work breakdown structure (wbs)
TRANSCRIPT
WORK BREAKDOWN STRUCTURE
KEADUE WWTP UPGRADE WORKS
KMCF ENGINEERING
DUBLIN ROAD
ATHLONE
2014
1
1.0 INTRODUCTION
The Work Breakdown Structure presented here represents all the work required to complete
this project.
OUTLINE VIEW
1. Feasibility Study 1.1 Initiation
1.1.1 Consider possible WWTPS
1.1.2 Conduct Desk Top Study
1.1.3 Develop basic selection criteria
1.2 Planning
1.2.1 Current and future working capacities of WWTP
1.2.2 Research County Development Plan
1.2.3 Consider required effluent standards
1.2.4 Determination of installation requirements
1.2.5 Consult EPA requirements
1.3 Execution
1.3.1 Preliminary design
1.3.2 Develop WWTP option checklist
1.3.3 Identify most attractive options
1.3.4 Source detailed information on chosen options
1.3.5 Compare technical requirements
1.4 Control
1.4.1 Further investigation on required effluent standards
1.4.2 Operators and machinery required
1.4.3 Analyse information
1.4.4 Identify maintenance costs, eco – footprint and impact on surroundings
1.4.5 Apply selection criteria
2
1.5 Closeout
1.5.1 Identify most suitable option
1.5.2 Handover Information on Chosen Option to Scheduling Team
2. Scheduling 2.1 Initiation
2.1.2 Source Information on the Construction of WWTPs
2.1.3 Develop Generic Schedule from Sourced Data
2.1.4 Incorporating Monitoring System into Generic
Schedule
2.2 Planning
2.2.1 Identify any Preliminary Works Required
2.2.2 Identify any Site Clearance Works Required
2.2.3 Identify Sections of Site Requiring Demolition/Upgrading
2.2.4 Study Existing Plant
2.2.5 Identify Existing/Required Services
2.3 Execution 2.3.1 Source Construction Info. For Chosen WWTP Option
2.3.2 Design Pipe Network & Size Units for Chosen WWTP Option
2.3.3 Tailor Generic Schedule to Suit Chosen WWTP Option
2.3.4 Develop Health & Safety Plan
2.4 Control
2.4.1 Compare Schedule Contents/Timeframes to Previous Similar Projects
2.4.2 Test Monitoring System’s Use for Contingencies
2.5 Closing
2.5.1 Document System’s Performance and all Lessons Learned
2.5.2 Incorporate System into Overall Package for Official Handover
3
3. Monitoring and Controlling 3.1 Initiation
3.1.1 Source Information of monitoring systems
3.1.2 Examine relevant legislation
3.2 Planning
3.2.1 Consider potential sources of delay
3.2.2 Source data required allowed for delay
3.2.3 Develop Monitoring System for Generic WWTP Project
3.2.4 Develop Automated System to allow for delays
3.3 Execution
3.3.1 Identify potential causes of delay in WWTP site
3.3.2 Develop Delay Costs relating WWTP site
3.4 Control
3.4.1 Test monitoring system in WWTP
3.4.2 Verified monitoring system against similar projects
3.5 Closing
3.5.1 Incorporate Monitoring System into Overall Schedule
4
Feasibility Study - WBS
Level 1 Level 2 Level 3
1 Feasibility Study
1.1 Initiation 1.1.1 Consider possible WWTPS
1.1.2 Conduct Desk Top Study
1.1.3 Develop basic selection criteria
1.2 Planning 1.2.1 Current and future working capacities of WWTP 1.2.2 Research County Development Plan 1.2.3 Consider required effluent standards 1.2.4 Determination of installation requirements 1.2.5 Consult EPA requirements
1.3 Execution 1.3.1 Preliminary design
1.3.2 Develop WWTP option checklist
1.3.3 Identify most attractive options
1.3.4 Source detailed information on chosen options
1.3.5 Compare technical requirements
1.4 Control 1.4.1 Further investigation on required effluent standards 1.4.2 Operators and machinery required 1.4.3 Analyse information 1.4.4 Identify maintenance costs, eco – footprint and impact on surroundings 1.4.5 Apply selection criteria
1.5 Closeout 1.5.1 Identify most suitable option 1.5.2 Handover Information on Chosen Option to Scheduling Team
5
Feasibility Study - WBS Dictionary
Level WBS Code
Element Name Definition
1 1 Feasibility Study .
