Sponsorship Sponsorship CommitmentCommitment

Aligned Aligned approachapproach

Can do but Can do but resource resource conflicts not conflicts not dealt withdealt with

Difficult to Difficult to predictpredict

Mission Mission impossibleimpossible

Effort of Effort of TransitionTransition

Both Top Both Top Down and Down and Bottom up Bottom up desiredesire

Benefits Benefits agreed but not agreed but not measurablemeasurable

Uncertainty Uncertainty about final about final outcomeoutcome

No fit with No fit with values of values of companycompany

Attractiveness Attractiveness of Futureof Future

Burning Burning platformplatform

Recognition of Recognition of need to need to changechange

Partial Partial recognition of recognition of problemproblem

It aint It aint broke broke

don’t fixdon’t fix it it

Dissatisfaction Dissatisfaction with presentwith present

RATINRATINGG CHANGE ORIENTATIONCHANGE ORIENTATION

1 4 7 10

KEY KEY FACTORSFACTORS

Page 25: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

25 © The Delos Partnership 2004

First Cut Priority CheckFirst Cut Priority Check

3.43.4773322332299

55445555556688

5.65.6885544447777

6.26.2556699883366

6.66.6559988774455

7.27.2997777667744

7.67.6888855889933

885510107788101022

10101010101010101010101011

Overall Overall AverageAverage

Change Change Orient.Orient.

Bus. Bus. ImpactImpact

Tech Fit Tech Fit Market Market Attract.Attract.

Strategic Strategic FitFit

ProgProg

Page 26: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

26 © The Delos Partnership 2004

The PMI Project The PMI Project Management Life CycleManagement Life Cycle

InitiatingProcesses

InitiatingProcesses

PlanningProcesses

PlanningProcesses

ControllingProcesses

ControllingProcesses

ClosingProcesses

ClosingProcesses

ExecutingProcesses

ExecutingProcesses

Business Case

Business Case CharterCharterInitial

Invest.

Initial Invest.IdeaIdea

Page 27: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

27 © The Delos Partnership 2004

Tech. Feasibility Study

• Refine Scope of Activity– Prepare Statement of Work.

• Make or Buy– Rationale and Options– Do we have or can we acquire the skills?

• Do we have a solution?– Technical Issues & Risks– Commercial Issues & Risks– Rough Cut Costs

• Background & Experience

Page 28: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

28 © The Delos Partnership 2004

Business Attractiveness

87.587.5100100

2525112525PositioningPositioning

3030113030GrowthGrowth

7.57.50.50.51515Route to MarketRoute to Market

550.50.51010CompetitionCompetition

2020112020Market SizeMarket Size

ScoreScoreRating*Rating*WeightWeightFactorFactor

* High = 1.0; Medium = 0.5; Low = 0.0

Page 29: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

29 © The Delos Partnership 2004

Operational Capability

3030100100

660.30.32020MarketingMarketing

7.57.50.50.51515InfrastructureInfrastructure

4.54.50.30.31515SystemsSystems

660.30.32020CapabilityCapability

660.20.23030CapacityCapacity

ScoreScoreRating*Rating*WeightWeightFactorFactor

* Strong = 1.0; Average = 0.5; Weak = 0.0

Page 30: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

30 © The Delos Partnership 2004

Resource Allocation

NoNo2.22.20.40.4202015157.27.244

NoNo1.81.80.20.2202045455588

NoNo1.61.60.40.4505040405.65.677

NoNo1.21.20.20.2202020206.26.266

YesYes1.01.0nilnil808018183.43.499

YesYes1.01.00.10.1808058586.66.655

YesYes0.90.90.10.1424266667.67.633

YesYes0.80.80.30.3808070708822

YesYes0.50.50.50.530308787101011

CommitCommitAccum.Accum.

ResourceResource

CriticalCritical

ResourceResource

Oper.Oper.

CapabilityCapability

Business Business Attract.Attract.

OverallOverallAverageAverage

ProgProg

Page 31: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

31 © The Delos Partnership 2004

Prog.Portfolio Mgmt

Weak

Average

Strong

Op

erat

ion

al C

apab

ilit

y

High Medium Low

Business Attractiveness

P1

P3

P8

P2

P4P6

P7

P5 P9

Page 32: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

32 © The Delos Partnership 2004

The PMI Project The PMI Project Management Life CycleManagement Life Cycle

InitiatingProcesses

InitiatingProcesses

PlanningProcesses

PlanningProcesses

ControllingProcesses

ControllingProcesses

ClosingProcesses

ClosingProcesses

ExecutingProcesses

ExecutingProcesses

Business Case

Business Case CharterCharterInitial

Invest.

Initial Invest.IdeaIdea

Page 33: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

33 © The Delos Partnership 2004

Tech. Feasibility StudyTech. Feasibility Study

• Refine Scope of Activity– Prepare Statement of Work.

• Make or Buy– Need for control, Intellectual Property– Do we have or can we/do we want to acquire the skills?

• Do we have a solution?– Technical Issues & Risks– Commercial Issues & Risks– Rough Cut Costs

• Background & Experience

Page 34: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

34 © The Delos Partnership 2004

Developing the Business CaseDeveloping the Business Case

BenefitsBenefits

ObjectivesObjectives

Critical Success Critical Success FactorsFactors

DeliverableDeliverable

CostsCosts

•What will be the Business Benefit?

• Benefits Mgmt Process

•What must be achieved?

•Strategic / Tactical / Operational

•What must go right ?

•Pertaining to Overall Success

•What must we do at Deliverable Level ? •High Level Work plan

•What will it cost? •Cost +/- 10% / Risks/ Assumptions

What ? ? How ?

Page 35: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

35 © The Delos Partnership 2004

Benefit Analysis TypesBenefit Analysis Types

Discounted Cash Flow Types

Net Present Value (NPV)

Return on Investment (ROI)

Non Discounted Case Flow Types

Benefit Cost Analysis (BCA)

Payback Period

Page 36: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

36 © The Delos Partnership 2004

The PMI Project The PMI Project Management Life CycleManagement Life Cycle

InitiatingProcesses

InitiatingProcesses

PlanningProcesses

PlanningProcesses

ControllingProcesses

ControllingProcesses

ClosingProcesses

ClosingProcesses

ExecutingProcesses

ExecutingProcesses

Business Case

Business Case CharterCharterInitial

Invest.

Initial Invest.IdeaIdea

Page 37: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

37 © The Delos Partnership 200418/04/23

Initiating the ProjectInitiating the Project

Develop goals and objectives Define project deliverables Define high level scope Identify high-level activities Document project assumptions Secure project sponsorship Obtain approval to proceed

Input OutputProcess

InitialProjectCharter

Initial Project Charter Major Constraints Identified Major Assumptions Listed Project Manager Assigned Authority to Proceed

BusinessCase

Page 38: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

38 © The Delos Partnership 2004

What is a Project Charter?What is a Project Charter?

The Project Charter provides authority for the project to proceed.

The Charter documents the agreement between the Sponsor, the Programme Manager (if appropriate) and the Project Manager and provides a blueprint for the project

Makes the project visible from “start”

Page 39: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

39 © The Delos Partnership 2004

The Charter Should The Charter Should ContainContainA clear statement of the project’s objectives,

High Level Scope and deliverables;

The rationale for the project (headlines from the business case)

Defining the project roles & responsibilities;

Outlining the High Level Plan;

Documenting related projects.

Roles and Responsibilities

Page 40: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

40 © The Delos Partnership 2004

Initiating the ProjectInitiating the ProjectKey Project Manager ActivitiesKey Project Manager Activities

• Define Project Objectives & Major Deliverables;

• Define Project Structure & Resource Plan;

• Prepare High Level Project Budget;

• Prepare Business Case

• Compile Project Charter;

Page 41: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

41 © The Delos Partnership 2004

What is an Objective?What is an Objective?

Specific (What is it we are trying to do?)

Measurable (How will we know we have achieved it?)

Achievable (Can we do it?)

Relevant (Is it the right thing to do?)

Time-related (When will we do it?)

A statement of a particular desired outcome supporting the Goal that is:

Page 42: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

42 © The Delos Partnership 2004

Case StudyCase Study

Breakout Session 1

Page 43: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

43 © The Delos Partnership 2004

The PMI® Project The PMI® Project Management Life CycleManagement Life Cycle

InitiatingProcesses

InitiatingProcesses

PlanningProcesses

PlanningProcesses

ControllingProcesses

ControllingProcesses

ClosingProcesses

ClosingProcesses

ExecutingProcesses

ExecutingProcesses

Page 44: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

44 © The Delos Partnership 2004

PlanningPlanning

At the end of this session you will have an understanding of the following:-

• The Planning Process

• The Planning Hierarchy

• WBS

• Plans

• Schedules

Up, Down and Acrossthe Company

Page 45: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

45 © The Delos Partnership 2004

Planning ProcessesPlanning Processes

6.3 Activity Duration

Estimating

6.3 Activity Duration

Estimating

5.2 Scope

Planning

5.2 Scope

Planning

5.3 Scope

Definition

5.3 Scope

Definition

6.1 Activity

Definition

6.1 Activity

Definition

7.1Resource Planning

7.1Resource Planning

6.2Activity

Sequencing

6.2Activity

Sequencing

7.2Cost

Estimating

7.2Cost

Estimating

6.4Schedule

Development

6.4Schedule

Development

7.3Cost

Budgeting

7.3Cost

Budgeting

4.1Project Plan Development

4.1Project Plan Development

N.B. All numbering refers to the PMI® Project Management Body of Knowledge (PMBOK) Knowledge Areas

Page 46: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

46 © The Delos Partnership 200418/04/23

InputInput OutputOutputProcessProcess

Phases

Objectives

Deliverables

Acceptance Criteria

Scope PlanningScope Planning

CharterProjectCharter Scope

Plan

Wave 1 Wave 2

Page 47: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

47 © The Delos Partnership 200418/04/23

InputInput OutputOutputProcessProcess

Decomposition

Scope DefinitionScope Definition

Objective

Work Breakdown Structure

Charter

ScopePlan

Charter

Scope Plan

WBS

Page 48: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

48 © The Delos Partnership 2004

Why Define the Why Define the Work Breakdown Work Breakdown Structure?Structure?

