robert adkins et 494 instructor: dr. cris koutsougeras advisor: mr. rode 12/04/2013
TRANSCRIPT
Senior Design Project
Robert AdkinsEt 494Instructor: Dr. Cris KoutsougerasAdvisor: Mr. Rode12/04/2013
Abstract
My senior design project will embody many disciplines from the engineering profession.
In particular, my project will demonstrate modern construction based engineering techniques that I have learned throughout my career at southeastern.
For this project I will fully design a multiple family home that will resemble a traditional New Orleans style home.
Project Will Include
Rough design sketch Construction estimate Detailed project schedule Property and structural drawings
(preformed on AutoCAD) Property analysis
Site Analysis
Investigated different types of structures
Took basic measurements to assist in design
Researched current building code in different areas to insure proper design for structure in this area.
Site Analysis contd.
The site I choose for my project is in Lakeview.
Lakeview is a community in New Orleans and was hit hard by hurricane Katrina and because of this all construction on new homes in this area must be raised.
Lot size: 50 x 145
6910 ORLEANS AVE NEW ORLEANS, LA 70124 (LAKEVIEW)
Piliminary Design
When building a house in New Orleans engineers face several building requirements and constraints.
All new homes build in New Orleans (Lakeview area) must be raised.
The height someone must build their home is based on FEMA BFE (base flood elevation) requirements.
The BFE for the area my building is between 1.5 ft – 3.5 ft.
Base Flood Elevation (New Orleans)
BFE (Lakeview)
Design contd.
Through my investigations and research I decided the suitable height for my structure should be 4ft or 48in.
Using this elevation will ultimately decrease the structures chances of being devastated by flooding.
To achieve this elevation proper foundation support is critical.
Footings
Footings for each post will consist of 24”x24”x12” concrete block pads with #4 rebar ties for support.
The exterior foundation walls will consist of 24”x24”x12” concrete around the perimeter of the structure.
Due to soil conditions in this area purlins must be utilized to decrease the chance of foundation and structure damage due to the land sinking.
Post and Beam
Posts typically extend from separate concrete footings to beams or girders that are connected to the foundation.
Posts are spaced at standard intervals around the perimeter of the building and at intermediate points beneath the building.
I have utilized a post and beam foundation.
Post
The post will consist of concrete masonry units. (CMU)
The post will consist of 5 CMU stacked with #3 rebar that will secure or tie into concrete pads.
The rebar is used to strengthen the structures foundation.
The post will be filled with concrete for additional support.
The post will support girder beam.
Foundation contd.
Girder
A girder is a structural support which is designed to carry transverse loads, and to transfer those loads to vertical supports such as columns.
The building I have design will use 6”x8” girder.
The girder will be spliced and connected using steal plates located above each post.
Foundation contd.
Floor joist- 2”x12”x20’ using these joist will allow me to span approximately 20’9’’ (16’’oc).
Each floor joist will be connected using joist hangers.
Rim joist- 2”x12”x20’ Sill plate- 2”x8”x8’
(treated) the sill plate will be secured to foundation using 5/8” anchor bolts (24”oc)
¾” plywood for flooring (tongue and groove)
Wall System
Wall studs – 2”x4”x10’ (16’’oc)
Corner post- (3) 2”x4”x10’ King stud- 2”x4”x10’ Header- 2”x6” Top and Bottom Plate-
2”x4”x8’ (double top plate and treated bottom plate)
Windows- 2’x3’ and 6’x6’ Doors- 80”x36”x1 ¾” Center wall
Wall studs- 2”x4”x10’ (staggered)
Top and Bottom Plate- 2”x6”x8’
Roof System
My structure has a Gable Style roof.
Ceiling joist- 2”x8” (16”oc)
Rafter- 2”x6” (24”oc) Pitch- 8/12 Ridge beam- 2”x12” Gable wall studs- 2”x4” Sheathing- ½” plywood Felt paper- 15lb Shingles- Three tab
36’’x12”
Floorplan
Door and Window Schedule
Front Elevation
Left Elevation
Rear Elevation
Right Elevation
Ceiling Joint
Schedule
Scheduling is the process of breaking down a large project into smaller activities to determine the amount of time each activity will take.
