Presented by: Stephen DeMatteo Engineering Technology, Construction ET- 494 Fall 2014 Advisors: Ed Rode Cris Koutsougeras Residential Fourplex Design

Upload: tamsin-mckinney

Post on 18-Jan-2018

220 views

Category:

Documents


0 download

DESCRIPTION

Comparable # Georgia Ave, Kenner La  Townhome/ 2-Plex  900 sq. ft  2 bed  2 bath Rent Price = $850  $100/sq ft = $180,000  Yearly income = $20,400  Pay off investment = 9 years

TRANSCRIPT

Page 1: Presented by: Stephen DeMatteo  Engineering Technology, Construction  ET- 494 Fall 2014  Advisors: Ed Rode Cris Koutsougeras

Presented by: Stephen DeMatteo

Engineering Technology, Construction

ET- 494 Fall 2014

Advisors: Ed Rode Cris Koutsougeras

Residential Fourplex Design

Page 2: Presented by: Stephen DeMatteo  Engineering Technology, Construction  ET- 494 Fall 2014  Advisors: Ed Rode Cris Koutsougeras

Cost Analysis

Site Survey

Floor Plan and Elevation Drawings

Deliverables

Page 3: Presented by: Stephen DeMatteo  Engineering Technology, Construction  ET- 494 Fall 2014  Advisors: Ed Rode Cris Koutsougeras

Comparable #14132 Georgia Ave, Kenner La

Townhome/ 2-Plex 900 sq. ft 2 bed 2 bath

Rent Price = $850 $100/sq ft = $180,000 Yearly income = $20,400

Pay off investment = 9 years

Cost Analysis

Page 4: Presented by: Stephen DeMatteo  Engineering Technology, Construction  ET- 494 Fall 2014  Advisors: Ed Rode Cris Koutsougeras

Comparable #2 4045 Idaho Dr, Kenner La

4-Plex 1,128 sq. ft 2 bed 2 bath

Rent Price = $900 $100/sq ft = $451,200 Yearly income = $43,200

Pay off investment = 10.5 years

Cost Analysis

Page 5: Presented by: Stephen DeMatteo  Engineering Technology, Construction  ET- 494 Fall 2014  Advisors: Ed Rode Cris Koutsougeras

Comparable #3 2916 Tennessee St, Kenner La

4-Plex 1,100 sq. ft 2 bed 1 full bath 1 half bath

Rent Price = $850 $100/sq ft = $440,000 Yearly income = $40,800

Pay off investment = 11 years

Cost Analysis

Page 6: Presented by: Stephen DeMatteo  Engineering Technology, Construction  ET- 494 Fall 2014  Advisors: Ed Rode Cris Koutsougeras

My Complex 4-Plex 912 sq. ft 2 bed 1 full bath

Rent Price = $1000 $100/sq ft = $364,800 Yearly income = $48,000

Pay off investment = 7.5 years

For this project each unit will consist of two bedrooms, one bath, a kitchen, living room, and dining room.

Without going into details of the finishes we can expect each unit to see anywhere between $900 to $1050 per month.

This is considering it is new construction and a highly desirable area.

Assessment

Page 7: Presented by: Stephen DeMatteo  Engineering Technology, Construction  ET- 494 Fall 2014  Advisors: Ed Rode Cris Koutsougeras

Kenner, LA 70065

37th Street and Connecticut Ave

Lot size: 60’x80’

Total of 4 lots

Projected Site

Page 8: Presented by: Stephen DeMatteo  Engineering Technology, Construction  ET- 494 Fall 2014  Advisors: Ed Rode Cris Koutsougeras

Survey

Page 9: Presented by: Stephen DeMatteo  Engineering Technology, Construction  ET- 494 Fall 2014  Advisors: Ed Rode Cris Koutsougeras

1st Floor

Page 10: Presented by: Stephen DeMatteo  Engineering Technology, Construction  ET- 494 Fall 2014  Advisors: Ed Rode Cris Koutsougeras

2nd Floor

Page 11: Presented by: Stephen DeMatteo  Engineering Technology, Construction  ET- 494 Fall 2014  Advisors: Ed Rode Cris Koutsougeras

Front Elevation

Page 12: Presented by: Stephen DeMatteo  Engineering Technology, Construction  ET- 494 Fall 2014  Advisors: Ed Rode Cris Koutsougeras

Right Side Elevation

Page 13: Presented by: Stephen DeMatteo  Engineering Technology, Construction  ET- 494 Fall 2014  Advisors: Ed Rode Cris Koutsougeras

Left Side Elevation

Page 14: Presented by: Stephen DeMatteo  Engineering Technology, Construction  ET- 494 Fall 2014  Advisors: Ed Rode Cris Koutsougeras

Back Elevation

Page 15: Presented by: Stephen DeMatteo  Engineering Technology, Construction  ET- 494 Fall 2014  Advisors: Ed Rode Cris Koutsougeras

February 21st – Finish Foundation Drawings

March 7th – Finish Detailed drawings

March 21st – Finish Electrical Drawings

April 14th – Complete Material Takeoff

April 25th – Finish Construction Schedule

Spring 2014 Semester