To manage a project successfully, you must first have a clear understanding of the amount of work you are required to complete

Only then can the cost and schedule of your project be estimated and controlled with any confidence

The WBS identifies all the work to be performed I.e. the Scope of the Project. If it is not in the WBS it is not part of the project

It can often be as important to say what is not within scope

Page 49: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

49 © The Delos Partnership 2004

GoalGoal

Objective 1Objective 1 Objective 2Objective 2 Objective 3Objective 3

Deliverable 1Deliverable 1 Deliverable 2Deliverable 2 Deliverable 3Deliverable 3

Defining the WBSDefining the WBS

TaskSub Tasks

Task Sub Task

TaskSub Tasks

Task Sub Task

TaskSub Tasks

Task Sub Task

Page 50: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

50 © The Delos Partnership 200418/04/23

InputInput OutputOutputProcessProcess

Activity Lists

Activity DefinitionActivity Definition

Charter

Scope Plan

WBS

Charter

Scope Plan

WBS

Project Task List

Page 51: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

51 © The Delos Partnership 2004

Case StudyCase Study

Breakout Session 2

Page 52: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

52 © The Delos Partnership 200418/04/23

InputInput OutputOutputProcessProcess

Dependencies

Activity SequencingActivity Sequencing

Project Visual (Network Diagram)

Charter

Scope Plan

WBS

Charter

Scope Plan

WBS

Project Task List Project Task List

NetworkDiagram

Page 53: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

53 © The Delos Partnership 200418/04/23

Creating the Project VisualCreating the Project Visual(The Network Diagram)(The Network Diagram)

• 3 Types of Dependencies– Mandatory

• No choice e.g. the walls must go up before the roof can go on

– Discretionary• Preferred by stakeholders e.g. like the kitchen done before

the lounge

– External• Legally required e.g. planning permission before you start

Page 54: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

54 © The Delos Partnership 2004

Creating the Project VisualCreating the Project Visual(The Network Diagram)(The Network Diagram)Facilitates engaging the project team and

other stakeholders

Sanity Check

Helps determine the critical path

A

D

B C

E

G

F

H I

Critical Path = A:D:E:F:H:I= 2+6+2+2+2 = 16 (weeks)

2

2 6

11 2

1 1

2

2

Page 55: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

55 © The Delos Partnership 2004

Critical Path MethodCritical Path Method

The focus on CPM is to determine float in order to determine which tasks have the most and the least scheduling flexibility

A

D

B C

E

G

F

H I

Critical Path = A:D:E:F:H:I= 2+6+2+2+2 = 16 (weeks)

2

2 6

11 2

1 1

2

2

Page 56: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

56 © The Delos Partnership 200418/04/23

Critical Path MethodCritical Path Method

• What is the critical path? (no scheduling flexibility)

• Where is the float/slack? (some scheduling flexibility)

Start Finish

A=1

F=1

B=4

P=3

M=3

I=3

D=2

O=2

G=1

N=1

Dummy

C= 2

Q=3

L=6H=2

Page 57: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

57 © The Delos Partnership 200418/04/23

Creating the Project VisualCreating the Project Visual(The Network Diagram)(The Network Diagram)

• Network Diagram (AON, AOA)– Shows interdependencies of all tasks– Used for planning the project– Used for crashing and fast tracking the

project

Page 58: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

58 © The Delos Partnership 200418/04/23

Network Diagrams Aid Network Diagrams Aid Planning Planning

• Crashing– Adding more resources to critical path tasks while maintaining scope

• E.g. move resources from non-critical tasks which have float or adding extra resources

• Fast Tracking– Doing critical path tasks in parallel that were originally planned in

series

• Resource Levelling– Plans out time of tasks (and costs) in favour of a stable number of

resources used consistently in full

Page 59: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

59 © The Delos Partnership 2004

Case StudyCase Study

Breakout Session 3

Page 60: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

60 © The Delos Partnership 200418/04/23

InputInput OutputOutputProcessProcess

Activity Duration EstimatingActivity Duration Estimating

Top Down (Analogous) Estimating

Expert Judgement

Monte Carlo Analysis

Heuristic (Rule of Thumb

Historical Information (Benchmarking)

PERT

a combination of the above….

Charter

Scope Plan

WBS

Project Task List

NetworkDiagram

Charter

Scope Plan

WBS

Project Task List

NetworkDiagram

Duration Estimates

&Assumptions

Page 61: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

61 © The Delos Partnership 200418/04/23

EstimatingEstimating

• Estimating– Should be done by people doing the work not just by project

managers• Estimating Methods

– CPM• Has one task per estimate• Emphasis on controlling costs and leaving time line flexible• Can only be drawn on AOA• Can have dummies

– PERT• Has 3 estimates per activity

– Optimistic, pessimistic, most likely– Can be used for time and cost– Emphasis on time with flexibility on cost

Page 62: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

© The Delos Partnership 200418/04/23

PERTPERT(Program Evaluation and Review Technique)(Program Evaluation and Review Technique)

1. Estimate for 3 separate scenarios:Best Case (B), Most Likely (ML) and Worst Case (W)

2. Calculate Weighted average estimate by:(B + 4 ML + W ) / 6

Page 63: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

© The Delos Partnership 200418/04/23

Pert AnalysisPert Analysis - Example - Example

1. Best Case estimate = 10 hours,

Most Likely estimate = 15 hours,

Worst Case estimate = 25 hours.

2. Average estimate = (10 + 4*15 + 25) / 6

= 16 hours.

N.B.Standard Deviation = (Best Case + Worse Case) / 6Variance = [(Best Case + Worse Case) / 6] 2

Page 64: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

64 © The Delos Partnership 200418/04/23

PERT PERT

• PERT– Estimate = (P+4M+O)/6– Standard Deviation = (P-O)/6– Variance = [(P-O)/6]2

Task

A

B

C

D

O

3

2

5

7

M

6

3

12

8

P

8

4

20

8

DurationStandardDeviation

Variance

Page 65: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

65 © The Delos Partnership 200418/04/23

InputInput OutputOutputProcessProcess

PERT (Project Evaluation and Review Technique)

CPM (Critical Path Method)

Resource Levelling

Schedule DevelopmentSchedule Development

Charter

Scope Plan

WBS

Project Task List

NetworkDiagram

Duration Estimates

&Assumptions

Charter

Scope Plan

WBS

Project Task List

NetworkDiagram

Duration Estimates

&Assumptions

Project Schedule

Page 66: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

66 © The Delos Partnership 2004

Project ScheduleProject Schedule

Project PlansProject Plans

Activity ListActivity List

• A multi page document (not a Gantt chart)

• Down to the level that you are going to control at

• Rolling Weekly schedule of tasks (<4 weeks out)

The Planning HierarchyThe Planning HierarchyWBS

Page 67: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

© The Delos Partnership 200418/04/23

Designed to reduce overhead associated with maintenance of more detailed project plan on a weekly basis

Activity List is a detailed picture of the work assignments and schedule of activities over the coming weeks ( <4 weeks)

It specifies tasks, resource assignments and the expected start and end dates

It is updated on a weekly basis, based on actual performance during the preceding week

Changes in the project work plan are reflected in the activity lists and vice-versa

99

1212

33

66

Activity ListsActivity Lists

Page 68: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

68 © The Delos Partnership 2004

What is required?...………………...

by when?…………………………….

What must be done?………………….

in what order?………………………….

and by whom?……………………….

How long will each activity (and therefore the whole project) take?...

So how do I make it fit ?…………...

Objectives and deliverables

High level estimates/external milestones

Activities

Dependencies

Resourcing

Detailed work estimates

Reconcile

Scheduling SummaryScheduling Summary

Page 69: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

69 © The Delos Partnership 2004

ReconcilingReconciling

More resources

De-scope

Further breakdown - focus on what’s actually required

Critical path analysis

Re-time

Levelling - better utilisation of existing resources

Overtime!

Crash

Fast Track

Page 70: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

70 © The Delos Partnership 200418/04/23

InputInput OutputOutputProcessProcess

What type of resources are required?

How many?

For how long?

What % of time

Resource PlanningResource Planning

Charter

Scope Plan

WBS

Project Task List

NetworkDiagram

Duration Estimates

&Assumptions

Project Schedule

Charter

Scope Plan

WBS

Project Task List

NetworkDiagram

Duration Estimates

&Assumptions

Project Schedule

ResourceRequirements

Page 71: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

71 © The Delos Partnership 200418/04/23

InputInput OutputOutputProcessProcess

Top Down (Analogous) Estimating

Bottom Up Estimating

Parametric Estimating

Cost EstimatingCost Estimating

Resource RatesChart of Accounts

Historical Information

Charter

Scope Plan

WBS

Project Task List

NetworkDiagram

Duration Estimates

&Assumptions

Project Schedule

ResourceRequirements

Charter

Scope Plan

WBS

Project Task List

NetworkDiagram

Duration Estimates

&Assumptions

Project Schedule

ResourceRequirements

Cost Estimates

Page 72: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

72 © The Delos Partnership 200418/04/23

InputInput OutputOutputProcessProcess

Grouping of estimates

Cost BudgetingCost Budgeting

Charter

Scope Plan

WBS

Project Task List

NetworkDiagram

Duration Estimates

&Assumptions

Project Schedule

ResourceRequirements

Cost Estimates

Charter

Scope Plan

WBS

Project Task List

NetworkDiagram

Duration Estimates

&Assumptions

Project Schedule

ResourceRequirements

Cost Estimates

Baseline Budget

Page 73: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

73 © The Delos Partnership 200418/04/23

InputInput OutputOutputProcessProcess

Project Management Information System

Project Plan DevelopmentProject Plan Development

C h a r t e rS c o p e P l a n

W B SP r o j e c t T a s kL i s tN e t w o r k

D i a g r a mD u r a t i o n E s t i m a t e s

&A s s u m p t i o n sP r o j e c t

S c h e d u l eR e s o u r c e

R e q u i r e m e n t s

C o s t E s t i m a t e s

B a s e l i n e B u d g e t

Page 74: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

74 © The Delos Partnership 200418/04/23

InputInput OutputOutputProcessProcess

Quality PlanOrganisational PlanCommunication Plan

External Resource PlanProcurement Plan

Risk Management Plan

Project Plan DevelopmentProject Plan Development

InitialProjectCharter

InitialProjectCharter

Project Management Information System

Project Standards

Stakeholder know how

Page 75: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

75 © The Delos Partnership 2004

Quality PlanQuality Plan

Standards

What requirements do you need to meet?