Each activities beginning will depend on a previous activity. The schedule will identify the total time duration of a
project as well as each activities time duration Project Name : New Orleans Multiply family home Start Date: 06/03/2013 End Date: 12/27/2013 Total Duration: 208 days Total Working Days : 151 days
Et 494 (backup)\Et 494 Schedule.xlsx
EstimateConstuction Material Estimate Perimeter 240 ft 2880 in.
Square Ft 3200 ft
Section Material Deninsion of Material Unit Quantity Waste (5%) Total Cost
FoundationA) Pillings 45 2.25 47.25 10,125.00B) Footings Cmu 16''x8''x8'' CMU 280 14 294 364.00
U Block 16''x8''x8'' CMU 40 2 42 58.00Concrete (footings) 24''x24''x12''(1.78 cy) c.y. 80.2 4.01 84.21 9,624.00Re-bar #4 ft. 550 27.5 577.5 479.16Re-bar #3 ft. 680 34 714 364.75Anchor Bolts 5/8'' x 9'' (J Bolt) Quan. 160 8 168 1,953.60Girder 6''x8''x12' ft. 7 0.35 7.35 336.00Steal Plates 4''x12'' Quan. 10 0.5 10.5 122.10Concrete (fill) 16" x 8" x 8" c.y. 40 2 42 4,800.00
Floor SystemA) Floor Joists Floor Joist 2''x12''x20' ft. 120 6 126 1,569.60
Joist hangers 2''x12'' Quan. 240 12 252 549.60Sill plate 2''X8''x10' (treated) ft. 32 1.6 33.6 169.28Rim joist 2''x12''x20' ft. 16 0.8 16.8 383.84Plywood 3/4''x4'x8' sq. ft. 110 5.5 115.5 3,408.90
Wall SystemStuds 2''x4''x10' ft. 400 20 420 1,316.00Plywood 1/2''x4'x8' sq. ft. 130 6.5 136.5 4,028.70Sheetrock 1/2" x4'x8' sq. ft. 95 4.75 99.75 1,300.00Windows 36" x 48" Quan. 6 0.3 6.3Windows 72''x48'' Quan. 2 0.1 2.1Lentals 2''x6''x8' ft. 4 0.2 4.2 12.72
A) Center Wall Top Plate 2''x6''x8' ft. 12 0.6 12.6 38.16Bottom Plate 2''x6''x8' ft. 12 0.6 12.6 38.16Sheetrock 5/8''x 4'x8' (type X) sq. ft. 55 2.75 57.75 825.00Studs 2''x4''x10' ft. 60 3 63 197.40Vinyl Siding 10" x 120" sq. ft. 240 12 252 1,509.60
Roof SystemCelling Joist 2''x8"x20' ft. 120 6 126 3,225.60Rafters 2"x6"x10' ft. 80 4 84 343.20Ridge Beam 2"x12"20' ft. 4 0.2 4.2 52.32Shealthing 1/2"x4'x8' sq. ft. 62 3.1 65.1 1,921.38Felt Paper 15 lb (400 Sq ft) sq. ft. 8 0.4 8.4 152.00Asphalt Shingles 36"x12" (bundles) sq. ft. 124.5 6.225 130.725 3,112.50
Deliverables (Last Semester)Timeline01/22/2013 – 02/07/2013 Determine structure design 02/07/2013 – 02/14/2013 Research and investigate different design possibilities02/14/2013 – 02/21/2013 Design foundation02/21/2013 – 02/28/2013 Design wall system02/28/2013 – 03/18/2013 Begin foundation estimate03/18/2013 – 03/28/2013 Design roof system and begin wall system estimate03/28/2013 – 04/12/2103 Begin roof estimate04/12/2013 – 04/22/2013 Complete estimate and design04/22/2013 – 05/10/2013 Finalize all aspect of project, make adjustments as needed, and verify project
outcome with advisor
Deliverables (This Semester)Timeline08/21/2013 – 10/20/2013 Perform detailed drawings of structure on auto cad10/20/2013 – 10/27/2013 Perform detailed schedule10/27/2013 – 10/30/2013 Make adjustments to drawings and schedule according to
design10/30/2013 – 11/15/2013 Finalize scheduling and begin detailed estimate according to
complete drawings11/15/2013 – 11/28/2013 Finish detailed estimate on excel11/28/2013 – 12/05/2013 Finish all aspects of project (design, drawings, schedule, and
estimate)