2 1.1 Initiation The work to initiate the project.
3 1.1.1 Consider Possible WWTPs
Gather information on WWTPs from
printed material, internet and other
various resources
3 1.1.2 Conduct Desk Top Study
Carry out a desk top study on all information obtained on WWTPs from various sources
3 1.1.3 Develop Basic Selection Criteria
Set up an excel sheet to analyse the chosen WWTPs with respect to P.E., overall size and cost in order to choose the most suitable system
2 1.2 Planning The work for the planning process for
the project.
3 1.2.1 Current and future working capacities of WWTP
Gather information about the current Keadue WWTP capacity and established a method to determine future capacities
3 1.2.2 Research County Development Plan
Source information from Roscommon Co. Co. for developments in the Keadue area and other relevant information necessary
3 1.2.3 Consider Required Effluent Standards
Search standards for information in relation to effluent requirements
6
3 1.2.4 Determination of Installation Requirements
Determine if any design work is required for the chosen WWTP
3 1.2.5 Consult EPA Requirements
Determine if WWTPs perform to EPA standards
2 1.3 Execution Work involved in executing the project.
3 1.3.1 Preliminary Design
Carry out any preliminary design work on WWTP.
3 1.3.2 Develop WWTP Option Checklist
Develop checklist of options to compare WWTPs
3 1.3.3 Identify Most Attractive Options
Eliminate most of non-suitable WWTPs based on checklist to determine the most attractive option
3 1.3.4 Source Detailed Information on Chosen Options
Gather required information on chosen WWTPs
3 1.4
Compare Technical Requirements
Compare and contrast various technological requirements between the chosen packages
2 1.4.1 Control The work involved for the control
process of the project.
3 1.4.2 Further Investigation of Required Effluent Standards
Source information in relation to required standards and carry out any checks/calculations in relation to sludge disposal etc.
3 1.4.3 Operators and Machinery Required
Source information in relation to construction cost and labour for the chosen systems.
7
3 1.4.4 Analyse Information
Analyse further information gathered previously in relation to construction and costs.
3 1.4.5
Identify Maintenance Costs, Eco-Footprint, Impact on Surroundings
Carry out various checks/calculations in relation to costs, eco – footprint etc. of the chosen WWTPs
3 1.4.6 Apply Selection Criteria
Decide which WWTPs is the most suitable based on selection criteria
2 1.5 Closeout The work to close-out the project.