Assurance

how will you assure the requirements will be met?

Control

How will you verify that the requirements have been met?

Page 76: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

76 © The Delos Partnership 2004

Organisation PlanOrganisation Plan

Responsibility Breakdown Structure

Who does what?

Staffing Management Plan

When and how human resources will be taken on and off the project

Organisational Chart

Page 77: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

77 © The Delos Partnership 2004

Communication PlanCommunication Plan

Themes

Objectives, Scope

Agree “What” to Communicate

Channels, Media

Principles

Agree “How” to Communicate

People

Materials

Develop CapabilityTo Communicate

Escalate Major Issues

Adjust Approach

Review EffectivenessAddress Issues

Listen & Document

Immediate Response

Gather Feedback

Check Understanding

Open Environment

Deliver Communication

Page 78: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

78 © The Delos Partnership 2004

Communication PlanCommunication Plan

Channel /Vehicle

Description Frequency Potential Audience

Project Plan Microsoft Project Plan withdeliverables by stage

Ongoing Steering Committee, Key Stakeholders

Status Reports Progress against deliverablesand identification of issuesand risks

Weekly Project Office

UpdatePresentations

Monthly summary of statusreports

Monthly All staff (via Key ProcessOwners)

Info letter Update on schedule, benefitsof Project One

Every Quarter All Staff

Page 79: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

79 © The Delos Partnership 2004

Case StudyCase Study

Breakout Session 4

Page 80: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

80 © The Delos Partnership 2004

Procurement Procurement Management PlanManagement PlanProcurement Planning

Solicitation Planning

Solicitation

Source Selection

Contract Administration

Contract Close Out

Page 81: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

81 © The Delos Partnership 200418/04/23

InputInput OutputOutputProcessProcess

Make or Buy

Expert Judgement (internal capability / internal capacity / need

for control/ Protection of Intellectual Property / Cost)

Contract Type Selection (Fixed Cost / Cost Reimbursable / Unit Price

Contract)

Procurement PlanningProcurement Planning

Scope Statement

Market Conditions

Procurement Management Plan

e.g. What type of contracts will be used?

How will multiple suppliers be managed?

Statement of Work

Page 82: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

82 © The Delos Partnership 200418/04/23

InputInput OutputOutputProcessProcess

Standard Forms

Expert Judgement

Solicitation PlanningSolicitation Planning

Procurement Management Plan e.g. What type of contracts will be used? How will multiple suppliers be

managed?

Statement of Work

Bid Documents

Evaluation Criteria

Page 83: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

83 © The Delos Partnership 200418/04/23

InputInput OutputOutputProcessProcess

Advertising

Bidders Conference

Agencies

Internet

SolicitationSolicitation

Bid Documents

Evaluation Criteria

Proposal

Page 84: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

84 © The Delos Partnership 200418/04/23

InputInput OutputOutputProcessProcess

Screening System

Weighting System

Contract Negotiation

Source SelectionSource Selection

ContractProposal

Evaluation Criteria

Organisational Policies

Page 85: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

85 © The Delos Partnership 200418/04/23

InputInput OutputOutputProcessProcess

Change Control

Performance Measurement

Payment

Contract AdministrationContract Administration

Contract

Work Results

Invoices

Change Requests

Contract Changes

Payment Requests

Page 86: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

86 © The Delos Partnership 200418/04/23

InputInput OutputOutputProcessProcess

Procurement Audit

Contract Close OutContract Close Out

Contract Documentation

Contract File

Formal Acceptance and Closure

Page 87: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

© The Delos Partnership 200418/04/23

Risk Management PlanRisk Management Plan

Risk Identification

Risk Quantification

Risk Response Development

Risk Response Control

Page 88: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

© The Delos Partnership 200418/04/23

EVERY project carries a number of risks...

• How likely is it to happen?

• How severe will the impact be if it does happen?

• How do we reduce the likelihood (mitigation)?

• How do we deal with the consequences if it occurs (contingency)?

What is a RiskWhat is a Risk??

A condition or circumstance which may occur which could a negative affect on the success of your project at some point IN THE FUTURE

Page 89: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

89 © The Delos Partnership 200418/04/23

InputInput OutputOutputProcessProcess

Check Lists

Interviewing

Feedback

Risk IdentificationRisk Identification

Contract Documentation

Sources of Risk

Potential Risk Events

Risk Symptoms

Page 90: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

90 © The Delos Partnership 200418/04/23

InputInput OutputOutputProcessProcess

Judgement

Decision Trees

Statistical Sums

Risk QuantificationRisk Quantification

Stakeholder Tolerance

Potential Risk Events

Cost Estimates

Duration Estimates

Risks to Accept

Risks to Pursue

Page 91: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

91 © The Delos Partnership 2004

Statistical SumsStatistical Sums

PERT

Standard Deviation = (Worse Case - Best Case)/6

Variance = [(Worse Case - Best Case)/6]2

The higher the variance the greater the risk...

Page 92: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

92 © The Delos Partnership 200418/04/23

InputInput OutputOutputProcessProcess

Mitigating Approach

Contingency Planning

Insurance

Procurement

Risk Response DevelopmentRisk Response Development

Risk Management Plan

Contingency Plans

Reserves

Risks to Accept

Risks to Pursue

Page 93: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

93 © The Delos Partnership 200418/04/23

InputInput OutputOutputProcessProcess

Work Arounds

Risk Response ControlRisk Response Control

Corrective ActionRisk Management Plan

Actual Risks

Page 94: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

© The Delos Partnership 200418/04/23

Some Common Risk Some Common Risk FactorsFactors

Project size and/or complexity

External environment influences

Technology (experience, reliability, etc)

Availability of experienced resources

Project sponsorship

Clarity of project direction

Page 95: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

95 © The Delos Partnership 2004

During the life of the project, the project manager should strive to reduce the:–impact, and–probability

of all risks facing the project. Regular (at least monthly) review meetings should re-assess the probability and impact of all risks and the risk management plan should be updated accordingly.

Severe risks should have a robust contingency plan and a comprehensive mitigation strategy, although a ‘wait and see’ policy may be appropriate in some circumstances.

Risk Management Plan Risk Management Plan (continued)(continued)

Page 96: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

96 © The Delos Partnership 2004

Rate Risks based on probability x Impact

Risk Probability x Impact = RatingMitigating ContingencyApproach Plan

a 1 1 = 1

b 3 3 = 9

c 2 3 = 6

Tips:

Avoid probability ratings of 2 (make a decision is it high or low)

Convert low probability risks to assumptions based on mitigating approach

Place mitigating approach to high probability risks into action plans

Escalate risks to steering committee based on severity and/or lack of contingency plan

Risk Management Plan Risk Management Plan (continued(continued))

Page 97: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

97 © The Delos Partnership 2004

Case StudyCase Study

Breakout Session 5

Page 98: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

98 © The Delos Partnership 2004

Planning the ProjectPlanning the ProjectKey Project Manager ActivitiesKey Project Manager Activities

• Review / Establish Project Standards & Procedures;

• Develop Project Management Information System

• Develop Project Plans

Page 99: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

99 © The Delos Partnership 2004

The PMI® Project The PMI® Project Management Life CycleManagement Life Cycle

InitiatingProcesses

InitiatingProcesses

PlanningProcesses

PlanningProcesses

ControllingProcesses

ControllingProcesses

ClosingProcesses

ClosingProcesses

ExecutingProcesses

ExecutingProcesses

Page 100: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

100 © The Delos Partnership 2004

Executing The ProjectExecuting The Project

At the end of this session you will have an understanding of the following:-

• Status Reporting

• Issue Management

• Technical Change Management

• Knowledge Management

• Project Mgrs Responsibilities

Page 101: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

101 © The Delos Partnership 2004

PMI® Executing ProcessesPMI® Executing Processes

4.2 Project PlanExecution

4.2 Project PlanExecution

N.B. All numbering refers to the PMI® Project Management Body of Knowledge (PMBOK) Knowledge Areas

Page 102: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

102 © The Delos Partnership 200418/04/23

Project Plan ExecutionProject Plan Execution

Work Authorisation to Perform activities in plan

For all issues, complete an issue report, including:

Issue description Project impact Proposed resolution

Develop mitigating approach and contingency plan for risks

Review and approve resolution Assess change Develop team skills / knowledge Communicate for commitment Manage 3rd party relationships Manage Knowledge

Input OutputProcess

Maintained Project Work plan

Work Results

Status

Reports

Change

Requests

Issues

Risks

Changes

Page 103: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

© The Delos Partnership 200418/04/23

Communicate status and expectations to the Programme/ Project Office and therefore Management

Inform team members and other Project Managers

Communicate changes, issues, variances

Facilitate coordination across the programme

Share good news (as well as bad)

Demonstrate that you are in control

Why report project status?

Status ReportingStatus Reporting

Page 104: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

© The Delos Partnership 200418/04/23

Syn

thes

ise

Issues

Progress Achieved

Risks

Activities Planned

Status Report

Make reports comprehensiveStatus Reporting (contd)Status Reporting (contd)

Time / Effort

Page 105: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

105 © The Delos Partnership 200418/04/23

Report Project StatusReport Project StatusGuiding PrinciplesGuiding PrinciplesBe careful what you ask for -- if you are only

concerned with task starts and completions, you will very likely get tasks that start and finish on time… but possibly at the expense of quality.

