NEW MEDICAL FACILITY BUILDING

By: Vincent Cannatella and Shelbi Remy

Advisor: Edward Rode

Instructor: Cris Koutsougeras

ET 493 - Senior Design 1

Page 2: NEW MEDICAL FACILITY BUILDING By: Vincent Cannatella and Shelbi Remy Advisor: Edward Rode Instructor: Cris Koutsougeras ET 493 - Senior Design 1

Introduction⦿ Our senior project this semester will involve complete development of a theoretical

medical building. ⦿ We will determine preliminary design, building and fire code requirements, the site

location, and begin the preliminary building estimates. ⦿ Rooms

⦿ Waiting Room ⦿ Play Room⦿ Restroom⦿ Utility Room⦿ Break Room⦿ Reception Room⦿ X-Ray Room⦿ Processing Room⦿ Ambulatory Room⦿ Doctor Office⦿ Administration Office⦿ Nurse Office⦿ 3 Exam Rooms

⦿ The building will be 2,378 square feet.

Page 3: NEW MEDICAL FACILITY BUILDING By: Vincent Cannatella and Shelbi Remy Advisor: Edward Rode Instructor: Cris Koutsougeras ET 493 - Senior Design 1

Preliminary Drawings⦿ Floor Plan

Page 4: NEW MEDICAL FACILITY BUILDING By: Vincent Cannatella and Shelbi Remy Advisor: Edward Rode Instructor: Cris Koutsougeras ET 493 - Senior Design 1

Preliminary Drawings⦿ North and South

Elevations

Page 5: NEW MEDICAL FACILITY BUILDING By: Vincent Cannatella and Shelbi Remy Advisor: Edward Rode Instructor: Cris Koutsougeras ET 493 - Senior Design 1

Preliminary Drawings⦿ East and West

Elevations

Page 6: NEW MEDICAL FACILITY BUILDING By: Vincent Cannatella and Shelbi Remy Advisor: Edward Rode Instructor: Cris Koutsougeras ET 493 - Senior Design 1

Exterior Finishes

⦿Roof●“S” Tile Roofing material

⦿Wall Finish●Stucco (decorative wall finish)●Owner will select color

⦿Trim Pieces●2x8 Fascia●2x2 window trim●Owner will select color

Page 7: NEW MEDICAL FACILITY BUILDING By: Vincent Cannatella and Shelbi Remy Advisor: Edward Rode Instructor: Cris Koutsougeras ET 493 - Senior Design 1

Building Codes⦿ The building codes come from the Hammond Zoning Ordinance

booklet. ⦿ Part 1: Principles and Objectives

● Section 1.3 - Commercial○ 1.306

⦿ Part 3: Schedule of District Regulations Adopted● Section 3.8 – C-1 Commercial District

○ 3.805 ○ 3.806 ○ 3.807

⦿ Part 5: Off-Street Parking and Loading Requirements● Section 5.3 – Commercial

○ 5.301 ● Section 5.6 – Off-Street Loading Requirements

○ 5.601

Page 8: NEW MEDICAL FACILITY BUILDING By: Vincent Cannatella and Shelbi Remy Advisor: Edward Rode Instructor: Cris Koutsougeras ET 493 - Senior Design 1

Fire Codes⦿ The fire codes came from the National Fire Protection Association 101

Life Safety Code booklet.⦿ Chapter 26: New Building Occupancies

● Section 26-1: General Requirements ○ 26-1.7

● Section 26-2: Means of Egress Requirements ○ 26-2.1.1○ 26-2.3.2○ 26-2.4○ 26-2.6○ 26-2.8

● Section 26-3: Protection○ 26-3.3.1○ 26-3.5

Page 9: NEW MEDICAL FACILITY BUILDING By: Vincent Cannatella and Shelbi Remy Advisor: Edward Rode Instructor: Cris Koutsougeras ET 493 - Senior Design 1

Determining Location⦿ Hammond, LA⦿Main road⦿ Zoning: Commercial⦿ Easy access ⦿ Narrowed down to 3 locations

Page 10: NEW MEDICAL FACILITY BUILDING By: Vincent Cannatella and Shelbi Remy Advisor: Edward Rode Instructor: Cris Koutsougeras ET 493 - Senior Design 1

Location 1⦿ 1107 West University Ave.⦿ 1.15 acres⦿ Price: $799,695⦿ Lot is cleared and ready to

build on

Page 11: NEW MEDICAL FACILITY BUILDING By: Vincent Cannatella and Shelbi Remy Advisor: Edward Rode Instructor: Cris Koutsougeras ET 493 - Senior Design 1

Location 2⦿ On the corner of East

University Ave. and North Cherry St.

⦿ 5.5 acres⦿ Price: $250,000⦿ Not cleared

Page 12: NEW MEDICAL FACILITY BUILDING By: Vincent Cannatella and Shelbi Remy Advisor: Edward Rode Instructor: Cris Koutsougeras ET 493 - Senior Design 1

Location 3⦿ Highway 190, West of I-55⦿ 3.07 acres⦿ Price: $129,000⦿ Not cleared

Page 13: NEW MEDICAL FACILITY BUILDING By: Vincent Cannatella and Shelbi Remy Advisor: Edward Rode Instructor: Cris Koutsougeras ET 493 - Senior Design 1

Final Location⦿We chose location 2⦿ Decision was based on location,

price, and lot size⦿ Only 3 acres will be used⦿ Sell the remaining 2.5 acres for

roughly $100,000⦿ A total of around $150,000

invested after selling land

Page 14: NEW MEDICAL FACILITY BUILDING By: Vincent Cannatella and Shelbi Remy Advisor: Edward Rode Instructor: Cris Koutsougeras ET 493 - Senior Design 1

Timeline/Deliverables Week 1-2 1/20/15 – 2/3/15 Determine a project and the tasks

involved

Week 3-4 2/4/15 – 2/18/15 Determine a site location and cost of the property

Week 5 2/19/15 – 2/26/15 Specify the building codes

Week 6 2/27/15 – 3/6/15 Specify the fire codes

Week 7 3/7/15 – 3/14/15 Work on preliminary drawings; floor plan and elevation plans

Week 8 3/15/15 – 3/22/15 Work on proposal document and presentation

Week 9-13 3/23/15 – 4/27/15 Begin estimation for materials

Week 14-15 4/28/15 – 5/8/15 Prepare final document and presentation

Page 15: NEW MEDICAL FACILITY BUILDING By: Vincent Cannatella and Shelbi Remy Advisor: Edward Rode Instructor: Cris Koutsougeras ET 493 - Senior Design 1

Any Questions?