3 1.5.1 Identify Most Suitable Option
The most suitable WWTP is chosen
3 1.5.2
Handover Information on Chosen Option to Scheduling Team
Official handover of chosen system to scheduling team to allow for the commencement of a site specific schedule
8
Feasibility Study
Initiation Planning Execution Control Close out
Consider Possible WWTPs
Develop Generic Schedule from Sourced Data
Conduct Desk Top Study
Current and future working
capacities of WWTP
Research County
Development Plan
Consider Required Effluent
Standards
Determination of Installation Requirements
Preliminary Design
Develop WWTP Option
Checklist
Identify Most Attractive
Options
Source Detailed Information on Chosen Options
Futher Investiagation of
Required Effluent
Standards
Operators and
Machinary Required
Identify Most Suitable Option
Handover Information on Choden Option to Scheduling
Team
Develop Basic
Selection Criteria
Consult EPA Requiremen
ts
Compare Technical
Requirements
Analyse Information
Identify Maintenance
Costs, Eco-Footprint, Impact on Surroundings
Apply Selection Critera
9
Scheduling WBS
Level 1 Level 2 Level 3
4 Construction Schedule
4.1 Initiation 4.1.1 Source Information on the Construction of WWTPs
4.1.2 Develop Generic Schedule from Sourced Data
4.1.3 Incorporating Monitoring System into Generic
Schedule
4.2 Planning 4.2.1 Identify any Preliminary Works Required
4.2.2 Identify any Site Clearance Works Required
4.2.3 Identify Sections of Site Requiring
Demolition/Upgrading
4.2.4 Study Existing Plant
4.2.5 Identify Existing/Required Services
4.3 Execution 4.3.1 Source Construction Info. For Chosen WWTP Option
4.3.2 Design Pipe Network & Size Units for Chosen WWTP Option
4.3.3 Tailor Generic Schedule to Suit Chosen WWTP Option
4.3.4 Develop Health & Safety Plan
4.4 Control 4.4.1 Compare Schedule Contents/Timeframes to Previous Similar Projects 4.4.2 Test Monitoring System’s Use for Contingencies
4.5 Closeout 4.5.1 Document System’s Performance and all Lessons Learned 4.5.2 Incorporate System into Overall Package for Official Handover
10
Scheduling - WBS Dictionary
Level WBS Code
Element Name Definition
1 4 Scheduling All work to develop the schedule for
the upgrade works at Keadue WWTP.
2 4.1 Initiation The work to initiate the project.
3 4.1.1
Source Information on the
Construction of WWTPs
Source general information on the
construction of WWTPs. This
information is not to be site specific.
3 4.1.2 Develop Generic Schedule from
Sourced Data
By using the general information
sourced, develop a generic schedule for
the construction of a typical WWTP
plant.
3 4.1.3 Incorporating Monitoring System
into Generic Schedule
Incorporate the generic monitoring
system into the generic schedule once
the system has been handed over by
the relevant development team.
2 4.2 Planning The work during the planning process
for the project.
3 4.2.1
Identify any Preliminary Works
Required
Observe site and identify any works
required prior to construction (Fencing,
widening of access route, traffic
management etc.)
3 4.2.2 Identify any Site Clearance
Works Required
Identify if any site clearance works are
required on site.
11
3 4.2.3 Identify Sections of Site
Requiring Demolition/Upgrading
Study existing site plans with the aim of
identifying any sections which may be
kept/ upgraded in the planned
development.
3 4.2.4 Identify Existing/Required
Services
Identify existing services and determine
if current provisions are sufficient for
planned development.
2 4.3 Execution Work involved in executing the project.
3 4.3.1
Source Construction Info. For
Chosen WWTP Option
Once chosen WWTP details have been
handed over to the scheduling team
any or all available information relating
to WWTP is to be sourced and filed.
3 4.3.2 Design Pipe Network & Size
Units for Chosen WWTP system
Conduct any design work required such
as pipe sizing, plant design, pump sump
design etc.
3 4.3.3 Tailor Generic Schedule to Suit
Chosen WWTP Option
Re-visit generic schedule and update
constantly to suit chosen WWTP
option.
3 4.3.4 Develop Health & Safety Plan Develop H&S plan for planned
development.
2 4.4 Control The work involved for the control
process of the project.
3 4.4.1
Compare Schedule
Contents/Timeframes to
Previous Similar Projects
Examine allocated timeframes and
contents and verify them against
similar project’s schedules.
12
3 4.4.2 Test Monitoring System’s Use for
Contingencies
Test monitoring system’s ability to
provide for common issues on site,
once again verify the contingencies
against similar project.
2 4.5 Closeout The work to close-out the project.
3 4.5.1
Document System’s
Performance and all Lessons
Learned
Compile all documentation relating to
similar documents and conclude on
overall performance.