If you ask for information, use it.

Make sure your reporting periods are realistic.

Be creative in designing your reports.

Make use of exception reporting.

Page 106: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

106 © The Delos Partnership 2004

An ISSUE is anything that is CURRENTLY or will SHORTLY affect the progress of a project or its ability to produce its stated deliverables, and about which no agreement has yet been reached.

As the Project Manager you own the issues and must address them early and drive them to resolution

Issue ManagementIssue Management

For example:• Limited availability of resources• Problems with technology• Ambiguous business requirements

Page 107: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

© The Delos Partnership 200418/04/23

Are issues being raised?

Are the issues raised being rated appropriately?

Are issues being assigned to appropriate people for resolution?

Do all accepted issues have a reasonable resolution due date?

Are any resolution due dates about to be missed?

Are there any concerns with implementing the approved resolutions?

Are there any issues you need to raise now before they become a change request?

Issue Management (contd)Issue Management (contd)

Page 108: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

108 © The Delos Partnership 2004

Knowledge ManagementKnowledge Management

Knowledge should be centrally managedA repository should be developed for all the information gathered and produced over the life of the programme. Its purpose is to ensure that all information is:

• Readily accessible;• Consistently presented;• Protected from damage or loss;• Coordinated and reused;

• Status Reports• Correspondence• Budgets• Deliverables• Project Plans• Project Charters• Working Papers• Contracts• Timesheets• Expense Records

Page 109: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

109 © The Delos Partnership 2004

Knowledge ManagementKnowledge Management

What are we trying to avoid?

• Lost Information• Duplicated Information• Inconsistent Information• Wasted Effort• Lost Time

Page 110: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

110 © The Delos Partnership 2004

Manage changes to:

Scope: more; less; different

Time: elapsed; actual effort

Approach: sign-off/consultation; prototype/big bang

Resource:team size; skill set

Cost: budget

Technical Technical Change ManagementChange Management

Page 111: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

111 © The Delos Partnership 200418/04/23

Technical Technical Change ManagementChange Management

Complete change request form– Description of proposed change– Benefits of change– Implications of not making the change

Log change request

Assign change request and due date

Investigate request and determine resolution

Review resolution

Approve resolution

Update budget, scope and work plan

Communicate

Page 112: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

112 © The Delos Partnership 200418/04/23

Assess ChangeAssess ChangeGuiding PrinciplesGuiding Principles

Shift happens -- the project world is dynamic

Set a tolerance level -- determine the amount of change you can safely accept without formal user approval.

When you exceed your tolerance level, use the formal change request process

Manage expectations as well as scope.

Page 113: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

113 © The Delos Partnership 2004

Executing the ProjectExecuting the ProjectKey Project Manager ActivitiesKey Project Manager Activities

Periodically (weekly) assess and report the

following project status:

• Schedule -- planned, current & forecast;

• Budget -- planned, current & forecast;

• Issues -- number, progress & age;

• Risk -- severity, likelihood & strategy;

• Deliverable -- completeness, quality;

• Change Request -- number, progress, impact

Page 114: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

114 © The Delos Partnership 2004

Executing the ProjectExecuting the ProjectKey Project Manager ActivitiesKey Project Manager Activities

• Identify variations in agreed project scope

(deliverable, functional, organisational, etc);

• Analyse impact on project schedule, resource

requirements and budget;

• Revise project schedule, budget and resource

plan if change accepted;

Page 115: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

115 © The Delos Partnership 2004

The PMI® Project The PMI® Project Management Life CycleManagement Life Cycle

InitiatingProcesses

InitiatingProcesses

PlanningProcesses

PlanningProcesses

ControllingProcesses

ControllingProcesses

ClosingProcesses

ClosingProcesses

ExecutingProcesses

ExecutingProcesses

Page 116: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

116 © The Delos Partnership 2004

Controlling The ProjectControlling The Project

At the end of this session you will have an understanding of the following:-

• Earned Value Management

• Quality Management

• Stage and Gate Process

• Project Managers Responsibilities

Page 117: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

117 © The Delos Partnership 2004

PMI® Controlling PMI® Controlling ProcessesProcesses

10.3 Performance

Reporting

10.3 Performance

Reporting

4.3 Overall Change Control

4.3 Overall Change Control

N.B. All numbering refers to the PMI® Project Management Body of Knowledge (PMBOK) Knowledge Areas

Page 118: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

118 © The Delos Partnership 200418/04/23

Controlling the ProjectControlling the Project

Capture actuals Evaluate actuals versus

plan Manage Change Requests Stage and Gate review Update project scope, as

required Update project work plan

Input OutputProcess

ProjectActuals

PerformanceMeasures

ChangeRequestsMaintained Project Work

plan

Page 119: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

119 © The Delos Partnership 2004

Detailed project plan &Project charter

Deliverables &Achievedobjectives

• Is the project progressing on schedule?

• Do actuals support estimates?

• How is the risk profile changing over the life of the project?

• Has contingency been used?

• What issues are hampering progress?

• Are deliverables being produced to the required levels of quality?

• Are changes being identified and how are these being managed?

What are we ControllingWhat are we Controlling??

Page 120: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

120 © The Delos Partnership 2004

You only control three dimensions...

Time

CostQuality

Dimensions of ControlDimensions of Control

Scope

Page 121: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

© The Delos Partnership 200418/04/23

Collect and verify project actuals

Compare project actuals against plan

Determine variances

Update plan to reflect actuals

Anticipate future impacts

Progress ManagementProgress Management

Page 122: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

122 © The Delos Partnership 2004

Earned Value ManagementEarned Value Management

• Is a control mechanism to allow a contractor and client to monitor progress in terms of – Cost– Schedule– Technical Performance

• Normally created and owned by the prime contractor• Traditional project mgmt practice tends to compare

actual costs with planned expenditure and confuses actual costs with actual progress. – EVM provides a third reference point; an objective view of

the status of the contract

Page 123: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

123 © The Delos Partnership 2004

Earned Value ManagementEarned Value Management

• It works by tracking 3 parameters– Planned Value (PV): the budgeted costs of work scheduled

– Actual Costs (AC): the actual cost of work performed (ACWP)

– Earned Vale (EV): the budgeted cost of work performed

• It relies on the Work Breakdown Structure (WBS) establishing all the goods and services to be supplied…the deliverables!

• The WBS should go down to the level that earned value will be reported against (the more levels the more heavier the burden of reporting…3/4 levels should meet the needs of most reasonably complex projects)

Page 124: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

124 © The Delos Partnership 2004

Earned Value ManagementEarned Value Management

• Each deliverable/activity in the WBS can have a value (money/hours) estimated to it

• Value is “earned” by the completion of those deliverables or activities

• Estimate vs actual variances can then be generated• Simple Example Project x

– 3 Stages• 1 deliverables per stage

– 2 activities per deliverable

What is the WBS?

Page 125: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

125 © The Delos Partnership 2004

Earned Value ManagementEarned Value ManagementTimeNow

PlannedCompletion

Date

Original estimated project budget

Actual cost o

f work perfo

rmed (A

C)(P

V)

(EV)

Cost Variance

Schedule Variance (Cost)

Schedule Variance (Time)

Budget at completion (BAC)

Forecast Cost Overrun

Page 126: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

126 © The Delos Partnership 2004

Earned Value ManagementEarned Value Management

• Backward looking measures– Cost Performance Index = Earned Value / Actual Cost

• CPI = EV/AC

– Schedule Performance Index = Earned Value / Planned Value• SPI = EV / PV

– Cost Variance = Earned Value - Actual Cost• Cost Variance = EV - AC

– Schedule Variance = Earned Value - Budget• Schedule variance = EV - PV

• Forward Looking Measures– Final Cost = Budgeted Cost / CPI– Final Project Duration = Planned Project Duration / SPI (time based)

Page 127: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

© The Delos Partnership 200418/04/23

Quality management should not be something which starts ‘at the end’ - when a deliverable has been produced…rather a “stage and gate” approach should be taken over the entire live cycle

Quality ManagementQuality Management

11 22 65 74

Idea BusinessCase

Go/No-Go?

3

ProgPlanning

Go/No Go?

Implement Handover/Launch

Close

Agreed? To Plan? Changes? Review?Go/No Go?

InitialInvest

InitiateInitiate PlanPlan ExecuteExecute ControlControl CloseClose

Page 128: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

© The Delos Partnership 200418/04/23

Quality ManagementQuality Management

Prevention

Have quality criteria been defined for each

stage/deliverable?

Has the training, coaching and knowledge transfer

prepared team members for their work?

Are the estimates of effort and planned duration sufficient

to produce acceptable quality work?

Have standards and procedures been developed and are

they being followed?

Page 129: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

© The Delos Partnership 200418/04/23

Inspection

Is time being made for the assessment of deliverables

against agreed quality criteria?

Are team reviews working?

Are both the project team and independent quality

reviewers involved in assessment/sign off of deliverables?

Are approvals of deliverables going smoothly?

Have there been any change requests regarding defects in

approved deliverables?

Quality Management Quality Management (contd(contd))

Page 130: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

© The Delos Partnership 200418/04/23

Key Components

Quality Management Quality Management (contd)(contd)

Cross functional review of deliverables by stage (Stage and Gate)

Enforcement of formal standards and procedures

Consistent application of PM processes and techniques

Continuous improvement through training and skills transfer

Provision of appropriately skilled people

Page 131: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

131 © The Delos Partnership 2004

• STAGES– Gather information– Multi-functional with

parallel activities– Drive uncertainty down– Where work is done

Stage and GateStage and Gate

•GATES– Decision points for next stage

- Go/ No Go,etc (‘GO’ authorises resources for next Stage)

– Serve as quality & prioritisation control

– Are predefined & specify a set of deliverables

11 22 65 74

Idea BusinessCase

Go/No-Go?

3

ProgPlanning

Go/No Go?

Implement Handover/Launch

Close

Agreed? To Plan? Changes? Review?Go/No Go?