3 4.5.2 Incorporate System into Overall
Package for Official Handover
Handover final schedule to relevant
development team to allow the system
to be included in the overall package.
13
Scheduling
Initiation Planning Execution Control Closeout
Source Information on
the Construction of
WWTPs
Develop Generic Schedule from Sourced Data
Incorporating Monitoring System into
Generic Schedule
Identify any Preliminary
Works Required
Identify any Site Clearance
Works Required
Identify Sections of Site Requiring
Demolition/Upgrading
Identify Existing/Required Services
Source Construction
Info. For Chosen WWTP Option
Design Pipe Network &
Size Units for Chosen
Tailor Generic Schedule to Suit Chosen WWTP
Option
Develop Health &
Safety Plan
Compare Schedule Contents/
Timeframes to Previous Similar
Projects
Test Monitoring System’s Use of Contingencies
Document System’s
Performance and all Lessons
Learned
Incorporate System into
Overall Package for Official Handover
14
Monitoring and Controlling WBS
Level 1 Level 2 Level 3
4 Monitoring and Controlling
4.1 Initiation 4.1.1 Source Information on monitoring systems
4.1.2 Examine relevant legislation
4.2 Planning 4.2.1 Consider potential sources of delay
4.2.2 Source data required to allow for delay
4.2.3 Develop Monitoring System for Generic
WWTP Project
4.2.4 Develop Automated System to allow for
delays
4.3 Execution 4.3.1 Identify potential causes of delay in WWTP site
4.3.2 Develop Delay Costs relating WWTP site
4.4 Control 4.4.1 Test monitoring system in WWTP 4.4.2 Verified monitoring system against similar projects
4.5 Closeout 4.5.1 Incorporate Monitoring System into Overall Schedule
15
Monitoring and Controlling - WBS Dictionary
Level WBS Code
Element Name Definition
1 4 Monitoring and Controlling
All work to develop the Monitoring and
Controlling schedule for the upgrade
works at Keadue WWTP.
2 4.1 Initiation The work to initiate the project.
3 4.1.1 Source Information of
monitoring systems
Gather information on Monitoring
Systems from printed material, internet
and other various resources
3 4.1.2 Examine relevant legislation
Gather information on Monitoring
Systems from the public works contract
for civil engineering works
2 4.2 Planning The work for the planning process for
the project.
3 4.2.1 Consider potential sources of
delay
Gather information on potential
sources of delay for the project
3 4.2.2 Source data required allowed
for delay
Search for information in relation to
allow days for delay
3 4.2.3 Develop Monitoring System for
Generic WWTP Project
Set up an excel sheet to analyse
sources of delay with respect to delay
of project
2 4.3 Execution Work involved executing the project.
3 4.3.1 Identify potential causes of delay
in WWTP site
Gather required information for causes
of delay in WWTPs
3 4.3.2 Develop Delay Costs relating
WWTP site
Carry out calculation in relation to
delay costs of WWTP
16
Develop Automated System to
allow for delays
Develop options to allow for delays in
WWTP
2 4.4 Control
3 4.4.1 Test monitoring system in
WWTP
Run monitoring systems for verified
delays and then analyse results
3 4.4.2 Verified monitoring system
against similar projects
After running monitoring systems for
verified delays, compare to similar
project
2 4.5 Closeout The work to close-out the project.
3 4.5.1 Incorporate Monitoring System
into Overall Schedule
Officially handover of the construction
schedule to the schedule developer
17
Monitoring System
Initiation Planning Execution Control Closing
Source Information
of monitoring systems
Examine relevant
legislation
Consider potential
sources of delay
Source data required
allowed for delay
Determine Monitoring System for
Generic WWTP Project
Identify causes of delay in
WWTP site
Develop Delay Costs
relating WWTP site
Develop automated
system to allow for delays
Test monitoring system in
WWTP
Verified monitoring
system against similar projects
Identify Most Suitable Option
`
Incorporate Monitoring System into
Overall Schedule