InitialInvest

InitiateInitiate PlanPlan ExecuteExecute ControlControl CloseClose

Page 132: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

132 © The Delos Partnership 2004

11 22 65 74

11 22 44 55 66

3

33 77

Stage and Gate (contd)Stage and Gate (contd)

Page 133: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

133 © The Delos Partnership 2004

Stage and GateStage and Gate(Functional Buy-In)(Functional Buy-In)

1 2 65 74

Idea Initial Invest.1 2 4 5 6

3

3 7Business

CasePlan

Devel.Risk

Assess.Produce Post Project

Eval.

R & D / MedicalR & D / Medical

Sales & Marketing/ OperationsSales & Marketing/ Operations

Finance / CommercialFinance / Commercial

InitiateInitiate PlanPlan ExecuteExecute ControlControl CloseClose

Page 134: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

134 © The Delos Partnership 2004

Case StudyCase Study

Breakout Session 6

Page 135: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

135 © The Delos Partnership 200418/04/23

Control the ProjectControl the ProjectGuiding PrinciplesGuiding PrinciplesControl the outcomes more than the

process.

Recognise the balance between formal and informal control.

Project management software is not a replacement for a full-time project manager.

Page 136: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

136 © The Delos Partnership 2004

Controlling the ProjectControlling the ProjectKey Project Manager ActivitiesKey Project Manager Activities

• Monitor & evaluate progress (schedule, budget);

• Make adjustments (schedule, resourcing, activity) necessary to achieve time, cost & quality targets;

• Identify and resolve all project issues

Page 137: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

137 © The Delos Partnership 2004

Controlling the ProjectControlling the ProjectKey Project Manager ActivitiesKey Project Manager Activities

• Identify and manage project risks;

• Monitor status and impact of all related projects;

• Co-ordinate allocation of project resource;

• Review & approve quality of all deliverables;

Page 138: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

138 © The Delos Partnership 2004

The PMI® Project The PMI® Project Management Life CycleManagement Life Cycle

InitiatingProcesses

InitiatingProcesses

PlanningProcesses

PlanningProcesses

ControllingProcesses

ControllingProcesses

ClosingProcesses

ClosingProcesses

ExecutingProcesses

ExecutingProcesses

Page 139: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

139 © The Delos Partnership 2004

Closing The ProjectClosing The Project

At the end of this session you will understand the importance of :-

• Post-Project Evaluation

• Evaluation of Team & Individual Performance

• Project Managers Responsibilities

Page 140: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

140 © The Delos Partnership 2004

PMI® Closing ProcessesPMI® Closing Processes

12.6 Contract Close Out

12.6 Contract Close Out

10.4 Administrative

Closure

10.4 Administrative

Closure

N.B. All numbering refers to the PMI® Project Management Body of Knowledge (PMBOK) Knowledge Areas

Page 141: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

141 © The Delos Partnership 200418/04/23

Closing the ProjectClosing the Project

Objective Review and Scope Verifications

Procurement Audit Update & Archive documentation Identify lessons learned and define

future improvements Review team members

Input OutputProcess

Contracts

ProjectCharter

ProjectAssessment

IndividualPerformanceAssessment

FutureImprovements

Contract Files

PerformanceMeasures

Page 142: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

142 © The Delos Partnership 200418/04/23

Conclude the ProjectConclude the ProjectGuiding PrinciplesGuiding Principles

This project management process provides the basis for continuous improvement.

Get some input from outside the project team.

This should not be your first attempt to document project information.

Debrief before parting.

Page 143: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

143 © The Delos Partnership 2004

Closing the ProjectClosing the ProjectKey Project Manager ActivitiesKey Project Manager Activities

• Obtain final review and approval of project deliverables;

• Assess performance against project schedule,

and budget;

• Archive project information;

• Compile closure report;

Page 144: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

144 © The Delos Partnership 2004

Project Management Project Management Framework &Framework &Organisation – Key Organisation – Key ConceptsConcepts

All numbering refers to the PMI® Project Management Body of Knowledge (PMBOK) Knowledge Areas

4. ProjectIntegration

Management

4. ProjectIntegration

Management

5. ProjectScope

Management

5. ProjectScope

Management

6. ProjectTime

Management

6. ProjectTime

Management

7. ProjectCost

Management

7. ProjectCost

Management

8. ProjectQuality

Management

8. ProjectQuality

Management

9. ProjectHuman Resource

Management

9. ProjectHuman Resource

Management

10. ProjectCommunications

Management

10. ProjectCommunications

Management

11. ProjectRisk

Management

11. ProjectRisk

Management

12. ProjectProcurementManagement

12. ProjectProcurementManagement

Page 145: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

145 © The Delos Partnership 2004

Role of the SponsorRole of the Sponsor

•The Sponsor is the customer. The one who will pay for the product the project is going to deliver

•Must be visible and lead from the Top• Own the Business Case

• Belief and energy to “Stay the course”• Balance Priorities with Business-As-Usual• Budget Holder

• Commitment to new ways of working• Manage and Influence Stakeholders• Ensure Resources are committed

Page 146: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

146 © The Delos Partnership 2004

Planning &Control

Prog Office

Role of the ProRole of the Project ject ManaManagerger.

Business Review

SystemInterface

Leadership

ChangeManagement

TeamBuilding

BenefitsManagement

Financial Well-Being

Page 147: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

147 © The Delos Partnership 200418/04/23

Functional OrganiFunctional Organissationation

FunctionalManager

ChiefExec.

FunctionalManager

FunctionalManager

• Part-time programme manager

• Direct reporting of team members to functional mgrs

• Project manager has little or no authority

• Virtually none of the team assigned full-time

ProProgrammegramme coordination coordination

Page 148: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

148 © The Delos Partnership 2004

Functional OrganisationsFunctional Organisations

Easier management of specialists

Team members report to only one supervisor

Similar resources are centralised, companies are grouped by specialisation

People place more emphasis on their functional speciality to the detriment of project

No career path in project management

Project manager has no authority

Advantages Disadvantages

Page 149: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

149 © The Delos Partnership 200418/04/23

Matrix OrganizationMatrix Organization

ProjectManager

Project

Manager

Prog.Manager

ProjectManager

ProjectManager

FunctionManager

FunctionManager

FunctionManager

TLTL

TLTL

TLTL

TLTL

TLTL

TLTL

TLTL

TLTL

TLTL

Page 150: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

150 © The Delos Partnership 2004

Matrix OrganisationsMatrix Organisations

Highly visible project objectives

Improved project manage control over resources

More support from functional organisations

Better coordination

Better horizontal and vertical dissemination of information than functional

Team members maintain a “home”

Not cost effective because of extra administrative personnel

More than one boss for project teams

More complex to monitor and control

Tougher problems with resource allocation

Need extensive policies and procedures

Functional managers may have different priorities than project managers

Higher potential for conflict and duplication of effort

Advantages Disadvantages

Page 151: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

151 © The Delos Partnership 200418/04/23

ProProjectised jectised OrganiOrganissationation

• Full-time project manager

• Direct reporting of team members to PM

• Project manager has high or total authority

• 85-100% of team assigned full-time

Prog.Manager

Prog.Manager

Project coordinationProject coordination

Page 152: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

152 © The Delos Partnership 2004

Projectised OrganisationsProjectised Organisations

Efficient project organisation

Loyalty to project

More effective communications that functional

No “home” when project complete

Lack of professionalism in disciplines

Duplication of facilities and job functions

Less efficient use of resources

Advantages Disadvantages

Page 153: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

153 © The Delos Partnership 2004

Organisational Structure Organisational Structure Influences on ProjectsInfluences on Projects

Project Manager’s Authority

% of Performing Organisation’s Personnel

Assigned Full Time to Project Work

Project Manager’s Role

Common Title for Project Manager’s Role

Project Management Administrative Staff

OrganisationType

Part-time

Project Coordinator/

Project Leader

Part-time

Virtually None

Little or None

Functional

Part-time Part-time Full-time Full-time

Part-time Full-time Full-time Full-time

Project Coordinator/

Project Leader

Project Manager/

Project Officer

Project / Program Manager

Project / Program Manager

0-25% 15-60% 50-95% 85-100%

LimitedLow to

ModerateModerate to

HighHigh to Almost

Total

ProjectisedMatrix

Weak MatrixBalanced

MatrixStrong Matrix

ProjectCharacteristics

Source: PMI® Project Management Body of Knowledge

Page 154: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

154 © The Delos Partnership 200418/04/23

ProProject ject OrganiOrganissationation

• No one “best” structure

• Major considerations are:

– Control

– Responsibility & Accountability

– Integration & Decision Making

– Communication & Visibility

– Priority & Trade-off

– Stakeholder Management

Page 155: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

155 © The Delos Partnership 2004

There are Two Life CyclesThere are Two Life Cycles

• Project Management Life Cycle– This describes what you need to do to manage the

project (Initiating, Planning, Executing, Controlling, Closing)

– You are concerned about this life cycle

• Product Life Cycle– The deliverable of a project that will be used by

the customer– The project team is not responsible for the

product life cycle

Page 156: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

156 © The Delos Partnership 2004

The Triple ConstraintThe Triple Constraint

•The three are so intertwined that a change in one will in most cases lead to a change in at least one of the others

•Management sets the priority of each constraint

Time

CostQuality

Scope

Page 157: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

157 © The Delos Partnership 200418/04/23

Project Integration Project Integration ManagementManagement

During execution…

The Project Team focus on completing tasks

The sponsor and senior management protect the project from changes and loss of resources

The project manager integrates all the pieces of the projects

Page 158: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

158 © The Delos Partnership 200418/04/23

Project Integration Project Integration ManagementManagement

• Constraints– Factors that limit the teams options– Financial, time, human, technical, other

• Historical Information– Can include tasks, WBS, Reports, Estimates, Plans, lessons

learned, benchmarks, correspondence

• Lessons Learned– Technical aspects– Project Management Life Cycle

Page 159: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

159 © The Delos Partnership 200418/04/23

Project Integration Project Integration ManagementManagement

• Project Management Methodology– Organisations set of standards, templates for managing projects

• Project Management Information System– The system set up in advance where the project manager goes

to find all project related information, to know the status of the project etc

• Baseline– The original plan plus any approved changes. Used to compare

actuals with original to monitor variances to budget

Page 160: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

160 © The Delos Partnership 200418/04/23

Project Integration Project Integration ManagementManagement

• Kick Off Meeting– A communications and coordination meeting of all parties to ensure all are

familiar with the details of the project and who will be responsible for what– Includes team, sponsor, customers, sellers, senior management, functional

managers)

• Work Authorisation System– A formal procedure for sanctioning work

• Change Requests– Formal changes to the project after it has been approved (during execution)

by integrated change control– The project plan is a formal document that needs to be controlled

Page 161: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

161 © The Delos Partnership 200418/04/23

Project Integration Project Integration ManagementManagement

• Change Control System– A collection of formal documented procedures and

supporting organisation detailing how changes will be managed, approved, and implemented

• Corrective Action– The project manager proactively looks for deviations

rather than just waiting for them to be brought to their attention

– Corrective action may involve cause and effect analysis, changes to schedule, costs, quality and risks

Page 162: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

162 © The Delos Partnership 200418/04/23

Project Integration Project Integration ManagementManagement

• Scope change control– Measure performance– Replanning– Making changes and adjusting the baseline– Taking corrective action– Documenting lessons learned

• Schedule Control• Cost Control• Quality Control• Performance Measurement• Risk Monitoring

Page 163: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

163 © The Delos Partnership 200418/04/23

Project Integration Project Integration ManagementManagement

• Managing Changes– Influencing the factors that affect change– Ensuring that change is beneficial– Determining that a change has occurred– Looking for alternatives to change– Minimising the negative impact of change– Notifying stakeholders affected by change– Managing changes as they occur

• Configuration Management– Managing the scope of the project so that the project delivers the

product required by the customer

Page 164: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

164 © The Delos Partnership 2004

Thank-you

Page 165: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

165 © The Delos Partnership 2004

Back-Up SlidesBack-Up Slides

Optional slides to be used as required to support the Q&A session following the case

study breakout sessions of to flex the course to meet a

clients particular focus area

Page 166: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

166 © The Delos Partnership 2004

The PMI® Project The PMI® Project Management Knowledge Management Knowledge Areas – Areas – Key ConceptsKey Concepts

All numbering refers to the PMI® Project Management Body of Knowledge (PMBOK) Knowledge Areas

4. ProjectIntegration

Management

4. ProjectIntegration

Management

5. ProjectScope

Management

5. ProjectScope

Management

6. ProjectTime

Management

6. ProjectTime

Management

7. ProjectCost

Management

7. ProjectCost

Management

8. ProjectQuality

Management

8. ProjectQuality

Management

9. ProjectHuman Resource

Management

9. ProjectHuman Resource

Management

10. ProjectCommunications

Management

10. ProjectCommunications

Management

11. ProjectRisk

Management

11. ProjectRisk

Management

12. ProjectProcurementManagement

12. ProjectProcurementManagement

Page 167: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

167 © The Delos Partnership 200418/04/23

Scope ManagementScope Management

• “Includes the processes required to ensure that the project includes all the work and only the work required to complete the project successfully. It is primarily concerned with controlling what is and what is not in the project”

• Check you are completing all the work• Say no to additional work• Prevent extra work or gold plating

Page 168: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

168 © The Delos Partnership 200418/04/23

Scope ManagementScope Management

• Project Selection– Murder Board– Peer Review– Scoring Models– Benefit compared to cost

• NPV, IRR, Payback, BCA

Page 169: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

169 © The Delos Partnership 200418/04/23

Scope ManagementScope Management

• Management by Objectives– Establish objectives– Periodically review– Take corrective action

• Delphi Technique– Obtain estimates from independent experts anonymously– Used to reduce bias and build consensus

Page 170: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

170 © The Delos Partnership 200418/04/23

Scope ManagementScope Management

• Work Breakdown Structure– The foundation of the project. All planning and controlling is

based on the WBS– Defines the scope of the project.– If it is not in the WBS the team should not be working on it

• WBS Dictionary– Created with the team to increase understanding of each task, who

is going to do what, – what they will need, – what they will deliver

Page 171: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

171 © The Delos Partnership 2004

Page 172: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

172 © The Delos Partnership 2004

The PMI® Project The PMI® Project Management Knowledge Management Knowledge Areas –Areas –Key ConceptsKey Concepts

All numbering refers to the PMI® Project Management Body of Knowledge (PMBOK) Knowledge Areas

4. ProjectIntegration

Management

4. ProjectIntegration

Management

5. ProjectScope

Management

5. ProjectScope

Management

6. ProjectTime

Management

6. ProjectTime

Management

7. ProjectCost

Management

7. ProjectCost

Management

8. ProjectQuality

Management

8. ProjectQuality

Management

9. ProjectHuman Resource

Management

9. ProjectHuman Resource

Management

10. ProjectCommunications

Management

10. ProjectCommunications

Management

11. ProjectRisk

Management

11. ProjectRisk

Management

12. ProjectProcurementManagement

12. ProjectProcurementManagement

Page 173: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

173 © The Delos Partnership 200418/04/23

Time ManagementTime Management

• Activity on Node (AON)– Four types of relationship

• Finish to start• Finish to finish• Start to Start• Start to finish

Activity A Activity B

Page 174: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

174 © The Delos Partnership 200418/04/23

Time ManagementTime Management

• Activity on Arrow (AOA)– One type of relationship

• Finish to start

– Can use dummies to show dependencies between tasks

– PERT and CPM can only be drawn on AOA

Activity A

Page 175: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

175 © The Delos Partnership 2004

The PMI® Project The PMI® Project Management Knowledge Management Knowledge Areas – Areas – Key ConceptsKey Concepts

All numbering refers to the PMI® Project Management Body of Knowledge (PMBOK) Knowledge Areas

4. ProjectIntegration

Management

4. ProjectIntegration

Management

5. ProjectScope

Management

5. ProjectScope

Management

6. ProjectTime

Management

6. ProjectTime

Management

7. ProjectCost

Management

7. ProjectCost

Management

8. ProjectQuality

Management

8. ProjectQuality

Management

9. ProjectHuman Resource

Management

9. ProjectHuman Resource

Management

10. ProjectCommunications

Management

10. ProjectCommunications

Management

11. ProjectRisk

Management

11. ProjectRisk

Management

12. ProjectProcurementManagement

12. ProjectProcurementManagement

Page 176: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

176 © The Delos Partnership 200418/04/23

Cost ManagementCost Management

• Cost Estimating– Should be done by the person doing the

work– Should be based on the WBS to improve

accuracy– Historical information is key to improving

accuracy

Page 177: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

177 © The Delos Partnership 200418/04/23

Cost ManagementCost Management

• Cost Estimating– Analogous Estimating

• Top down expert judgement• Quick and cheap to do• Less accurate

– Bottom Up estimating• Estimates based on WBS are rolled up to get a project total• Takes time and more costly to do• More Accurate

– Parametric Testing (Uses a mathematical model e.g.x hours per test)

• Regression analysis (Scatter Diagram)• Learning Curve

– The 100th test will be quicker than the 1st

Page 178: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

178 © The Delos Partnership 200418/04/23

Cost ManagementCost Management

• Progress Reporting– 50/50 Rule

• A task is considered 50% complete when it begins and only gets remaining 50% when task complete

– 20/80 Rule• A task is considered 20% complete when it begins and only gets

remaining 80% when task complete

– 0/100 Rule• A task only gets credit when completed

Page 179: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

179 © The Delos Partnership 2004

Earned Value ManagementEarned Value Management

• Is a control mechanism to allow a contractor and client to monitor progress in terms of – Cost– Schedule– Technical Performance

• Normally created and owned by the prime contractor• Traditional project mgmt practice tends to compare

actual costs with planned expenditure and confuses actual costs with actual progress. – EVM provides a third reference point; an objective view of

the status of the contract

Page 180: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

180 © The Delos Partnership 2004

Earned Value ManagementEarned Value Management

• It works by tracking 3 parameters– Planned Value (PV): the budgeted costs of work scheduled

– Actual Costs (AC): the actual cost of work performed (ACWP)

– Earned Vale (EV): the budgeted cost of work performed

• It relies on the Work Breakdown Structure (WBS) establishing all the goods and services to be supplied…the deliverables!

• The WBS should go down to the level that earned value will be reported against (the more levels the more heavier the burden of reporting…3/4 levels should meet the needs of most reasonably complex projects)

Page 181: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

181 © The Delos Partnership 2004

Earned Value ManagementEarned Value Management

• Each deliverable/activity in the WBS can have a value (money/hours) estimated to it

• Value is “earned” by the completion of those deliverables or activities

• Estimate vs actual variances can then be generated• Simple Example Project x

– 3 Stages• 1 deliverables per stage

– 2 activities per deliverable

What is the WBS?

Page 182: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

182 © The Delos Partnership 2004

Earned Value ManagementEarned Value ManagementTimeNow

PlannedCompletion

Date

Original estimated project budget

Actual cost o

f work perfo

rmed (A

C)(P

V)

(EV)

Cost Variance

Schedule Variance (Cost)

Schedule Variance (Time)

Budget at completion (BAC)

Forecast Cost Overrun

Page 183: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

183 © The Delos Partnership 2004

Earned Value ManagementEarned Value Management

Acronym Term Meaning

PV Planned ValueWhat is the estimated vale of the work planned to be done?

EV Earned Value What is the estimated vale of the work actually done?

AC Actual Cost What is the actual cost incurred?

BACBudget at

CompletionWhat was the budget for the total job?

EACEstimate at completion

What is now expected to be the total cost of the project?

ETCEstimate to complete

From today, how much more is the project expected to cost?

VACVariance at Completion

How much under or over budget is the project now expected to be?

Page 184: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

184 © The Delos Partnership 2004

Earned Value ManagementEarned Value Management

Acronym Term Meaning

Cost Variance CV EV-ACNegative is over budgetPositive is under budget

Schedule Variance SV EV-PVNegative is behind schedulePositive is ahead of schedule

Cost Performance Index CPI

EV/AC The project is achieving $_ out of every $1spent

Schedule Performance Index SPI

EV/PVThe project is progressing at _% of the rate originally planned

Estimate at Completion EAC

BAC/CPIWhat is now expected to be the total cost of the project?

Estimate to Complete ETC

EAC-ACFrom today, how much more is the project expected to cost?

Variance at Completion VAC

BAC-EACHow much under or over budget is the project now expected to be?

Page 185: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

185 © The Delos Partnership 2004

Earned Value ManagementEarned Value Management

• Each deliverable/activity in the WBS can have a value (money/hours) estimated to it

• Value is “earned” by the completion of those deliverables or activities

• Estimate vs actual variances can then be generated• Simple Example Project x

– 3 Stages• 1 deliverables per stage

– 2 activities per deliverable

What is the WBS?

Page 186: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

186 © The Delos Partnership 2004

Earned Value ManagementEarned Value Management

• Tips– EV comes at the beginning of every formula– If it is a “variance” it is EV minus something– If it is an “index” it is EV divided by something– If the formula relates to cost use AC– If the formula relates to schedule us PV– Negative is bad; positive is good– Greater than one is good; less than one is bad

Page 187: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

187 © The Delos Partnership 200418/04/23

Cost ManagementCost Management

PV

AC ETCEAC

BAC

TodayOriginal Plan

Page 188: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

188 © The Delos Partnership 2004

Project SelectionProject Selection

Project A Which Project To Pick?

Net Present Value $85,000

Project B

$75,000

IRR 14% 18%

Payback Period 20 Months 25 Months

Benefit Cost Ratio 2.43 1.23

Page 189: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

189 © The Delos Partnership 2004

Project Cost ManagementProject Cost Management

• Sunk Costs– A project with a budget of £300,000 is halfway

through and has spent £600,000. Do you consider the £300,000 when deciding to continue?

– Accounting standards require that sunk costs are not considered when deciding whether to continue with a troubled project

Page 190: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

190 © The Delos Partnership 2004

Project Cost ManagementProject Cost Management

• Variable Costs– Any cost that varies with the amount of work e.g. team wages,

consultancy fees

• Fixed Cost– Any cost that do not change, e.g. insurance

• Direct Costs– Costs directly attributable to the work on the project

• Indirect Costs– Overhead costs that are shared e.g. HR support

Page 191: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

191 © The Delos Partnership 2004

The PMI® Project The PMI® Project Management Knowledge Management Knowledge Areas – Areas – Key ConceptsKey Concepts

All numbering refers to the PMI® Project Management Body of Knowledge (PMBOK) Knowledge Areas

4. ProjectIntegration

Management

4. ProjectIntegration

Management

5. ProjectScope

Management

5. ProjectScope

Management

6. ProjectTime

Management

6. ProjectTime

Management

7. ProjectCost

Management

7. ProjectCost

Management

8. ProjectQuality

Management

8. ProjectQuality

Management

9. ProjectHuman Resource

Management

9. ProjectHuman Resource

Management

10. ProjectCommunications

Management

10. ProjectCommunications

Management

11. ProjectRisk

Management

11. ProjectRisk

Management

12. ProjectProcurementManagement

12. ProjectProcurementManagement

Page 192: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

192 © The Delos Partnership 200418/04/23

Quality ManagementQuality Management

• Pareto Analysis

• Cause and Effect / Fishbone / Ishikawa Diagram

• Statistical Sampling– Studying the whole population would take too long,

cost too much, be destructive

Page 193: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

193 © The Delos Partnership 200418/04/23

Quality ManagementQuality Management

• Find the following on the charts following– Upper control Limit– Lower Control Limit– The process is out of control– Assignable cause– Normal and expected variation– Rule of Seven– Specification limits– Three Sigma– Six Sigma– Normal Distribution Curve

Page 194: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

194 © The Delos Partnership 2004

Quality ManagementQuality Management

Page 195: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

195 © The Delos Partnership 2004

Quality ManagementQuality Management

Page 196: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

196 © The Delos Partnership 2004

Page 197: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

197 © The Delos Partnership 2004

The PMI® Project The PMI® Project Management Knowledge Management Knowledge Areas Areas Key ConceptsKey Concepts

All numbering refers to the PMI® Project Management Body of Knowledge (PMBOK) Knowledge Areas

4. ProjectIntegration

Management

4. ProjectIntegration

Management

5. ProjectScope

Management

5. ProjectScope

Management

6. ProjectTime

Management

6. ProjectTime

Management

7. ProjectCost

Management

7. ProjectCost

Management

8. ProjectQuality

Management

8. ProjectQuality

Management

9. ProjectHuman Resource

Management

9. ProjectHuman Resource

Management

10. ProjectCommunications

Management

10. ProjectCommunications

Management

11. ProjectRisk

Management

11. ProjectRisk

Management

12. ProjectProcurementManagement

12. ProjectProcurementManagement

Page 198: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

198 © The Delos Partnership 200418/04/23

Human Resource Human Resource ManagementManagement

• Responsibility Exercise Handout

• Halo Effect– Thinking someone will be good at everything

just because they are very good at one thing

• MCGregor’s Theory X and Yx x

X Y

Page 199: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

199 © The Delos Partnership 2004

Maslow’s Hierarchy of Maslow’s Hierarchy of NeedsNeeds

SelfActualisation

Esteem

Social

Safety

Physiological

• Growth, learning

• Accomplishment, appreciation

• Love, affection, friends, approval

• Security, stability, freedom

• Food, water, shelter

Page 200: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

200 © The Delos Partnership 2004

Sources of ConflictSources of Conflictwithin Projectswithin Projects

Schedules

Competing priorities

Resources

Technical Opinions

Administrative procedures

Cost

Personality

Frequency as cause of conflict

Low

High

Source: PMI Project Management Body of Knowledge

Page 201: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

201 © The Delos Partnership 2004

Effectiveness in Project Situations

Low

High

Conflict Resolving Conflict Resolving TechniquesTechniquesConfronting (Problem Solving)

Working a shared problem

Smoothing

Emphasizing common ground

Compromising

Bringing some degree of satisfaction to both sides

Withdrawal (avoidance)

Postponing/waiting for better timing

ForcingPush your viewpoint at expense of others

Page 202: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

202 © The Delos Partnership 2004

Power TypesPower Types

Expert

Power based on knowledge/skills/experience

Reward

Power based on ability to reward

Formal

Power based on position

Referent

Power based on association with someone in a higher position

Penalty

Power based on ability to penalise

Effectiveness in Project Situations

Low

High

Page 203: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

203 © The Delos Partnership 2004

Hertzberg's Motivation Hertzberg's Motivation TheoryTheory

Hygiene factors cannot motivate but lack of them will de-motivate

Working conditions, Salary, Personal life, Relationships at work, Security, Status

Motivating agents motivate people

Responsibility, Self Actualisation, Professional Growth, Recognition

Design Jobs with right balanceStretch vs Comfort Zone vs Grunge

“If you want people to do a good job give them a good job to do” (Hertzberg)

Page 204: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

204 © The Delos Partnership 2004

Page 205: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

205 © The Delos Partnership 2004

The PMI® Project The PMI® Project Management Knowledge Management Knowledge AreasAreasKey ConceptsKey Concepts

All numbering refers to the PMI® Project Management Body of Knowledge (PMBOK) Knowledge Areas

4. ProjectIntegration

Management

4. ProjectIntegration

Management

5. ProjectScope

Management

5. ProjectScope

Management

6. ProjectTime

Management

6. ProjectTime

Management

7. ProjectCost

Management

7. ProjectCost

Management

8. ProjectQuality

Management

8. ProjectQuality

Management

9. ProjectHuman Resource

Management

9. ProjectHuman Resource

Management

10. ProjectCommunications

Management

10. ProjectCommunications

Management

11. ProjectRisk

Management

11. ProjectRisk

Management

12. ProjectProcurementManagement

12. ProjectProcurementManagement

Page 206: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

206 © The Delos Partnership 2004

Project CommunicationsProject CommunicationsManagementManagement• Can the project manager control all

communications

– No

• Should the project manager try to control communications

– Yes, otherwise rumours and speculations and mis-understanding fill the vacuum

• 90% of a project managers time is spent communicating– Communication is the single most important skill in

project management

Page 207: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

207 © The Delos Partnership 200418/04/23

Project CommunicationsProject CommunicationsManagementManagement

• Communication Channels– # Channels = (N2-N)/2

• Where N is the number of people

• How many communication channels are there when there are 5 stakeholders involved in a project?

• How many are there when there 10?

Page 208: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

208 © The Delos Partnership 2004

Project CommunicationsProject CommunicationsManagementManagement• Communications Planning

– Determining the information needs of the stakeholders

• Communications Management Plan

– What information do you need to send to who, when, how etc

• Information Distribution

– Implementing the communications management plan

Page 209: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

209 © The Delos Partnership 2004

Project CommunicationsProject CommunicationsManagementManagement• Non-Verbal

– 55% of all communication is non-verbal

• Para lingual

– The pitch and tone of your voice which often conveys your real message

• Active Listening

– Confirming you are listening, paraphrasing back, asking for clarification

• Effective Listening

– Watching the speaker for body language, thinking about what you are going to say before responding, asking questions, providing feedback

• Feedback

– Checking understanding of the message

Page 210: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

210 © The Delos Partnership 2004

Project CommunicationsProject CommunicationsManagementManagement• Performance Reporting

– Reports are communication tools and may include

• Status reports• Progress reports• Trend reports• Variance reports• Earned value reports• Forecasting reports

Page 211: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

211 © The Delos Partnership 2004

Project CommunicationsProject CommunicationsManagementManagement• Administrative Closure is part of communications

– All projects must be closed out• At end of project• At end of each phase• When contract is terminated

– Administrative Closure includes• Product Verification• Financial closure• Lessons Learned• Update records• Final project performance reporting• Project Archives

Page 212: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

212 © The Delos Partnership 2004

Page 213: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

213 © The Delos Partnership 2004

The PMI® Project The PMI® Project Management Knowledge Management Knowledge Areas – Areas – Key ConceptsKey Concepts

All numbering refers to the PMI® Project Management Body of Knowledge (PMBOK) Knowledge Areas

4. ProjectIntegration

Management

4. ProjectIntegration

Management

5. ProjectScope

Management

5. ProjectScope

Management

6. ProjectTime

Management

6. ProjectTime

Management

7. ProjectCost

Management

7. ProjectCost

Management

8. ProjectQuality

Management

8. ProjectQuality

Management

9. ProjectHuman Resource

Management

9. ProjectHuman Resource

Management

10. ProjectCommunications

Management

10. ProjectCommunications

Management

11. ProjectRisk

Management

11. ProjectRisk

Management

12. ProjectProcurementManagement

12. ProjectProcurementManagement

Page 214: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

214 © The Delos Partnership 200418/04/23

Project Risk ManagementProject Risk Management

• Is there more risk at the start or the end of a project?

• Risk Management Involves– Risk management planning– Risk Identification– Qualitative Risk Analysis– Quantitative Risk Analysis– Risk Response Planning

Page 215: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

215 © The Delos Partnership 200418/04/23

Project Risk ManagementProject Risk Management

• Step 1 – Risk Management Planning– Formal or informal dependent on perceived risk of

project• Formal risk management plans may include

– Methodology– Roles and Responsibilities– Budget for risk– Timing– Risks thresholds– Risk Tracking

Page 216: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

216 © The Delos Partnership 200418/04/23

Project Risk ManagementProject Risk Management

• Step 2 – Risk Identification– Brainstorming– Delphi Technique– Interviewing stakeholders / experts– SWOT– During team meetings (status meetings)

• Outputs from Risk Identification– Risks– Risk triggers

• what will be the symptom or early warning sign

Page 217: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

217 © The Delos Partnership 200418/04/23

Project Risk ManagementProject Risk Management

• Step 3 – Qualitative Risk Analysis– Probability and impact– Assumption testing

• Too many guesses make the data unreliable

– Data Precision Ranking• How reliable is our information

• Output from Risk Analysis– Risk Rating Matrix

Page 218: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

218 © The Delos Partnership 200418/04/23

Project Risk ManagementProject Risk Management

• Step 4 – Quantitative Risk Analysis– Expected value

• Which risks warrant a response• Determine overall project risk• Determine cost and schedule reserves

Page 219: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

219 © The Delos Partnership 200418/04/23

Project Risk ManagementProject Risk Management

• Step 4 – Quantitative Risk AnalysisDecision Tree

Would you volume test?Do Volume Test$100,000

Do Not doVolume Test$0

Failure: 30% probability and $140,000 impact

Pass: No impact

Pass: No impact

Failure: 75% probability and $440,000 impact

Page 220: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

220 © The Delos Partnership 200418/04/23

Project Risk ManagementProject Risk Management

• Step 4 – Quantitative Risk Analysis– Monte Carlo Simulation

• Evaluates the project not the task

• Provides the probability of completing the project on any specific day for any specific cost

• Determines probability of any given task being on the critical path

• Can be used to assess cost and schedule impacts

Page 221: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

221 © The Delos Partnership 200418/04/23

Project Risk ManagementProject Risk Management

• Step 5 – Risk Response Planning– Assign Owner– Decide risk response strategy

• Avoid– Eliminate cause of risk

• Mitigate– Reduce probability or impact

• Accept– Do nothing and live with consequences if it happens

• Transfer– Insure against

Page 222: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

222 © The Delos Partnership 2004

Page 223: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

223 © The Delos Partnership 2004

The PMI® Project The PMI® Project Management Knowledge Management Knowledge AreasAreasKey ConceptsKey Concepts

All numbering refers to the PMI® Project Management Body of Knowledge (PMBOK) Knowledge Areas

4. ProjectIntegration

Management

4. ProjectIntegration

Management

5. ProjectScope

Management

5. ProjectScope

Management

6. ProjectTime

Management

6. ProjectTime

Management

7. ProjectCost

Management

7. ProjectCost

Management

8. ProjectQuality

Management

8. ProjectQuality

Management

9. ProjectHuman Resource

Management

9. ProjectHuman Resource

Management

10. ProjectCommunications

Management

10. ProjectCommunications

Management

11. ProjectRisk

Management

11. ProjectRisk

Management

12. ProjectProcurementManagement

12. ProjectProcurementManagement

Page 224: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

224 © The Delos Partnership 2004

Procurement ManagementProcurement Management

Step What happens Output

1 Procurement Planning Make or Buy?Do it yourself or outsource. Select Contract Type. Draft scope of work

2 Solicitation Planning RFP created RFP

3 Solicitation Questions and Answers Proposal Created

4 Source Selection Pick One Contract Signed

5 Contract administration Make or Buy? Work completed

1 Procurement Planning Finish Done

Page 225: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

225 © The Delos Partnership 2004

Procurement ManagementProcurement Management

• 1 Procurement Planning• Make vs Buy• Main reason to buy is to reduce

risk (cost, performance, scope of work)• Main reason to make is to utilise

own resources, retain control, protect Intellectual Property

Page 226: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

226 © The Delos Partnership 2004

Procurement ManagementProcurement Management

• 2 Solicitation Planning– Evaluation Criteria

• Understanding or need

• Life cycle cost

• Technical ability

• Management approach

• Project Management ability

• Contract Type Selection• 4 Main Contract Types

– Cost Reimbursable

– Time & Material

– Fixed Price

– Purchase Order

Page 227: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

227 © The Delos Partnership 2004

Procurement ManagementProcurement Management

A contract is a formal agreement

All requirements should be specifically stated in the contract

All contract requirements must be met

Changes must be in writing and formally documented

Page 228: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

228 © The Delos Partnership 2004

Procurement ManagementProcurement Management

• Contract Types– Cost Reimbursable (risk mostly with the buyer)

• Cost plus fixed fee (CPFF)– Most common form of fixed fee as seller incentivised to

control project as extra work does not result in extra profit

• Cost plus percentage of costs (CPPC)– Illegal in most governments. Why?

• Cost plus incentive/award fee (CPIF/CPAF)

Page 229: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

229 © The Delos Partnership 2004

Procurement ManagementProcurement Management

• Contract Types– Time & Material (risk mostly with the

buyer)• Quick to arrange• Suitable for low cost/short term contracts• Simple to administer

Page 230: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

230 © The Delos Partnership 2004

Procurement ManagementProcurement Management

• Contract Types– Fixed Price (Risk mostly with the seller)

• Fixed Price Incentive Fee (FPIF)– E.g. Fixed fee plus $X for every month you finish

early

• Fixed Price Economic Price Adjustment– E.g. Annual adjustment based on inflation for

long term contracts

Page 231: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

231 © The Delos Partnership 2004

Procurement ManagementProcurement Management

• Contract Types– Purchase Order

• Unilateral (signed by one party only)• Used for simple commodity items

Page 232: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

232 © The Delos Partnership 2004

Procurement ManagementProcurement Management

SituationType of Contract

to Use

You need work to start right away ?

You want to buy expertise in determining what needs to be done ?

You know exactly what needs to be done ?

You are buying the services of a programmer to augment your staff ?

You need work done but you do not have time to audit invoices on this work

?

Page 233: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

233 © The Delos Partnership 2004

Procurement ManagementProcurement Management

• 3 Solicitation– Bidders conference– Qualified sellers list– Advertising

Page 234: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

234 © The Delos Partnership 2004

Procurement ManagementProcurement Management

• 4 Source Selection– Presentations by sellers– Negotiations with short listed sellers

• Main items to negotiate on a contract are– Responsibilities– Authority– Applicable law– Technical and management approaches– Contract financing– Price

Page 235: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

235 © The Delos Partnership 2004

Procurement ManagementProcurement Management

• 5 Contract Administration– FP

• Check to make sure work in scope is being done• Watch for overpriced change orders• Check for scope mis-understandings

– T&M• Provide day to day direction• Focus on deliverables and project schedule• Decide if alternative contract type better

– CPFF• Audit sellers costs• Watch for seller adding resources that do not add value

or part of scope

Page 236: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

236 © The Delos Partnership 2004

Procurement ManagementProcurement Management

• 6 Contract Closeout (When a contract ends or when terminated before work completed– Product Verification– Financial closure

• make final payments

– Contract performance reporting• Assess effectiveness of contract type chosen

– Contract File• Archive documents

– Procurement Audits• A structured review of the procurement process to capture

lessons learned

Page 237: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

237 © The Delos Partnership 2004

The PMI® Project The PMI® Project Management Knowledge Management Knowledge AreasAreasKey ConceptsKey Concepts

All numbering refers to the PMI® Project Management Body of Knowledge (PMBOK) Knowledge Areas

4. ProjectIntegration

Management

4. ProjectIntegration

Management

5. ProjectScope

Management

5. ProjectScope

Management

6. ProjectTime

Management

6. ProjectTime

Management

7. ProjectCost

Management

7. ProjectCost

Management

8. ProjectQuality

Management

8. ProjectQuality

Management

9. ProjectHuman Resource

Management

9. ProjectHuman Resource

Management

10. ProjectCommunications

Management

10. ProjectCommunications

Management

11. ProjectRisk

Management

11. ProjectRisk

Management

12. ProjectProcurementManagement

12. ProjectProcurementManagement

Professional ResponsibilityProfessional Responsibility

Page 238: 1 © The Delos Partnership 2004 Welcome to the Project Management Foundation Course Based on the Project Management Body of Knowledge (PMBOK TM ) from the

238 © The Delos Partnership 2004

Professional ResponsibilityProfessional Responsibility

• In a broad sense professional responsibility means– Do the right thing– Follow the right process– Act ethically, fairly and professionally– Watch for conflicts of interest– Report violations– Increase knowledge and practice– Deal with problems